1. General Comment:
1. This shop drawing shall follow as per latest IFC.
2. Hatching in Legend and plan should match.
3. To avoid hatching in void area.
4. To standardize title, font colour, font size, legend, plan, room names, dimension
colour, dimension size, line weight, line etc.
5. To add sectional detail, blow up detail and termination detail of ceiling in critical
area as below.
6. To indicate electrical fittings and ceiling hatches where applicable in the ‘blow-up’
reflected ceiling plan.
7. Drawings should clearly shown type of ceiling for ease of review.
8. Setting out of ceiling panel to take into consideration method of mounting for light
fittings, speaker, cctv and signages. All fittings installed to be fully covered with
capping etc.
9. To include detail of termination at edge of wall, escalator area, edge of F.O.H. (Front
of House) towards outside of station.
10. Ceiling height to take into consideration of cable containment above ceiling and
mounting of exhaust fan.
11. Termination detail between retail ceiling and slab/beam.(Refer attachment)
12. Termination detail between mineral fibre board ceiling and slab/beam. (Refer
attachment)