REQUISITION FOR
GROUNDWATER DRILLING
THIS VOLUME EMBODIES PROPRIETARY INFORMATION OF PT. PP PERSERO THIS VOLUME OF THE MATERIAL DESCRIBED THEREON MAY
NOT BE COPIED OR DISCLOSED IN ANY FORM OR MEDIUM TO THIRD PARTIES, OR USED FOR OTHER THAN THE PURPOSE FOR WHICH IT
HAS BEEN PROVIDED, IN WHOLE OR IN PART IN ANY MANNER EXCEPT AS EXPRESSLY PERMITTED BY PT. PP PERSERO.
Doc No.
REVISION LOG
Page |2
Doc No.
TABLE OF CONTENT
1. GENERAL 4
2. ITEMS TO BE PURCHASED 4
3. DOCUMENT ATTACHED TO THIS REQUISITION 4
4. ORDER OF PRECENDENCE 5
5. SCOPE OF WORK AND SUPPLY 5
6. DEVIATION 5
7. DOCUMENT REQUIREMENT 6
8. VENDOR RESPONSIBILITY 6
9. TECHNICAL SPECIFICATION 6
10. SCHEDULE 7
a. APPENDIX-1: List Scope of Work and Supply
b. APPENDIX-2: Vendor Data Requirement Sheets
c. APPENDIX-3: Technical Deviation Form
d. APPENDIX-4: List of Shop Inspection and Test
Page |3
Doc No.
1. GENERAL
This requisition covers the requirement for an Groundwater Drilling to be purchased by PT.PP Persero, for
Proyek Pembangunan Pabrik Peleburan (Smelter) Feronikel, Kolaka of Ceria Nugraha Indotama (CNI) in
Wolo, Kolaka, Sulawesi Tenggara, Indonesia.
Definitions
Purchaser – means PT.PP Persero and its designee who acts on its behalf for Purchase Order.
Owner – means the Owner for whom the Purchaser performs work in which Goods are to be
incorporated.
Vendor – means the firm or company with whom Purchase Order is to be placed.
2. ITEMS TO BE PREPARED
The material and quantities to be furnished shall be in accordance with the requirements specified in this
requisition and reference documents specified in Section 3, vendor shall provide material list/equipment list
to be prepared as per table below.
Page |4
Doc No.
The following documents shall form a part of the requirement of this requisition
4. ORDER OF PRECENDENCE
In the event of conflict between requirements in different documents at the same level of the hierarchy,
the most stringent requirement shall apply. If lower-level requirement is more stringent than an upper
level one in the hierarchy, Vendor must bring the matter to Purchaser’s attention in writing for positive
clarification and to obtain Purchaser’s instruction at bidding stage.
(1) National, regional or local laws, and regulations
(2) This requisition
(3) Material/Equipment datasheets
(4) Project Specifications
(5) Drawings
(6) Relevant international codes and standards
(7) Vendor’s specifications, documents, and information
6. DEVIATION
Unless vendor purposes any exceptions and alternatives, Vendor’s design shall be strictly in compliance
with this purchasing specification. If Vendor purposes any deviation and exception which are deemed
necessary, a list of deviations and exceptions with explanations shall be submitted with their proposal to
Purchaser. Please fill in the FORM-3 Deviation. (See APPENDIX-3)
Only deviations submitted in writing using the Deviation Form per FORM-3, and approved by
Purchaser/Owner before order, will be accepted. In the event that Vendor complied without any
exceptions to the requirement, Vendor shall also return FORM-2 with statement “NO DEVIATION”
printed, together with Vendor’s quotation.
7. DOCUMENT REQUIREMENT
Page |5
Doc No.
1. The document stated on the Vendor Data Requirement Sheet (APPENDIX-2) will be required as part of
this purchasing specification. Vendor shall include cost for these requirements in the quotation at the time
of submittal.
2. Purchaser's review is mainly to ensure that the technical requirement is in full conformance with the
Project technical requirement and specification, and it shall not relieve Vendor’s responsibility to meet
the requirement. Purchaser has the right to reject any sub vendor and or material that does not meet
requirement of this requisition.
3. All documents and drawings shall state the name of Purchaser’s Work No, Item No., and description of
equipment/material/services.
4. Language to be used in the documents shall be in :
[ ] English
[x] English with Indonesian translation
[ ] Others : ______________
5. Unit to be used in the documents shall be in :
[ ] Metric and Celsius unit
[ x ] SI Unit
[ ] Refer to specification _________________________
[ x ] Inch and pound system for pipe size and pressure temperature rating as exception
6. Unless otherwise specified, five (5) copies shall be submitted for proposal.
7. The documents required for review shall be submitted as Electronic File, with the specified period
(weeks) after purchase order placement. Any revised issue reflecting Purchaser comments shall be
submitted within 2 weeks after date of receipt.
8. VENDOR RESPONSIBILITY
Vendor shall be responsible for any discrepancies, errors or omissions in drawings and other documents
prepared by vendor. Needless to say, this shall be applied to documents and materials not only for shop
fabrication work, but also for field work performed by Purchaser in accordance with the vendor’s ones. All
vendor’s documents shall be prepared, checked and approved by Vendor’s responsible persons, and then
submitted to Purchaser.
9. TECHNICAL SPECIFICATION
9.1 General
The purpose of groundwater drilling is to obtain a water supply for clean water needs for workers and to
fulfill work activities . This Specification for groundwater drilling minimum requirements for
groundwater drilling design to be performed by Vendor during, procurement, construction and
Installation, including test and commissioning service for CNI Lapaopao Block Laterite RKEF Project.
9.2 Design Conditions
Groundwater drilling follows reference from geoelectric which functions to find out the depth and to find
out the available water capacity. Further provisions will be discussed at the time of technical clarification
between the PP and the vendor .
Vendor water drilling equipment must be prepared and installed by the vendor to safe specifications.
9.4 Material Specification
All the material specification shall comply the local standard and international standard.
9.5 Loading Condition
Groundwater drilling will be carried out at a depth that refers to geoelectric data.
9.6 Inspection, Testing (including repair and rejection), and Commissioning
a. Vendor’s Responsibility for Supplier and/or Sub-Vendors
The vendor shall identity, in procurement documents to its supplier and/or sub-vendors, all applicable
QA/QC inspection and test requirement imposed by the purchaser’s specification on the vendor and shall
ensure compliance there to standards. Vendors are responsible for the reviewed approval of its suppliers
and sub-vendors, and for at least 2nd line inspection and test oversight during fabrication and
construction. Availability of QA/QC programs and associated inspection plans shall when requested,
provide purchaser with objective evidence that QA/QC activities occurred as requested.
b. Pre-Construction Review
Prior to the order of any material and/or the start of fabrication and construction, the vendor shall review
the procurement document including the specification and its previously purchaser approved QA/QC
program with the purchaser’s quality representative. The vendor shall demonstrate its understanding of
the QA/QC contractual requirement and present its QA/QC methods complying with quality
requirements. In addition, the vendor shall show how it is monitoring and passing down the QA/QC
requirement applicable its suppliers and sub-vendors.
c. Inspection plan Submittal
Thirty day after award, and unless otherwise specified, prior to the construction QA/QC meeting, the
vendor shall submit copies of its fabrication and construction inspection plan to the purchaser for their
review and subsequent establishment of notification points.
d. Documentation
The vendor shall maintain a written procedure to control quality related documents to ensure that
appropriate documents are available at the proper location where operation essential to the work are
performed. Invalid or obsolete documents shall be removed or suitably marked to prevent use. Change to
documents or data shall be reviewed and approved by the originating group, and properly identified. As
required by procurement documents and this specification, specific documents are required to be
submitted to the purchaser for review, approval, or information. When required, certain vendor’s
suppliers/sub-vendors documents for completeness, legality, and accuracy, and note its approval on the
face of the documents after purchaser’s approval shall be submitted for purchaser’s approval.
e. Commissioning
Commissioning and Testing consumable supply by vendor.
f. See APPENDIX-4
9.7 Warranty
The warranty of the package is 1 years after approved by owner and 1 year extended warranty as an
optional.
9.8 Reporting
All the work shall be captured and filed with purchaser approval. the final report document in English and
Bahasa will be provided by vendor. Submission in hardcopy and softcopy in email and inside flashdisk.
9.9 Others
All additional requirement that needed will be updated by purchaser. Purchaser and vendor shall conduct
the coordination to discussed and solved all the additional requirements.
10. SCHEDULE
Page |7
Doc No.
1. Vendor shall submit the overall schedule showing detailed items of engineering work, manufacturing,
inspection and test, and estimated time arrival (ETA).
2. Partial shipment will be allowed if it is contributed to improve the schedule.
Page |8
Doc No.
APPENDIX- 1
LIST SCOPE OF WORK AND SUPPLY
FORM-1
(X : Required)
CONTRACTOR
NO. ITEM VENDOR VENDOR’s
/ PURCHASER
CONFIRMATION
Notes:
APPENDIX- 2
Page |9
Doc No.
7 Inspection Report and Record specification [] [X] 2 weeks after Inspection [X]
Notes:
1. The above list is indicative only, vendor shall finalize and propose the document list to Purchaser prior to
purchase order / vendor agreement.
2. The document required for approval shall be submitted with the specified period (weeks) after Purchaser’s order
replacement, unless otherwise specified. Any revised issue reflecting Purchaser’s comments shall be submitted
within two (2) weeks after date of receipt.
3. One (1) original & three (3) copies of document are required for quotation and one (1) original & four (4) copies
of documents are required for review and approval, unless otherwise specified in the vendor data requirement
sheet.
P a g e | 10
Doc No.
4. One (1) original & six (6) copies + two (2) copies documents in CD format required for final record (MDR
Document), unless otherwise specified in the requirement sheet. For review purpose electronic file on PDF or
MS Office format is required.
5. For quote is means this document should be submitted for proposal/tender stage
P a g e | 11
Doc No.
APPENDIX- 3
TECHNICAL DEVIATION FORM
FORM-2
P a g e | 12
Doc No.
APPENDIX- 4
LIST OF SHOP INSPECTION AND TEST
a. Material certificate *R R R
b. Geoelectric Test *M I R
c. Final Inspection M R R
d. VENDOR’s data report M W W
e. Performance and running test equipment *M W W
(complete unit)
ABBREVIATION: