Professional Documents
Culture Documents
Tugas 10 - C13 - CASH FLOW ESTIMATION AND RISK ANALYSIS
Tugas 10 - C13 - CASH FLOW ESTIMATION AND RISK ANALYSIS
Tugas 10 - C13 - CASH FLOW ESTIMATION AND RISK ANALYSIS
Dosen pengampu:
Ratna Nurhayati, S.E. M.Com.Ak. CA. PhD.
Disusun Oleh:
Sheila Syifanur Rosyida (22/498906/NEK/26554)
Rachmat Fazil Isda (22/498907/NEK/26555)
Iskandar (22/498913/NEK/26558)
Wismayanti Ginasari (22/498931/NEK/26566)
Mujaddidul Amri (22/498954/NEK/26575)
Mohammad Iqbal Baihaqi Aminuddin (22/499000/NEK/26593)
b. What is the initial investment outlay for the machine for capital budgeting purposes, that
is, what is the Year 0 project cash flow?
CAPEX = the base price of buying new milling machine + shipping and installation
costs
= 108.000 + 12.500 = 120.500
Year 0 project cash flow = CAPEX + the net operating working capital at the start
of the project
= 120.500 + 5.500 = 126.000
c. What are the project’s annual cash flows during Year 1, 2, and 3?
Annual cash flows during Year 1 = $42.518
Annual cash flows during Year 2 = $47.579
Annual cash flows during Year 3 = $85.629
Jawab:
Berdasarkan nilai positif yang diperoleh dari NPV dari arus kas yang akan terjadi selama
masa umur manfaat mesin baru atas penggantian mesin lama maka penggantian mesin
baru masih fisibel untuk dilakukan. Indikator lain yang memperkuat kesimpulan ini adalah
nilai IRR dan MIRR yang masih lebih besar dari WACC serta periode payback yang tidak
mencapai setengah umur mesin baru.
13-12
PROJECT RISK ANALYSIS
The Butler-Perkins Company (BPC) must decide between two mutually exclusive projects.
Each costs $6.750 and has an expected life of 3 years. Annual project cash flows begin 1
year after the initial investment and are subject to following probability distribution:
Project A Project B
Probability Cash Flows ($) Probability Cash Flows ($)
0,2 6.000 0,2 -
0,6 6.750 0,6 6.750
0,2 7.500 0,2 18.000
BPC has decided to evaluate the riskier project at 12% and the less-risky project at 10%.
a. What is each project's expected annual cash flow? Project B's standard deviation (σB) is
$5.978, and its coefficient of variation (CVB) is 0,76. What are the values of σA and CVA?
Project A
Probability Cash Flows (r) P.ri r’ = r -r̂ 𝑃(𝑟−𝑟̂)2
0,2 $6.000 $0 - 750 112.500
0,6 6.750 4.050 -0 0
0,2 7.500 3.600 750 112.500
Expected Cash Flow (r̂ ) 7.650 225.000
Coefficient Variation
σ
CV = 𝑟̂
474,34
= 6.750
= 0,07
Project B
Probability Cash Flows (r) P.ri r’ = r -r̂ 𝑃(𝑟−𝑟̂)2
0,2 $0 $0 - 7.650 11.704.500
0,6 6.750 4.050 - 900 486.000
0,2 18.000 3.600 10.350 21.424.500
Expected Cash Flow (r̂ ) 7.650 33.615.000
Coefficient Variation
σ
CV = 𝑟̂
5.797,84
= 7.650
= 0,76
Based on risk-adjusted NPVs, BPC should choose Project B because Project B has the
biggest NPV value.
c. If you knew that Project B's cash flows were negatively correlated with the firm's other
cash flows, but Project A's cash flows were positively correlated, how might this affect
the decision? If Project B's cash flows were negatively correlated with gross domestic
product (GDP), while A's cash flows were positively correlated, would that influence
your risk assessment?
Korelasi negatif antara arus kas Project B dengan arus kas perusahaan lainnya dapat
menurunkan risiko pada portofolio perusahaan karena adanya diversifikasi arus kas
perusahaan. Apabila arus kas Project B berkorelasi negatif dengan GDP maka akan
memberikan efek yang sama terhadap risiko portofolio perusahaan yang akan menjadi
turun. Apabila arus kas berkorelasi positif pada arus kas perusahaan lainnya maka tidak
memberikan efek penurunan risiko portofolio.
13-13
UNEQUAL LIVES
Haley’s Graphic Designs Inc. is considering two mutually exclusive projects. Both projects
require an initial investment of $10,000 and are typical average-risk projects for the firm.
Project A has an expected life of 2 years with after-tax cash inflows of $6,000 and $8,000 at
the end of Years 1 and 2, respectively. Project B has an expected life of 4 years with
after-tax cash inflows of $4,000 at the end of each of the next 4 years, The firm’s WACC is
10%.
a. If the projects cannot be repeated, which project should be selected if Haley uses NPV
as its criterion for project selection?
Answer
Project A
𝐶𝐹1 𝐶𝐹2
NPV A = CF0 + 1 + 2
(1+𝑟) (1+𝑟)
6.000 8.000
= -10.000 + 1 + 2
(1+0,10) (1+0,10)
= (-10,000) + 5,454.55 + 6,611.57
= $ 2,066.12
·
Project B
Jika proyek tidak dapat diulang, maka sebaiknya Haley memilih proyek B, karena
nilai NPV yang didapatkan dari proyek B lebih besar dibandingkan dengan proyek
A.
b. Assume that the projects can be repeated and that there are no anticipated changes in
the cash flows. Use the replacement chain analysis to determine the NPV of the project
selected.
𝐶𝐹1 𝐶𝐹2 𝐶𝐹3 𝐶𝐹4
NPV A = CF0 + 1 + 2 + 3 + 4
(1+𝑟) (1+𝑟) (1+𝑟) (1+𝑟)
6.000 8.000−10.000 6.000 8.000
= -10.000 + 1 + 2 + 3 + 4
(1+0,10) (1+0,10) (1+0,10) (1+0,10)
= (-10,000) + 5,454.55 + (-1652.89) + 4507.89 + 5464.11
= 3773.65
c. Make the same assumption as in part b. Using the equivalent annual annuity (EAA)
method, what is the EAA of the project selected?
= $1.190,48 $845,29