Professional Documents
Culture Documents
Time Extension Request Final Draft 1
Time Extension Request Final Draft 1
Time Extension Request Final Draft 1
C
RB
c=.›`.u=.c= ›Ç=e ›=”Í=’]”Ó .¾}.¾ÓM TIu`
Ref No: CRBC/WG/ 1195/11 Date: June 21, 2011,
Dear Sirs,
This refers to your letter ref 1005/CRBC/GM/11 dated June 1y 2011, a
response to our claim No-3 (CRBC/WG/1159/11 dated April 27, 2011),
whereby you instructed us to submit all additional claim issues so as to enable
you carry out a comprehensive assessment covering the time to date.
Attached is our further time extension request for the period from October 1,
2010 – end of June, 2011.
Sincerely yours,
Wang Yang
General Manager
CC:
-Addis Ababa City Roads Authority
-Project Manager
A. Shortage of cement
CRBC notified the Engineer that the cement price has been
increased and also there was no adequate supply. Though
the actual demand was 5,000 quintal per week, it was only
possible to collect 500 randomly in a week.
B. ROW problem
The above details shows that, the delay of relocation and clearing
works has hampered the construction of the road section from
K10+080 – K10+260 RHS frontage road and main road as well as
the Deberamarkos roundabout which is currently the critical work.
The Septic tank existing around the mentioned road section has
got solution one month ago after the contractor proposed to
construct temporary manhole and diversion system to avoid the
seepage of the sewage and so as to proceed the suspended earth
work and retaining wall construction.
There are still Row problems due to the Tele cable, high tension
cable and water line within Debremarkos roundabout .These Row
problems have still affected the roundabout construction. The
construction of the roundabout and the entire project at large will
suffer further delay unless immediate solution is given regarding
these Row problems.
Even if some of the Row problems other than those not cleared
until now, were cleared or got solution lately, the operation
couldn’t go smoothly as there was very considerable suspension or
delay of works in the cleared areas due to the scarcity of the
cement supply as it is already discussed in the above section. The
delays of the works in this area are directly attributable to these
major delay causes which are very much clear to every party.
Hence, the contractor is entitled to get reasonable time extension
as the problems are beyond his control. The delay time can be
calculated as follows.
1060
=16.98%
The concrete retaining wall at the west side and east side of
the roundabout were introduced during this dry season
which made the scope of the work to be increased and put
forward the construction of the sub grade and drainage
system at that particular area.
From the above calculation of the time extension, the total days due to the
inclement weather condition, cement shortage and Row problems will become
Since time extension of 206 days is already requested in claim no. 3, the same
number days shall be deducted from this request.
Hence, the additional time required in this request will be 295 – 206 = 89days.
Accordingly, the revised completion date of the project shall be changed from
April 24, 2012 (proposed in claim no. 3) to July 22, 2012.
In view of the above, we request the Engineer to approve the additional time
extension of 89 days while the claim for associated financial compensation
shall be submitted in future.