LEAD STATEMENT

LEAD STATEMENT FOR THE YEAR 2021-2022 (EFFECTIVE FROM 13.9.2021)

S.NO NAME OF SOURCE UNIT DIST IN CONVEYANCE COST OF TOTAL COST


MATERIAL kMS CHARGES MATERIAL

1 Cement Local MT 0 0 5960.00 5960.00

2 Steel Local MT 0 0 51750.00 51750.00

3 Sand for mortar Vaduvanthangal M3 132 1013.50 447.00 1460.50

4 Sand for filling Uthukottai M3 35 329.50 447.00 776.50

5 IInd class ground Uthukottai 1000 35 493.20 6435.00 6928.20


moulded chamfer NOS
burnt bricks of size
9”x4 3/8”x2 3/4”
6 Brick jelly 20mm Uthukottai M3 35 226.50 767.00 993.50

7 Brick jelly 40mm Uthukottai M3 35 226.50 688.00 914.50

8 HBG stone jelly sathiyavedu M3 40 370.50 1432.00 1802.50


20mm

9 HBG stone jelly sathiyavedu M3 40 370.50 1029.00 1399.50


40mm

10 HBG stone jelly sathiyavedu M3 40 370.50 1329.00 1699.50


12mm

11 Machine pressed Red hills 1000 40 208.40 16106.00 16314.40


tiles 23x23x2cm NOS

12 Slaked lime pollaachi M3 413.00 2825.95 1322.00 4147.95

13 Rough stone for sathiyavedu M3 40 370.50 445.00 815.50


masonry
14 Rough stone for sathiyavedu M3 40 370.50 385.00 755.50
Revetment
15 Bond stone sathiyavedu M3 40 370.50 642 1012.50

16 Gravel Red hills M3 40 370.50 216.30 586.80


``

SUB DATA

S.NO QTY DESCRIPTION RATE PER AMOUNT

1 CEMENT MORTAR 1:1.5


960.00 CEMENT 5960.00 MT 5721.60
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 7282.10

2 CEMENT MORTAR 1:2


720.00 CEMENT 5960.00 MT 4291.20
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 5851.70

3 CEMENT MORTAR 1:3


480.00 CEMENT 5960.00 MT 2860.80
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 4421.30

4 CEMENT MORTAR 1:4


360.00 CEMENT 5960.00 MT 2145.60
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 3706.10

5 CEMENT MORTAR 1:5


288.00 CEMENT 5960.00 MT 1716.48
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 3277.00

6 CEMENT MORTAR 1:6


240.00 CEMENT 5960.00 MT 1430.40
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 2991.00
``

DATA

S.NO QTY PER DESCRIPTION RATE PER AMOUNT

1. 1.00 M2 Dismantling of one course of pressed tile 20.00 M2 20.00


roof finish in cement mortar
( As per S.R schedule IT no 38c page no 22 )

2. 1.00 M3 Dismantling of lime concrete like 278.00 M3 278.00


weathearing coarse.
( As per S.R schedule IT no 36 page no 22 )

3. Weathering course using concrete


broken brick jelly 20mm gauge in pure
slacked lime(no sand to be used) over RCC
Roof slab. The proportion of broken jelly to
slaked lime being 32:12.5 cft well beaten by
wooden beaters for giving required slope
and thickness requiredetc, .complying with
standard specification and as directed by
the departmental officers .

12.8 M3 Brick jelly 20mm 993.50 M3 12716.80


5.00 M3 Unslakedpollachi lime 4147.95 M3 20739.75
1.80 Nos Mason 1st class 861.00 Each 1549.80
17.70 Nos Mazdoor cat-1 562.00 Each 9947.40
14.10 Nos Mazdoor cat-2 461.00 Each 6500.10
10 M2 51453.85
1 M2 5154.40

4. Finishing the top of roof with one course of


machine pressed tiles of size 23x23x2mm
of approved quality laid in cement mortar
1:3, mixed with 2% of water proofing
compound by weight of cement used and
pointed with same oiled mortar including
mixing of red oxide etc, complete.
complying with standard specification and
as directed by the departmental officers

Sub data for pointing- 10M2

0.04 M3 Cement mortar 1:3 4421.30 M3 176.85


2.2 Nos Mason 2nd class 804.00 Each 1768.80
0.5 Nos Mazdoor cat-1 562.00 Each 281.00
1.1 Nos Mazdoor cat-2 461.00 Each 507.10
0.384 kg Water proof compound 42.30 kg 16.24
``

10 M2 2750.00
For pointing 1 M2 275.00

189.0 Nos Pressed tiles23x23x2cm 16314.40 1000. 3083.42


0 00
0.12 M3 Cement mortar 1:3 4421.30 M3 530.56
1.152 kg Water proof compound 42.30 kg 48.73
10.00 M2 Pointing with Cement mortar 1:3 275.00 M2 2750.00
1.10 Nos Mason 1st class 861.00 Each 947.10
2.10 Nos Mason 2nd class 804.00 Each 1688.40
2.20 Nos Mazdoor cat-1 562.00 Each 1236.40
1.10 Nos Mazdoor cat-2 461.00 Each 507.10
10 M2 10791.71
1 M2 1079.00

5. Painting two coats of newly plastered wall


surface with ready mixed plastic emulsion
paint of first quality and of approved colour
over a priming coat including thorough
scrapping,clean removal of dirt,and
including necessary plaster of paris
putty,wherever required etc, complying
with standard specification

10.00 M2 Cleaning the plastered surface 6.65 M2 66.50


1.40 Litre Plastic emulsion paint 292.70 Litre 409.78
0.98 Litre primer 146.10 Litre 143.18
2.20 Nos Painter 1st class 688.00 Nos 1513.60
L.S Sundries for brushes, sand paper,plaster of L.S 6.94
paris putty, etc.
10 M2 2140.00
1 M2 214.00

6. Painting old iron works such as steel


doors,windows,ventilators,windowbars,bal
ustradesetc, with two coats of best
approved first quality and colour of
synthetic enamel paint including ordinary
scrapping using brushes and neat finishing
etc,complete. Complying with standard
specification .( The make,quality and colour
of paint should be got approved by the
executive engineer before use of works.

10.00 M2 Through scrapping 7.90 M2 79.00


1.89 lit Synthetic enamel paint fof iron 225.40 lit 426.00
``

1.11 Nos Painter/varnisher 1st class 688.00 Each 763.68


10 M2 1268.68
1 M2 126.90

7. Painting old wood works with two coats of


best approved first quality and colour of
synthetic enamel paint including ordinary
scrapping using brushes and neat finishing
etc,complete. Complying with standard
specification .( The make,quality and colour
of paint should be got approved by the
executive engineer before use of works.

10.00 M2 Through scrapping 12.50 M2 125.00


2.22 lit Synthetic enamel paint fof wood 236.60 lit 525.25
1.20 Nos Painter/varnisher 1st class 688.00 Each 825.60
10 M2 1475.85
1 M2 147.60
``

DETAILED ESTIMATE

S.NO DESCRIPTION NOS LEN BRD DEP CONTENTS

1. Dismantling of one course of pressed


tile roof finish in cement mortar

FOR REST MANDAPAM BUILDING

Total Terrace Area ( Flooring ) 1X1 23.95 9.60 - 229.92


Total Terrace Area ( Skirting ) 1x1 52.00 0.20 - 10.40
Deduct Head room Area 1X1 9.60 2.90 - (- ) 27.84
Deduct R.O Water plant Area 1x1 3.80 3.00 - (- ) 11.40

201.08 M2

2. Dismantling of lime concrete, like


weathearing coarse.

FOR REST MANDAPAM BUILDING

Total Terrace Area ( Flooring ) 1X1 23.95 9.60 0.15 34.49


Deduct Head room Area 1X1 9.60 2.90 0.15 (- ) 4.18
Deduct R.O Water plant Area 1x1 3.80 3.00 0.15 (- ) 1.71

28.60 M3

3. Weathering course using concrete


broken brick jelly 20mm gauge in pure
slacked lime(no sand to be used) over
RCC Roof slab. The proportion of
broken jelly to slaked lime being
32:12.5 cft well beaten by wooden
beaters for giving required slope and
thickness requiredetc, .complying with
standard specification and as directed
by the departmental officers .

FOR REST MANDAPAM BUILDING

Total Terrace Area ( Flooring ) 1X1 23.95 9.60 0.15 34.49


Deduct Head room Area 1X1 9.60 2.90 0.15 (- ) 4.18
Deduct R.O Water plant Area 1x1 3.80 3.00 0.15 (- ) 1.71

28.60 M3
``

4. Finishing the top of roof with one


course of machine pressed tiles of size
23x23x2mm of approved quality laid in
cement mortar 1:3, mixed with 2% of
water proofing compound by weight of
cement used and pointed with same
oiled mortar including mixing of red
oxide etc, complete. complying with
standard specification and as directed
by the departmental officers

FOR REST MANDAPAM BUILDING

Total Terrace Area ( Flooring ) 1X1 23.95 9.60 - 229.92


Total Terrace Area ( Skirting ) 1x1 52.00 0.20 - 10.40
Deduct Head room Area 1X1 9.60 2.90 - (- ) 27.84
Deduct R.O Water plant Area 1x1 3.80 3.00 - (- ) 11.40

201.08 M2

5. Painting two coats of newly plastered


wall surface with ready mixed plastic
emulsion paint of first quality and of
approved colour over a priming coat
including thorough scrapping,clean
removal of dirt,and including necessary
plaster of paris putty,wherever
required etc, complying with standard
specification

FOR REST MANDAPAM BUILDING

Outer walls ( Alround ) 1x1 68.90 - 9.00 620.10


Column offsets 2x9 0.60 - 9.00 97.20
Head room( Alround ) 1x1 26.80 - 2.90 77.72
Sunshades of windows 2x16 2.25 - 1.00 72.00
(North & south sides)
Sunshades of windows 1x3 1.95 - 1.00 5.85
(North & south sides)
Through sunshades 1x2 23.95 - 1.50 71.85
(North & south sides)
Deduct windows open 2x16 1.80 - 1.35 (-) 77.76
Deduct Door open 1x3 1.50 - 2.40 (-)10.80
Inner walls ( Alround ) 1x2 67.10 - 3.15 422.73
Ground & 1ST floor
Head room( Alround ) 1x1 25.00 - 2.80 70.00
Ground & 1ST floor Ceiling 1x2 23.95 9.60 - 459.84
``

Roof beams 2x9 9.60 - 1.00 172.80


Deduct wall tile Area 1x2 64.20 - 2.10 (-)269.64
Ground & 1ST floor
Deduct windows open 2x16 1.80 - 1.35 (-) 77.76
Deduct Door open 1x3 1.50 - 2.40 (-)10.80

1623.33M2

6. Painting old iron works such as steel


doors,windows,ventilators,windowbars
,balustradesetc, with two coats of best
approved first quality and colour of
synthetic enamel paint including
ordinary scrapping using brushes and
neat finishing etc,complete. Complying
with standard specification .( The
make,quality and colour of paint should
be got approved by the executive
engineer before use of works.

windows Grill 2x16 1.80 - 1.35 77.76 M2

7. Painting old wood works with two


coats of best approved first quality and
colour of synthetic enamel paint
including ordinary scrapping using
brushes and neat finishing
etc,complete. Complying with standard
specification .( The make,quality and
colour of paint should be got approved
by the executive engineer before use of
works.

Doors 1x3 1.50 - 2.40 10.80 M2


``

ABSTRACT ESTIMATE

S.NO QTY DESCRIPTION OF WORKS RATE PER AMOUNT

1. 201.08 Dismantling of one course of pressed tile roof finish in 20.00 M2 4022.00
cement mortar

2. 28.60 Dismantling of lime concrete, like weathearing coarse. 278.00 M3 7951.00

3. 28.60 Weathering course using concrete 5154.40 M3 147416.00


broken brick jelly 20mm gauge in pure slacked lime(no
sand to be used) over RCC Roof slab. The proportion of
broken jelly to slaked lime being 32:12.5 cft well beaten
by wooden beaters for giving required slope and
thickness requiredetc, .complying with standard
specification and as directed by the departmental
officers .

4. 201.08 Finishing the top of roof with one course of machine 1079.00 M2 216965.00
pressed tiles of size 23x23x2mm of approved quality laid
in cement mortar 1:3, mixed with 2% of water proofing
compound by weight of cement used and pointed with
same oiled mortar including mixing of red oxide etc,
complete. complying with standard specification and as
directed by the departmental officers

5. 1623.33 Painting two coats of newly plastered wall surface with 214.00 M2 347393.00
ready mixed plastic emulsion paint of first quality and of
approved colour over a priming coat including thorough
scrapping,clean removal of dirt,and including necessary
plaster of paris putty,wherever required etc, complying
with standard specification

6. 77.76 Painting old iron works such as steel 126.90 M2 9868.00


doors,windows,ventilators,windowbars,balustradesetc,
with two coats of best approved first quality and colour
of synthetic enamel paint including ordinary scrapping
using brushes and neat finishing etc,complete.
Complying with standard specification .( The
make,quality and colour of paint should be got approved
by the executive engineer before use of works.

7. 10.80 Painting old wood works with two coats of best 147.60 M2 1594.00
approved first quality and colour of synthetic enamel
paint including ordinary scrapping using brushes and
neat finishing etc,complete. Complying with standard
specification .( The make,quality and colour of paint
``

should be got approved by the executive engineer


before use of works.

SUB TOTAL 735209.00

ADD GST 12% 88225.00

PROVISION FOR CENTAGE CHARGES 2 % 17000.00

PROVISION FOR LABOUR WELFARE FUND 1% 8500.00

PROVISION FOR UNFORSEEN ITEMS 1066.00

TOTAL 850000.00
``

ESTIMATE

NAME OF WORK: RENOVATION WORK OFREST MANDAPAM FOR

ARULMIGU BHAVANI AMMAN THIRUKOVIL, PERIYAPALAYAM,

UTHUKOTTAI TALUK, THIRUVALLUR DISTRICT.

ESTIMATE AMOUNT : RS - 8.50 LAKHS


``

Report to accompany along with the estimate for the work of “ Renovation work in

Rest MandapamforArulmigu Bhavani Amman Thirukovil, Periyapalayam,

Uthukottai Taluk, Tiruvallur Dist.

Estimate Amount : RS – 8.50 Lakhs

IT has been proposed by the temple authorities to work of“ Renovation work in

Rest Mandapam forArulmigu Bhavani Amman Thirukovil, Periyapalayam,

Uthukottai Taluk, Tiruvallur Dist.

which an estimate is prepared . the estimate amount is RS – 8.50 Lakhs for the following are the

specification for the works.

1. Dismantling of one course of pressed tile roof finish in cement mortar


2. Dismantling of lime concrete, like weathearing coarse.
3. Weathering course using concrete
4. Finishing the top of roof with one course of machine pressed tiles
5. Painting two coats of newly plastered wall surface with ready mixed plastic
emulsion paint
6. Painting old iron works such as steel
7. Painting old wood works with two coats of best approved first quality

The necessary lumpsum provisions are made for centage @ 2% and labour welfare fund @ 1%The

current year schedule of rate for the year (2021-22) is adopted in the preparation of estimate.

(Effect from 13.09.2021)


``

LEAD STATEMENT

LEAD STATEMENT FOR THE YEAR 2021-2022 (EFFECTIVE FROM 13.9.2021)

S.NO NAME OF SOURCE UNIT DIST IN CONVEYANCE COST OF TOTAL COST


MATERIAL kMS CHARGES MATERIAL

1 Cement Local MT 0 0 5960.00 5960.00

2 Steel Local MT 0 0 51750.00 51750.00

3 Sand for mortar Vaduvanthangal M3 132 1013.50 447.00 1460.50

4 Sand for filling Vaduvanthangal M3 132 1013.50 447.00 1460.50

5 IInd class ground Thirumazhisai 1000 38 497.76 6435.00 6932.76


moulded chamfer NOS
burnt bricks of size
9”x4 3/8”x2 3/4”
6 Brick jelly 20mm Thirumazhisai M3 38 243.42 767.00 1010.42

7 Brick jelly 40mm Thirumazhisai M3 38 243.42 688.00 931.42

8 HBG stone jelly pallavaram M3 58 508.92 1432.00 1940.92


20mm

9 HBG stone jelly pallavaram M3 58 508.92 1029.00 1537.92


40mm

10 HBG stone jelly pallavaram M3 58 508.92 1329.00 1837.92


12mm

11 Machine pressed Red hills 1000 25 278.50 16106.00 16245.25


tiles 23x23x2cm NOS

12 Slaked and pollachi M3 458.00 2127.82 974.00 3101.82


screened burnt
lime stone

13 Cut stone suryanagaram M3 74 631.96 14000.00 14631.96


``

SUB DATA

S.NO QTY DESCRIPTION RATE PER AMOUNT

1 CEMENT MORTAR 1:1.5


960.00 CEMENT 5960.00 MT 5721.60
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 7282.10

2 CEMENT MORTAR 1:2


720.00 CEMENT 5960.00 MT 4291.20
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 5851.70

3 CEMENT MORTAR 1:3


480.00 CEMENT 5960.00 MT 2860.80
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 4421.30

4 CEMENT MORTAR 1:4


360.00 CEMENT 5960.00 MT 2145.60
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 3706.10

5 CEMENT MORTAR 1:5


288.00 CEMENT 5960.00 MT 1716.48
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 3277.00

6 CEMENT MORTAR 1:6


240.00 CEMENT 5960.00 MT 1430.40
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 2991.00
``

DATA

S.NO QTY PER DESCRIPTION RATE PER AMOUNT

1. 1.00 M2 Dismantling of one course of pressed tile 20.00 M2 20.00


roof finish in cement mortar
( As per S.R schedule IT no 38c page no 22 )

2. 1.00 M3 Dismantling of lime concrete like 278.00 M3 278.00


weathearing coarse.
( As per S.R schedule IT no 36 page no 22 )

3. Weathering course using concrete


broken brick jelly 20mm gauge in pure
slacked lime(no sand to be used) over RCC
Roof slab. The proportion of broken jelly to
slaked lime being 32:12.5 cft well beaten by
wooden beaters for giving required slope
and thickness requiredetc, .complying with
standard specification and as directed by
the departmental officers .

12.8 M3 Brick jelly 20mm 1010.42 M3 12933.38


5.00 M3 Unslakedpollachi lime 3101.82 M3 15509.10
1.80 Nos Mason 1st class 861.00 Each 1549.80
17.70 Nos Mazdoor cat-1 562.00 Each 9947.40
14.10 Nos Mazdoor cat-2 461.00 Each 6500.10
10 M2 46439.78
1 M2 4643.98

4. Finishing the top of roof with one course of


machine pressed tiles of size 23x23x2mm
of approved quality laid in cement mortar
1:3, mixed with 2% of water proofing
compound by weight of cement used and
pointed with same oiled mortar including
mixing of red oxide etc, complete.
complying with standard specification and
as directed by the departmental officers

Sub data for pointing- 10M2

0.04 M3 Cement mortar 1:3 4421.30 M3 176.85


2.2 Nos Mason 2nd class 804.00 Each 1768.80
0.5 Nos Mazdoor cat-1 562.00 Each 281.00
``

1.1 Nos Mazdoor cat-2 461.00 Each 507.10


0.384 kg Water proof compound 42.30 kg 16.24
10 M2 2750.00
For pointing 1 M2 275.00

189.00 Nos Pressed tiles23x23x2cm 16245.25 1000.00 3070.35


0.12 M3 Cement mortar 1:3 4421.30 M3 530.56
1.152 kg Water proof compound 42.30 kg 48.73
10.00 M2 Pointing with Cement mortar 1:3 275.00 M2 2750.00
1.10 Nos Mason 1st class 861.00 Each 947.10
2.10 Nos Mason 2nd class 804.00 Each 1688.40
2.20 Nos Mazdoor cat-1 562.00 Each 1236.40
1.10 Nos Mazdoor cat-2 461.00 Each 507.10
10 M2 10778.64
1 M2 1077.86

5. Painting two coats of newly plastered wall


surface with water based exterior emulsion
paint of first quality and of approved colour
over a priming coat including thorough
scrapping,clean removal of dirt,and
including necessary plaster of paris
putty,wherever required etc, complying
with standard specification

10.00 M2 Cleaning the plastered surface 6.65 M2 66.50


1.40 Litre Water based exterior emulsion 292.70 Litre 409.78
0.98 Litre primer 146.10 Litre 143.18
2.20 Nos Painter 1st class 688.00 Nos 1513.60
L.S Sundries for brushes, sand paper,plaster of L.S 6.94
paris putty, etc.
10 M2 2140.00
1 M2 214.00

6. Painting old iron works such as steel


doors,windows,ventilators,windowbars,bal
ustradesetc, with two coats of best
approved first quality and colour of
synthetic enamel paint including ordinary
scrapping using brushes and neat finishing
etc,complete. Complying with standard
specification .( The make,quality and colour
of paint should be got approved by the
executive engineer before use of works.

10.00 M2 Through scrapping 7.90 M2 79.00


``

1.89 lit Synthetic enamel paint fof iron 225.40 lit 426.00
1.11 Nos Painter/varnisher 1st class 688.00 Each 763.68
10 M2 1268.68
1 M2 126.90

7. Painting old wood works with two coats of


best approved first quality and colour of
synthetic enamel paint including ordinary
scrapping using brushes and neat finishing
etc,complete. Complying with standard
specification .( The make,quality and colour
of paint should be got approved by the
executive engineer before use of works.

10.00 M2 Through scrapping 12.50 M2 125.00


2.22 lit Synthetic enamel paint fof wood 236.60 lit 525.25
1.20 Nos Painter/varnisher 1st class 688.00 Each 825.60
10 M2 1475.85
1 M2 147.60
``

DETAILED ESTIMATE

S.NO DESCRIPTION NOS LEN BRD DEP CONTENTS

1. Dismantling of one course of pressed


tile roof finish in cement mortar

FOR HAIR TONSURE BUILDING

Total Terrace Area ( Flooring ) 1X1 17.95 9.60 - 172.32


Total Terrace Area ( Skirting ) 1x1 33.00 0.20 - 6.60
Deduct Head room Area 1X1 9.60 2.90 - (- ) 27.84
151.08 M2

2. Dismantling of lime concrete, like


weathearing coarse.

FOR HAIR TONSURE BUILDING

Total Terrace Area ( Flooring ) 1X1 17.95 9.60 0.15 25.85


Deduct Head room Area 1X1 9.60 2.90 0.15 (- ) 4.18
21.67 M3

3. Weathering course using concrete


broken brick jelly 20mm gauge in pure
slacked lime(no sand to be used) over
RCC Roof slab. The proportion of
broken jelly to slaked lime being
32:12.5 cft well beaten by wooden
beaters for giving required slope and
thickness requiredetc, .complying with
standard specification and as directed
by the departmental officers .

FOR HAIR TONSURE BUILDING

Total Terrace Area ( Flooring ) 1X1 17.95 9.60 0.10 17.23


Deduct Head room Area 1X1 9.60 2.90 0.10 (- ) 2.78
14.45 M3

4. Finishing the top of roof with one


course of machine pressed tiles of size
23x23x2mm of approved quality laid in
cement mortar 1:3, mixed with 2% of
water proofing compound by weight of
``

cement used and pointed with same


oiled mortar including mixing of red
oxide etc, complete. complying with
standard specification and as directed
by the departmental officers

FOR HAIR TONSURE BUILDING

Total Terrace Area ( Flooring ) 1X1 17.95 9.60 - 172.32


Total Terrace Area ( Skirting ) 1x1 33.00 0.20 - 6.60
Deduct Head room Area 1X1 9.60 2.90 - (- ) 27.84
151.08 M2

5. Painting two coats of newly plastered


wall surface with water based exterior
emulsion paint of first quality and of
approved colour over a priming coat
including thorough scrapping,clean
removal of dirt,and including necessary
plaster of paris putty,wherever
required etc, complying with standard
specification

FOR HAIR TONSURE BUILDING

Outer walls ( Alround ) 1x1 56.90 - 5.25 298.73


Column offsets 2x7 0.60 - 5.25 44.10
Head room( Alround ) 1x1 26.80 - 3.20 85.76
Sunshades of windows 2x6 2.25 - 1.00 27.00
(East & West sides)
Sunshades of doors 1x2 1.95 - 1.00 3.90
(North & south sides)
Through sunshades 1x2 17.95 - 1.25 44.88
(East & West sides)
Deduct windows open 2x6 1.80 - 1.35 (-)29.16
Deduct Door open 1x2 1.50 - 2.40 (-)7.20
Inner walls ( Alround ) 1x1 55.10 - 3.15 173.57
Head room( Alround ) 1x1 25.00 - 2.75 68.75
Ground 1x1 17.95 9.60 - 172.32
Roof beams 1x9 9.60 - 1.00 86.40
Deduct wall tile Area 1x1 55.10 - 2.40 (-)132.24
Deduct windows open 2x6 1.80 - 1.35 (-)29.16
Deduct Door open 1x2 1.50 - 2.40 (-)7.20

800.45M2

6. Painting old iron works such as steel


``

doors,windows,ventilators,windowbars
,balustradesetc, with two coats of best
approved first quality and colour of
synthetic enamel paint including
ordinary scrapping using brushes and
neat finishing etc,complete. Complying
with standard specification .( The
make,quality and colour of paint should
be got approved by the executive
engineer before use of works.

windows Grill 2x6 1.80 - 1.35 29.16 M2

7. Painting old wood works with two


coats of best approved first quality and
colour of synthetic enamel paint
including ordinary scrapping using
brushes and neat finishing
etc,complete. Complying with standard
specification .( The make,quality and
colour of paint should be got approved
by the executive engineer before use of
works.

Doors 1x3 1.50 - 2.40 7.20 M2


``

ABSTRACT ESTIMATE

S.NO QTY DESCRIPTION OF WORKS RATE PER AMOUNT

1. 151.08 Dismantling of one course of pressed tile roof finish in 20.00 M2 3022.00
cement mortar

2. 21.67 Dismantling of lime concrete, like weathearing coarse. 278.00 M3 6024.00

3. 14.45 Weathering course using concrete 4643.98 M3 67106.00


broken brick jelly 20mm gauge in pure slacked lime(no
sand to be used) over RCC Roof slab. The proportion of
broken jelly to slaked lime being 32:12.5 cft well beaten
by wooden beaters for giving required slope and
thickness requiredetc, .complying with standard
specification and as directed by the departmental
officers .

4. 151.08 Finishing the top of roof with one course of machine 1077.86 M2 162843.00
pressed tiles of size 23x23x2mm of approved quality laid
in cement mortar 1:3, mixed with 2% of water proofing
compound by weight of cement used and pointed with
same oiled mortar including mixing of red oxide etc,
complete. complying with standard specification and as
directed by the departmental officers

5. 800.45 Painting two coats of newly plastered wall surface with 214.00 M2 171296.00
water based exterior emulsion paint of first quality and
of approved colour over a priming coat including
thorough scrapping,clean removal of dirt,and including
necessary plaster of paris putty,wherever required etc,
complying with standard specification

6. 29.16 Painting old iron works such as steel 126.90 M2 3700.00


doors,windows,ventilators,windowbars,balustradesetc,
with two coats of best approved first quality and colour
of synthetic enamel paint including ordinary scrapping
using brushes and neat finishing etc,complete.
Complying with standard specification .( The
make,quality and colour of paint should be got approved
by the executive engineer before use of works.

7. 7.20 Painting old wood works with two coats of best 147.60 M2 1063.00
approved first quality and colour of synthetic enamel
paint including ordinary scrapping using brushes and
neat finishing etc,complete. Complying with standard
``

specification .( The make,quality and colour of paint


should be got approved by the executive engineer
before use of works.

SUB TOTAL 415054.00

ADD GST 12% 49806.00

PROVISION FOR CENTAGE CHARGES 2 % 9700.00

PROVISION FOR LABOUR WELFARE FUND 1% 4850.00

PROVISION FOR UNFORSEEN ITEMS 5590.00

TOTAL 485000.00
``

ESTIMATE

NAME OF WORK : REPAIRS AND REPAINTING OFHAIR TONSURE BUILDINGFOR

ARULMIGU BHAVANI AMMAN THIRUKOVIL, PERIYAPALAYAM,

UTHUKOTTAI TALUK, THIRUVALLUR DISTRICT.

ESTIMATE AMOUNT : RS - 4.85 LAKHS


``

Report to accompany along with the estimate for the work of “ Repairs and Repainting work in

Hair Tonsure BuildingforArulmigu Bhavani Amman Thirukovil, Periyapalayam,

Uthukottai Taluk, Tiruvallur Dist.

Estimate Amount : RS – 4.85 Lakhs

IT has been proposed by the temple authorities to work of“Repairs and Repainting work in

Hair Tonsure Building forArulmigu Bhavani Amman Thirukovil, Periyapalayam,

Uthukottai Taluk, Tiruvallur Dist.

which an estimate is prepared . the estimate amount is RS – 4.85 Lakhs for the following are the

specification for the works.

1. Dismantling of one course of pressed tile roof finish in cement mortar


2. Dismantling of lime concrete, like weathearing coarse.
3. Weathering course using concrete
4. Finishing the top of roof with one course of machine pressed tiles
5. Painting two coats of newly plastered wall surface with water based exterior
emulsion paint
6. Painting old iron works such as steel
7. Painting old wood works with two coats of best approved first quality

The necessary lumpsum provisions are made for centage @ 2% and labour welfare fund @ 1%The

current year schedule of rate for the year (2021-22) is adopted in the preparation of estimate.

(Effect from 13.09.2021)


``

LEAD STATEMENT

LEAD STATEMENT FOR THE YEAR 2021-2022 (EFFECTIVE FROM 13.9.2021)

S.NO NAME OF SOURCE UNIT DIST IN CONVEYANCE COST OF TOTAL COST


MATERIAL kMS CHARGES MATERIAL

1 Cement Local MT 0 0 5960.00 5960.00

2 Steel Local MT 0 0 51750.00 51750.00

3 Sand for mortar Vaduvanthangal M3 132 1013.50 447.00 1460.50

4 Sand for filling Vaduvanthangal M3 132 1013.50 447.00 1460.50

5 IInd class ground Thirumazhisai 1000 38 497.76 6435.00 6932.76


moulded chamfer NOS
burnt bricks of size
9”x4 3/8”x2 3/4”
6 Brick jelly 20mm Thirumazhisai M3 38 243.42 767.00 1010.42

7 Brick jelly 40mm Thirumazhisai M3 38 243.42 688.00 931.42

8 HBG stone jelly pallavaram M3 58 508.92 1432.00 1940.92


20mm

9 HBG stone jelly pallavaram M3 58 508.92 1029.00 1537.92


40mm

10 HBG stone jelly pallavaram M3 58 508.92 1329.00 1837.92


12mm

11 Machine pressed Red hills 1000 25 278.50 16106.00 16245.25


tiles 23x23x2cm NOS

12 Slaked and pollachi M3 458.00 2127.82 974.00 3101.82


screened burnt
lime stone

13 Cut stone suryanagaram M3 74 631.96 14000.00 14631.96


``

SUB DATA

S.NO QTY DESCRIPTION RATE PER AMOUNT

1 CEMENT MORTAR 1:1.5


960.00 CEMENT 5960.00 MT 5721.60
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 7282.10

2 CEMENT MORTAR 1:2


720.00 CEMENT 5960.00 MT 4291.20
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 5851.70

3 CEMENT MORTAR 1:3


480.00 CEMENT 5960.00 MT 2860.80
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 4421.30

4 CEMENT MORTAR 1:4


360.00 CEMENT 5960.00 MT 2145.60
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 3706.10

5 CEMENT MORTAR 1:5


288.00 CEMENT 5960.00 MT 1716.48
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 3277.00

6 CEMENT MORTAR 1:6


240.00 CEMENT 5960.00 MT 1430.40
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 2991.00
``

DATA

S.NO QTY PER DESCRIPTION RATE PER AMOUNT

1. 1.00 M2 Dismantling of one course of pressed tile 20.00 M2 20.00


roof finish in cement mortar
( As per S.R schedule IT no 38c page no 22 )

2. 1.00 M3 Dismantling of lime concrete like 278.00 M3 278.00


weathearing coarse.
( As per S.R schedule IT no 36 page no 22 )

3. Weathering course using concrete


broken brick jelly 20mm gauge in pure
slacked lime(no sand to be used) over RCC
Roof slab. The proportion of broken jelly to
slaked lime being 32:12.5 cft well beaten by
wooden beaters for giving required slope
and thickness requiredetc, .complying with
standard specification and as directed by
the departmental officers .

12.8 M3 Brick jelly 20mm 1010.42 M3 12933.38


5.00 M3 Unslakedpollachi lime 3101.82 M3 15509.10
1.80 Nos Mason 1st class 861.00 Each 1549.80
17.70 Nos Mazdoor cat-1 562.00 Each 9947.40
14.10 Nos Mazdoor cat-2 461.00 Each 6500.10
10 M2 46439.78
1 M2 4643.98

4. Finishing the top of roof with one course of


machine pressed tiles of size 23x23x2mm
of approved quality laid in cement mortar
1:3, mixed with 2% of water proofing
compound by weight of cement used and
pointed with same oiled mortar including
mixing of red oxide etc, complete.
complying with standard specification and
as directed by the departmental officers

Sub data for pointing- 10M2

0.04 M3 Cement mortar 1:3 4421.30 M3 176.85


2.2 Nos Mason 2nd class 804.00 Each 1768.80
0.5 Nos Mazdoor cat-1 562.00 Each 281.00
``

1.1 Nos Mazdoor cat-2 461.00 Each 507.10


0.384 kg Water proof compound 42.30 kg 16.24
10 M2 2750.00
For pointing 1 M2 275.00

189.00 Nos Pressed tiles23x23x2cm 16245.25 1000.00 3070.35


0.12 M3 Cement mortar 1:3 4421.30 M3 530.56
1.152 kg Water proof compound 42.30 kg 48.73
10.00 M2 Pointing with Cement mortar 1:3 275.00 M2 2750.00
1.10 Nos Mason 1st class 861.00 Each 947.10
2.10 Nos Mason 2nd class 804.00 Each 1688.40
2.20 Nos Mazdoor cat-1 562.00 Each 1236.40
1.10 Nos Mazdoor cat-2 461.00 Each 507.10
10 M2 10778.64
1 M2 1077.86

5. Painting two coats of newly plastered wall


surface with water based exterior emulsion
paint of first quality and of approved colour
over a priming coat including thorough
scrapping,clean removal of dirt,and
including necessary plaster of paris
putty,wherever required etc, complying
with standard specification

10.00 M2 Cleaning the plastered surface 6.65 M2 66.50


1.40 Litre Water based exterior emulsion 292.70 Litre 409.78
0.98 Litre primer 146.10 Litre 143.18
2.20 Nos Painter 1st class 688.00 Nos 1513.60
L.S Sundries for brushes, sand paper,plaster of L.S 6.94
paris putty, etc.
10 M2 2140.00
1 M2 214.00

6. Painting old iron works such as steel


doors,windows,ventilators,windowbars,bal
ustradesetc, with two coats of best
approved first quality and colour of
synthetic enamel paint including ordinary
scrapping using brushes and neat finishing
etc,complete. Complying with standard
specification .( The make,quality and colour
of paint should be got approved by the
executive engineer before use of works.

10.00 M2 Through scrapping 7.90 M2 79.00


``

1.89 lit Synthetic enamel paint fof iron 225.40 lit 426.00
1.11 Nos Painter/varnisher 1st class 688.00 Each 763.68
10 M2 1268.68
1 M2 126.90

7. Painting old wood works with two coats of


best approved first quality and colour of
synthetic enamel paint including ordinary
scrapping using brushes and neat finishing
etc,complete. Complying with standard
specification .( The make,quality and colour
of paint should be got approved by the
executive engineer before use of works.

10.00 M2 Through scrapping 12.50 M2 125.00


2.22 lit Synthetic enamel paint fof wood 236.60 lit 525.25
1.20 Nos Painter/varnisher 1st class 688.00 Each 825.60
10 M2 1475.85
1 M2 147.60
``

DETAILED ESTIMATE

S.NO DESCRIPTION NOS LEN BRD DEP CONTENTS

1. Dismantling of one course of pressed


tile roof finish in cement mortar

FOR VEAPPANCHEALAI MANDAPAM

Total Terrace Area ( Flooring ) 1X1 17.95 9.60 - 172.32


Total Terrace Area ( Skirting ) 1x1 33.00 0.20 - 6.60
Deduct Head room Area 1X1 9.60 2.90 - (- ) 27.84
151.08 M2

2. Dismantling of lime concrete, like


weathearing coarse.

FOR VEAPPANCHEALAI MANDAPAM

Total Terrace Area ( Flooring ) 1X1 17.95 9.60 0.15 25.85


Deduct Head room Area 1X1 9.60 2.90 0.15 (- ) 4.18
21.67 M3

3. Weathering course using concrete


broken brick jelly 20mm gauge in pure
slacked lime(no sand to be used) over
RCC Roof slab. The proportion of
broken jelly to slaked lime being
32:12.5 cft well beaten by wooden
beaters for giving required slope and
thickness requiredetc, .complying with
standard specification and as directed
by the departmental officers .

FOR VEAPPANCHEALAI MANDAPAM

Total Terrace Area ( Flooring ) 1X1 17.95 9.60 0.10 17.23


Deduct Head room Area 1X1 9.60 2.90 0.10 (- ) 2.78
14.45 M3

4. Finishing the top of roof with one


course of machine pressed tiles of size
23x23x2mm of approved quality laid in
cement mortar 1:3, mixed with 2% of
water proofing compound by weight of
``

cement used and pointed with same


oiled mortar including mixing of red
oxide etc, complete. complying with
standard specification and as directed
by the departmental officers

FOR VEAPPANCHEALAI MANDAPAM

Total Terrace Area ( Flooring ) 1X1 17.95 9.60 - 172.32


Total Terrace Area ( Skirting ) 1x1 33.00 0.20 - 6.60
Deduct Head room Area 1X1 9.60 2.90 - (- ) 27.84
151.08 M2

5. Painting two coats of newly plastered


wall surface with water based exterior
emulsion paint of first quality and of
approved colour over a priming coat
including thorough scrapping,clean
removal of dirt,and including necessary
plaster of paris putty,wherever
required etc, complying with standard
specification

FOR VEAPPANCHEALAI MANDAPAM

Outer walls ( Alround ) 1x1 56.90 - 5.25 298.73


Column offsets 2x7 0.60 - 5.25 44.10
Head room( Alround ) 1x1 26.80 - 3.20 85.76
Sunshades of windows 2x6 2.25 - 1.00 27.00
(East & West sides)
Sunshades of doors 1x2 1.95 - 1.00 3.90
(North & south sides)
Through sunshades 1x2 17.95 - 1.25 44.88
(East & West sides)
Deduct windows open 2x6 1.80 - 1.35 (-)29.16
Deduct Door open 1x2 1.50 - 2.40 (-)7.20
Inner walls ( Alround ) 1x1 55.10 - 3.15 173.57
Head room( Alround ) 1x1 25.00 - 2.75 68.75
Ground 1x1 17.95 9.60 - 172.32
Roof beams 1x9 9.60 - 1.00 86.40
Deduct wall tile Area 1x1 55.10 - 2.40 (-)132.24
Deduct windows open 2x6 1.80 - 1.35 (-)29.16
Deduct Door open 1x2 1.50 - 2.40 (-)7.20

800.45M2

6. Painting old iron works such as steel


``

doors,windows,ventilators,windowbars
,balustradesetc, with two coats of best
approved first quality and colour of
synthetic enamel paint including
ordinary scrapping using brushes and
neat finishing etc,complete. Complying
with standard specification .( The
make,quality and colour of paint should
be got approved by the executive
engineer before use of works.

windows Grill 2x6 1.80 - 1.35 29.16 M2

7. Painting old wood works with two


coats of best approved first quality and
colour of synthetic enamel paint
including ordinary scrapping using
brushes and neat finishing
etc,complete. Complying with standard
specification .( The make,quality and
colour of paint should be got approved
by the executive engineer before use of
works.

Doors 1x3 1.50 - 2.40 7.20 M2


``

ABSTRACT ESTIMATE

S.NO QTY DESCRIPTION OF WORKS RATE PER AMOUNT

1. 151.08 Dismantling of one course of pressed tile roof finish in 20.00 M2 3022.00
cement mortar

2. 21.67 Dismantling of lime concrete, like weathearing coarse. 278.00 M3 6024.00

3. 14.45 Weathering course using concrete 4643.98 M3 67106.00


broken brick jelly 20mm gauge in pure slacked lime(no
sand to be used) over RCC Roof slab. The proportion of
broken jelly to slaked lime being 32:12.5 cft well beaten
by wooden beaters for giving required slope and
thickness requiredetc, .complying with standard
specification and as directed by the departmental
officers .

4. 151.08 Finishing the top of roof with one course of machine 1077.86 M2 162843.00
pressed tiles of size 23x23x2mm of approved quality laid
in cement mortar 1:3, mixed with 2% of water proofing
compound by weight of cement used and pointed with
same oiled mortar including mixing of red oxide etc,
complete. complying with standard specification and as
directed by the departmental officers

5. 800.45 Painting two coats of newly plastered wall surface with 214.00 M2 171296.00
water based exterior emulsion paint of first quality and
of approved colour over a priming coat including
thorough scrapping,clean removal of dirt,and including
necessary plaster of paris putty,wherever required etc,
complying with standard specification

6. 29.16 Painting old iron works such as steel 126.90 M2 3700.00


doors,windows,ventilators,windowbars,balustradesetc,
with two coats of best approved first quality and colour
of synthetic enamel paint including ordinary scrapping
using brushes and neat finishing etc,complete.
Complying with standard specification .( The
make,quality and colour of paint should be got approved
by the executive engineer before use of works.

7. 7.20 Painting old wood works with two coats of best 147.60 M2 1063.00
approved first quality and colour of synthetic enamel
paint including ordinary scrapping using brushes and
neat finishing etc,complete. Complying with standard
``

specification .( The make,quality and colour of paint


should be got approved by the executive engineer
before use of works.

SUB TOTAL 415054.00

ADD GST 12% 49806.00

PROVISION FOR CENTAGE CHARGES 2 % 9700.00

PROVISION FOR LABOUR WELFARE FUND 1% 4850.00

PROVISION FOR UNFORSEEN ITEMS 5590.00

TOTAL 485000.00
``

ESTIMATE

NAME OF WORK : REPAIRS AND REPAINTING OF VEAPPANCHEALAI MANDAPAMFOR

ARULMIGU BHAVANI AMMAN THIRUKOVIL, PERIYAPALAYAM,

UTHUKOTTAI TALUK, THIRUVALLUR DISTRICT.

ESTIMATE AMOUNT : RS - 4.85 LAKHS


``

Report to accompany along with the estimate for the work of “ Repairs and Repainting work in

Veappanchealai Mandapam for Arulmigu Bhavani Amman Thirukovil, Periyapalayam,

Uthukottai Taluk, Tiruvallur Dist.

Estimate Amount : RS – 4.85 Lakhs

IT has been proposed by the temple authorities to work of“Repairs and Repainting work in

Veappanchealai Mandapam forArulmigu Bhavani Amman Thirukovil, Periyapalayam,

Uthukottai Taluk, Tiruvallur Dist.

which an estimate is prepared . the estimate amount is RS – 4.85 Lakhs for the following are the

specification for the works.

1. Dismantling of one course of pressed tile roof finish in cement mortar


2. Dismantling of lime concrete, like weathearing coarse.
3. Weathering course using concrete
4. Finishing the top of roof with one course of machine pressed tiles
5. Painting two coats of newly plastered wall surface with water based exterior
emulsion paint
6. Painting old iron works such as steel
7. Painting old wood works with two coats of best approved first quality

The necessary lumpsum provisions are made for centage @ 2% and labour welfare fund @ 1%The

current year schedule of rate for the year (2021-22) is adopted in the preparation of estimate.

(Effect from 13.09.2021)


``

LEAD STATEMENT

LEAD STATEMENT FOR THE YEAR 2021-2022 (EFFECTIVE FROM 13.9.2021)

S.NO NAME OF SOURCE UNIT DIST IN CONVEYANCE COST OF TOTAL COST


MATERIAL kMS CHARGES MATERIAL

1 Cement Local MT 0 0 5960.00 5960.00

2 Steel Local MT 0 0 51750.00 51750.00

3 Sand for mortar Vaduvanthangal M3 132 1013.50 447.00 1460.50

4 Sand for filling Vaduvanthangal M3 132 1013.50 447.00 1460.50

5 IInd class ground Thirumazhisai 1000 38 497.76 6435.00 6932.76


moulded chamfer NOS
burnt bricks of size
9”x4 3/8”x2 3/4”
6 Brick jelly 20mm Thirumazhisai M3 38 243.42 767.00 1010.42

7 Brick jelly 40mm Thirumazhisai M3 38 243.42 688.00 931.42

8 HBG stone jelly pallavaram M3 58 508.92 1432.00 1940.92


20mm

9 HBG stone jelly pallavaram M3 58 508.92 1029.00 1537.92


40mm

10 HBG stone jelly pallavaram M3 58 508.92 1329.00 1837.92


12mm

11 Machine pressed Red hills 1000 25 278.50 16106.00 16245.25


tiles 23x23x2cm NOS

12 Slaked and pollachi M3 458.00 2127.82 974.00 3101.82


screened burnt
lime stone

13 Cut stone suryanagaram M3 74 631.96 14000.00 14631.96


``

SUB DATA

S.NO QTY DESCRIPTION RATE PER AMOUNT

1 CEMENT MORTAR 1:1.5


960.00 CEMENT 5960.00 MT 5721.60
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 7282.10

2 CEMENT MORTAR 1:2


720.00 CEMENT 5960.00 MT 4291.20
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 5851.70

3 CEMENT MORTAR 1:3


480.00 CEMENT 5960.00 MT 2860.80
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 4421.30

4 CEMENT MORTAR 1:4


360.00 CEMENT 5960.00 MT 2145.60
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 3706.10

5 CEMENT MORTAR 1:5


288.00 CEMENT 5960.00 MT 1716.48
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 3277.00

6 CEMENT MORTAR 1:6


240.00 CEMENT 5960.00 MT 1430.40
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 2991.00
``

DATA

S.NO QTY PER DESCRIPTION RATE PER AMOUNT

1. 1.00 M2 Dismantling of one course of pressed tile 20.00 M2 20.00


roof finish in cement mortar
( As per S.R schedule IT no 38c page no 22 )

2. 1.00 M3 Dismantling of lime concrete like 278.00 M3 278.00


weathearing coarse.
( As per S.R schedule IT no 36 page no 22 )

3. Weathering course using concrete


broken brick jelly 20mm gauge in pure
slacked lime(no sand to be used) over RCC
Roof slab. The proportion of broken jelly to
slaked lime being 32:12.5 cft well beaten by
wooden beaters for giving required slope
and thickness requiredetc, .complying with
standard specification and as directed by
the departmental officers .

12.8 M3 Brick jelly 20mm 1010.42 M3 12933.38


5.00 M3 Unslakedpollachi lime 3101.82 M3 15509.10
1.80 Nos Mason 1st class 861.00 Each 1549.80
17.70 Nos Mazdoor cat-1 562.00 Each 9947.40
14.10 Nos Mazdoor cat-2 461.00 Each 6500.10
10 M2 46439.78
1 M2 4643.98

4. Finishing the top of roof with one course of


machine pressed tiles of size 23x23x2mm
of approved quality laid in cement mortar
1:3, mixed with 2% of water proofing
compound by weight of cement used and
pointed with same oiled mortar including
mixing of red oxide etc, complete.
complying with standard specification and
as directed by the departmental officers

Sub data for pointing- 10M2

0.04 M3 Cement mortar 1:3 4421.30 M3 176.85


2.2 Nos Mason 2nd class 804.00 Each 1768.80
0.5 Nos Mazdoor cat-1 562.00 Each 281.00
``

1.1 Nos Mazdoor cat-2 461.00 Each 507.10


0.384 kg Water proof compound 42.30 kg 16.24
10 M2 2750.00
For pointing 1 M2 275.00

189.00 Nos Pressed tiles23x23x2cm 16245.25 1000.00 3070.35


0.12 M3 Cement mortar 1:3 4421.30 M3 530.56
1.152 kg Water proof compound 42.30 kg 48.73
10.00 M2 Pointing with Cement mortar 1:3 275.00 M2 2750.00
1.10 Nos Mason 1st class 861.00 Each 947.10
2.10 Nos Mason 2nd class 804.00 Each 1688.40
2.20 Nos Mazdoor cat-1 562.00 Each 1236.40
1.10 Nos Mazdoor cat-2 461.00 Each 507.10
10 M2 10778.64
1 M2 1077.86

5. Painting two coats of newly plastered wall


surface with water based exterior emulsion
paint of first quality and of approved colour
over a priming coat including thorough
scrapping,clean removal of dirt,and
including necessary plaster of paris
putty,wherever required etc, complying
with standard specification

10.00 M2 Cleaning the plastered surface 6.65 M2 66.50


1.40 Litre Water based exterior emulsion 292.70 Litre 409.78
0.98 Litre primer 146.10 Litre 143.18
2.20 Nos Painter 1st class 688.00 Nos 1513.60
L.S Sundries for brushes, sand paper,plaster of L.S 6.94
paris putty, etc.
10 M2 2140.00
1 M2 214.00

6. Painting old iron works such as steel


doors,windows,ventilators,windowbars,bal
ustradesetc, with two coats of best
approved first quality and colour of
synthetic enamel paint including ordinary
scrapping using brushes and neat finishing
etc,complete. Complying with standard
specification .( The make,quality and colour
of paint should be got approved by the
executive engineer before use of works.

10.00 M2 Through scrapping 7.90 M2 79.00


``

1.89 lit Synthetic enamel paint fof iron 225.40 lit 426.00
1.11 Nos Painter/varnisher 1st class 688.00 Each 763.68
10 M2 1268.68
1 M2 126.90

7. Painting old wood works with two coats of


best approved first quality and colour of
synthetic enamel paint including ordinary
scrapping using brushes and neat finishing
etc,complete. Complying with standard
specification .( The make,quality and colour
of paint should be got approved by the
executive engineer before use of works.

10.00 M2 Through scrapping 12.50 M2 125.00


2.22 lit Synthetic enamel paint fof wood 236.60 lit 525.25
1.20 Nos Painter/varnisher 1st class 688.00 Each 825.60
10 M2 1475.85
1 M2 147.60
``

DETAILED ESTIMATE

S.NO DESCRIPTION NOS LEN BRD DEP CONTENTS

1. Dismantling of one course of pressed


tile roof finish in cement mortar

FOR REST MANDAPAM BUILDING

Total Terrace Area ( Flooring ) 1X1 23.95 9.60 - 229.92


Total Terrace Area ( Skirting ) 1x1 52.00 0.20 - 10.40
Deduct Head room Area 1X1 9.60 2.90 - (- ) 27.84
Deduct R.O Water plant Area 1x1 3.80 3.00 - (- ) 11.40

201.08 M2

2. Dismantling of lime concrete, like


weathearing coarse.

FOR REST MANDAPAM BUILDING

Total Terrace Area ( Flooring ) 1X1 23.95 9.60 0.15 34.49


Deduct Head room Area 1X1 9.60 2.90 0.15 (- ) 4.18
Deduct R.O Water plant Area 1x1 3.80 3.00 0.15 (- ) 1.71

28.60 M3

3. Weathering course using concrete


broken brick jelly 20mm gauge in pure
slacked lime(no sand to be used) over
RCC Roof slab. The proportion of
broken jelly to slaked lime being
32:12.5 cft well beaten by wooden
beaters for giving required slope and
thickness requiredetc, .complying with
standard specification and as directed
by the departmental officers .

FOR REST MANDAPAM BUILDING

Total Terrace Area ( Flooring ) 1X1 23.95 9.60 0.15 34.49


Deduct Head room Area 1X1 9.60 2.90 0.15 (- ) 4.18
Deduct R.O Water plant Area 1x1 3.80 3.00 0.15 (- ) 1.71

28.60 M3
``

4. Finishing the top of roof with one


course of machine pressed tiles of size
23x23x2mm of approved quality laid in
cement mortar 1:3, mixed with 2% of
water proofing compound by weight of
cement used and pointed with same
oiled mortar including mixing of red
oxide etc, complete. complying with
standard specification and as directed
by the departmental officers

FOR REST MANDAPAM BUILDING

Total Terrace Area ( Flooring ) 1X1 23.95 9.60 - 229.92


Total Terrace Area ( Skirting ) 1x1 52.00 0.20 - 10.40
Deduct Head room Area 1X1 9.60 2.90 - (- ) 27.84
Deduct R.O Water plant Area 1x1 3.80 3.00 - (- ) 11.40

201.08 M2

5. Painting two coats of newly plastered


wall surface with water based exterior
emulsion paint of first quality and of
approved colour over a priming coat
including thorough scrapping,clean
removal of dirt,and including necessary
plaster of paris putty,wherever
required etc, complying with standard
specification

FOR REST MANDAPAM BUILDING

Outer walls ( Alround ) 1x1 68.90 - 9.00 620.10


Column offsets 2x9 0.60 - 9.00 97.20
Head room( Alround ) 1x1 26.80 - 2.90 77.72
Sunshades of windows 2x16 2.25 - 1.00 72.00
(North & south sides)
Sunshades of windows 1x3 1.95 - 1.00 5.85
(North & south sides)
Through sunshades 1x2 23.95 - 1.50 71.85
(North & south sides)
Deduct windows open 2x16 1.80 - 1.35 (-) 77.76
Deduct Door open 1x3 1.50 - 2.40 (-)10.80
Inner walls ( Alround ) 1x2 67.10 - 3.15 422.73
Ground & 1ST floor
``

Head room( Alround ) 1x1 25.00 - 2.80 70.00


Ground & 1ST floor Ceiling 1x2 23.95 9.60 - 459.84
Roof beams 2x9 9.60 - 1.00 172.80
Deduct wall tile Area 1x2 64.20 - 2.10 (-)269.64
Ground & 1ST floor
Deduct windows open 2x16 1.80 - 1.35 (-) 77.76
Deduct Door open 1x3 1.50 - 2.40 (-)10.80

1623.33 M2

6. Painting old iron works such as steel


doors,windows,ventilators,windowbars
,balustradesetc, with two coats of best
approved first quality and colour of
synthetic enamel paint including
ordinary scrapping using brushes and
neat finishing etc,complete. Complying
with standard specification .( The
make,quality and colour of paint should
be got approved by the executive
engineer before use of works.

windows Grill 2x16 1.80 - 1.35 77.76 M2

7. Painting old wood works with two


coats of best approved first quality and
colour of synthetic enamel paint
including ordinary scrapping using
brushes and neat finishing
etc,complete. Complying with standard
specification .( The make,quality and
colour of paint should be got approved
by the executive engineer before use of
works.

Doors 1x3 1.50 - 2.40 10.80 M2


``

ABSTRACT ESTIMATE

S.NO QTY DESCRIPTION OF WORKS RATE PER AMOUNT

1. 201.08 Dismantling of one course of pressed tile roof finish in 20.00 M2 4022.00
cement mortar

2. 28.60 Dismantling of lime concrete, like weathearing coarse. 278.00 M3 7951.00

3. 28.60 Weathering course using concrete 4643.98 M3 132818.00


broken brick jelly 20mm gauge in pure slacked lime(no
sand to be used) over RCC Roof slab. The proportion of
broken jelly to slaked lime being 32:12.5 cft well beaten
by wooden beaters for giving required slope and
thickness requiredetc, .complying with standard
specification and as directed by the departmental
officers .

4. 201.08 Finishing the top of roof with one course of machine 1077.86 M2 216736.00
pressed tiles of size 23x23x2mm of approved quality laid
in cement mortar 1:3, mixed with 2% of water proofing
compound by weight of cement used and pointed with
same oiled mortar including mixing of red oxide etc,
complete. complying with standard specification and as
directed by the departmental officers

5. 1623.33 Painting two coats of newly plastered wall surface with 214.00 M2 347393.00
water based exterior emulsion paint of first quality and
of approved colour over a priming coat including
thorough scrapping,clean removal of dirt,and including
necessary plaster of paris putty,wherever required etc,
complying with standard specification

6. 77.76 Painting old iron works such as steel 126.90 M2 9868.00


doors,windows,ventilators,windowbars,balustradesetc,
with two coats of best approved first quality and colour
of synthetic enamel paint including ordinary scrapping
using brushes and neat finishing etc,complete.
Complying with standard specification .( The
make,quality and colour of paint should be got approved
by the executive engineer before use of works.

7. 10.80 Painting old wood works with two coats of best 147.60 M2 1594.00
approved first quality and colour of synthetic enamel
paint including ordinary scrapping using brushes and
neat finishing etc,complete. Complying with standard
``

specification .( The make,quality and colour of paint


should be got approved by the executive engineer
before use of works.

SUB TOTAL 720382.00

ADD GST 12% 86446.00

PROVISION FOR CENTAGE CHARGES 2 % 17000.00

PROVISION FOR LABOUR WELFARE FUND 1% 8500.00

PROVISION FOR UNFORSEEN ITEMS 17672.00

TOTAL 850000.00
``

ESTIMATE

NAME OF WORK : REPAIRS AND REPAINTING OF REST MANDAPAMFOR

ARULMIGU BHAVANI AMMAN THIRUKOVIL, PERIYAPALAYAM,

UTHUKOTTAI TALUK, THIRUVALLUR DISTRICT.

ESTIMATE AMOUNT : RS - 8.50 LAKHS


``

Report to accompany along with the estimate for the work of “ Repairs and Repaintingwork in

Rest Mandapam forArulmigu Bhavani Amman Thirukovil, Periyapalayam,

Uthukottai Taluk, Tiruvallur Dist.

Estimate Amount : RS – 8.50 Lakhs

IT has been proposed by the temple authorities to work of“Repairs and Repainting work in

Rest Mandapam forArulmigu Bhavani Amman Thirukovil, Periyapalayam,

Uthukottai Taluk, Tiruvallur Dist.

which an estimate is prepared . the estimate amount is RS – 8.50 Lakhs for the following are the

specification for the works.

1. Dismantling of one course of pressed tile roof finish in cement mortar


2. Dismantling of lime concrete, like weathearing coarse.
3. Weathering course using concrete
4. Finishing the top of roof with one course of machine pressed tiles
5. Painting two coats of newly plastered wall surface with water based
exterioremulsion paint
6. Painting old iron works such as steel
7. Painting old wood works with two coats of best approved first quality

The necessary lumpsum provisions are made for centage @ 2% and labour welfare fund @ 1%The

current year schedule of rate for the year (2021-22) is adopted in the preparation of estimate.

(Effect from 13.09.2021)


``

LEAD STATEMENT

LEAD STATEMENT FOR THE YEAR 2021-2022 (EFFECTIVE FROM 13.9.2021)

S.NO NAME OF SOURCE UNIT DIST IN CONVEYANCE COST OF TOTAL COST


MATERIAL kMS CHARGES MATERIAL

1 Cement Local MT 0 0 5960.00 5960.00

2 Steel Local MT 0 0 51750.00 51750.00

3 Sand for mortar Vaduvanthangal M3 132 1013.50 447.00 1460.50

4 Sand for filling Vaduvanthangal M3 132 1013.50 447.00 1460.50

5 IInd class ground Thirumazhisai 1000 38 497.76 6435.00 6932.76


moulded chamfer NOS
burnt bricks of size
9”x4 3/8”x2 3/4”

6 Brick jelly 20mm Thirumazhisai M3 38 243.42 767.00 1010.42

7 Brick jelly 40mm Thirumazhisai M3 38 243.42 688.00 931.42

8 HBG stone jelly pallavaram M3 58 508.92 1432.00 1940.92


20mm

9 HBG stone jelly pallavaram M3 58 508.92 1029.00 1537.92


40mm

10 HBG stone jelly pallavaram M3 58 508.92 1329.00 1837.92


12mm

11 Machine pressed Red hills 1000 25 278.50 16106.00 16245.25


tiles 23x23x2cm NOS

12 Slaked and pollachi M3 458.00 2127.82 974.00 3101.82


screened burnt
lime stone

13 Cut stone suryanagaram M3 74 631.96 14000.00 14631.96


``

SUB DATA

S.NO QTY DESCRIPTION RATE PER AMOUNT

1 CEMENT MORTAR 1:1.5


960.00 CEMENT 5960.00 MT 5721.60
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 7282.10

2 CEMENT MORTAR 1:2


720.00 CEMENT 5960.00 MT 4291.20
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 5851.70

3 CEMENT MORTAR 1:3


480.00 CEMENT 5960.00 MT 2860.80
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 4421.30

4 CEMENT MORTAR 1:4


360.00 CEMENT 5960.00 MT 2145.60
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 3706.10

5 CEMENT MORTAR 1:5


288.00 CEMENT 5960.00 MT 1716.48
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 3277.00

6 CEMENT MORTAR 1:6


240.00 CEMENT 5960.00 MT 1430.40
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 2991.00
``

DATA

S.NO QTY PER DESCRIPTION RATE PER AMOUNT

1. 1.00 M2 Dismantling of one course of pressed tile 20.00 M2 20.00


roof finish in cement mortar
( As per S.R schedule IT no 38c page no 22 )

2. 1.00 M3 Dismantling of lime concrete like 278.00 M3 278.00


weathearing coarse.
( As per S.R schedule IT no 36 page no 22 )

3. Weathering course using concrete


broken brick jelly 20mm gauge in pure
slacked lime(no sand to be used) over RCC
Roof slab. The proportion of broken jelly to
slaked lime being 32:12.5 cft well beaten by
wooden beaters for giving required slope
and thickness requiredetc, .complying with
standard specification and as directed by
the departmental officers .

12.8 M3 Brick jelly 20mm 1010.42 M3 12933.38


5.00 M3 Unslakedpollachi lime 3101.82 M3 15509.10
1.80 Nos Mason 1st class 861.00 Each 1549.80
17.70 Nos Mazdoor cat-1 562.00 Each 9947.40
14.10 Nos Mazdoor cat-2 461.00 Each 6500.10
10 M2 46439.78
1 M2 4643.98

4. Finishing the top of roof with one course of


machine pressed tiles of size 23x23x2mm
of approved quality laid in cement mortar
1:3, mixed with 2% of water proofing
compound by weight of cement used and
pointed with same oiled mortar including
mixing of red oxide etc, complete.
complying with standard specification and
as directed by the departmental officers

Sub data for pointing- 10M2

0.04 M3 Cement mortar 1:3 4421.30 M3 176.85


2.2 Nos Mason 2nd class 804.00 Each 1768.80
0.5 Nos Mazdoor cat-1 562.00 Each 281.00
``

1.1 Nos Mazdoor cat-2 461.00 Each 507.10


0.384 kg Water proof compound 42.30 kg 16.24
10 M2 2750.00
For pointing 1 M2 275.00

189.0 Nos Pressed tiles23x23x2cm 16245.25 1000. 3070.35


0 00
0.12 M3 Cement mortar 1:3 4421.30 M3 530.56
1.152 kg Water proof compound 42.30 kg 48.73
10.00 M2 Pointing with Cement mortar 1:3 275.00 M2 2750.00
1.10 Nos Mason 1st class 861.00 Each 947.10
2.10 Nos Mason 2nd class 804.00 Each 1688.40
2.20 Nos Mazdoor cat-1 562.00 Each 1236.40
1.10 Nos Mazdoor cat-2 461.00 Each 507.10
10 M2 10778.64
1 M2 1077.86

5. Scrapping the old cement plastering and


raking out the joints 20 mm deep and
Replastering with CM 1:5, 20mm thick
using river sand including curing, and
finishing neatly , complying with standard
specification and as directed by the
departmental officers etc.

10.00 M2 Scrapping the old cement plastering and 8.85 M2 88.50


raking out the joints 20 mm deep
0.22 M3 Cement mortar 1:5 3277.00 M3 720.94
2.20 Nos Mason 1st class 861.00 Each 1894.20
0.50 Nos Mazdoor cat-1 562.00 Each 281.00
3.20 Nos Mazdoor cat-2 461.00 Each 1475.20
Sundries 0.16
10 M2 4460.00
1 M2 446.00

6. - - Clearing the debris from site by jcb and - - LUMP


lorries.
``

DETAILED ESTIMATE

S.NO DESCRIPTION NOS LEN BRD DEP CONTENTS

1. Dismantling of one course of pressed


tile roof finish in cement mortar

FOR OUTER PRAHARA MANDAPAM

Total Terrace Outer Area 1 1X2 55.10 7.10 - 782.42


(North & south side)

Total Terrace Outer Area 2 1x2 31.55 7.10 - 448.01


(East & West side)

Invertered beam 1 1x4 15.60 - 0.20 12.48

Invertered beam 2 1x2 15.40 - 0.20 6.16

Invertered beam 3 1X2 17.20 - 0.20 6.90

Total Terrace Outer Area 1 1X1 201.70 - 0.20 40.34


(skirting)

Total Terrace Outer Area 2 1X1 144.90 - 0.20 28.98


(skirting)

1325.29 M2

2. Dismantling of lime concrete, like


weathearing coarse.

FOR OUTER PRAHARA MANDAPAM

Total Terrace Outer Area 1 1X2 55.10 7.10 0.12 93.89


(North & south side)

Total Terrace Outer Area 2 1x2 31.55 7.10 0.12 53.76


(East & West side)

Deduct Invertered beam 1 1x4 7.45 0.35 0.12 1.25 (-)

Deduct Invertered beam 2 1x2 7.35 0.35 0.12 0.62 (-)

DeductInvertered beam 3 1X2 8.25 0.35 0.12 0.69 (-)


``

145.09 M2

3. Weathering course using concrete


broken brick jelly 20mm gauge in pure
slacked lime(no sand to be used) over
RCC Roof slab. The proportion of
broken jelly to slaked lime being
32:12.5 cft well beaten by wooden
beaters for giving required slope and
thickness requiredetc, .complying with
standard specification and as directed
by the departmental officers .

FOR OUTER PRAHARA MANDAPAM

Total Terrace Outer Area 1 1X2 55.10 7.10 0.12 93.89


(North & south side)

Total Terrace Outer Area 2 1x2 31.55 7.10 0.12 53.76


(East & West side)

Deduct Invertered beam 1 1x4 7.45 0.35 0.12 1.25 (-)

Deduct Invertered beam 2 1x2 7.35 0.35 0.12 0.62 (-)

Deduct Invertered beam 3 1X2 8.25 0.35 0.12 0.69 (-)

145.09 M2

4. Finishing the top of roof with one


course of machine pressed tiles of size
23x23x2mm of approved quality laid in
cement mortar 1:3, mixed with 2% of
water proofing compound by weight of
cement used and pointed with same
oiled mortar including mixing of red
oxide etc, complete. complying with
standard specification and as directed
by the departmental officers

FOR OUTER PRAHARA MANDAPAM

Total Terrace Outer Area 1 1X2 55.10 7.10 - 782.42


(North & south side)
``

Total Terrace Outer Area 2 1x2 31.55 7.10 - 448.01


(East & West side)
Invertered beam 1 1x4 15.60 - 0.20 12.48

Invertered beam 2 1x2 15.40 - 0.20 6.16

Invertered beam 3 1X2 17.20 - 0.20 6.90

Total Terrace Outer Area 1 1X1 201.70 - 0.20 40.34


(skirting)

Total Terrace Outer Area 2 1X1 144.90 - 0.20 28.98


(skirting)

1325.29 M2

5. Scrapping the old cement plastering


and raking out the joints 20 mm deep
and Replastering with CM 1:5, 20mm
thick using river sand including curing,
and finishing neatly , complying with
standard specification and as directed
by the departmental officers etc.

FOR OUTER PRAHARA MANDAPAM

Total Terrace Outer Area 1 1X1 201.70 - 1.10 221.87


( PARAPET WALL )

Total Terrace Outer Area 2 1X1 144.90 - 1.10 159.39


( PARAPET WALL )

381.26 M2

6. Clearing the debris from site by jcb and - - - - LUMPSUM


lorries.
``

ABSTRACT ESTIMATE

S.NO QTY DESCRIPTION OF WORKS RATE PER AMOUNT

1. 1325.29 Dismantling of one course of pressed tile roof finish in 20.00 M2 26506.00
cement mortar

2. 145.09 Dismantling of lime concrete, like weathearing coarse. 278.00 M3 40335.00

3. 145.09 Weathering course using concrete 4643.98 M3 673795.00


broken brick jelly 20mm gauge in pure slacked lime(no
sand to be used) over RCC Roof slab. The proportion of
broken jelly to slaked lime being 32:12.5 cft well beaten
by wooden beaters for giving required slope and
thickness requiredetc, .complying with standard
specification and as directed by the departmental
officers .

4. 1325.29 Finishing the top of roof with one course of machine 1077.86 M2 1428477.00
pressed tiles of size 23x23x2mm of approved quality laid
in cement mortar 1:3, mixed with 2% of water proofing
same oiled mortar including mixing of red oxide etc,
complete. complying with standard specification and as
directed by the departmental officers

5. 381.26 Scrapping the old cement plastering and raking out the 446.00 M2 170042.00
joints 20 mm deep and Replastering with CM 1:5,
20mm thick using river sand including curing, and
finishing neatly , complying with standard specification
and as directed by the departmental officers etc.

6. 1.NO Clearing the debris from site by jcb and lorries 1.NO LUM 200000.00

SUB TOTAL 2539155.00

ADD GST 12% 304699.00

PROVISION FOR CENTAGE CHARGES 2 % 62000.00

PROVISION FOR LABOUR WELFARE FUND 1% 31000.00

PROVISION FOR ADVERTISEMENT CHARGES 100000.00

PROVISION FOR UNFORSEEN ITEMS 63146.00


``

TOTAL 3100000.00

ESTIMATE

NAME OF WORK : REPAIRS FOR THE LEAKY TERRACE AT OUTER PRAHARAM FOR

ARULMIGU BHAVANI AMMAN THIRUKOVIL, PERIYAPALAYAM,

UTHUKOTTAI TALUK, THIRUVALLUR DISTRICT.

ESTIMATE AMOUNT : RS - 31.00 LAKHS


``

Report to accompany along with the estimate for the work of “ Repairs for the leaky Terrace work at

Outerpraharam forArulmigu Bhavani Amman Thirukovil, Periyapalayam,

Uthukottai Taluk, Tiruvallur Dist.

Estimate Amount : RS – 31.00 Lakhs

IT has been proposed by the temple authorities to work of“Repairs for the leaky Terrace work at

Outerpraharam forArulmigu Bhavani Amman Thirukovil, Periyapalayam,

Uthukottai Taluk, Tiruvallur Dist.

which an estimate is prepared . the estimate amount is RS – 31.00 Lakhs for the following are the

specification for the works.

1. Dismantling of one course of pressed tile roof finish in cement mortar


2. Dismantling of lime concrete, like weathearing coarse.
3. Weathering course using concrete
4. Finishing the top of roof with one course of machine pressed tiles
5. Scrapping the old cement plastering and raking out the joints 20 mm deep and
Replastering
6. Clearing the debris from site by jcb and lorries

The necessary lumpsum provisions are made for centage @ 2% and labour welfare fund @ 1%The

current year schedule of rate for the year (2021-22) is adopted in the preparation of estimate.

(Effect from 13.09.2021)


``

LEAD STATEMENT

LEAD STATEMENT FOR THE YEAR 2021-2022 (EFFECTIVE FROM 13.9.2021)

S.NO NAME OF SOURCE UNIT DIST IN CONVEYANCE COST OF TOTAL COST


MATERIAL kMS CHARGES MATERIAL

1 Cement Local MT 0 0 5960.00 5960.00

2 Steel Local MT 0 0 51750.00 51750.00

3 Sand for mortar Vaduvanthangal M3 132 1013.50 447.00 1460.50

4 Sand for filling Vaduvanthangal M3 132 1013.50 447.00 1460.50

5 IInd class ground Thirumazhisai 1000 38 497.76 6435.00 6932.76


moulded chamfer NOS
burnt bricks of size
9”x4 3/8”x2 3/4”
6 Brick jelly 20mm Thirumazhisai M3 38 243.42 767.00 1010.42

7 Brick jelly 40mm Thirumazhisai M3 38 243.42 688.00 931.42

8 HBG stone jelly pallavaram M3 58 508.92 1432.00 1940.92


20mm

9 HBG stone jelly pallavaram M3 58 508.92 1029.00 1537.92


40mm

10 HBG stone jelly pallavaram M3 58 508.92 1329.00 1837.92


12mm

11 Machine pressed Red hills 1000 25 278.50 16106.00 16245.25


tiles 23x23x2cm NOS

12 Slaked and pollachi M3 458.00 2127.82 974.00 3101.82


screened burnt
lime stone

13 Cut stone suryanagaram M3 74 631.96 14000.00 14631.96


``

SUB DATA

S.NO QTY DESCRIPTION RATE PER AMOUNT

1 CEMENT MORTAR 1:1.5


960.00 CEMENT 5960.00 MT 5721.60
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 7282.10

2 CEMENT MORTAR 1:2


720.00 CEMENT 5960.00 MT 4291.20
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 5851.70

3 CEMENT MORTAR 1:3


480.00 CEMENT 5960.00 MT 2860.80
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 4421.30

4 CEMENT MORTAR 1:4


360.00 CEMENT 5960.00 MT 2145.60
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 3706.10

5 CEMENT MORTAR 1:5


288.00 CEMENT 5960.00 MT 1716.48
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 3277.00

6 CEMENT MORTAR 1:6


240.00 CEMENT 5960.00 MT 1430.40
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 2991.00
``

DATA

S.NO QTY PER DESCRIPTION RATE PER AMOUNT

1. 1.00 M2 Dismantling of one course of pressed tile 20.00 M2 20.00


roof finish in cement mortar
( As per S.R schedule IT no 38c page no 22 )

2. 1.00 M3 Dismantling of lime concrete like 278.00 M3 278.00


weathearing coarse.
( As per S.R schedule IT no 36 page no 22 )

3. Weathering course using concrete


broken brick jelly 20mm gauge in pure
slacked lime(no sand to be used) over RCC
Roof slab. The proportion of broken jelly to
slaked lime being 32:12.5 cft well beaten by
wooden beaters for giving required slope
and thickness requiredetc, .complying with
standard specification and as directed by
the departmental officers .

12.8 M3 Brick jelly 20mm 1010.42 M3 12933.38


5.00 M3 Unslakedpollachi lime 3101.82 M3 15509.10
1.80 Nos Mason 1st class 861.00 Each 1549.80
17.70 Nos Mazdoor cat-1 562.00 Each 9947.40
14.10 Nos Mazdoor cat-2 461.00 Each 6500.10
10 M2 46439.78
1 M2 4643.98

4. Finishing the top of roof with one course of


machine pressed tiles of size 23x23x2mm
of approved quality laid in cement mortar
1:3, mixed with 2% of water proofing
compound by weight of cement used and
pointed with same oiled mortar including
mixing of red oxide etc, complete.
complying with standard specification and
as directed by the departmental officers

Sub data for pointing- 10M2

0.04 M3 Cement mortar 1:3 4421.30 M3 176.85


2.2 Nos Mason 2nd class 804.00 Each 1768.80
0.5 Nos Mazdoor cat-1 562.00 Each 281.00
``

1.1 Nos Mazdoor cat-2 461.00 Each 507.10


0.384 kg Water proof compound 42.30 kg 16.24
10 M2 2750.00
For pointing 1 M2 275.00

189.0 Nos Pressed tiles23x23x2cm 16245.25 1000. 3070.35


0 00
0.12 M3 Cement mortar 1:3 4421.30 M3 530.56
1.152 kg Water proof compound 42.30 kg 48.73
10.00 M2 Pointing with Cement mortar 1:3 275.00 M2 2750.00
1.10 Nos Mason 1st class 861.00 Each 947.10
2.10 Nos Mason 2nd class 804.00 Each 1688.40
2.20 Nos Mazdoor cat-1 562.00 Each 1236.40
1.10 Nos Mazdoor cat-2 461.00 Each 507.10
10 M2 10778.64
1 M2 1077.86

5. Scrapping the old cement plastering and


raking out the joints 20 mm deep and
Replastering with CM 1:5, 20mm thick
using river sand including curing, and
finishing neatly , complying with standard
specification and as directed by the
departmental officers etc.

10.00 M2 Scrapping the old cement plastering and 8.85 M2 88.50


raking out the joints 20 mm deep
0.22 M3 Cement mortar 1:5 3277.00 M3 720.94
2.20 Nos Mason 1st class 861.00 Each 1894.20
0.50 Nos Mazdoor cat-1 562.00 Each 281.00
3.20 Nos Mazdoor cat-2 461.00 Each 1475.20
Sundries 0.16
10 M2 4460.00
1 M2 446.00

6. - - Clearing the debris from site by jcb and - - LUMP


lorries.
``

DETAILED ESTIMATE

S.NO DESCRIPTION NOS LEN BRD DEP CONTENTS

1. Dismantling of one course of pressed


tile roof finish in cement mortar

FOR INNER PRAHARA MANDAPAM

(North & south side flooring)

Part 1 1X2 5.50 5.45 - 59.95

Part 2 1X2 5.45 2.25 - 24.53

Part 3 1X2 5.45 2.90 - 31.61

Part 4 1X2 5.45 2.50 - 27.25

Part 5 1X2 5.45 3.10 - 33.79

Part 6 1X2 5.45 2.85 - 31.07

Part 7 1X2 5.45 2.30 - 25.07

Part 8 1X2 5.45 4.85 - 52.87

(East side flooring)

Part 1 1X1 4.85 2.55 - 12.37

Part 2 1X1 4.85 3.30 - 16.00

Part 3 1X1 4.85 2.60 - 12.61

(West side flooring)

Part 1 1X1 5.50 2.55 - 14.03

Part 2 1X1 5.50 3.30 - 12.65

Part 3 1X1 5.50 2.60 - 14.30

Middle portion flooring 1X1 17.50 9.10 - 159.25


``

Deduct vimanam 1X1 3.40 2.55 - 8.67 (-)

(North & south side skirting)

Part 1 1x2 21.90 - 0.20 8.76

Part 2 1x2 15.40 - 0.20 6.16

Part 3 1x2 16.70 - 0.20 6.68

Part 4 1x2 15.90 - 0.20 6.36

Part 5 1x2 17.10 - 0.20 6.84

Part 6 1x2 16.60 - 0.20 6.64

Part 7 1x2 7.75 - 0.20 3.10

Part 8 1x2 10.30 - 0.20 4.12

(East side skirting)

Part 1 1X1 14.80 - 0.20 2.96

Part 2 1X1 16.30 - 0.20 3.26

Part 3 1X1 14.90 - 0.20 2.98

(West side skirting)

Part 1 1X1 16.10 - 0.20 3.22

Part 2 1X1 15.60 - 0.20 3.12

Part 3 1X1 16.20 - 0.20 3.24

Middle portion skirting 1x1 53.20 - 0.20 10.64

For Mahamandapam 1X2 12.60 - 0.20 5.04

601.80 M2

2. Dismantling of lime concrete, like


weathearing coarse.

FOR INNER PRAHARA MANDAPAM


``

(North & south side flooring)

Part 1 1X2 5.50 5.45 0.12 7.19

Part 2 1X2 5.45 2.25 0.12 2.94

Part 3 1X2 5.45 2.90 0.12 3.79

Part 4 1X2 5.45 2.50 0.12 3.27

Part 5 1X2 5.45 3.10 0.12 4.05

Part 6 1X2 5.45 2.85 0.12 3.73

Part 7 1X2 5.45 2.30 0.12 3.01

Part 8 1X2 5.45 4.85 0.12 6.34

(East side flooring)

Part 1 1X1 4.85 2.55 0.12 1.48

Part 2 1X1 4.85 3.30 0.12 1.92

Part 3 1X1 4.85 2.60 0.12 1.51

(West side flooring)

Part 1 1X1 5.50 2.55 0.12 1.68

Part 2 1X1 5.50 3.30 0.12 2.18

Part 3 1X1 5.50 2.60 0.12 1.72

Middle portion flooring 1X1 17.50 9.10 0.12 19.11

Deduct vimanam 1X1 3.40 2.55 0.12 1.04 (-)

62.88 M3

3. Weathering course using concrete


broken brick jelly 20mm gauge in pure
slacked lime(no sand to be used) over
RCC Roof slab. The proportion of
broken jelly to slaked lime being
32:12.5 cft well beaten by wooden
beaters for giving required slope and
``

standard specification and as directed


by the departmental officers .
FOR INNER PRAHARA MANDAPAM

(North & south side flooring)

Part 1 1X2 5.50 5.45 0.12 7.19

Part 2 1X2 5.45 2.25 0.12 2.94

Part 3 1X2 5.45 2.90 0.12 3.79

Part 4 1X2 5.45 2.50 0.12 3.27

Part 5 1X2 5.45 3.10 0.12 4.05

Part 6 1X2 5.45 2.85 0.12 3.73

Part 7 1X2 5.45 2.30 0.12 3.01

Part 8 1X2 5.45 4.85 0.12 6.34

(East side flooring)

Part 1 1X1 4.85 2.55 0.12 1.48

Part 2 1X1 4.85 3.30 0.12 1.92

Part 3 1X1 4.85 2.60 0.12 1.51

(West side flooring)

Part 1 1X1 5.50 2.55 0.12 1.68

Part 2 1X1 5.50 3.30 0.12 2.18

Part 3 1X1 5.50 2.60 0.12 1.72

Middle portion flooring 1X1 17.50 9.10 0.12 19.11

Deduct vimanam 1X1 3.40 2.55 0.12 1.04 (-)

62.88 M3

4. Finishing the top of roof with one


course of machine pressed tiles of size
23x23x2mm of approved quality laid in
``

cement mortar 1:3, mixed with 2% of


water proofing compound by weight of
cement used and pointed with same
oiled mortar including mixing of red
oxide etc, complete. complying with
standard specification and as directed
by the departmental officers

FOR INNER PRAHARA MANDAPAM

(North & south side flooring)

Part 1 1X2 5.50 5.45 - 59.95

Part 2 1X2 5.45 2.25 - 24.53

Part 3 1X2 5.45 2.90 - 31.61

Part 4 1X2 5.45 2.50 - 27.25

Part 5 1X2 5.45 3.10 - 33.79

Part 6 1X2 5.45 2.85 - 31.07

Part 7 1X2 5.45 2.30 - 25.07

Part 8 1X2 5.45 4.85 - 52.87

(East side flooring)

Part 1 1X1 4.85 2.55 - 12.37

Part 2 1X1 4.85 3.30 - 16.00

Part 3 1X1 4.85 2.60 - 12.61

(West side flooring)

Part 1 1X1 5.50 2.55 - 14.03

Part 2 1X1 5.50 3.30 - 12.65

Part 3 1X1 5.50 2.60 - 14.30

Middle portion flooring 1X1 17.50 9.10 - 159.25

Deduct vimanam 1X1 3.40 2.55 - 8.67 (-)


``

(North & south side skirting)

Part 1 1x2 21.90 - 0.20 8.76

Part 2 1x2 15.40 - 0.20 6.16

Part 3 1x2 16.70 - 0.20 6.68

Part 4 1x2 15.90 - 0.20 6.36

Part 5 1x2 17.10 - 0.20 6.84

Part 6 1x2 16.60 - 0.20 6.64

Part 7 1x2 7.75 - 0.20 3.10

Part 8 1x2 10.30 - 0.20 4.12

(East side skirting)

Part 1 1X1 14.80 - 0.20 2.96

Part 2 1X1 16.30 - 0.20 3.26

Part 3 1X1 14.90 - 0.20 2.98

(West side skirting)

Part 1 1X1 16.10 - 0.20 3.22

Part 2 1X1 15.60 - 0.20 3.12

Part 3 1X1 16.20 - 0.20 3.24

Middle portion skirting 1x1 53.20 - 0.20 10.64

For Mahamandapam 1X2 12.60 - 0.20 5.04

601.80 M2

5. Scrapping the old cement plastering


and raking out the joints 20 mm deep
and Replastering with CM 1:5, 12mm
thick using river sand including curing,
and finishing neatly , complying with
``

standard specification and as directed


by the departmental officers etc.
( PARAPET WALL Area 1 ) 1X4 27.00 - 0.73 78.84

( PARAPET WALL Area 2 ) 1X4 20.50 - 0.73 59.86

Middle portion 1x1 53.20 - 0.73 38.84

177.54 M2

6. Clearing the debris from site by jcb and - - - - LUMPSUM


lorries.
``

ABSTRACT ESTIMATE

S.NO QTY DESCRIPTION OF WORKS RATE PER AMOUNT

1. 601.80 Dismantling of one course of pressed tile roof finish in 20.00 M2 12036.00
cement mortar

2. 62.88 Dismantling of lime concrete, like weathearing coarse. 278.00 M3 17481.00

3. 62.88 Weathering course using concrete 4643.98 M3 292013.00


broken brick jelly 20mm gauge in pure slacked lime(no
sand to be used) over RCC Roof slab. The proportion of
broken jelly to slaked lime being 32:12.5 cft well beaten
by wooden beaters for giving required slope and
thickness requiredetc, .complying with standard
specification and as directed by the departmental
officers .

4. 601.80 Finishing the top of roof with one course of machine 1077.86 M2 648656.00
pressed tiles of size 23x23x2mm of approved quality laid
in cement mortar 1:3, mixed with 2% of water proofing
same oiled mortar including mixing of red oxide etc,
complete. complying with standard specification and as
directed by the departmental officers

5. 177.54 Scrapping the old cement plastering and raking out the 446.00 M2 79183.00
joints 20 mm deep and Replastering with CM 1:5,
20mm thick using river sand including curing, and
finishing neatly , complying with standard specification
and as directed by the departmental officers etc.

6. 1.NO Clearing the debris from site by jcb and lorries 1.NO LUM 100000.00

SUB TOTAL 1149369.00

ADD GST 12% 137924.00

PROVISION FOR CENTAGE CHARGES 2 % 28000.00

PROVISION FOR LABOUR WELFARE FUND 1% 14000.00

PROVISION FOR ADVERTISEMENT CHARGES 50000.00


``

PROVISION FOR UNFORSEEN ITEMS 20707.00

TOTAL 1400000.00

ESTIMATE
``

NAME OF WORK : REPAIRS FOR THE LEAKY TERRACE AT INNER PRAHARAM OF AMBAL SANNIDHI FOR

ARULMIGU BHAVANIAMMAN THIRUKOVIL, PERIYAPALAYAM,

UTHUKOTTAI TALUK, THIRUVALLUR DISTRICT.

ESTIMATE AMOUNT : RS - 14.00 LAKHS

Report to accompany along with the estimate for the work of “ Repairs for the leaky terrace at Inner

praharam of Ambal sannidhi forArulmigu Bhavani Amman Thirukovil, Periyapalayam,

Uthukottai Taluk, Tiruvallur Dist.

Estimate Amount : RS – 14.00 Lakhs

IT has been proposed by the temple authorities to work of“Repairs for the leaky terrace at Inner

praharam of Ambal sannidhi forArulmigu Bhavani Amman Thirukovil, Periyapalayam


``

Uthukottai Taluk, Tiruvallur Dist.

which an estimate is prepared . the estimate amount is RS – 14.00 Lakhs for the following are the

specification for the works.

1. Dismantling of one course of pressed tile roof finish in cement mortar


2. Dismantling of lime concrete, like weathearing coarse.
3. Weathering course using concrete
4. Finishing the top of roof with one course of machine pressed tiles
5. Scrapping the old cement plastering and raking out the joints 20 mm deep and
Replastering
6. Clearing the debris from site by jcb and lorries

The necessary lumpsum provisions are made for centage @ 2% and labour welfare fund @ 1%The

current year schedule of rate for the year (2021-22) is adopted in the preparation of estimate.

(Effect from 13.09.2021)


``

LEAD STATEMENT

LEAD STATEMENT FOR THE YEAR 2021-2022 (EFFECTIVE FROM 13.9.2021)

S.NO NAME OF SOURCE UNIT DIST IN CONVEYANCE COST OF TOTAL COST


MATERIAL kMS CHARGES MATERIAL

1 Cement Local MT 0 0 5960.00 5960.00

2 Steel Local MT 0 0 51750.00 51750.00

3 Sand for mortar Vaduvanthangal M3 132 1013.50 447.00 1460.50

4 Sand for filling Vaduvanthangal M3 132 1013.50 447.00 1460.50

5 IInd class ground Thirumazhisai 1000 38 497.76 6435.00 6932.76


moulded chamfer NOS
burnt bricks of size
9”x4 3/8”x2 3/4”
6 Brick jelly 20mm Thirumazhisai M3 38 243.42 767.00 1010.42

7 Brick jelly 40mm Thirumazhisai M3 38 243.42 688.00 931.42

8 HBG stone jelly pallavaram M3 58 508.92 1432.00 1940.92


20mm

9 HBG stone jelly pallavaram M3 58 508.92 1029.00 1537.92


40mm

10 HBG stone jelly pallavaram M3 58 508.92 1329.00 1837.92


12mm

11 Machine pressed Red hills 1000 25 278.50 16106.00 16245.25


tiles 23x23x2cm NOS

12 Slaked and pollachi M3 458.00 2127.82 974.00 3101.82


screened burnt
lime stone

13 Cut stone suryanagaram M3 74 631.96 14000.00 14631.96


``

SUB DATA

S.NO QTY DESCRIPTION RATE PER AMOUNT

1 CEMENT MORTAR 1:1.5


960.00 CEMENT 5960.00 MT 5721.60
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 7282.10

2 CEMENT MORTAR 1:2


720.00 CEMENT 5960.00 MT 4291.20
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 5851.70

3 CEMENT MORTAR 1:3


480.00 CEMENT 5960.00 MT 2860.80
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 4421.30

4 CEMENT MORTAR 1:4


360.00 CEMENT 5960.00 MT 2145.60
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 3706.10

5 CEMENT MORTAR 1:5


288.00 CEMENT 5960.00 MT 1716.48
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 3277.00

6 CEMENT MORTAR 1:6


240.00 CEMENT 5960.00 MT 1430.40
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 2991.00
``

DATA

S.NO QTY PER DESCRIPTION RATE PER AMOUNT

1. 1.00 M2 Dismantling of one course of pressed tile 20.00 M2 20.00


roof finish in cement mortar
( As per S.R schedule IT no 38c page no 22 )

2. 1.00 M3 Dismantling of lime concrete like 278.00 M3 278.00


weathearing coarse.
( As per S.R schedule IT no 36 page no 22 )

3. Weathering course using concrete


broken brick jelly 20mm gauge in pure
slacked lime(no sand to be used) over RCC
Roof slab. The proportion of broken jelly to
slaked lime being 32:12.5 cft well beaten by
wooden beaters for giving required slope
and thickness requiredetc, .complying with
standard specification and as directed by
the departmental officers .

12.8 M3 Brick jelly 20mm 1010.42 M3 12933.38


5.00 M3 Unslakedpollachi lime 3101.82 M3 15509.10
1.80 Nos Mason 1st class 861.00 Each 1549.80
17.70 Nos Mazdoor cat-1 562.00 Each 9947.40
14.10 Nos Mazdoor cat-2 461.00 Each 6500.10
10 M2 46439.78
1 M2 4643.98

4. Finishing the top of roof with one course of


machine pressed tiles of size 23x23x2mm
of approved quality laid in cement mortar
1:3, mixed with 2% of water proofing
compound by weight of cement used and
pointed with same oiled mortar including
mixing of red oxide etc, complete.
complying with standard specification and
as directed by the departmental officers

Sub data for pointing- 10M2

0.04 M3 Cement mortar 1:3 4421.30 M3 176.85


2.2 Nos Mason 2nd class 804.00 Each 1768.80
0.5 Nos Mazdoor cat-1 562.00 Each 281.00
1.1 Nos Mazdoor cat-2 461.00 Each 507.10
0.384 kg Water proof compound 42.30 kg 16.24
``

10 M2 2750.00
For pointing 1 M2 275.00

189.0 Nos Pressed tiles23x23x2cm 16245.25 1000. 3070.35


0 00
0.12 M3 Cement mortar 1:3 4421.30 M3 530.56
1.152 kg Water proof compound 42.30 kg 48.73
10.00 M2 Pointing with Cement mortar 1:3 275.00 M2 2750.00
1.10 Nos Mason 1st class 861.00 Each 947.10
2.10 Nos Mason 2nd class 804.00 Each 1688.40
2.20 Nos Mazdoor cat-1 562.00 Each 1236.40
1.10 Nos Mazdoor cat-2 461.00 Each 507.10
10 M2 10778.64
1 M2 1077.86

5. - - Clearing the debris from site by jcb and - - LUMP


lorries.
``

DETAILED ESTIMATE

S.NO DESCRIPTION NOS LEN BRD DEP CONTENTS

1. Dismantling of one course of pressed


tile roof finish in cement mortar

Roof over oyyaali Mandapam 1x1 107.00 2.60 - 278.20


(Alround 4 Sides)

Deduct East Rajagopuram 1x1 7.09 2.60 - 18.43 (-)

Deduct South Rajagopuram 1x1 5.72 2.60 - 14.87 (-)

Deduct West Rajagopuram 1x1 5.72 2.60 - 14.87 (-)

Deduct North Rajagopuram 1x1 5.72 2.60 - 14.87 (-)

215.16 M2

2. Dismantling of lime concrete like


weathearing coarse.

Roof over oyyaali Mandapam 1x1 107.00 2.60 0.15 41.73


(Alround 4 Sides)

Deduct East Rajagopuram 1x1 7.09 2.60 0.15 2.77 (-)

Deduct South Rajagopuram 1x1 5.72 2.60 0.15 2.23 (-)

Deduct West Rajagopuram 1x1 5.72 2.60 0.15 2.23 (-)

Deduct North Rajagopuram 1x1 5.72 2.60 0.15 2.23 (-)

32.27 M3

3. Weathering course using concrete


broken brick jelly 20mm gauge in pure
slacked lime(no sand to be used) over
RCC Roof slab. The proportion of
broken jelly to slaked lime being
32:12.5 cft well beaten by wooden
beaters for giving required slope and
thickness requiredetc, .complying with
standard specification and as directed
by the departmental officers .
``

Roof over oyyaali Mandapam 1x1 107.00 2.60 0.15 41.73


(Alround 4 Sides)

Deduct East Rajagopuram 1x1 7.09 2.60 0.15 2.77 (-)

Deduct South Rajagopuram 1x1 5.72 2.60 0.15 2.23 (-)

Deduct West Rajagopuram 1x1 5.72 2.60 0.15 2.23 (-)

Deduct North Rajagopuram 1x1 5.72 2.60 0.15 2.23 (-)

32.27 M3

4. Finishing the top of roof with one


course of machine pressed tiles of size
23x23x2mm of approved quality laid in
cement mortar 1:3, mixed with 2% of
water proofing compound by weight of
cement used and pointed with same
oiled mortar including mixing of red
oxide etc, complete. complying with
standard specification and as directed
by the departmental officers

Roof over oyyaali Mandapam 1x1 107.00 2.60 - 278.20


(Alround 4 Sides)

Deduct East Rajagopuram 1x1 7.09 2.60 - 18.43 (-)

Deduct South Rajagopuram 1x1 5.72 2.60 - 14.87 (-)

Deduct West Rajagopuram 1x1 5.72 2.60 - 14.87 (-)

Deduct North Rajagopuram 1x1 5.72 2.60 - 14.87 (-)

215.16 M2

5. Clearing the debris from site by jcb and - - - - LUMP


lorries.
``

ABSTRACT ESTIMATE

S.NO QTY DESCRIPTION OF WORKS RATE PER AMOUNT

1. 215.16 Dismantling of one course of pressed tile roof finish in 20.00 M2 4303.00
cement mortar

2. 32.27 Dismantling of lime concrete, like weathearing coarse. 278.00 M3 8971.00

3. 32.27 Weathering course using concrete 4643.98 M3 149861.00


broken brick jelly 20mm gauge in pure slacked lime(no
sand to be used) over RCC Roof slab. The proportion of
broken jelly to slaked lime being 32:12.5 cft well beaten
by wooden beaters for giving required slope and
thickness requiredetc, .complying with standard
specification and as directed by the departmental
officers .

4. 215.16 Finishing the top of roof with one course of machine 1077.86 M2 242691.00
pressed tiles of size 23x23x2mm of approved quality laid
in cement mortar 1:3, mixed with 2% of water proofing
same oiled mortar including mixing of red oxide etc,
complete. complying with standard specification and as
directed by the departmental officers

5. 1.NO Clearing the debris from site by jcb and lorries 1.NO LUM 20000.00

SUB TOTAL 425826.00

ADD GST 12% 51099.00

PROVISION FOR CENTAGE CHARGES 2 % 9900.00

PROVISION FOR LABOUR WELFARE FUND 1% 4950.00

PROVISION FOR UNFORSEEN ITEMS 3225.00

TOTAL 495000.00
``

ESTIMATE

NAME OF WORK : REPAIRS FOR THE LEAKY TERRACE AT OYYAALI MANDAPAM

( INNER PRAHARA MANDAPAM LOW ROOF PORTION)FOR

ARULMIGU BHAVANI AMMAN THIRUKOVIL, PERIYAPALAYAM,

UTHUKOTTAI TALUK, THIRUVALLUR DISTRICT.

ESTIMATE AMOUNT : RS - 4.95 LAKHS


``

Report to accompany along with the estimate for the work of “ Repairs for the leaky terrace at

oyyaali mandapam ( Inner prahara mandapam low roof portion)

For Arulmigu Bhavani Amman Thirukovil, Periyapalayam,

Uthukottai Taluk, Tiruvallur Dist.

Estimate Amount : RS – 4.95 Lakhs

IT has been proposed by the temple authorities to work of“Repairs for the leaky terrace at

oyyaali mandapam ( Inner prahara mandapam low roof portion)

For Arulmigu Bhavani Amman Thirukovil, Periyapalayam,

Uthukottai Taluk, Tiruvallur Dist.

which an estimate is prepared . the estimate amount is RS – 4.95 Lakhs for the following are the

specification for the works.

1. Dismantling of one course of pressed tile roof finish in cement mortar


2. Dismantling of lime concrete, like weathearing coarse.
3. Weathering course using concrete
4. Finishing the top of roof with one course of machine pressed tiles
5. Clearing the debris from site by jcb and lorries

The necessary lumpsum provisions are made for centage @ 2% and labour welfare fund @ 1%The

current year schedule of rate for the year (2021-22) is adopted in the preparation of estimate.

(Effect from 13.09.2021)


``
``

LEAD STATEMENT

LEAD STATEMENT FOR THE YEAR 2021-2022 (EFFECTIVE FROM 13.9.2021)

S.NO NAME OF SOURCE UNIT DIST IN CONVEYANCE COST OF TOTAL COST


MATERIAL kMS CHARGES MATERIAL

1 Cement Local MT 0 0 5960.00 5960.00

2 Steel Local MT 0 0 51750.00 51750.00

3 Sand for mortar Vaduvanthangal M3 132 1013.50 447.00 1460.50

4 Sand for filling Vaduvanthangal M3 132 1013.50 447.00 1460.50

5 IInd class ground Thirumazhisai 1000 38 497.76 6435.00 6932.76


moulded chamfer NOS
burnt bricks of size
9”x4 3/8”x2 3/4”

6 Brick jelly 20mm Thirumazhisai M3 38 243.42 767.00 1010.42

7 Brick jelly 40mm Thirumazhisai M3 38 243.42 688.00 931.42

8 HBG stone jelly pallavaram M3 58 508.92 1432.00 1940.92


20mm

9 HBG stone jelly pallavaram M3 58 508.92 1029.00 1537.92


40mm

10 HBG stone jelly pallavaram M3 58 508.92 1329.00 1837.92


12mm

11 Machine pressed Red hills 1000 25 278.50 16106.00 16245.25


tiles 23x23x2cm NOS

12 Slaked and pollachi M3 458.00 2127.82 974.00 3101.82


screened burnt
lime stone

13 Shell lime slacked pollachi M3 458.00 2127.82 1322.00 3449.82


and screened

14 Cut stone suryanagaram M3 74 631.96 14000.00 14631.96


``

SUB DATA

S.NO QTY DESCRIPTION RATE PER AMOUNT

1 CEMENT MORTAR 1:1.5


960.00 CEMENT 5960.00 MT 5721.60
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 7282.10

2 CEMENT MORTAR 1:2


720.00 CEMENT 5960.00 MT 4291.20
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 5851.70

3 CEMENT MORTAR 1:3


480.00 CEMENT 5960.00 MT 2860.80
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 4421.30

4 CEMENT MORTAR 1:4


360.00 CEMENT 5960.00 MT 2145.60
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 3706.10

5 CEMENT MORTAR 1:5


288.00 CEMENT 5960.00 MT 1716.48
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 3277.00

6 CEMENT MORTAR 1:6


240.00 CEMENT 5960.00 MT 1430.40
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 2991.00
``

DATA

S.NO QTY PER DESCRIPTION RATE PER AMOUNT

1. 1.00 M2 Dismantling and removing of glazed tiles 47.80 M2 47.80


From floors
( As per S.R , SI No 38G, Page no 22 )

2. Earth work open well excavation complying


with relevant clauses of T.N.D.S.S. Well
sinking and with lead up to 10 metre in sand,
silt or other loose soil, wet sand or silt not
under water, light black cotton soil, sandy
loam and ordinary soil- First depth up to 2
Meter.

1.00 M2 ( As per S.R , SI No 48, Page no 23 ) 64.50 M2 64.50


Sundries 0.50
M2 65.00

3. Supplying and filling in foundation ,


basement,etc with filling sand in layers of not
more than 15cm thick well watered ,
rammed and consolidated etc.complete
complying with standard specification and as
directed by the departmental officers.

1.00 M3 Cost of river sand 1460.50 M3 1460.50


1.00 M3 Refilling charges 29.50 M3 29.50
Add sundries 1.00
M3 1491.00

4. Flooring with cut stone slab of size


600mmx600mm and other sizes suitable for
site requirement not less than 100mm thick
with machine cut edges and top surface
dressed as directed by the departmental
officers including cost and conveyance of
materials to site and labour charges for
paving and pointing with cement mortar 1:5
& combination mortar 1:1:5 etc complete.

Combination Mortar 1:1:5

288 KG Cement 5960.00 KG 1716.48


1.00 M3 Sand for mortar 1460.50 M3 1460.50
0.20 M3 Shell lime slacked and screened 3449.82 M3 689.96
``

1.00 M3 Grinding charges 242.00 M3 242.00


1.00 M3 Mixing charges 100.00 M3 100.00
2.00 KG Gallnut 80.00 KG 160.00
1.00 KG Jaggery 55.00 KG 55.00
M3 4423.94

Pointing withCombination Mortar 1:1:5

0.06 M3 Combination Mortar 1:1:5 4423.94 M3 265.44


1.60 M3 Mason 2ndclass 804.00 M3 1286.40
0.50 Nos Mazdoor 1stclass 562.00 Each 281.00
1.10 Nos Mazdoor 2nd class 461.00 Each 507.10
10.M2 2339.94

Main Data

1.00 M3 Cut stone dressed to size and shape for all 14631.96 M3 14631.96
faces of 10cm thick
0.37 M3 Cement mortar 1:3 4421.30 M3 1635.88
10.00 M2 Pointing with Combination Mortar 1:1:5 2339.94 10.M2 2339.94
1.10 Nos Mason 1st class 861.00 Each 947.10
nd
1.10 Nos Mason 2 class 804.00 Each 884.40
2.20 Nos Mazdoor 1st class 562.00 Each 1236.40
1.10 Nos Mazdoor 2nd class 461.00 M2 507.10
10.00 M2 Labour charges for 3 live dressing at top 1076.43 M2 10764.30
32947.08
M2 3295.00

5. Supplying & fixing in position of best


approved BIS quality 110mm diapvc pipe for
water down fall pipe having 4kg/m2
including the cost of necessary pvc shoe,
bend, with special clamps, brass screws, nails
etc, for 3RM.

3.00 RM 110 MM diapvc pipe 193.50 Rm 580.50


1.00 No 110 MM diapvc bend 79.50 Each 79.50
1.00 Nos 110 MM diapvc shoe 99.20 Each 99.20
2.00 Nos Cost of clamps for fixing 19.90 Each 39.80
4.00 No Cost of teak wood plugs 287.00 1000.0 1.15
0
1.00 No Plumber I class 747.00 Each 747.00
Sundries 2.85
3.0 RM 1550.00
RM 516.70
``

DETAILED ESTIMATE

S.NO DESCRIPTION NOS LEN BRD DEP CONTENTS

1. Dismantling and removing of glazed


tiles from floors.

Outside of praharam ( Alround )

North &south side 1x2 54.60 7.10 - 775.32

East &west side 1x2 31.30 6.80 - 425.68

Deduct

Column offsets of North & south side 2x22 0.27 0.80 - (-) 9.50

Column offsets of East & West side 2x18 0.27 0.80 - (-) 7.78

Entrance of North & south side 2x2 2.80 1.40 - (-) 15.68

Entrance of East & West side 2x2 2.40 1.50 - (-) 14.40

Ramp of East side 1x2 2.00 7.10 - (-)28.40

Water purifier of south side 1x1 1.80 1.50 - (-) 2.70

1123.00 M2

2. Earth work open well excavation


complying with relevant clauses of
T.N.D.S.S. Well sinking and with lead up
to 10 metre in sand, silt or other loose
soil, wet sand or silt not under water,
light black cotton soil, sandy loam and
ordinary soil- First depth up to 2 Meter.

Open Area between outer


praharam& Inner praharam

East side 1x1 31.32 2.97 0.25 23.26

Deduct Rajagopuram projections 1x1 7.62 2.06 0.25 3.92 (-)

South side 1x1 34.29 1.75 0.25 15.00


``

Deduct Rajagopuram projections 1x1 6.25 1.68 0.25 2.63 (-)

West side 1x1 31.32 2.97 0.25 23.26

Deduct Rajagopuram projections 1x1 6.55 1.68 0.25 2.75 (-)

North side 1x1 34.29 1.83 0.25 15.69

Deduct Rajagopuram projections 1x1 6.25 1.68 0.25 2.63 (-)

Open Area in front of office room


& information centre

West side 1x1 3.5 +2.2/2 21.05 0.25 15.00

80.28 M3

3. Supplying and filling in foundation ,


basement,etc with filling sand in layers
of not more than 15cm thick well
watered , rammed and consolidated
etc.complete complying with standard
specification and as directed by the
departmental officers.

Open Area between outer


praharam& Inner praharam

East side 1x1 31.32 2.97 0.15 13.95

Deduct Rajagopuram projections 1x1 7.62 2.06 0.15 2.36 (-)

South side 1x1 34.29 1.75 0.15 9.00

Deduct Rajagopuram projections 1x1 6.25 1.68 0.15 1.58 (-)

West side 1x1 31.32 2.97 0.15 13.95

Deduct Rajagopuram projections 1x1 6.55 1.68 0.15 1.65 (-)

North side 1x1 34.29 1.83 0.15 9.41

Deduct Rajagopuram projections 1x1 6.25 1.68 0.15 1.58 (-)

Open Area in front of office room


& information centre
``

West side 1x1 3.5 +2.2/2 21.05 0.15 8.99

48.13 M3

4. Flooring with cut stone slab of size


600mmx600mm and other sizes
suitable for site requirement not less
than 100mm thick with machine cut
edges and top surface dressed as
directed by the departmental officers
including cost and conveyance of
materials to site and labour charges for
paving and pointing with cement
mortar 1:5 & combination mortar 1:1:5
etc complete.

Outside of praharam ( Alround )

North & south side 1x2 54.60 7.10 - 775.32

East & west side 1x2 31.30 6.80 - 425.68

Open Area between outer


praharam& Inner praharam

East side 1x1 31.32 2.97 - 93.02

Deduct Rajagopuram projections 1x1 7.62 2.06 - 15.70 (-)

South side 1x1 34.29 1.75 - 60.00

Deduct Rajagopuram projections 1x1 6.25 1.68 - 10.50 (-)

West side 1x1 31.32 2.97 - 93..02

Deduct Rajagopuram projections 1x1 6.55 1.68 - 11.00 (-)

North side 1x1 34.29 1.83 - 62.75

Deduct Rajagopuram projections 1x1 6.25 1.68 - 10.50 (-)

Open Area in front of office room


& information centre

West side 1x1 3.5 +2.2/2 21.05 - 60.00


``

Deduct

Column offsets of North & south 2x22 0.27 0.80 - 9.50 (-)
side

Column offsets of East & West side 2x18 0.27 0.80 - 7.78 (-)

Entrance of North & south side 2x2 2.80 1.40 - 15.68 (-)

Entrance of East & West side 2x2 2.40 1.50 - 14.40 (-)

Ramp of East side 1x2 2.00 7.10 - 28.40 (-)

Water purifier of south side 1x1 1.80 1.50 - 2.70 (-)

1444.00 M2

5. Supplying & fixing of 110 MM Pvc


pipes with all accessories, over roof
wherever the slope area required

For Rain water Drain from sannadhies 1x20 12.00 - - 240.00 RMT

6. Provision of man hole chamfer with 1X20 - - - 20.00 NOS


complete package of work with filling
of brick jelly, pebble stones
``

ABSTRACT ESTIMATE

S.NO QTY DESCRIPTION OF WORKS RATE PER AMOUNT

1. 1123.00 Dismantling and removing of glazed tiles from floors 47.80 M2 53679.00

2. 80.28 Earth work open well excavation complying with relevant 65.00 M3 5218.00
clauses of T.N.D.S.S. Well sinking and with lead up to 10
metre in sand, silt or other loose soil, wet sand or silt not
under water, light black cotton soil, sandy loam and
ordinary soil- First depth up to 2 Meter.

3. 48.13 Supplying and filling in foundation , basement,etc with 1491.00 M3 71762.00


filling sand in layers of not more than 15cm thick well
watered , rammed and consolidated etc.complete
complying with standard specification and as directed by
the departmental officers.

4. 1444.00 Flooring with cut stone slab of size 600mmx600mm and 3295.00 M2 4757980.00
other sizes suitable for site requirement not less than
100mm thick with machine cut edges and top surface
dressed as directed by the departmental officers including
cost and conveyance of materials to site and labour charges
for paving and pointing with cement mortar 1:5 &
combination mortar 1:1:5 etc complete.

5. 240.00 Supplying & fixing of 110 MM Pvc pipes with all 516.70 RMT 124008.00
accessories

6. 20.00 Provision of man hole chamfer with complete package of 10000.00 NOS 200000.00
work with filling of brick jelly, pebble stones& Man hole
cover on Top of chamfer.

SUB TOTAL 5212647.00

ADD GST 12% 625518.00

PROVISION FOR CENTAGE CHARGES 2 % 124000.00

PROVISION FOR LABOUR WELFARE FUND 1% 62000.00

PROVISION FOR ADVERTISEMENT CHARGES 100000.00

PROVISION FOR UNFORSEEN ITEMS 75835.00


``

TOTAL 6200000.00

ESTIMATE

NAME OF WORK:IMPROVEMENTS TO THE OUTER PRAHARAM AND OUTSIDE OF INNER

PRAHARA MANDAPAM,ALROUND FOR ARULMIGU BHAVANIAMMAN THIRUKOVIL

PERIYAPALAYAM, UTHUKOTTAI TALUK, THIRUVALLUR DISTRICT

ESTIMATE AMOUNT : RS : 62.00 LAKHS


``

Report to accompany along with the estimate for the work of “Improvements to the outer

praharam and outside of inner praharamandapamalround forArulmiguBhavani Amman Thirukovil,

Periyapalayam, UthukottaiTaluk, Tiruvallur Dist.

Estimate Amount : RS – 62.00 lakhs

IT has been proposed by the temple authorities to workof“Improvements to the outer

praharam and outside of inner praharamandapamalround for ArulmiguBhavani Amman Thirukovil,

Periyapalayam, UthukottaiTaluk, Tiruvallur Dist.

which an estimate is prepared . the estimate amount is RS – 62.00 lakhs for the following are the

specification for the works.

1. Dismantling and removing of glazed tiles from floors


2. Earth work open well excavation complying with relevant clauses
3. Supplying and filling in foundation , basement,etc with filling sand
4. Flooring with cut stone slab of size 600mmx600mm and other sizes
5. Supplying & fixing of 110 MM Pvc pipes with all accessories
6. Provision of man hole chamfer with complete package

The necessary lumpsum provisions are made for centage @ 2% and labour welfare fund @ 1%The

current year schedule of rate for the year (2021-22) is adopted in the preparation of estimate.

( Effect from 13.09.2021 )


``

LEAD STATEMENT

LEAD STATEMENT FOR THE YEAR 2021-2022 (EFFECTIVE FROM 13.9.2021)

S.NO NAME OF SOURCE UNIT DIST IN CONVEYANCE COST OF TOTAL COST


MATERIAL kMS CHARGES MATERIAL

1 Cement Local MT 0 0 5960.00 5960.00

2 Steel Local MT 0 0 51750.00 51750.00

3 Sand for mortar Vaduvanthangal M3 132 1013.50 447.00 1460.50

4 Sand for filling Vaduvanthangal M3 132 1013.50 447.00 1460.50

5 IInd class ground Thirumazhisai 1000 38 497.76 6435.00 6932.76


moulded chamfer NOS
burnt bricks of size
9”x4 3/8”x2 3/4”

6 Brick jelly 20mm Thirumazhisai M3 38 243.42 767.00 1010.42

7 Brick jelly 40mm Thirumazhisai M3 38 243.42 688.00 931.42

8 HBG stone jelly pallavaram M3 58 508.92 1432.00 1940.92


20mm

9 HBG stone jelly pallavaram M3 58 508.92 1029.00 1537.92


40mm

10 HBG stone jelly pallavaram M3 58 508.92 1329.00 1837.92


12mm

11 Machine pressed Red hills 1000 25 278.50 16106.00 16245.25


tiles 23x23x2cm NOS

12 Slaked and pollachi M3 458.00 2127.82 974.00 3101.82


screened burnt
lime stone

13 Cut stone suryanagaram M3 74 631.96 14000.00 14631.96


``

SUB DATA

S.NO QTY DESCRIPTION RATE PER AMOUNT

1 CEMENT MORTAR 1:1.5


960.00 CEMENT 5960.00 MT 5721.60
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 7282.10

2 CEMENT MORTAR 1:2


720.00 CEMENT 5960.00 MT 4291.20
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 5851.70

3 CEMENT MORTAR 1:3


480.00 CEMENT 5960.00 MT 2860.80
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 4421.30

4 CEMENT MORTAR 1:4


360.00 CEMENT 5960.00 MT 2145.60
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 3706.10

5 CEMENT MORTAR 1:5


288.00 CEMENT 5960.00 MT 1716.48
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 3277.00

6 CEMENT MORTAR 1:6


240.00 CEMENT 5960.00 MT 1430.40
1.00 SAND FOR MORTAR 1460.50 M3 1460.50
1.00 MIXING CHARGES 100.00 M3 100.00
RATE/M3 2991.00
``

DATA

S.NO QTY PER DESCRIPTION RATE PER AMOUNT

1. Dadooing the walls with glazed tiles of


printed design size 150x150x6mm of best
approved quality and colour in all shade
of the glazed tiles in all floor over a base
layer in cement mortar 1:2, 10 mm thick
and laid in situ true alignment and
pointed neatly with colour cement at the
rate of 0.40kg/m2 to suit the colour of
the tiles fixed in position without any
airgap in the tiles neatly etc, complete
complying with standard specification
and as directed by the departmental
officers . . The colour and quality of tiles
should be approved by the executive
engineer before use of work.
445 NOS Glazed tiles of printed design of size 11.00 Each 4895.00
150x150x6mm
0.1 M3 Cement mortar 1:2 5851.70 M3 585.17
4.0 Kg White cement 22.40 Kg 89.60
1.1 Nos Mason 1st class 861.00 Each 947.10
4.1 Nos Mason 2nd class 804.00 Each 3296.40
2.7 Nos Mazdoor cat-1 562.00 Each 1517.40
3.3 Nos Mazdoor cat-2 461.00 Each 1521.30
10 M2 12851.97
1 M2 1285.00
2. Painting two coats of newly plastered
wall surface with water based exterior
emulsion paint of first quality and of
approved colour over a priming coat
including thorough scrapping,clean
removal of dirt,and including necessary
plaster of parisputty,wherever required
etc, complying with standard
specification
10.00 M2 Cleaning the plastered surface 6.65 M2 66.50
1.40 Litre Plastic emulsion paint 292.70 Litre 409.78
0.98 Litre primer 146.10 Litre 143.18
2.20 Nos Painter 1st class 688.00 Nos 1513.60
L.S Sundries for brushes, sand paper,plaster L.S 6.94
of paris putty, etc.
10 M2 2140.00
``

1 M2 214.00

DETAILED ESTIMATE

S.NO DESCRIPTION NOS LEN BRD DEP CONTENTS

1. Dadooing the walls with glazed tiles of


printed design size 150x150x6mm of
best approved quality and colour in all
shade of the glazed tiles in all floor over
a base layer in cement mortar 1:2, 10
mm thick and laid in situ true alignment
and pointed neatly with colour cement
at the rate of 0.40kg/m2 to suit the
colour of the tiles fixed in position
without any airgap in the tiles neatly
etc, complete complying with standard
specification and as directed by the
departmental officers . . The colour and
quality of tiles should be approved by
the executive engineer before use of
work.

For ground floor


( Annadhaanakoodam)

Inner walls ( Alround ) 1x1 56.70 - 2.40 136.08


Deduct kitchen open 1x1 4.20 - 2.40 (-) 10.08
Entrance open 1x1 1.15 - 2.70 (-)3.11
Window 1 1x14 1.80 - 1.30 (-) 32.76
Gate 1 1x1 1.10 - 2.40 (-) 2.64
87.49 M2

2. Painting two coats of newly plastered


wall surface with water based exterior
emulsion paint of first quality and of
approved colour over a priming coat
including thorough scrapping,clean
removal of dirt,and including necessary
plaster of parisputty,wherever
required etc, complying with standard
specification

Annadhaanakoodam& office building

Outer walls ( Alround ) 1x1 75.50 - 7.70 581.35


``

Sunshades of window 1 1x32 2.40 1.30 - 99.84


Sunshades of window 2 1x1 1.35 1.30 - 1.76
Sunshades of Gate1 1x5 2.40 1.30 - 15.60
Sunshades of Gate2 1x1 1.70 1.30 - 2.21
Deduct
window 1 1x32 1.80 - 1.30 (-) 74.88
window 1 1x1 0.90 - 1.20 (-) 1.08
Gate1 1x5 1.80 - 2.30 (-) 20.70
Gate2 1x1 1.10 - 2.40 (-) 2.64
Inner walls ( Alround )
Ground & First floor 1X2 69.96 - 3.00 419.76
Partition wall between step & hall 1x1 8.30 - 3.00 24.90
Ground & First floor ceiling 1x2 24.04 10.94 - 526.00
Ground & First floor step bottom 1x2 4.00 1.20 - 9.60
Deduct
window 1 1x32 1.80 - 1.30 (-) 74.88
window 1 1x1 0.90 - 1.20 (-) 1.08
Gate1 1x5 1.80 - 2.30 (-) 20.70
Gate2 1x1 1.10 - 2.40 (-) 2.64
1482.42 M2
``

ABSTRACT ESTIMATE

S.NO QTY DESCRIPTION OF WORKS RATE PER AMOUNT

1. 87.49 Dadooing the walls with glazed tiles of printed design 1285.00 M2 112425.00
size 150x150x6mm of best approved quality and colour
in all shade of the glazed tiles in all floor over a base
layer in cement mortar 1:2, 10 mm thick and laid in situ
true alignment and pointed neatly with colour cement at
the rate of 0.40kg/m2 to suit the colour of the tiles fixed
in position without any airgap in the tiles neatly etc,
complete complying with standard specification and as
directed by the departmental officers . . The colour and
quality of tiles should be approved by the executive
engineer before use of work.

2. 1482.42 Painting two coats of newly plastered wall surface with 214.00 M2 317238.00
water based exterior emulsion paint of first quality and
of approved colour over a priming coat including
thorough scrapping,clean removal of dirt,and including
necessary plaster of parisputty,wherever required etc,
complying with standard specification

SUB TOTAL 429663.00

ADD GST 12% 51560.00

PROVISION FOR CENTAGE CHARGES 2 % 9940.00

PROVISION FOR LABOUR WELFARE FUND 1% 4970.00

PROVISION FOR UNFORSEEN ITEMS 837.00

TOTAL 497000.00
``

ESTIMATE

NAME OF WORK :IMPROVEMENTS AND PAINTING OF ANNADHAANA KOODAM AND OFFICE BUILDING

FOR ARULMIGU BHAVANI AMMAN THIRUKOVIL, PERIYAPALAYAM,


,

UTHUKOTTAI TALUK, THIRUVALLUR DISTRICT.

ESTIMATE AMOUNT : RS . 4.97 LAKHS


``

Report to accompany along with the estimate for the work of “Improvements and painting work in

AnnadhaanaKoodam& Office Building forArulmiguBhavani Amman Thirukovil,

Periyapalayam, UthukottaiTaluk, Tiruvallur Dist.

Estimate Amount : RS – 4.97 lakhs

IT has been proposed by the temple authorities to workof“Improvements and painting work in

AnnadhaanaKoodam& Office Building forArulmiguBhavani Amman Thirukovil,

Periyapalayam, UthukottaiTaluk, Tiruvallur Dist.

which an estimate is prepared . the estimate amount is RS – 4.97 lakhs for the following are the

specification for the works.

1. Dadooing the walls with glazed tiles of printed design size 150x150x6mm
2. Painting two coats of newly plastered wall surface withwater based exterior
emulsion

The necessary lumpsum provisions are made for centage @ 2% and labour welfare fund @ 1%The

current year schedule of rate for the year (2021-22) is adopted in the preparation of estimate.

( Effect from 13.09.2021 )


``
``

DATA

S.N QTY PER DESCRIPTION RATE PER AMOUNT


O
1 Chipping the existing
damaged plastering in
cement mortar and clearing
away the rubbish etc,
complete and as directed by
the departmental officers.

1.00 M2 As per schedule item no 320 4.50 M2 4.50


( page-28)
5% for thiruvallur 0.23
Add sundries 0.27
M2 5.00
2 Earth work excavation for
foundation in all soils and sub-
soils and to full depth as may
be directed exept in rock
requiring biasting inclusive of
shoring,shuttering,bailing out
water wherever necessary and
depositing the surplus earth
within the compound in places
shown by the departmental
officers with an initial lead of
10 mts and initial lift of
2mts.and clearing and levelling
the site,etc; complete
complying with standard
specification.
1.00 M3 As per sr item no 53.05 M3 53.05
(50+62/2=42.50+63.60/2
1.00 M3 Add 100% for narrow 53.05 M3 53.05
excavation
5% for thiruvallur 2.65
0.33 M3 Refilling the side foundation 22.20 M3 7.33
with excavated earth
Add sundries 0.92
``

M3 117.00
3 Supplying and filling in
foundation , basement,etc
with filling sand in layers of not
more than 15cm thick well
watered , rammed and
consolidated etc.complete
complying with standard
specification and as directed
by the departmental officers.
1.00 M3 Cost of river sand 346.50 M3 346.50
1.00 M3 Refilling charges 19.50 M3 19.50
M3 366.00
4 Plain cement concrete 1:5:10
(one cement,five sand and ten
broken stone jelly) using
40mm gauge hard broken
granite stone jelly for
foundation including
dewatering wherever
necessary and laid in layers of
not more than 15cm thick well
rammed consolidated and
curing etc.complete complying
with standard specification.
9.00 M3 40mm HBG 1249.30 M3 11243.70
4.50 M3 CM 1:5 2005.04 M3 9022.68
1.80 Nos Mason 2nd class 508.00 Each 914.40
17.70 Nos Mazdoor cat-1 355.00 Each 6283.50
14.1 Nos Mazdoor cat-2 320.00 Each 4512.00
Add sundries 0.72
10M3 31977.00
1M3 3197.70
5 Supplying fabricating and
placing in position Mild
steel /Ribbed tor steel grills for
all rcc works as per design
1.00 qtl Plain/ RTS rods 4419.00 qtl 4419.00
1.00 kg GI binding wire(18g) 43.00 kg 43.00
3.50 Nos Fitter 1st class 501.00 Each 1753.50
Add sundries 0.50
1 qtl 6216.00
6 Supplying and erecting
centering for sidesand soffits
including necessary supports
and strutting up to 3.29m
height for plane surfaces as
``

detailed below in all floors


with all cross bracings using
mild steel sheets of size 90x60
cm and 10BG Stiffened with
welded mild steel angle of size
25mmx25mmx3mm for
boarding laid over silver oak
joists of size 10cm x 6.50cm
spaced 90cm c/c and
supported by casurina props of
10cm to 13cm dia spaced at
not more than 75 cm c/c
etc.complete complying with
standard specification
(payment for centering shall
be given after the concrete is
laid
A) For column,footing,grade
beam
19.7 RM Casurina crops 10 cm to 13cm 24.00 RM 472.80
at 7.5cmc/c
0.3 Nos Carpenter 1st class 555.00 Each 166.50
0.3 Nos Mazdoor cat-1 355.00 Each 106.50
Add sundries 0.20
746.00
Centering for plane surface 4571.00 10 M2 4571.00
Deduct for casurina props and 746.00 (-)
labours
10 M2 3825.00
1 M2 382.50
B) For plane surface slab, beam
etc
3.8 nos Carpenter 1st class 555.00 Each 2109.00
5.4 nos Mazdoor cat-1 355.00 Each 1917.00
1.0 nos Fitter 2nd class 467.00 Each 467.00
L.S Add welding grills,nails 53.60
For periodical cleaning and 24.00
painting of MS sheet and
angle( 5% of cost of sheet and
angle
Add sundries 0.40
10 M2 4571.00
1 M2 457.10
C) For square or rectangular
column
1.00 M2 Centering for plane surface 457.10 457.10
Add 20% extra 457.10 91.42
``

Add sundries 0.48


1 M2 549.00
7 Reinforced cement concrete
1:1.5:3
(one cement,one and a half
sand and three hard broken
stone jelly) using 20mm gauge
hard broken granite stone jelly
for all RCC items of works
including cost of
reinforcement grill and
fabricating charges ,centering
and shuttering and including
laying, vibrating with
mechanical
vibrators,finishing,curing and
providing fixtures like fan
clamps in rcc floor/roof slab
wherever necessary and
bearing surfaces of
walls,beams etc shall be
finished smooth with cm 1:3
(one cement and three sand)
complete complying with
standard specification and as
directed by the departmental
9.00 M3 20 mm HBG 1613.30 M3 14519.70
4.50 M3 River sand 346.50 M3 1559.25
4.308 Mt cement 5530.00 Mt 23823.24
3.5 Nos Mason 2nd class 508.00 Each 1778.00
21.2 Nos Mazdoor cat-1 355.00 Each 7526.00
35.3 Nos Mazdoor cat-2 320.00 Each 11296.00
0.81
10 M3 60503.00
For foundation and Basement 1 M3 6050.30
For ground floor up to 4.5m 6050.30 68.00 6118.30
height
8 Special plastering the surface
of walls with cement mortar
1:3 (one cement and three
sand) 10mm thick in all floors
including curing etc, complete
complying with standard
specification and as directed
by the departmental officers.
0.1 M3 Cement mortar 1:3 3066.80 M3 306.68
1.1 Nos Mason 1st class 567.00 Each 623.70
``

1.1 Nos Mazdoor cat-1 355.00 Each 390.50


1.1 Nos Mazdoor cat-2 320.00 Each 352.00
Add sundries 0.12
10 M2 1673.00
1 M2 167.30
9 Brick masonry in CM 1:5 in
foundation,basement and
superstructure walls using
second class ground moulded
chamfer burnt bricks of size
9”x 4” 3/8 x 2” ¾ etc,
complete complying with
standard specifications and
drawings and as directed by
departmental engineers.
1300 NO Cost of bricks 5245.95 1000 N 6819.74
S
0.708 M3 Cement mortar 1:5 2005.04 M3 1419.57
1.0 Nos Mason 1st class 567.00 Each 567.00
3.0 Nos Mason 2nd class 508.00 Each 1524.00
2.0 Nos Mazdoor cat-1 355.00 Each 710.00
6.0 Nos Mazdoor cat-2 320.00 Each 1920.00
Sundries 0.69
Total for 100 cft ( or) 2.832 M3 4574.00
For foundation and basement 4574.00 1 M2 4574.00
For ground floor up to 4.50M 4574.00 44.80 4618.8
high
10 Plastering with CM 1:5,
12mm thick using river sand
including curing, and finishing
neatly , complying with
standard specification and as
directed by the departmental
officers etc.
0.14 M3 Cement mortar 1:5 2005.04 M3 280.71
1.1 Nos Mason 1st class 567.00 Each 623.70
0.5 Nos Mazdoor cat-1 355.00 Each 177.50
1.1 Nos Mazdoor cat-2 320.00 Each 352.00
Sundries 1.09
10 M2 1435.00
1 M2 143.50
11 Plastering with CM 1:5,
20mm thick using river sand
including curing, and finishing
neatly , complying with
standard specification and as
``

directed by the departmental


officers etc.
0.22 M3 Cement mortar 1:5 2005.04 M3 441.11
2.2 Nos Mason 1st class 567.00 Each 1247.40
0.5 Nos Mazdoor cat-1 355.00 Each 177.50
3.2 Nos Mazdoor cat-2 320.00 Each 1024.00
10 M2 2890.00
1 M2 289.00
12 Plastering with CM 1:3,
12mm thick using river sand
including curing, and finishing
neatly , complying with
standard specification and as
directed by the departmental
officers etc.
0.14 M3 Cement mortar 1:3 3066.80 M3 429.35
1.1 Nos Mason 1st class 567.00 Each 623.70
0.5 Nos Mazdoor cat-1 355.00 Each 177.50
1.1 Nos Mazdoor cat-2 320.00 Each 352.00
10 M2 1582.55
1 M2 158.30

13 Plastering with CM 1:3,


20mm thick using river sand
including curing, and finishing
neatly , complying with
standard specification and as
directed by the departmental
officers etc.
0.22 M3 Cement mortar 1:3 3066.80 M3 674.70
2.2 Nos Mason 1st class 567.00 Each 1247.40
0.5 Nos Mazdoor cat-1 355.00 Each 177.50
3.2 Nos Mazdoor cat-2 320.00 Each 1024.00
10 M2 3123.30
1 M2 312.33
14 Flooring with CM 1:3, 20mm
thick using river sand including
curing, and finishing neatly ,
complying with standard
specification and as directed
by the departmental officers
etc.
0.22 M3 Cement mortar 1:3 3066.80 M3 674.70
2.2 Nos Mason 1st class 567.00 Each 1247.40
0.5 Nos Mazdoor cat-1 355.00 Each 177.50
3.2 Nos Mazdoor cat-2 320.00 Each 1024.00
10 M2 3123.30
``

1 M2 312.33
15 Painting new iron works such
as steel
doors,windows,ventilators,win
dow bars,balustrades etc, with
two coats of best approved
first quality and colour of
synthetic enamel paint over
the existing red oxide priming
coat in all floors including cost
of priming coat etc, complete.
Complying with standard
specification .( The
make,quality and colour of
paint should be got approved
by the executive engineer
before use of works.
a) 1.33 Lit Red oxide primer 126.70 Lit 168.51
0.70 Nos Painter/varnisher 1st class 454.00 Each 317.80
sundries 1.69
10 M2 488.00
1 M2 48.80
b) 2.22 Lit Synthetic enamel paint fof iron 211.00 Lit 468.42
1.10 Nos Painter/varnisher 1st class 454.00 Each 499.40
sundries 2.18
10 M2 970.00
1 M2 97.00
a+b =( 48.80+97.00) 1 M2 145.80
16 Painting old iron works such as
steel
doors,windows,ventilators,win
dow bars,balustrades etc, with
two coats of best approved
first quality and colour of
synthetic enamel paint
including ordinary scrapping
using brushes and neat
finishing etc,complete.
Complying with standard
specification .( The
make,quality and colour of
paint should be got approved
by the executive engineer
before use of works.
10.00 M2 Through scrapping 5.30 M2 53.00
1.89 lit Synthetic enamel paint fof iron 211.00 lit 398.79
1.11 Nos Painter/varnisher 1st class 454.00 Each 503.94
``

sundries 2.27
10 M2 958.00
1 M2 95.80
17 Painting old wood works with
two coats of best approved
first quality and colour of
synthetic enamel paint
including ordinary scrapping
using brushes and neat
finishing etc,complete.
Complying with standard
specification .( The
make,quality and colour of
paint should be got approved
by the executive engineer
before use of works.
10.00 M2 Through scrapping 5.70 M2 57.00
2.22 lit Synthetic enamel paint fof iron 221.00 lit 490.62
1.20 Nos Painter/varnisher 1st class 454.00 Each 544.80
sundries 1.58
10 M2 1094.00
1 M2 109.40
18 Painting new wood works with
two coats of best approved
first quality and colour of
synthetic enamel paint over
one coat primer including
ordinary scrapping using
brushes and neat finishing
etc,complete. Complying with
standard specification .( The
make,quality and colour of
paint should be got approved
by the executive engineer
before use of works.
a) 1.44 Lit Ready mixed primer 136.50 Lit 196.56
0.70 Nos Painter/varnisher 1st class 454.00 Each 317.80
Sundries including 1.64
brushes,soap,putty .
10 M2 516.00
1 M2 51.60
Two coats over one coat of
primer
b) 2.55 Lit Synthetic enamel paint fof 221.00 Lit 563.55
wood
10.00 M2 Primer 51.60 M2 516.00
1.20 Nos Painter/varnisher 1st class 454.00 Each 544.80
``

Sundries including 1.65


brushes,soap,putty
10 M2 1626.00
1 M2 162.60
19 White washing with freshly
burnt white shell lime in all
floors including cost of
lime,blue powder,fevicol type
gum,brushes,scaffolding
charges,etc, complete.
Complying with standard
specification as directed by
officers.
For one coat – 100M2
0.05 M3 Fine screened shell lime 1314.00 M3 65.70
1.1 Nos Mason 2nd class 508.00 Each 558.80
0.3 Nos Mazdoor cat-1 355.00 Each 106.50
1.9 Nos Mazdoor cat-2 320.00 Each 608.00
Gum, conjee water or prickly 11.00
pear juice including necessary
fire wood and brushes
100 1350.00
M2
1 M2 13.50
For Two coats – 100M2
0.07 M3 Fine screened shell lime 1314.00 M3 91.98
1.6 Nos Mason 2nd class 508.00 Each 812.80
0.5 Nos Mazdoor cat-1 355.00 Each 177.50
2.7 Nos Mazdoor cat-2 320.00 Each 864.00
Gum, conjee water or prickly 13.72
pear juice including necessary
fire wood and brushes
100 1960.00
M2
1 M2 19.60
20 Painting two coats of newly
plastered wall surface with
ready mixed plastic emulsion
paint of first quality and of
approved colour over a
priming coat including
thorough scrapping,clean
removal of dirt,and including
necessary plaster of paris
putty,wherever required etc,
complying with standard
specification
``

10.00 M2 Cleaning the plastered surface 2.45 M2 24.50


1.40 Litr Plastic emulsion paint 274.00 Litre 383.60
e
0.98 Litr primer 136.50 Litre 133.77
e
2.20 Nos Painter 1st class 454.00 Nos 998.80
L.S Sundries for brushes, sand L.S 0.33
paper,plaster of paris putty,
etc.
10 M2 1541.00
1 M2 154.10
21 Painting with multicolour
panchavarnam with good
emulsion paint. Complete for
the vimanam/gopuram
including cost and conveyance
of all materials, labour charges
including artist painter
working in the height , lifting
of material,cost of brushes
etc,complete which includes
all extra for folding
a) Vimanam / gopuram of 4.5m
height excluding kalkaram
1.65 Lit Wall primer 124.10 Lit 204.77
4.00 Lit R.M Good emulsion paint 1,2 249.55 Lit 998.20
& 3 coats all shading
2.00 Nos Asst.painter 228.00 Each 456.00
3.00 Nos Artist painter 1st class 281.00 Each 843.00
3.00 Nos Artist painter 2nd class 254.00 Each 762.00
1.50 Nos Mazdoor 1st class 355.00 Each 532.50
Cost of brushes, putty, cotton 0.53
wastage
10 M2 3797.00
1 M2 379.70

22 Laying the floor with plain


ceramic tiles of approved
quality,colour and design joint
free of size 305x305x6mm
thick of approved make,
quality and colour in all floors
over a base layer of cement
mortar 1:3 with 20mm thick
and laid straight alignment and
pointed neatly with colour
``

cement at the rate of


0.40kg/m2 laid without any air
gap in the tiles neatly and
fixing in position as per
standard specifications and as
directed by the departmental
officers . The colour and
quality of tiles should be
approved by the executive
engineer before use of work.
Labour charges and mortar
0.21 M3 Cement mortar 1:3 3066.80 M3 644.03
3.00 kg White cement 22.00 kg 66.00
50.00 kg Colouring pigments 25.40 kg 1.27
1.2 Nos Mason 1st class 567.00 Each 680.40
1.0 Nos Mason 2nd class 508.00 Each 508.00
0.5 Nos Stone cutter 1st class 436.00 Each 218.00
1.0 Nos Mazdoor cat-1 355.00 Each 355.00
1.0 Nos Mazdoor cat-2 320.00 Each 320.00
0.5 kg Cotton waste 9.70 kg 4.85
Rate for 10M2 2797.55
108 Nos Plain ceramic tiles of size 32.20 Each 3477.60
305x305x6mm
10 M2 Labour charges 2797.55 10 M2 2797.55
Rate for 10M2 10 M2 6275.15
1 M2 627.52
23 Dadooing the walls with glazed
tiles of printed design size
150x150x6mm of best
approved quality and colour in
all shade of the glazed tiles in
all floor over a base layer in
cement mortar 1:2, 10 mm
thick and laid in situ true
alignment and pointed neatly
with colour cement at the rate
of 0.40kg/m2 to suit the colour
of the tiles fixed in position
without any airgap in the tiles
neatly etc, complete
complying with standard
specification and as directed
by the departmental officers . .
The colour and quality of tiles
should be approved by the
executive engineer before use
of work.
``

445 NO Glazed tiles of printed design 10.50 Each 4672.50


S of size 150x150x6mm
0.1 M3 Cement mortar 1:2 4394.00 M3 439.40
4.0 Kg White cement 22.00 Kg 88.00
1.1 Nos Mason 1st class 567.00 Each 623.70
4.1 Nos Mason 2nd class 508.00 Each 2082.80
2.7 Nos Mazdoor cat-1 355.00 Each 958.50
3.3 Nos Mazdoor cat-2 320.00 Each 1056.00
10 M2 9920.90
1 M2 992.09
24 Laying the floors with new CC
laminated tiles (like dora tiles,
eurocon tiles ,antiskid) of
20mm thick approved special
quality and set in CM 1:3 20
mm thick using river sand and
pointing with colour cement
at the rate of 0.40kg/m2 and
mixing with colour pigment at
the rate of 0.30kg/m2
including finishing
etc,complete. complying with
standard specification and as
directed by the departmental
officers . . The colour and
quality of tiles should be
approved by the executive
engineer before use of work.
10.5 NO Eurocon tiles with antiskid 571.00 Each 5995.50
S
0.21 M3 Cement mortar 1:3 3066.80 M3 644.03
1.1 Nos Mason 1st class 567.00 Each 623.70
1.1 Nos Mason 2nd class 508.00 Each 558.80
2.2 Nos Mazdoor cat-1 355.00 Each 781.00
2.2 Nos Mazdoor cat-2 320.00 Each 704.00
4.0 kg Colour cement 25.40 kg 101.60
3.0 Kg Colouring pigments 25.40 Kg 76.20
L.S Sundries 2.17
10 M2 9487.00
1 M2 948.70
25 Weathering course using
concrete broken brick jelly
20mm gauge in pure slacked
lime(no sand to be used) over
RCC Roof slab. The proportion
of broken jelly to slaked lime
being 32:12.5 cft well beaten
``

by wooden beaters for giving


required slope and thickness
requiredetc, .complying with
standard specification and as
directed by the departmental
officers .

12.8 M3 Brick jelly 20mm 801.30 M3 10256.64


5.00 M3 Slaked and screened lime 985.00 M3 4925.00
1.80 Nos Mason 1st class 567.00 Each 1020.60
17.70 Nos Mazdoor cat-1 355.00 Each 6283.50
14.10 Nos Mazdoor cat-2 320.00 Each 4512.00
10 M2 26997.74
1 M2 2699.77
26 Finishing the top of roof with
one course of machine pressed
tiles of size 23x23x2mm of
approved quality laid in
cement mortar 1:3, mixed with
2% of water proofing
compound by weight of
cement used and pointed with
same oiled mortar including
mixing of red oxide etc,
complete. complying with
standard specification and as
directed by the departmental
officers
Sub data for pointing- 10m2
0.04 M3 Cement mortar 1:3 3066.80 M3 122.67
2.2 Nos Mason 2nd class 508.00 Each 1247.40
0.5 Nos Mazdoor cat-1 355.00 Each 177.50
1.1 Nos Mazdoor cat-2 320.00 Each 352.00
0.384 kg Water proof compound 37.73 kg 14.49
10 M2 1914.06
For pointing 1 M2 191.41
189.0 Nos Pressed tiles23x23x2cm 14870.0 1000.0 2810.43
0 0 0
0.12 M3 Cement mortar 1:3 3066.80 M3 368.02
1.152 kg Water proof compound 37.73 kg 43.46
10.00 M2 Pointing with Cement mortar 191.41 Each 1914.10
1:3
1.10 Nos Mason 1st class 567.00 Each 623.70
2.10 Nos Mason 2nd class 508.00 Each 1066.80
2.20 Nos Mazdoor cat-1 355.00 Each 781.00
1.10 Nos Mazdoor cat-2 320.00 Each 352.00
10 M2 7959.51
``

1 M2 795.95
27 Supplying & fixing of M.S Grills
for
windows,gates,ventilators&
steps in position of finishing of
welding buds with filing, and
applying of yellow oxide one
coat neatly.
Area of gate –
0.67mx2.08m=1.39 m2
1x6 nos 12 mm flat rod in vertical 2.08 rmt 12.48
phase
1X8 nos 12 mm flat rod in horizontal 0.67 rmt 5.36
phase
17.84 RMT
1X2 nos 25x7mm flat 2.08 rmt 4.16 RMT
1X1 no Equal angle 40x40x6mm in 2.08 rmt 2.08
vertical
1x2 nos Equal angle 40x40x6mm in 0.67 rmt 1.34
horizontal
3.42 RMT
12 mm flat rod 17.84 20.16 KG
RMTX1.13 Kg/rmt
25x7mm flat 4.16 RMTX1.18 4.90 KG
KG/RMT
L angle 40x40x6mm 11.97 KG
3.42RMTX3.5KG/RM
37.03 Kg
Area of gate=1.39 m2
37.03/1.39 = 26.64 kg/m2
M.S grills calculated as 26.64KG/
M2
Supplying of M.S Grills for
windows,gates,ventilators&
steps with applying of yellow
oxide one coat neatly.
(AS PER SR PAGE 22 , SERIAL 53.60
NO 168)
Fixing of M.S Grills for
windows,gates,ventilators &
steps in position of finishing of
welding buds with filing, and
checking with plumbob
(AS PER SR PAGE 33 , SERIAL 18.20
NO 169)
71.80/kg
``

DATA

S.NO QTY PER DESCRIPTION RATE PER AMOUNT

1. 21-22 Earth work excavation for foundation in


all soils and sub-soils and to full depth as
may be directed exept in rock requiring
biasting inclusive of
shoring,shuttering,bailing out water
wherever necessary and depositing the
surplus earth within the compound in
places shown by the departmental
officers with an initial lead of 10 mts and
initial lift of 2mts.and clearing and
levelling the site,etc; complete complying
with standard specification.

1.00 M3 Average rate 96.60 M3 96.60


1.00 M3 Add 100% for narrow excavation 96.60 M3 96.60
0.33 M3 Refilling the side foundation with 33.60 M3 11.09
excavated earth
Add sundries 0.71
M3 205.00

2. 21-22 Supplying and filling in foundation ,


basement,etc with filling sand in layers of
not more than 15cm thick well watered ,
rammed and consolidated etc.complete
complying with standard specification
and as directed by the departmental
officers.

1.00 M3 Cost of river sand 1460.50 M3 1460.50


1.00 M3 Refilling charges 29.50 M3 29.50
Add sundries 1.00
M3 1491.00

3. 21-22 Plain cement concrete 1:5:10 (one


cement,five sand and ten broken stone
jelly) using 40mm gauge hard broken
granite stone jelly for foundation
including dewatering wherever
necessary and laid in layers of not more
than 15cm thick well rammed
consolidated and curing etc.complete
``

complying with standard specification.

9.00 M3 40mm HBG 1399.50 M3 12595.50


4.50 M3 CM 1:5 3277.00 M3 14746.50
1.80 Nos Mason 2nd class 804.00 Each 1447.20
17.70 Nos Mazdoor cat-1 562.00 Each 9947.40
14.1 Nos Mazdoor cat-2 461.00 Each 6500.10
Add sundries 0.30
10M3 45237.00
1M3 4523.70

4. 21-22 Brick masonry in CM 1:5 in


foundation,basement and superstructure
walls using second class ground
moulded chamfer burnt bricks of size 9”x
4” 3/8 x 2” ¾ etc, complete complying
with standard specifications and
departmental engineers.
1300 NOS Cost of bricks 6928.20 1000 N 9006.66
0.708 M3 Cement mortar 1:5 3277.00 M3 2320.12
1.0 Nos Mason 1st class 861.00 Each 861.00
3.0 Nos Mason 2nd class 804.00 Each 2412.00
2.0 Nos Mazdoor cat-1 562.00 Each 1124.00
6.0 Nos Mazdoor cat-2 461.00 Each 2766.00
Sundries 1.12
Total for 100 cft ( or) 2.832 M3 6530.00
For foundation and basement 6530.00 1 M3 6530.00

For ground floor up to 4.50M high 6530.00 68.00 6598.00

5. 21-22 Providing and laying in position


standardized concrete mix M20 grade in
accordance with IS 456 2000 using 20mm
and down graded hard broken granite
stone jelly for all RCC items of works with
minimum cement concrete of 325
kg/cum and maximum water cement
ratio of 0.55 including admixture
(plasticizer/super plasticizer) in
recommended proportions as per IS
9103 to accelerate, retard setting of
concrete, improve workability without
impairing strength and durability with
about (5 cum) 7730 kg of 20mm machine
workability without impairing strength of
( 3.3 cum) 5156 kg of 10-12 mm machine
crushed stone jelly and with about (4.79
``

cum) 7670 kg of sand,but excluding cost


of reinforcement grill and fabricating
charges, centering and shuttering and
also including laying, vibrating with
mechanical vibrators finishing curing etc.,
and fixtures like fan clampsin the RCC
floor/ roof slabs wherever necessary
without claiming etc, complete
complying with standard specification
and as directed by the departmental
officers. The coarse and fine aggregates
to be used , comply with requirements of
IS standards.

5.00 M3 20mm machine crushed stone jelly 1802.50 M3 9012.50


3.30 M3 10-12mm machine crushed stone jelly 1699.50 M3 5608.35
4.79 M3 Sand 1460.50 M3 6995.80
3250 Kg Cement 5960.00 MT 19370.00
19.50 Kg Plasticizer/ super plasticizer @ 0.6% of 42.80 Kg 834.60
cement
3.50 Nos Mason ll class 804.00 Each 2814.00
21.20 Nos Mazdoor l class 562.00 Each 11914.40
35.30 Nos Mazdoor ll class 461.00 Each 16273.30
For 10 M3 72822.95
7282.30
Add for vibration charges 81.30
Add sundries 0.40
For 1 M3 Foundation & 7364.00
basement
For ground floor (As per sr item no 92) 7364.00 103.30 7467.30

6. 21-22 Supplying fabricating and placing in


position Mild steel /Ribbed tor steel grills
for all rcc works as per design.

1.00 qtl Plain/ RTS rods 5175.00 qtl 5175.00


1.00 kg GI binding wire(18g) 50.30 kg 50.30
3.50 Nos Fitter 1st class 760.00 Each 2660.00
Add sundries 0.70
1 qtl 7886.00

7. 21-22 Supplying and erecting centering for


sidesand soffits including necessary
supports and strutting up to 3.29m
height for plane surfaces as detailed
below in all floors with all cross bracings
using mild steel sheets of size 90x60 cm
``

and 10BG Stiffened with welded mild


steel angle of size 25mmx25mmx3mm
for boarding laid over silver oak joists of
size 10cm x 6.50cm spaced 90cm c/c and
supported by casurina props of 10cm to
13cm dia spaced at not more than 75 cm
c/c etc.complete complying with
standard specification (payment for
centering shall be given after the
concrete is laid

1.0 A) For column,footing,grade beam 726.00 M2 726.00

1.0 B) For plane surface slab, beam etc 818.00 M2 818.00

1.0 C) For square or rectangular column 981.00 M2 981.00

8. 21-22 Plastering with CM 1:5, 12mm thick


using river sand including curing, and
finishing neatly , complying with
standard specification and as directed by
the departmental officers etc.
0.14 M3 Cement mortar 1:5 3277.00 M3 458.78
1.1 Nos Mason 1st class 861.00 Each 947.10
0.5 Nos Mazdoor cat-1 562.00 Each 281.00
1.1 Nos Mazdoor cat-2 461.00 Each 507.10
Sundries 1.02
10 M2 2195.00
1 M2 219.50

9. 21-22 Plastering with CM 1:3, 10mm thick


using river sand including curing, and
finishing neatly , complying with
standard specification and as directed by
the departmental officers etc.
0.10 M3 Cement mortar 1:3 4421.30 M3 442.13
1.10 Nos Mason 1st class 861.00 Each 947.10
1.10 Nos Mazdoor cat-1 562.00 Each 618.20
1.10 Nos Mazdoor cat-2 461.00 Each 507.10
10 M2 2514.53
Sundries 1.47
10 M2 2516
1 M2 251.60

10. 21-22 Flooring with CM 1:3, 10mm thick using


river sand including curing, and finishing
neatly , complying with standard
``

specification and as directed by the


departmental officers etc.

0.22 M3 Cement mortar 1:3 4421.30 M3 972.69


2.20 Nos Mason 1st class 861.00 Each 1894.20
0.50 Nos Mazdoor cat-1 562.00 Each 281.00
3.20 Nos Mazdoor cat-2 461.00 Each 1475.20
10 M2 4623.09
1 M2 462.00

11. 21-22 Brick partition wall in cm 1:3, 11.50 cm


thickness using 2nd class chamfer burnt
bricks of size 9’’x4 3/8’’x2 3/4.
1300 Nos 2nd class ground moulded chamfer burnt 6928.20 Each 9006.70
bricks.
0.397 M3 Cement mortar 1:3 4265.56 M3 1693.43
1.00 Nos Mason 1st class 861.00 Each 861.00
3.00 Nos Mason 2nd c lass 804.00 Each 2412.00
2.00 Nos Mazdoor 1st class 562.00 Each 1124.00
6.00 Nos Mazdoor 2nd class 461.00 Each 2766.00
L.S - Sundries 0.87
Total for 100cft (or) 2.832 cu.m. 17864.00
For foundation & basement. 6307.90
For ground floor up to 4.50 m height 6307.90 68.00 6375.90
1.15 M3 Brick work in cm 1:3 6375.90 M3 7332.00
1.00 No Mason 1st class 861.00 Each 861.00
Rate for 10 M2 8193.00
Rate for 1 M2 819.30

12. 21-22 Painting two coats of newly plastered


wall surface with ready mixed plastic
emulsion paint of first quality and of
approved colour over a priming coat
including thorough scrapping,clean
removal of dirt,and including necessary
plaster of paris putty,wherever required
etc, complying with standard
specification
10.00 M2 Cleaning the plastered surface 6.65 M2 66.50
1.40 Litre Plastic emulsion paint 292.70 Litre 409.78
0.98 Litre primer 146.10 Litre 143.18
2.20 Nos Painter 1st class 688.00 Nos 1513.60
L.S Sundries for brushes, sand paper,plaster L.S 6.94
of paris putty, etc.
10 M2 2140.00
1 M2 214.00
``

13. 21-22 Supplying & fixing of M.S Grills for


windows,gates,ventilators & steps in
position of finishing of welding buds
with filing, and applying of yellow oxide
one coat neatly.
Area of gate – 0.67mx2.08m=1.39 m2
1x6 nos 12 mm flat rod in vertical phase 2.08 rmt 12.48
1X8 nos 12 mm flat rod in horizontal phase 0.67 rmt 5.36
17.84 RMT
1X2 nos 25x7mm flat 2.08 rmt 4.16 RMT
1X1 no Equal angle 40x40x6mm in vertical 2.08 rmt 2.08
1x2 nos Equal angle 40x40x6mm in horizontal 0.67 rmt 1.34
3.42 RMT
12 mm flat rod 17.84 RMTX1.13 Kg/rmt 20.16 KG
25x7mm flat 4.16 RMTX1.18 KG/RMT 4.90 KG
L angle 40x40x6mm 3.42RMTX3.5KG/RM 11.97 KG
37.03 Kg
Area of gate=1.39 m2
37.03/1.39 = 26.64 kg/m2
M.S grills calculated as 26.64KG/M2
Supplying of M.S Grills for
windows,gates,ventilators& steps with
applying of yellow oxide one coat neatly.
(AS PER SR PAGE 22 , SERIAL NO 168) 62.60
Fixing of M.S Grills for
windows,gates,ventilators & steps in
position of finishing of welding buds
with filing, and checking with plumbob
(AS PER SR PAGE 33 , SERIAL NO 169) 25.60
Sundries 0.80
89.00 /Kg
14. 21-22 Painting new iron works such as steel
doors,windows,ventilators,window
bars,balustrades etc, with two coats of
best approved first quality and colour of
synthetic enamel paint over the existing
red oxide priming coat in all floors
including cost of priming coat etc,
complete. Complying with standard
specification .( The make,quality and
colour of paint should be got approved
by the executive engineer before use of
works.
a) 1.33 Lit Red oxide primer 135.60 Lit 180.35
0.70 Nos Painter/varnisher 1st class 688.00 Each 481.60
sundries 2.05
``

10 M2 664.00
1 M2 66.40

b) 2.22 Lit Synthetic enamel paint fof iron 225.40 Lit 500.39
1.10 Nos Painter/varnisher 1st class 688.00 Each 756.80
sundries 2.81
10 M2 1260.00
1 M2 126.00

a+b =( 66.40+126.00) 1 M2 192.40

15. 21-22 Random Rubble masonry in cement


mortar 1:5, (one of cement and five of
sand) using selected stones and bond
stones in foundation and basement
including dewatering wherever
necessary proper setting , curing etc.,
complete in all respects, complying with
relevant standard specifications.

10.00 M3 Rough stone for masonry. 815.50 M3 8155.00


1.00 M3 Bond stone 1012.50 M3 1012.50
3.40 M3 C.M 1:5 3277.00 M3 11141.80
7.10 Nos Mason I class 861.00 Nos 6113.10
10.60 Nos Mason II class 804.00 Nos 8522.40
14.10 Nos Mazdoor I class 562.00 Nos 7924.20
14.10 Nos Mazdoor II class 461.00 Nos 6500.10
49369.10
sundries 0.90
Rate for 10 M3 49370.00
Rate for 1 M3 4937.00

16. 21-22 Weathering course using concrete


broken brick jelly 20mm gauge in pure
slacked lime(no sand to be used) over
RCC Roof slab. The proportion of broken
jelly to slaked lime being 32:12.5 cft well
beaten by wooden beaters for giving
required slope and thickness requiredetc,
.complying with standard specification
and as directed by the departmental
officers .
12.8 M3 Brick jelly 20mm 993.50 M3 12716.80
5.00 M3 Unslakedpollachi lime 4147.95 M3 20739.75
1.80 Nos Mason 1st class 861.00 Each 1549.80
17.70 Nos Mazdoor cat-1 562.00 Each 9947.40
14.10 Nos Mazdoor cat-2 461.00 Each 6500.10
``

10 M2 51453.85
1 M2 5154.40

17. 21-22 Finishing the top of roof with one course


of machine pressed tiles of size
23x23x2mm of approved quality laid in
cement mortar 1:3, mixed with 2% of
water proofing compound by weight of
cement used and pointed with same
oiled mortar including mixing of red oxide
etc, complete. complying with standard
specification and as directed by the
departmental officers
Sub data for pointing- 10m2
0.04 M3 Cement mortar 1:3 4421.30 M3 176.85
2.2 Nos Mason 2nd class 804.00 Each 1768.80
0.5 Nos Mazdoor cat-1 562.00 Each 281.00
1.1 Nos Mazdoor cat-2 461.00 Each 507.10
0.384 kg Water proof compound 42.30 kg 16.24
10 M2 2750.00
For pointing 1 M2 275.00
189.00 Nos Pressed tiles23x23x2cm 16314.40 1000.0 3083.42
0
0.12 M3 Cement mortar 1:3 4421.30 M3 530.56
1.152 kg Water proof compound 42.30 kg 48.73
10.00 M2 Pointing with Cement mortar 1:3 275.00 M2 2750.00
1.10 Nos Mason 1st class 861.00 Each 947.10
2.10 Nos Mason 2nd class 804.00 Each 1688.40
2.20 Nos Mazdoor cat-1 562.00 Each 1236.40
1.10 Nos Mazdoor cat-2 461.00 Each 507.10
10 M2 10791.71
1 M2 1079.00

18. 21-22 Painting with multicolourpanchavarnam


with good emulsion paint. Complete for
the vimanam/gopuram including cost
and conveyance of all materials, labour
charges including artist painter working
in the height , lifting of material,cost of
brushes etc,complete which includes all
extra for scaffolding
a) Vimanam / gopuram of 4.5m height
excluding kalkaram
1.65 Lit Wall primer 146.10 Lit 241.07
4.00 Lit R.M Good emulsion paint 1,2 & 3 coats 292.70 Lit 1170.80
all shading
``

2.00 Nos Asst.painter 570.00 Each 1140.00


3.00 Nos Artist painter 1st class 1080.00 Each 3240.00
3.00 Nos Artist painter 2nd class 911.00 Each 2733.00
1.50 Nos Mazdoor 1st class 562.00 Each 843.00
Cost of brushes, putty, cotton wastage 7.13
10 M2 9375.00
1 M2 937.50
19. 21-22 Painting old wood works with two coats
of best approved first quality and colour
of synthetic enamel paint including
ordinary scrapping using brushes and
neat finishing etc,complete. Complying
with standard specification .( The
make,quality and colour of paint should
be got approved by the executive
engineer before use of works.
10.00 M2 Through scrapping 12.50 M2 125.00
2.22 lit Synthetic enamel paint fof wood 236.60 lit 525.25
1.20 Nos Painter/varnisher 1st class 688.00 Each 825.60
10 M2 1475.85
1 M2 147.60
20. 21-22 Painting old iron works such as steel
doors,windows,ventilators,windowbars,b
alustradesetc, with two coats of best
approved first quality and colour of
synthetic enamel paint including ordinary
scrapping using brushes and neat
finishing etc,complete. Complying with
standard specification .( The make,quality
and colour of paint should be got
approved by the executive engineer
before use of works.
10.00 M2 Through scrapping 7.90 M2 79.00
1.89 lit Synthetic enamel paint fof iron 225.40 lit 426.00
1.11 Nos Painter/varnisher 1st class 688.00 Each 763.68
10 M2 1268.68
1 M2 126.90

21. 21-22 Gravel backing for revetment and apron


in layers not exceeding 15 cm thick,
including watering consolidation and
trimming the top surface to receive the
rough stone and etc., complete as per
standard specification etc, complete.
``

11.60 M3 Gravel 586.80 M3 6806.88


7.10 Nos Mazdoor I class 562.00 Nos 3990.20
3.50 Nos Mazdoor II class 461.00 Nos 1613.50
12410.58
sundries 2.42
Rate for 10 M3 12413.00
Rate for 1 M3 1241.30

22. 21-22 Rough stone dry packing for revetment


using new rough stone including wedges
and tools & plants etc , complete
complying with standard specifications.

11.00 M3 Rough stone for revetment 755.50 M3 8310.50


3.50 Nos Wodder I class 556.00 Nos 1946.00
10.60 Nos Mazdoor I class 562.00 Nos 5957.20
7.10 Nos Mazdoor II class 461.00 Nos 3273.10
19486.80
sundries 0.20
Rate for 10 M3 19487.00
Rate for 1 M3 1948.70

23. 21-22 Pointing the step stone with Cement


Mortar 1:3 including cost and conveyance
of all materials, Labour charges for
pointing,curing etc., all complete.

0.04 M3 Cement mortar 1:3 4421.30 M3 176.85


2.20 Nos Mason II class 804.00 Nos 1768.80
0.50 Nos Mazdoor I class 562.00 Nos 281.00
1.10 Nos Mazdoor II class 461.00 Nos 507.10
L.S Add for red oxide 0.25
Rate for 10 M2 2734.00
Rate for 1 M2 273.40
24. 21-22 Laying the floor with plain ceramic tiles of
approved quality,colour and design joint
free of size 305x305x6mm thick of
approved make, quality and colour in all
floors over a base layer of cement mortar
1:3 with 20mm thick and laid straight
alignment and pointed neatly with colour
cement at the rate of 0.40kg/m2 laid
without any air gap in the tiles neatly and
fixing in position as per standard
specifications and as directed by the
departmental officers . The colour and
quality of tiles should be approved by the
``

executive engineer before use of work.


Labour charges and mortar
0.21 M3 Cement mortar 1:3 4421.30 M3 928.43
3.00 kg White cement 22.40 kg 67.20
50.00 kg Colouring pigments 27.00 kg 1350.00
1.2 Nos Mason 1st class 861.00 Each 1033.20
1.0 Nos Mason 2nd class 804.00 Each 804.00
0.5 Nos Stone cutter 1st class 661.00 Each 330.50
1.0 Nos Mazdoor cat-1 562.00 Each 562.00
1.0 Nos Mazdoor cat-2 461.00 Each 461.00
0.5 kg Cotton waste 10.30 kg 5.15
Rate for 10M2 5541.48
108 Nos Plain ceramic tiles of size 305x305x6mm Each 3650.40
10 M2 Labour charges 10 M2 5541.48
Rate for 10M2 10 M2 9191.88
1 M2 919.20

25. 21-22 Dadooing the walls with glazed tiles of


printed design size 150x150x6mm of best
approved quality and colour in all shade
of the glazed tiles in all floor over a base
layer in cement mortar 1:2, 10 mm thick
and laid in situ true alignment and
pointed neatly with colour cement at the
rate of 0.40kg/m2 to suit the colour of
the tiles fixed in position without any
airgap in the tiles neatly etc, complete
complying with standard specification
and as directed by the departmental
officers . . The colour and quality of tiles
should be approved by the executive
engineer before use of work.
445 NOS Glazed tiles of printed design of size 11.00 Each 4895.00
150x150x6mm
0.1 M3 Cement mortar 1:2 5851.70 M3 585.17
4.0 Kg White cement 22.40 Kg 89.60
1.1 Nos Mason 1st class 861.00 Each 947.10
4.1 Nos Mason 2nd class 804.00 Each 3296.40
2.7 Nos Mazdoor cat-1 562.00 Each 1517.40
3.3 Nos Mazdoor cat-2 461.00 Each 1521.30
10 M2 12851.97
1 M2 1285.00

26. 21-22 Laying the floors with new CC laminated


tiles (like dora tiles, eurocon
tiles ,antiskid) of 20mm thick approved
special quality and set in CM 1:3 20 mm
``

thick using river sand and pointing with


colour cement at the rate of 0.40kg/m2
and mixing with colour pigment at the
rate of 0.30kg/m2 including finishing
etc,complete. complying with standard
specification and as directed by the
departmental officers . . The colour and
quality of tiles should be approved by the
executive engineer before use of work.
10.5 NOS Eurocon tiles with antiskid 58.34 Each 612.57
0.21 M3 Cement mortar 1:3 4421.30 M3 928.47
1.1 Nos Mason 1st class 861.00 Each 947.10
1.1 Nos Mason 2nd class 804.00 Each 884.40
2.2 Nos Mazdoor cat-1 562.00 Each 1236.40
2.2 Nos Mazdoor cat-2 461.00 Each 1014.20
4.0 kg Colour cement 27.00 kg 108.00
3.0 Kg Colouring pigments 27.00 Kg 81.00
L.S Sundries 2.86
10 M2 5815.00
1 M2 581.50

27. Paving the floor with granite slab 18mm


thick of approved quality ,over a base
layer of cement mortar 1:3 (one cement
three sand) 20mm thick and laid straight
alignment and pointed neatly with same
cement mortar without any air gap in the
slab neatly and polishing ,curing, fixing in
position as per standard specifications
and as directed by the departmental
officers. The quality of slab should be got
approved by the executive engineer
before use on work.

Flooring

10.00 M2 Granite flooring (jet black) 18 to 20mm 1720.00 M2 17200.00


0.21 M3 Cement mortar 1:3 4421.30 M3 928.47
18.0 kg White cement 22.40 kg 403.20
3.00 Nos Mason 1st class 861.00 Each 258.30
1.25 Nos Mason 2nd class 804.00 Each 1005.00
8.00 Nos Mazdoor 1s class 562.00 Each 4496.00
7.00 Nos Mazdoor 2nd class 461.00 Each 3227.00
0.50 Nos Stone cutter 1st class 661.00 Each 330.50
Cutting blade at 12% of labour charges 3341.82
Polishing
1.25 Nos Carborundum stones rough (80) 66.40 Each 83.00
``

0.75 Nos Carborundum stones rough (200) 88.70 Each 66.53


0.30 Nos Carborundum stones rough (360) 101.70 Each 30.51
1.00 kg Oxalic acid 38.40 kg 38.40
0.25 kg Tin oxide 143.80 kg 35.95
1.00 kg Granite powder 4.50 kg 4.50
0.50 kg Cotton waste 10.30 kg 5.15
1.00 M2 Kithan bag 15.00 M2 15.00
10.00 M2 Polishing machine hire charges 600.00 M2 6000.00
Rate for 10 M2 37469.33
Rate for 1 M2 3747.00

28. Flooring with cut stone slab of size


600mmx600mm and other sizes suitable
for site requirement not less than 100mm
thick with machine cut edges and top
surface dressed as directed by the
departmental officers including cost and
conveyance of materials to site and
labour charges for paving and pointing
with cement mortar 1:5 & combination
mortar 1:1:5 etc complete.

Combination Mortar 1:1:5

288 KG Cement 5960.00 KG 1716.48


1.00 M3 Sand for mortar 1460.50 M3 1460.50
0.20 M3 Shell lime slacked and screened 3449.82 M3 689.96
1.00 M3 Grinding charges 242.00 M3 242.00
1.00 M3 Mixing charges 100.00 M3 100.00
2.00 KG Gallnut 80.00 KG 160.00
1.00 KG Jaggery 55.00 KG 55.00
M3 4423.94

Pointing withCombination Mortar 1:1:5

0.06 M3 Combination Mortar 1:1:5 4423.94 M3 265.44


1.60 M3 Mason 2nd class 804.00 M3 1286.40
0.50 Nos Mazdoor 1st class 562.00 Each 281.00
1.10 Nos Mazdoor 2nd class 461.00 Each 507.10
10.M2 2339.94

Main Data

1.00 M3 Cut stone dressed to size and shape for 14631.96 M3 14631.96
``

all faces of 10cm thick


0.37 M3 Cement mortar 1:3 4421.30 M3 1635.88
10.00 M2 Pointing with Combination Mortar 1:1:5 2339.94 10.M2 2339.94
1.10 Nos Mason 1st class 861.00 Each 947.10
1.10 Nos Mason 2nd class 804.00 Each 884.40
2.20 Nos Mazdoor 1st class 562.00 Each 1236.40
1.10 Nos Mazdoor 2nd class 461.00 M2 507.10
10.00 M2 Labour charges for 3 live dressing at top 1076.43 M2 10764.30
32947.08
M2 3295.00

DATA

S.NO QTY PER DESCRIPTION RATE PER AMOUNT

1 Scrapping the old enamel paint by manual labour and


cleaning the surface including of all charges

1.00 M2 As per schedule item no 79 ( page-26) 8.50 M2 4.50

Add sundries 0.50

M2 9.00

2 Proving scaffolding for Vimanams/gopurams with


casurina posts, wherever necessary for farm work
and providing net-lawn/ pvc mesh and providing
ladder arrangements for country wood for working,
``

Hire charges only for erection

(A) 1.00 M2 For gopuram/ vimanam up to 15’-0’’ Ht 232.00 M2 232.00

(B) 1.00 M2 For gopuram/ vimanam above 15’-0’’ up to 25’-0’’ Ht 311.00 M2 311.00

(C) 1.00 M2 For gopuram/ vimanam above 25’-0’’ up to 50’-0’’ Ht 397.00 M2 397.00

3. Cleaning the wall surface with brush and water and


Repainting two coats of newly plastered wall surface
with Water based exterior emulsion paint of first
including thorough scrapping,clean removal of
dirt,and including necessary plaster of paris
putty,wherever required etc, complying with
standard specification

10.00 M2 Cleaning the plastered surface 6.65 M2 66.50

1.40 Litre Water based exterior emulsion paint 292.70 Litre 409.78

0.98 Litre Primer 146.10 Litre 143.18

2.20 Nos Painter 1st class 688.00 Nos 1513.60

L.S Sundries for brushes, sand paper,plaster of paris L.S 6.94


putty, etc.
10 M2 2140.00

1 M2 214.00

4. Cleaning the wall surface with brush and water and


Repainting with multicolourpanchavarnam with good
emulsion paint. Complete for the vimanam/gopuram
including cost and conveyance of all materials,
labour charges including artist painter working in the
height , lifting of material,cost of brushes
etc,complete which includes all extra for scaffolding

(A) Vimanam / gopuram of 15’-0’’ height excluding


kalkaram

1.65 Lit Wall primer 146.10 Lit 241.07

4.00 Lit R.M Good emulsion paint 1,2 & 3 coats all shading 292.70 Lit 1170.80

2.00 Nos Asst.painter 570.00 Each 1140.00


``

3.00 Nos Artist painter 1st class 1080.00 Each 3240.00

3.00 Nos Artist painter 2nd class 911.00 Each 2733.00

1.50 Nos Mazdoor 1st class 562.00 Each 843.00

L.S - Thinner and seadoil including all shadings L.S - 80.00

L.S - Cost of brushes, putty, cotton wastage L.S - 52.13

100 Sft 9500.00

1 M2 1022.58

(B) Vimanam / gopuram Above 15’-0’’up to 25’-0’’


height excluding kalkaram

1.65 Lit Wall primer 146.10 Lit 241.07

4.00 Lit R.M Good emulsion paint 1,2 & 3 coats all shading 292.70 Lit 1170.80

3.00 Nos Asst.painter 570.00 Each 1710.00

3.00 Nos Artist painter 1st class 1080.00 Each 3240.00

3.00 Nos Artist painter 2nd class 911.00 Each 2733.00

2.50 Nos Mazdoor 1st class 562.00 Each 1405.00

L.S - Thinner and seadoil including all shadings L.S - 80.00

L.S - Cost of brushes, putty, cotton wastage L.S - 93.13

100 Sft 10673.00

1 M2 1148.84

(B) Vimanam / gopuram Above 25’-0’’up to 50’-0’’


height excluding kalkaram

2.00 Lit Wall primer 146.10 Lit 292.20

5.00 Lit R.M Good emulsion paint 1,2 & 3 coats all shading 292.70 Lit 1463.50

5.00 Nos Asst.painter 570.00 Each 2850.00


``

4.00 Nos Artist painter 1st class 1080.00 Each 4320.00

4.00 Nos Artist painter 2nd class 911.00 Each 3644.00

2.75 Nos Mazdoor 1st class 562.00 Each 1545.50

L.S - Thinner and seadoil including all shadings L.S - 80.00

L.S - Cost of brushes, putty, cotton wastage L.S - 94.80

100 Sft 14290.00

1 M2 1538.18

5. Painting old iron works such as steel


doors,windows,ventilators,windowbars,balustradeset
c, with two coats of best approved first quality and
colour of synthetic enamel paint including ordinary
scrapping using brushes and neat finishing
etc,complete. Complying with standard specification .
( The make,quality and colour of paint should be got
approved by the executive engineer before use of
works.

10.00 M2 Through scrapping 7.90 M2 79.00

1.89 lit Synthetic enamel paint fof iron 225.40 lit 426.00

1.11 Nos Painter/varnisher 1st class 688.00 Each 763.68

Sundries 11.32

10 M2 1280.00

1 M2 128.00

6. Cleaning the wall surface with brush and water and


Repainting two coats of newly plastered wall surface
with Multi colour Water based exterior emulsion
paint of first quality and of approved colour, 3 coats
scrapping,clean removal of dirt,and including
necessary plaster of paris putty,wherever required
etc, complying with standard specification for
(ceiling)
``

Rate of panchavarnam painting

Vimanam / gopuram of 15’-0’’ height = 1022.58/M2


So, 2/3 x 1022.58 = 681.72

( For ceiling ) 1 M2 681.72

7. Removing the old varnish for doors by manual labour


and revarnishing wood work with best shellac amd
Teakwood natural finishing including preparation of
surfaces with sand papering with priming etc,
complete complying with standard specifications and
as directed bu Departmental officers

10.00 M2 Through scrapping 8.50 M2 85.00

1.20 lit Best varnish 268.60 lit 322.32

0.90 lit Leinsed oil- Berilead 23.50 lit 21.15

1.10 No Varnisher 1st class 688.00 Each 756.80

1.10 No Varnisher 2nd class 562.00 Each 618.20

Sundries 16.53

10 M2 1820.00

1 M2 182.00

DETAILED ESTIMATE

S.NO DESCRIPTION NOS LEN BRD DEP CONTENTS

1. Scrapping the old enamel paint by manual


labour and cleaning the surface including of
all charges

Moolasthaanam Outer walls ( Alround ) 1x2 34.92 - 10.67 745.19

Add for folds 30% - - - - 223.56

Pillars alround and in front of mandapam 1x26 6.00 - 10.67 1664.52

Add for folds 30% - - - - 499.36

Praharam ceiling 1x1 62.33 34.50 - 2150.39


``

Alround moolasthaanam deduct Temple 1x1 20.25 - 14.67 297.07 (-)

Moolasthaanam praharamandapam

Beam alround inside 1x1 181.67 - 1.00 181.67

Beam alround Outerside 1x1 193.67 - 1.00 193.67

Cross beams ( sides ) 2x2 31.50 - 1.00 126.00

Cross beams ( sides ) 2x2 9.25 - 1.50 55.50

Moolasthaanam upapeetam

Praharamandapam alround 1x1 193.67 - 1.50 290.51

Inner praharamandapam

Including ceiling and oyyaali mandapam 1x1 108.25 84.25 - 9120.06

Deduct praharamandapam 1x1 62.33 34.50 - 2150.39 (-)

Deduct Rajagopuram portions

East side 1x1 23.25 - 10.00 232.50 (-)

south side 1x1 18.75 - 10.00 187.50 (-)

west side 1x1 18.75 - 10.00 187.50 (-)

North side 1x1 18.75 - 10.00 187.50 (-)

Pillars alround oyyaali mandapam 1x39 9.00 - 10.00 3510.00

Add for folds 30% - - - - 1053.00

oyyaali mandapam wall inside alround 1x2 192.50 - 11.00 4235.00

Deduct Rajagopuram portions

East side 1x1 23.25 - 11.00 255.75 (-)

south side 1x1 18.75 - 11.00 206.25 (-)

west side 1x1 18.75 - 11.00 206.25 (-)


``

North side 1x1 18.75 - 11.00 206.25 (-)

Inner praharamandapam -

Wall above roof of oyyaali mandapam 1x2 321.00 - 7.25 4654.50

Deduct Rajagopuram portions

East side 1x2 23.25 - 7.25 337.1 (-)

south side 1x2 18.75 - 7.25 271.88 (-)

west side 1x2 18.75 - 7.25 271.88 (-)

North side 1x2 18.75 - 7.25 271.88 (-)

Add sides of cross walls of oyyaali 2x2 10.00 - 11.00 880.00


mandapam

Deduct top of cross wall 2x2 10.00 0.75 - 30.00 (-)

Add sides of L Beam over oyyaali mandapam 1x2 321.00 - 1.00 642.00

Deduct Rajagopuram portions

East side 1x2 23.25 - 1.00 46.50 (-)

south side 1x2 18.75 - 1.00 37.50 (-)

west side 1x2 18.75 - 1.00 37.50 (-)

North side 1x2 18.75 - 1.00 37.50 (-)

Add sides of L Beam below roof of outer


praharamandapam, alround moolasthaanam

Outer side Alround 1x1 193.50 - 1.00 193.50

Inner side Alround 1x1 181.50 - 1.00 181.50

Add for uncovered Measurements L.S - - - 1000.00

Add sudhai pillars and wall l.s - - - 1500.00

Salagaram over oyyaali mandapam alround 1x1 389.50 - 13.50 5258.25


``

Add for folds 30 % - - - - 1577.48

Parapet wall over mandapam 1x1 305.00 - 4.00 1220.00

Outside alround cross beams 1x2 88.25 4.67 - 824.26

Outside alround cross beams 1x22 10.00 4.67 - 1027.40

East Rajagopuram

Kalkaram ( front & rear sides ) 2x1 25.50 - 19.50 994.50

Kalkaram ( sides ) 2x1 16.50 - 19.50 643.50

Deduct for opening both sides 2x1 9.00 14.50 261.00 (-)

Add for folds 30 % - - - - 413.10

Kalkaram inside Alround 1x2 22.25 - 17.50 778.75

Add extra at ends 2x2 1.50 - 16.00 96.00

Staircase room Alround 1x2 13.25 - 17.50 463.75

Sides of beam 2x2 6.00 - 0.75 18.00

Above gopuram

Front & rear sides 1x2 18.25 - 38.50 1405.25

Sides 1x2 12.25 - 38.50 943.25

Add for vigrahams - - - - 1500.00

Add for folds 100 % - - - - 3848.50

South Rajagopuram

Kalkaram ( front & rear sides ) 2x1 23.00 - 11.50 529.00

Kalkaram ( sides ) 2x1 17.25 - 11.50 396.75

Deduct for opening both sides 2x1 6.00 - 10.00 120.00 (-)
``

Add for folds 30 % - - - - 313.73

Kalkaram inside Alround 1x2 24.08 - 11.25 541.80

Add extra at ends 2x2 1.50 - 10.25 61.50

Ceiling 1x2 13.83 10.25 - 141.76

Above gopuram

Front & rear sides 1x2 16.50 - 25.00 825.00

Sides 1x2 10.13 - 25.00 506.50

Add for vigrahams - - - - 750.00

Add for folds 100 % - - - - 2081.25

West Rajagopuram

Kalkaram ( front & rear sides ) 2x1 23.00 - 11.50 529.00

Kalkaram ( sides ) 2x1 17.25 - 11.50 396.75

Deduct for opening both sides 2x1 6.00 - 10.25 123.00 (-)

Add for folds 30 % - - - - 240.83

Kalkaram inside Alround 1x2 24.25 - 12.75 618.38

Add extra at ends 2x2 1.50 - 10.25 61.60

Ceiling 1x1 14.00 10.25 - 143.50

Above gopuram

Front & rear sides 1x2 16.50 - 25.00 825.00

Sides 1x2 10.13 - 25.00 506.50

Add for vigrahams - - - - 750.00

Add for folds 100 % - - - - 2081.25

North Rajagopuram

Kalkaram ( front & rear sides ) 2x1 23.00 - 11.50 529.00


``

Kalkaram ( sides ) 2x1 17.25 - 11.50 396.75

Deduct for opening both sides 2x1 6.00 - 10.00 120.00 (-)

Add for folds 30 % - - - - 241.73

Kalkaram inside Alround 1x2 24.08 - 11.25 541.80

Add extra at ends 2x2 1.50 - 10.25 61.50

Ceiling 1x1 13.83 - 10.25 141.76

Above gopuram

Front & rear sides 1x2 16.50 - 25.00 825.00

Sides 1x2 10.13 - 25.00 506.50

Add for vigrahams - - - - 750.00

Add for folds 100 % - - - - 2081.25

Elevated inner praharamandapam 1x1 318.00 6.75 - 2146.50

Vimanam over Moolasthaanam

Vimanam Bottom 1x2 9.75 - 3.50 68.25

Vimanam Bottom 1x2 12.50 - 3.50 87.50

Vimanam Bottom 1x2 9.63 - 1.83 35.25

Vimanam Bottom 1x2 7.38 - 1.83 27.01

Parapet alround 1x1 11.00 22.00 - 242.00

Mahamandapam sides 1x2 6.50 5.25 - 68.25

Mahamandapam head alround 1x2 9.25 - 2.00 37.00

Add for vigrahams - - - - 250.00

Add for folds 50 % - - - - 407.61

Parapet wall alround mandapam 1x1 40.00 5.75 - 230.00


``

Vimanam bottom portion Alround 1x1 43.00 - 3.50 150.50

Kodungai Alround 1x1 56.00 3.25 - 182.00

Terrace of amman sannidhi 1x1 193.67 - 3.50 677.85

Outer praharamandapam

Pillars Alround 1x72 10.67 - 19.08 14658.02

Add bodiyal in pillars 72x3 3.50 3.50 - 2646.00

Add for folds 25 % - - - - 4326.00

Ceiling of east & west 1x2 182.00 23.50 - 8554.00

Ceiling of north & south 1x2 101.00 23.50 - 4747.00

L beam alround outside 1x1 668.00 - 1.00 668.00

L beam alround Inside 1x1 660.00 - 1.00 660.00

Inner beam alround outside 1x1 472.00 - 1.00 472.00

Inner beam alround Inside 1x1 464.00 - 1.00 464.00

Tee beam sides 4x6x2 21.83 - 1.00 1047.84

Tee beam sides 4x12x2 21.83 - 1.00 2095.68

Kodungai outer alround 1x1 674.00 - 7.25 4886.50

Kodungai Inner alround 1x1 486.00 - 7.25 3523.50

Deductions

East Rajagopuram 1x1 25.50 7.25 - 184.88 (-)

South Rajagopuram 1x1 23.00 7.25 - 166.75 (-)

West Rajagopuram 1x1 23.00 7.25 - 166.75 (-)

North Rajagopuram 1x1 23.00 7.25 - 166.75 (-)

Vigraham over roof


``

Outer alround 1x1 655.5 3.75 - 2458.13

Inner alround 1x1 467.5 3.75 - 1753.13

Dwarf wall alround between pillars 1x1 660.00 3.75 - 2475.00

Deduct outer pillars 1x48 2.67 3.75 - 480.60 (-)

Garbaharam outside alround 1x4 8.25 - 11.08 365.54

Add for folds 30 % - - - - 109.69

Vimanam bottom alround 1x4 6.50 - 1.00 26.00

Paudial alround Mandapam 1x3.14 6.50 - 4.00 81.64

Sloped portion 1x1 12.00 - 3.00 36.00

Add for vigrahams - - - - 200.00

Add for folds 50 % - - - - 171.82

Compound wall

Compound wall alround 1x1 79.50 - 10.42 828.39

Deduct gateway 1x1 6.00 - 9.75 58.50 (-)

Add pillars Alround 1x9 3.00 - 3.33 89.91

Gate pillars Alround 1x2 5.00 - 5.50 55.00

127189.39 Sft

11816.18 M2

2. Proving scaffolding for Vimanams/gopurams


with casurina posts, wherever necessary for
farm work and providing net-lawn/ pvc
mesh and providing ladder arrangements for
country wood for working, Hire charges only
for erection

(A) For vimanam up to 15’-0’’ Height


``

Vimanam over moolasthaanam above


terrace

Front & Rear sides 2x1 21.00 - 6.50 273.00

Sides 2x1 18.50 - 6.50 240.50

Above triangular portion 2x1 9.25 - 10.00 185.00

Sloped portion both sides 1x2 21.00 14.00 - 588.00

Vimanam over sakthi mandapam

Garbaharam alround 1x4 15.25 - 11.08 675.88

Vimanam above 1x4 14.25 - 12.00 684.00

Top covering 1x1 13.25 13.25 - 175.56

2821.94 sft

262.16 M2

(B) For Gopuram & vimanam from 15’-0’’ to


25’-0’’ Height.

South Rajagopuram

Up to kalkaram Top 1x2 31.00 - 11.50 713.00

Ends 1x2 25.25 - 11.50 580.75

Rajagopuram Above front & Rear sides 1x2 26.00 - 20.00 1040.00

Ends 1x2 18.13 - 20.00 725.20

Triangular portion 1x2 7.00 - 9.00 126.00

Sloped portion 1x2 21.00 - 11.75 493.50

West Rajagopuram

Up to kalkaram Top 1x2 31.00 - 11.50 713.00

Ends 1x2 25.25 - 11.50 580.75


``

Rajagopuram Above front & Rear sides 1x2 26.00 - 20.00 1040.00

Ends 1x2 18.13 - 20.00 725.20

Triangular portion 1x2 7.00 - 9.00 126.00

Sloped portion 1x2 21.00 - 11.75 493.50

North Rajagopuram

Up to kalkaram Top 1x2 31.00 - 11.50 713.00

Ends 1x2 25.25 - 11.50 580.75

Rajagopuram Above front & Rear sides 1x2 26.00 - 20.00 1040.00

Ends 1x2 18.13 - 20.00 725.20

Triangular portion 1x2 7.00 - 9.00 126.00

Sloped portion 1x2 21.00 - 11.75 493.50

11035.35 sft

1025.21 M2

(C) For Gopuram & vimanam from 25’-0’’ to


50’-0’’ Height.

Up to kalkaram Top 1x2 33.50 - 19.50 1306.50

Ends 1x2 24.50 - 19.50 955.50

Rajagopuram Above front & Rear sides 1x2 27.38 - 33.50 1834.46

Ends 1x2 20.25 - 33.50 1356.75

Triangular portion 1x2 8.00 - 10.00 160.00

Sloped portion 1x2 21.25 - 13.00 552.50

For kalkaram alround inner


praharamandapam

Outside alround 1x1 347.60 - 20.00 6952.00


``

Excluding gopurams 1x1 273.00 - 8.00 2184.00

Top cover 1x1 310.00 - 8.00 2480.00

17781.71 sft

1651.96 M2

3. Cleaning the wall surface with brush and


water and Repainting two coats of newly
plastered wall surface with Water based
exterior emulsion paint of first quality and
of approved colour over a priming coat
including thorough scrapping,clean removal
of dirt,and including necessary plaster of
paris putty,wherever required etc,
complying with standard specification

Moolasthaanam Outer walls ( Alround ) 1x2 34.92 - 10.67 745.19

Add for folds 30% - - - - 223.56

Moolasthaanam praharamandapam

Beam alround inside 1x1 181.67 - 1.00 181.67

Beam alround Outerside 1x1 193.67 - 1.00 193.67

Cross beams ( sides ) 2x2 31.50 - 1.00 126.00

Cross beams ( sides ) 2x2 9.25 - 1.50 55.50

Moolasthaanam upapeetam

Praharamandapam alround 1x1 193.67 - 1.50 290.51

Inner praharamandapam

Including ceiling and oyyaali mandapam 1x2 192.50 - 11.00 4235.00

Deduct Rajagopuram portions

East side 1x1 23.25 - 11.00 255.75 (-)

south side 1x1 18.75 - 11.00 206.25 (-)


``

west side 1x1 18.75 - 11.00 206.25 (-)

North side 1x1 18.75 - 11.00 206.25 (-)

Inner praharamandapam -

Wall above roof of oyyaali mandapam 1x2 321.00 - 7.25 4654.50

Deduct Rajagopuram portions

East side 1x2 23.25 - 7.25 337.1 (-)

south side 1x2 18.75 - 7.25 271.88 (-)

west side 1x2 18.75 - 7.25 271.88 (-)

North side 1x2 18.75 - 7.25 271.88 (-)

Add sides of cross walls of oyyaali 2x2 10.00 - 11.00 880.00


mandapam

Deduct top of cross wall 2x2 10.00 0.75 - 30.00 (-)

Add sides of L Beam over oyyaali mandapam 1x2 321.00 - 1.00 642.00

Deduct Rajagopuram portions

East side 1x2 23.25 - 1.00 46.50 (-)

south side 1x2 18.75 - 1.00 37.50 (-)

west side 1x2 18.75 - 1.00 37.50 (-)

North side 1x2 18.75 - 1.00 37.50 (-)

Add sides of L Beam below roof of outer


praharamandapam, alround moolasthaanam

Outer side Alround 1x1 193.50 - 1.00 193.50

Inner side Alround 1x1 181.50 - 1.00 181.50

Add for uncovered Measurements L.S - - - 1000.00


``

Parapet wall over inner praharamandapam 1x1 305.00 - 4.00 1200.00

Outside alround cross beams 1x2 88.25 4.67 - 824.26

Outside alround cross beams 1x22 10.00 4.67 - 1027.40

East Rajagopuram

Kalkaram ( front & rear sides ) 2x1 25.50 - 19.50 994.50

Kalkaram ( sides ) 2x1 16.50 - 19.50 643.50

Deduct for opening both sides 2x1 9.00 14.50 261.00 (-)

Add for folds 30 % - - - - 413.10

Kalkaram inside Alround 1x2 22.25 - 17.50 778.75

Add extra at ends 2x2 1.50 - 16.00 96.00

Staircase room Alround 1x2 13.25 - 17.50 463.75

Sides of beam 2x2 6.00 - 0.75 18.00

South Rajagopuram

Kalkaram ( front & rear sides ) 2x1 23.00 - 11.50 529.00

Kalkaram ( sides ) 2x1 17.25 - 11.50 396.75

Deduct for opening both sides 2x1 6.00 - 10.00 120.00 (-)

Add for folds 30 % - - - - 313.73

Kalkaram inside Alround 1x2 24.08 - 11.25 541.80

Add extra at ends 2x2 1.50 - 10.25 61.50

Ceiling 1x2 13.83 10.25 - 141.76

West Rajagopuram

Kalkaram ( front & rear sides ) 2x1 23.00 - 11.50 529.00

Kalkaram ( sides ) 2x1 17.25 - 11.50 396.75


``

Deduct for opening both sides 2x1 6.00 - 10.25 123.00 (-)

Add for folds 30 % - - - - 240.83

Kalkaram inside Alround 1x2 24.25 - 12.75 618.38

Add extra at ends 2x2 1.50 - 10.25 61.60

Ceiling 1x1 14.00 10.25 - 143.50

North Rajagopuram

Kalkaram ( front & rear sides ) 2x1 23.00 - 11.50 529.00

Kalkaram ( sides ) 2x1 17.25 - 11.50 396.75

Deduct for opening both sides 2x1 6.00 - 10.00 120.00 (-)

Add for folds 30 % - - - - 241.73

Kalkaram inside Alround 1x2 24.08 - 11.25 541.80

Add extra at ends 2x2 1.50 - 10.25 61.50

Ceiling 1x1 13.83 - 10.25 141.76

Elevated inner praharamandapam 1x1 318.00 6.75 - 2146.50

Parapet wall alround mandapam 1x1 40.00 5.75 - 230.00

Vimanam bottom portion Alround 1x1 43.00 - 3.50 150.50

Terrace of amman sannidhi 1x1 193.67 - 3.50 677.85

Ceiling of east & west 1x2 182.00 23.50 - 8554.00

Ceiling of north & south 1x2 101.00 23.50 - 4747.00

L beam alround outside 1x1 668.00 - 1.00 668.00

L beam alround Inside 1x1 660.00 - 1.00 660.00

Inner beam alround outside 1x1 472.00 - 1.00 472.00

Inner beam alround Inside 1x1 464.00 - 1.00 464.00


``

Tee beam sides 4x6x2 21.83 - 1.00 1047.84

Tee beam sides 4x12x2 21.83 - 1.00 2095.68

Kodungai outer alround 1x1 674.00 - 7.25 4886.50

Kodungai Inner alround 1x1 486.00 - 7.25 3523.50

Deductions

East Rajagopuram 1x1 25.50 7.25 - 184.88 (-)

South Rajagopuram 1x1 23.00 7.25 - 166.75 (-)

West Rajagopuram 1x1 23.00 7.25 - 166.75 (-)

North Rajagopuram 1x1 23.00 7.25 - 166.75 (-)

Vigraham over roof

Outer alround 1x1 655.5 3.75 - 2458.13

Inner alround 1x1 467.5 3.75 - 1753.13

Dwarf wall alround between pillars 1x1 660.00 3.75 - 2475.00

Deduct outer pillars 1x48 2.67 3.75 - 480.60


(-)

Garbaharam outside alround 1x4 8.25 - 11.08 365.54

Add for folds 30 % - - - - 109.69

Compound wall

Compound wall alround 1x1 79.50 - 10.42 828.39

Deduct gateway 1x1 6.00 - 9.75 58.50 (-)

Add pillars Alround 1x9 3.00 - 3.33 89.91

Gate pillars Alround 1x2 5.00 - 5.50 55.00

60342.69 sft

5605.97 M2
``

4. Cleaning the wall surface with brush and


water and Repainting with
multicolourpanchavarnam with good
emulsion paint. Complete for the
vimanam/gopuram including cost and
conveyance of all materials, labour charges
including artist painter working in the height
, lifting of material,cost of brushes
etc,complete which includes all extra for
scaffolding

(A) For vimanam up to 15’-0’’ Height

Vimanam over Moolasthaanam

Vimanam Bottom 1x2 9.75 - 3.50 68.25

Vimanam Bottom 1x2 12.50 - 3.50 87.50

Vimanam Bottom 1x2 9.63 - 1.83 35.25

Vimanam Bottom 1x2 7.38 - 1.83 27.01

Parapet alround 1x1 11.00 22.00 - 242.00

Mahamandapam sides 1x2 6.50 5.25 - 68.25

Mahamandapam head alround 1x2 9.25 - 2.00 37.00

Add for vigrahams - - - - 250.00

Sakthi Mandapam

Vimanam bottom alround 1x4 6.50 - 1.00 260.00

Pandial alround 1x3.14 6.50 - 4.00 81.64

Sloped portion alround 1x1 12.00 - 3.00 36.00

Add for vigraharam - - - - 200.00

Salagaram alround oyyaali mandapam

Alround 1x1 389.50 13.5 - 5258.25

Deduct east rajagopuram 1x1 23.25 13.5 - 313.88 (-)


``

Deduct south rajagopuram 1x1 18.75 13.5 - 253.13 (-)

Deduct west rajagopuram 1x1 18.75 13.5 - 253.13 (-)

Deduct north rajagopuram 1x1 18.75 13.5 - 253.13 (-)

Pillars alround praharamandapam 1x26 6.00 - 10.67 1664.52

Pillars alround ouyaali mandapam 1x39 9.00 - 10.00 3510.00

10752.40 sft

998.92 M2

(B) For Gopuram & vimanam from 15’-0’’ to


25’-0’’ Height.

South Rajagopuram

Gopuram front “& Rear sides 2x1 16.50 - 25.00 825.00

At ends 2x1 10.13 - 25.00 506.50

Add for vigraham - - - - 750.00

West Rajagopuram

Gopuram front “& Rear sides 2x1 16.50 - 25.00 825.00

At ends 2x1 10.13 - 25.00 506.50

Add for vigraham - - - - 750.00

NorthRajagopuram

Gopuram front “& Rear sides 2x1 16.50 - 25.00 825.00

At ends 2x1 10.13 - 25.00 506.50

Add for vigraham - - - - 750.00

Outer prahara mandapam

Pillars 1x72 10.67 - 19.08 14658.02


``

Add bodiyal in pillars 72x3 3.50 3.50 - 2646.00

23548.52 sft

2187.71 M2

(C) For Gopuram & vimanam from 25’-0’’ to


50’-0’’ Height.

Front & Rear sides 1X2 18.25 - 38.50 1405.25

Sides 1x2 12.25 - 38.50 943.25

Add for vigraham - - - - 1500.00

3848.50 Sft

357.53 M2

5. Painting old iron works such as steel


doors,windows,ventilators,windowbars,balu
stradesetc, with two coats of best approved
first quality and colour of synthetic enamel
brushes and neat finishing etc,complete.
Complying with standard specification .( The
make,quality and colour of paint should be
before use of works.

Prahara mandapam roof below oyyaali 1x1 321.00 - 2.00 1284.00


mandapam

Deduct Rajagopuram portions

East side 1x1 23.25 - 2.00 46.50 (-)

south side 1x1 18.75 - 2.00 37.50 (-)

west side 1x1 18.75 - 2.00 37.50 (-)

North side 1x1 18.75 - 2.00 37.50 (-)

Deduct pillars 1x1 1.25 - 2.00 97.50 (-)

Grills over inner praharamandapam 1x1 181.67 - 2.00 363.34


``

Deduct pillars 1x22 1.00 - 2.00 22.00 (-)

Weld mesh kalkaram 1x2 8.00 - 2.58 41.28

Grills 1x11 4.67 3.25 - 166.95

Grills 1x2 2.75 3.00 - 16.50

1593.57 sft

148.05 M2

6. Cleaning the wall surface with brush and


water and Repainting two coats of newly
plastered wall surface with Multi colour
Water based exterior emulsion paint of first
quality and of approved colour, 3 coats over
a priming coat including thorough
scrapping,clean removal of dirt,and
including necessary plaster of paris
putty,wherever required etc, complying
with standard specification for (ceiling)

Ceiling of praharamandapam alround 1x1 62.33 34.5 - 2150.39


mulasthaanam

Deduct Temple poprtion 1x1 20.25 14.67 - 297.07 (-)

Inner praharamandapam ceiling including 1x1 108.25 84.25 - 9120.06


oyyaali mandapam

Deduct moolasthaana prahara mandapam 1x1 62.33 34.5 - 2150.39 (-)

Deduct Rajagopuram projection

East side 1x1 23.25 - 10.00 232.50

south side 1x1 18.75 - 10.00 187.50 (-)

west side 1x1 18.75 - 10.00 187.50 (-)

North side 1x1 18.75 - 10.00 187.50 (-)

Outer praharamandapam ceiling 36x3.1 4.00 4.00 - 1808.64


``

4
10301.63 sft

957.04 M2

7. Removing the old varnish for doors by


manual labour and revarnishing wood work
with best shellac amd with fine best varnish
of approved quality varnish of Teakwood
natural finishing including preparation of
surfaces with sand papering with priming
etc, complete complying with standard
specifications and as directed bu
Departmental officers

TEAK WOOD DOOR

East Rajagopuram 1x2 25.50 - 19.50 994.50

south Rajagopuram 2x2 6.00 - 10.00 240.00

West Rajagopuram 1x2 6.00 - 10.25 123.00

North Rajagopuram 1x2 6.00 - 10.25 123.00

Add for folds 25% - - - - 370.13

Sakthi mandapam door 1x2 3.00 - 5.50 33.00

Add for folds 25% - - - - 8.25

Add for moolasthaanam door - - - - 60.00

1951.88 sft

181.33 M2
``

ABSTRACT ESTIMATE

S.NO QTY DESCRIPTION OF WORKS RATE PER AMOUNT

1. 11816.18 Scrapping the old enamel paint by manual labour and 9.00 M2 106346.00
cleaning the surface including of all charges

2. Proving scaffolding for Vimanams/gopurams with


casurina posts, wherever necessary for farm work
and providing net-lawn/ pvc mesh and providing
ladder arrangements for country wood for working,
Hire charges only for erection

(A) 262.16 For gopuram/ vimanam up to 15’-0’’ Ht 232.00 M2 60821.00

(B) 1025.21 For gopuram/ vimanam above 15’-0’’ up to 25’-0’’ Ht 311.00 M2 318840.00
``

(C) 1651.96 For gopuram/ vimanam above 25’-0’’ up to 50’-0’’ Ht 397.00 M2 655828.00

3. 5605.97 Cleaning the wall surface with brush and water and 214.00 M2 1199678.00
Repainting two coats of newly plastered wall surface
with Water based exterior emulsion paint of first
quality and of approved colour over a priming coat
including thorough scrapping,clean removal of
dirt,and including necessary plaster of paris
putty,wherever required etc, complying with
standard specification

4. Cleaning the wall surface with brush and water and


Repainting with multicolourpanchavarnam with good
emulsion paint. Complete for the vimanam/gopuram
including cost and conveyance of all materials,
labour charges including artist painter working in the
height , lifting of material,cost of brushes
etc,complete which includes all extra for scaffolding

(A) 998.92 For gopuram/ vimanam up to 15’-0’’ Ht 1022.58 M2 1021476.00

(B) 2187.71 For gopuram/ vimanam above 15’-0’’ up to 25’-0’’ Ht 1148.84 M2 2513329.00

(C) 357.53 For gopuram/ vimanam above 25’-0’’ up to 50’-0’’ Ht 1538.18 M2 549945.00

5. 148.05 Painting old iron works such as steel 128.00 M2 18950.00


doors,windows,ventilators,windowbars,balustradeset
c with two coats of best approved first quality and
colour of synthetic enamel
brushes and neat finishing etc,complete. Complying
with standard specification .( The make,quality and
colour of paint should be before use of works.

6. 957.04 Cleaning the wall surface with brush and water and 681.72 M2 652433.00
Repainting two coats of newly plastered wall surface
with Multi colour Water based exterior emulsion
paint of first quality and of approved colour, 3 coats
over a priming coat including thorough
scrapping,clean removal of dirt,and including
necessary plaster of paris putty,wherever required
etc, complying with standard specification for
(ceiling)

7. 181.33 Removing the old varnish for doors by manual labour 182.00 M2 33002.00
and revarnishing wood work with best shellac amd
with fine best varnish of approved quality varnish of
``

Teakwood natural finishing including preparation of


surfaces with sand papering with priming etc,
complete complying with standard specifications and
as directed bu Departmental officers

SUB TOTAL 7130648.00

ADD GST 12% 855678.00

PROVISION FOR CENTAGE CHARGES 2 % 170000.00

PROVISION FOR LABOUR WELFARE FUND 1% 85000.00

PROVISION FOR ADVERTISEMENT CHARGES 100000.00

PROVISION FOR CONTIGENCIES & UNFORSEEN 158674.00


ITEMS

TOTAL 8500000.00
``