List of handover

Bagan Datuk Project

1. To continue update/monitor all the correspondence from bagan datuk project. (all
corrospondance need to send the hardcopy to Weststar and to be email)
2. To keep safe all the documents from bagan datuk site. Ie, RFWI, PVD shop drawing, list of
machinery, site diary, settlement monitoring (will be update by arif/zakaria) and others.
Depends on requirement needed from HQ.
3. Update/prepare shop drawing for bagan datuk if needed (All softcopy are inside the PT SUB
– Drawing & Specifications). Based on MC comment.

Penang Project

1. To make progress claim for penang project (Discuss with Ms Lim)


2. Continue monitor settlement monitoring from Asyraf. (to continue update by Asyraf)
3. Update/prepare shop drawing for Penang project (all softcopy are inside the PT SUB –
drawing & Specifications).
4. Keep monitoring and to make sure all result for instrumentations from pacific geoscience are
in order (All the result are in PT sub – Inspection and testing Plan)