Professional Documents
Culture Documents
CPM Pert
CPM Pert
By
RAMJI KHATRI
CTEVT
(OXFORD ADVANCED ENGINEERING
COLLEGE)
2072
Unit 3: CPM AND PERT
• TOPICS INCLUDED:
- Introduction to CPM
- Elements of Network
- Networks Rules
- Definition of the terms: Network Diagram, Activity, Events, fore
ward pass, backward pass, critical path.
- Determination of critical path & floats.
- Introduction to PERT.
3.0 Introduction to CPM
Network Model:
Network analysis is technics of planning, scheduling and controlling
of large and complex project comprising various activities.
The application of this techniques is inevitable when there is a
constraint on resources and a need for higher productivity.
Commonly use network technics are CPM & PERT.
3 4
Contd:
Activity on Node (A-O-N) System:-
Start
C
B
Some Terminology
Network:- It is a diagrammatic representation of a
project’s different activities and their logical
interrelationship between various activities. Arrows
and circles are used in the diagram. They represents
activity and events respectively.
Activity:-Tasks to be performed . It take time to
completion . Activity are represented by arrow which
are usually drawn from left to right.
Events:- The point where arrow start or end are called
events. It is represented by circle.
IF2= TF-FF
RULES FOR DEVELOPING NETWORKS
exavate
Contd..
Logical placement of an activity in the network is
governed by the following three consideration.
Which activity must be completed before this activity
can commence.
Which activity can be carried out along with this
activity.
Which activity can not commence until his activity is
completed.
No activity should lead back to previous event there
must not be any looping.
Place concrete
1 2
Test cubes Cure concrete
3
Contd…
In any network there must be only one start point and
one finish (with any number of activities in between)
i.e. no activity should be left dangling.
3
1 2
Incorrect(2-3)is left dangling 4
3
1 2
Correct network
4
Draw a network diagram and find critical path, critical
activities, EST,EFT,LST,LFT,TF,IF & FF.
S.N. Activity Durations Predecessor Successor
1 A 5 _ B,C
2 B 2 A D,E
3 C 6 A F,G
4 D 4 B H
5 E 4 B I
6 F 2 C H
7 G 3 C J
8 H 7 D,F _
9 I 8 E _
10 J 2 G _
Network Diagram
E
I
B D
A H
F
C
J
G
Solution:-
Critical activities :- A,C,F & H.
Critical path :-
A C F H