10% Jan22
10% Jan22
10% Jan22
Total
Sl.No ADE TARGET ACTUAL LINE LENGTH Observations made Remarks
Line
113.26 11.326 20.01.2022 220KV NKP -Malkaram line 42 --- --- Disc flash over R-ph flash overed Disc
Insulators replaced with new
ADE/LINES/ SRC string at loc no 42
1
NALGONDA Normal
22.01.2022 220KV NKP -Malkaram line 133 to 152 6.40 --- Special line patrolling done
24.01.2022 220KV NKP -Malkaram line 72 to 90 5.39 84,86 to 90 Regrowth of trees Tree cutting done
27.01.2022 220KV NKP -SRPT & HZNR line 353 to 331 7.50 350 to 348.344 Regrowth of trees Tree cutting done
03.01.2022 132KV NKP-USTPL 1 to 8 2.40 1 to 8
Regrowth of trees Tree cutting done PMI
04.01.2022 132KV NLG-Narketpally Line 38 to 48 3.3 39 to 42 Regrowth of trees Tree cutting done PMI
05.01.2022 132K NKP-USAI FORGE,132KV OCTL 1 to6, 0 to 1 2 1 to6, 0 to 1 Regrowth of trees Tree cutting done PMI
194.75 19.48 17.01.2022 132KV CTPL-RMPT-I Line 48 to 58 2.95 --- --- Special line patrolling done PMI
10% Line Patrolling Report of AE/LINES/NALGONDA (NKP & NLG Sub-Divisions) for the month of January- 2022.
Total
Sl.No ADE TARGET ACTUAL LINE LENGTH Observations made Remarks
Line