Professional Documents
Culture Documents
Valeo Technical Paper
Valeo Technical Paper
MD2004-04016
PRODUCTIVITY IMPROVEMENT OF THE HYDRAULIC
MOTOR ASSEMBLY LINE AT VALEO
Stefan Enjem Joe Van Hofwegen
Industrial & Systems Industrial & Systems
Engineering Engineering
Figure 1. Shows the layout of the studied system. Assembly begins at the bottom-left and continues until it
loops back to the EOLT (top-left).
MD2004-04016
Proceedings of KGCOE-MD2004: Multi-Disciplinary Engineering Design Conference Page 3
force applied to keep the connectors in place was 223 During the design process, some of the custom parts
lbs with a hydraulic pressure of 800psi. Since the needed to have a Finite Element Analysis (FEA)
EOLT runs a test with almost 1600psi, a cylinder to performed to assure that they would not deflect when
keep the connectors in place needed to apply a force the system is fully loaded. The main area of concern
of 446 lbs. In order to create a forced seal, the was the back off pin (see Figure 4), which is pressed
pneumatic cylinder must exert enough pressure to up behind the connector assembly once the
overcome the force from the 1600psi hydraulic fluid. connectors are placed into the motor. This pin’s
A load safety factor of 25% was used to account for purpose is to keep the connectors from backing out of
frictional and other losses. [7] the motor when the hydraulic fluid is pressurized
Load Safety Factor – 25% during testing. If the connectors back off more than a
FR = (446 * .25) + 446 = 557 lbs few thousandths of an inch, the seal will be broken,
Concept Cylinder the test will fail, and fluid will leak.
F = pi * 1.252 * 160 = 785 lbs
From Bimba Supplied Power Factor (pf = 5) [5]
F = 5 * 160 = 800 lbs
Cylinder Safety Factor
( 557 lbs ) / ( 800 lbs ) = 1.44
According to the analysis of the pressures and forces
encountered in the two hydraulic systems, these
modifications are possible. The new air cylinder will
be able to provide more than adequate force to
withstand the 1800psi hydraulic fluid. The new
cylinder has an additional safety factor of 1.44
beyond the calculated value, which already included
a 25% increase in the load for unaccounted for losses.
Figure 4. Finite Element Analysis on the back off
In the modified assembly cell mating concept, a pin for EOLT.
support bar is used to lock the connections forward
once they successfully mate with the motor. This will The design reduces micro-stops which saves the
prevent the connectors from backing off when the system an estimated half hour per shift, of downtime.
hydraulic fluid flow has been started. The final design was completed and submitted to the
customer for review and the next phase of
Design work began with reviewing models of the implementation.
current EOLT and assembly cell components. With
the information gathered from these drawings, space Leak Testing and Optical Inspection (Station
constraints were noted and the initial design began. 210):
Pressure and force calculations were used in which After collecting data and making observations, there
the results aided in the choosing of the pneumatic were two problems identified with producing
cylinders that will be used in the new design. A final downtime. Most downtime on station 210
assembly with both custom and purchased parts was was caused by a false failure that occurred on the
created in Solidworks. With this assembly model, optical check of the snap ring. The second problem,
clearance and fit issues could be seen and corrected if which became evident through a more recent
necessary. collection of data, showed that the station was having
a lot of trouble with false leak test failures.
The source of the optical problem was investigated,
and it was discovered that the pictures obtained from
the camera, presented shining sections that the
software mistakenly labels as the holes in the snap
ring. The test would then use these false holes in the
position measurement, and therefore falsely failing
the part. The bright sections on the snap ring occur
because the light that is shined on the snap holes
approaches the ring at an angle, reflecting glare into
the lens creating a false hole in the program
interpretation.
The solution to this problem was to develop a
concept that would reduce the glare entering the
lens. (See Figure 5) Since polarized filters were
Figure 3. Design to increase EOLT reliability. tried in the past with little success, it was decided that
the problem could be solved by placing the camera Initial Assembly Operation (Station 90):
behind an angled mirror and the light source would Originally, the 6 part bins that contain the parts
reflect off the mirror from the side. A mirror and required to build the PCV assembly at station 90
light source device specifically designed for this were located to the left side of the operator. The
application was found [3, 4], and will be installed worker would waste valuable assembly time by
into the station. Due to the simplicity of the change, continuously reaching across his/her body to pick up
no downtime of the line is required for installation. the parts to be assembled. After talking to production
workers, considering ergonomic guidelines [1], and
understanding the constraints of the workstation,
optimal performance of this assembly cell was
achieved by placing the 6 part bins to a height that is
approximately waist high and in front of the
operator. (See Figure 6) By doing this the operator
works with both hands and does not need to reach
across his/her body to get parts. Additionally, the
program that presses PVC assemblies was modified
to allow 2 PCV assemblies to be pressed together
simultaneously. This design is expected to reduce the
Figure 5. Before and after mirror implementation. assembly time of the PCV assembly by 5 seconds.
The leak test failure problem was caused by a poor The number of each part box corresponds to the order
seal between the motor and the rubber connector of operation. The part in box 1 is assembled with the
fittings. To fix the problem, the worn rubber part in box 2. The part in box 3 is then added to the
connectors were replaced. This resulted in a previous assembly. This continues until all 6 parts are
significant improvement in the stations micro-stops. assembled into the PCV assembly.
The changing of these connectors will be put into the
preventative maintenance schedule.
Tester
The combination of these two solutions is estimated
to eliminate micro-stops on this station, which will
save about $750/year in downtime alone. This does 5 6
not account for the additional throughput of motors. 3 4
130
160
180
190
205
210
110A
110B
120A
120B
140A
140B
150A
150B
170A
170B
200A
200B
230A
230B
Direction of Assembly
Station Production Board:
Figure 6. Shows the relationship of process time.
MD2004-04016
Proceedings of KGCOE-MD2004: Multi-Disciplinary Engineering Design Conference Page 5
The board is a graphical representation, on a per hour during the production shift to get completed at a time
basis, of the number of parts produced per person on that the line is not operating. This will result in an
the line. So regardless of manpower, the numbers are increase in production.
relative. A computer currently outputs the number of
parts per half hour. Two half hours will be added Work Flow Enhancements
together, divided by the current manpower in the Improvements in workflow were investigated using
room and plotted on the board. This number will simulation techniques to identify alternative
conform to the company’s standard way of measuring configurations in manpower, number of pallets, and
QPH, or quantity of parts per person, per hour. The queuing. Different alternatives were tested and
main purpose of this board will be to create a method recommendations were made as to what is the best
of positive reinforcement for the operators and configuration for the line.
provide a way for benchmarking their current
production against their past production. So, in Inhibitor Controls Code for Failure Response and
essence they will be competing against themselves to blocking:
In the given case that a module becomes full, due to a
achieve better results.
part failing a test or the module becoming jammed,
This board will also serve as a communication hub the inhibit process will propagate until it gets to a
between personnel and management. Problems manual module. An important characteristic of the
occurring on the line will be documented via created program is the fact that a manual station will not send
data sheets and the solutions to those problems will any value to the previous module, preventing the
be addressed and also recorded for reference in case blocking of the line in case an assembler is not
of future occurrences. present at that module.
Preventive Maintenance: The code consists of three different sequences of
A schedule was made that contains all the routine instructions. When the code is running the sum of the
preventive maintenance that needs to be completed three sets of instructions will monitor the flow of the
and the frequency of completion. This way the line. Whenever an automatic module becomes full
workers will know exactly what tasks need to be either due to failure, or simply because a module is
finished, the order to complete them, and wasted time slower at processing pallets, the module will inhibit
will be reduced to a minimum. The schedule was the previous station from releasing pallets until there
created by consulting personnel and reviewing is space to receive more pallets. Each of the modules
downtime data to identify the major problems on the along the path of the block will display that the
line. Two people will come in on an off day module is blocked and also will indicate where the
(Saturday or Sunday) every week and work for 6 block occurred. The program will not allow the
hours. During this shift they will follow the schedule release of a pallet on the manual station, so the user
initialing and dating each completed task. will not be able to build any more parts until it
attends to the source of the block.
The PM schedule consists of all the routine
maintenance that should be done to keep the By implementing this plan a person is always
assembly line working at maximum efficiency. While responsible for station failures and they will be fixed
completing this maintenance the workers will also promptly. It also eliminates the problem of having
observe any possible problems that are not easily multiple people respond to a failure. This failure
observed during the normal work day, such as leaks response plan will allow for a better flow of parts
in air lines. These leaks are often not heard because through the line because stations will be fixed more
of the large fans and noise developed by normal quickly. It will also reduce blocking because the
production. When a problem is found the worker will people responding will be from stations that are
note it on the PM schedule and, if possible, fix it or feeding the failed stations so new parts will not be
order the parts that are needed so that it can be fixed flowing towards it. Through improvements in failure
during the next scheduled maintenance. response and a reduction in blocking, this
implementation increases the overall throughput of
By following this PM schedule the line will see many
the system.
benefits. After analyzing the data it was found that
many of the problems that cause failures in Optimal Configuration Identification:
automated stations are not because of failures in the In order to study Valeo’s HDFS Prodel line a
parts but because of false failures that are caused by simulation model was created using Arena. The
the testing equipment. model made it possible to study the existing system
as it is today and compare it to a series of “what-ifs”
PM is also going to help prevent catastrophic failures.
which otherwise would be too expensive, time-
Since the stations are going to be inspected weekly
consuming, or disruptive to reproduce directly.
many problems that lead to these failures will be
noticed. The greatest benefit of the PM schedule is Several aspects of the production line were studied
that it allows the maintenance that is normally done through the simulation model including: operator
allocation and utilization, number of pallets in the The net present value was calculated for all
system and line speed. improvements and is detailed in the table below.
This proves that the identified improvements are a
The simulation model provided a means to allocate
worthwhile investment.
operators to manual stations. [8] The model simulates
different scenarios in which operators are utilized in Table 4. Net Present Value Calculation
different aspects of the assembly process. The Interest Rate 10%
following table shows the optimal line configuration. Total Cost $ (71,537.00)
The configuration is based on the number of Return After 1 Year $ 78,915.90
operators available and using the best worker Return After 2 Years $157,831.80
rotation. Regardless of number of operators the Net Present Value $59,476.80
optimal number of pallets in the system is 45.
However, the number of assembly processes to CONCLUSION
complete prior to an operator moving to a new station Through improvements in downtime, process time,
varies according to the number of operators available procedures, and workflow the 4-6% increase in motor
(denoted by ‘Parts’ in the Table 1). output has been demonstrated. Using the optimal
Table 1. Using optimal sequence of operator configuration and considering the projected
rotation, the optimal configuration for the system improvements a 9.5% improvement in quantity of
based on manpower. parts, per person, per hour has been demonstrated
Operators Speed Parts Motors with the use of simulation. The 2-year payback has
1 1 15 210 been met solely using the overtime that will be saved,
2 1 25 381 by the increase in throughput of the system. With the
3 1 30 530 improvements described the system will now run
4 1 10 538 more efficiently that it has in the past.
5 1.1 -- 558
Mechanical improvements made to the system were ACKNOWLEDGMENTS
translated into the Arena model to obtain the new Team Valeo would like to thank Mentor, Dr. Michael
system’s output of motors. Using this system, line Kuhl; Coordinator, Dr. Paul Stiebitz; The entire
speed and number of pallets in the system were tested Valeo Staff including Richard Guerin, Paul
at different values to find an optimal configuration Vandeursen, James Ely, and the Valeo machine shop.
for 5 operators. The optimal configuration with 5
operators is 47 pallets in the system and a line speed REFERENCES
of 1.1 ft/sec. Table 2 provides the percent [1] Niebal, Benjamin, W. & Freivalds, Andris.
improvement with station improvements (EOL, Methods, Standards and Work Design 10th ed. New
Station 90 & 210) followed by the ‘Optimal System’, York: McGraw Hill, 1999.
which includes both station improvements and the [2] Prodel. “The system catalog.” Prodel USA.
aforementioned optimal configuration. 2002.<http://prodel.net/prodel/groupe_prodel.htm>.
[3]DVT sensors. “Doal-50-led.” Northeast Robotics
Table 2. Improvements based on mechanical LLC. 1999. <http://www.dvtsensors.com
station improvements and overall improvements. /shopcart/specs/INRD-50.pdf>.
Station Optimal [4] DVT sensors. “FrameWork 2.6.3. Installation
Improvements System Program.” DVT Corporation. 2001.
Motors Out 593 601 <http://www.dvtsensors.com/support/DownloadsMan
% Improvement 8% 9.5% ager.php?KW=Release>.
[5] Bimba. “How proper mounting prevents
COST BENEFIT ANALYSIS premature cylinder wear.” Bimba Stainless.1999.
The upfront costs have been estimated for the <http://www.bimba.com/techctr/techcenter.htm>.
improvements to this system. They have been [6] Avallone, Eugene A. & Baumeister, Theodore,
justified to reflect a 2-year payback based on the III. Mark’s Standard Handbook for Mechanical
overtime that will be saved. It is important to note Engineers. New York: McGraw-Hill, 1996.
that this does not account for the profit from the [7] McMaster-Carr. “Linear Pneumatics Actuators.”
increase in motor production. McMaster-Carr. 2004. http://www.mcmaster.com/.
Table 3. Shows Payback based on manpower. [8] Kelton, David, W. & Sadowski, Randall, P.
Improvement Cost OT Saved (After 2yrs) Simulation with Arena. New York: McGraw-Hill
EOLT $ 13,000.00 $ 12,331.80 2002.
Preventative Maintenance (4% improvement) $ 50,000.00 $ 144,000.00
Station 210 $ 1,536.00 $ 1,500.00
Procedures $ 91.00
Station 90 $ 6,910.00 Agreed to w/o Payback
Total $ 71,537.00 $ 157,831.80
MD2004-04016