JSA (Job Safety Analysis

Activity Name:- Installation of Isolation valves in MTF line at Polymer block

Location:- Polymer Block

Sr.No. Sub-Activity Name Type Of Hazard


1 Manpower Mobilization Untrained worker,
Physically unfit person deployed for the
job

2 Insulation removal from the Fall Hazard


line Cut Hazard

3 Cutting of existing line Spark ignition


Fixing of the Isolation valves Heat Hazard
in Polymer block

4 Cutting of preused lines Spark ignition


Fixing of the Isolation valves Heat Hazard
in Polymer block

Name & Signature of Sr.Officer : Praveen Kumar Auti

Name & Signature of Manager Engineering :Mr. Krishna Rawat


(Job Safety Analysis) Sheet
MTF line at Polymer block

Risk(s) Involved
Personal injury.

Personal injury.

Personal injury.
Property loss

Personal injury.
Property loss
sis) Sheet
Ref-

Date : 07/02/2020

Risk Control measures


After medical examination only depute, medically fit person
Only inducted worker shall be deputed at the work place.

Workmen will use ladder of scaffolding to climb and come down during
activity
All Workmen will be allowed to work on pipe rack with safety harness
anchored to lifeline
Insulation will be removed with hack saw by wearing gloves

All the PET inlet will be blinded


Area will be cleaned, no flammable material will be kept near the hot
work area
No Equipment manhole or nozzle will be kept open
Line LEL will be checked before the HOT work and in between the
activity
Both ends of the pipe will be kept disconnected with the source and
destination

All the PET inlet will be blinded


Area will be cleaned, no flammable material will be kept near the hot
work area
No Equipment manhole or nozzle will be kept open
Line LEL will be checked before the HOT work and in between the
activity
Both ends of the pipe will be kept disconnected with the source and
destination
Inert gas purging will be ensured during the activity

Name & Signature of Safety Sr.Officer : Mr. Manish Kumar Sahni


JSA (Job Safety Analysis
Activity Name:- Existing lines welding in pipe rack from MTF to PB

Location:- MTF to PB

Sr.No. Sub-Activity Name Type Of Hazard


1 Manpower Mobilization Untrained worker,
Physically unfit person deployed for the
job

2 Insulation removal from the Fall Hazard


line Cut Hazard

3 Pneumatic testing with soap Pressure hazard


solution

5 All Pipe line joints welding in pipeFire Hazard

5 All Pipe line joints welding in MT Fire Hazard

5 All Pipe line joints welding in Po Fire Hazard

Name & Signature of Sr.Officer : Praveen Kumar Auti

Name & Signature of Manager Engineering :Mr. Krishna Rawat


(Job Safety Analysis) Sheet
k from MTF to PB

Risk(s) Involved
Personal injury.

Personal injury.

Personal injury.

Property loss
Personal injury

Property loss
Personal injury

Property loss
Personal injury
sis) Sheet
Ref-

Date : 07/02/2020

Risk Control measures


After medical examination only depute, medically fit person
Only inducted worker shall be deputed at the work place.

Workmen will use ladder of scaffolding to climb and come down during
activity
All Workmen will be allowed to work on pipe rack with safety harness
anchored to lifeline
Insulation will be removed with hack saw by wearing gloves

All workmen participating in the activity will be given safety goggles, to


avoid water pressure into eyes.
Pressure will be depressurized through proper drain facility.
Line insulation will be cleaned
All line welding joints will be welded by closing the Main isolation valve
provided inside the polymer block
Lines used earlier I,e BA, MMA will be done with Inert gas flushing continuosly
until the LEL and VOC levels are minimal.

Line will be opened both ends shifted to workshop or other allocated area
cleaned the welding space and welded
Lines used earlier I,e BA, MMA will be done with Inert gas flushing continuosly
until the LEL and VOC levels are minimal.
All the PET inlet will be blinded
Area will be cleaned, no flammable material will be kept near the hot
work area
No Equipment manhole or nozzle will be kept open
Line LEL will be checked before the HOT work and in between the
activity
Both ends of the pipe will be kept disconnected with the source and
destination

Name & Signature of Safety Sr.Officer : Mr. Manish Kumar Sahni


JSA (Job Safety Analysis
Activity Name:- Pipe and equipment installation in MTF

Location:- MTF

Sr.No. Sub-Activity Name Type Of Hazard


1 Manpower Mobilization Untrained worker,
Physically unfit person deployed for the
job

2 Climbing the pipe rack for Fall Hazard


installation

3 Shifting of the pipe line or Fall Hazard


equipment Trip Hazard

5 Erection of Pipe line and Fall Hazard


equipment

5
5

Name & Signature of Sr.Officer : Praveen Kumar Auti

Name & Signature of Manager Engineering :Mr. Krishna Rawat


(Job Safety Analysis) Sheet

Risk(s) Involved
Personal injury.

Personal injury.

Personal injury.
Property Loss

Personal injury.
Property Loss
sis) Sheet
Ref-

Date : 07/02/2020

Risk Control measures


After medical examination only depute, medically fit person
Only inducted worker shall be deputed at the work place.

Workmen will use ladder of scaffolding to climb and come down during
activity
All Workmen will be allowed to work on pipe rack with safety harness
anchored to lifeline or fixed support

Equipment and pipes will be shifted through manual or using farana to


place in the position
Minor pipe line parts will be shifted manually
All Material while shifting will be tied one end with rope to control the
movement
All pipes erected in rack will be given stopper in case of loose ends
Equipment will be bolted when fixed in position
All Material while installation will be tied one end with rope to control the
movement

Name & Signature of Safety Sr.Officer : Mr. Manish Kumar Sahni