Professional Documents
Culture Documents
Polybuild - DVP - Weekly Report 2022 11 07-12
Polybuild - DVP - Weekly Report 2022 11 07-12
WEATHER: SUNNY (SU) FAIR (F) LIGHT RAIN (LR) RAINY (R) HEAVY R (HR) STORMY (S)
SU
6 7 8 9 10 11 12 13 14 15 16 17 18 19
PO AoR PM CM SA/E
MANPOWER:
✔ ✔
Name Position Present Absent
1 Arnelito Igna Foreman ✔
2 Angelito Igna All Around Skilled ✔
3 Aris Gregorio Specific Skilled - Mason ✔
4 Roy Catactan Labor ✔
5 Manolito Abad Labor ✔
6 Christopher Brozo Labor ✔
7 Agapito Banguel Specific Skilled - Mason ✔
8 Rizaldo Ramos Labor ✔
9 Starvie Balajadia Labor ✔
10 Joshua Joson Labor ✔
11 Amilito Legaspi Specific Skilled - Steelman ✔
12 Jericho De Guzman Labor ✔
13 Edwin Barja Labor ✔
14 Joshua Baltazar Labor ✔
15 Resty Valencia Labor ✔
16 Wilson Joson Labor ✔
17 Gregorio Santos Specific Skilled - Mason ✔
TEAM 2
18 Mark Villa Foreman ✔
19 Jay Carlo Abino Carpenter/ Steelman ✔
20 John Roel Abino Carpenter/ Steelman ✔
21 Jervy Abino Carpenter/ Steelman ✔
29 Kevin Cudia ✔
Total Manpower: 25
WORK PERFORMED:
WBS %P Work Packages Description Location Remarks
Installation of Scaffoldings & Beam runners
For Attic Level
Concrete & Fixing of beam Stirrups for Third Floor Side
Reinforcement
Fabrication and Repairing of Formworks
EQUIPMENT USED:
CONSULTANTS’ COMMENTS:
To be completed by the Architect-of-Record /
Allied Consultants
VISITORS:
Name Position Company Purpose
Arch. Reynold De Leon Arch. Joramae Balbin Arch. Alvin Paul Dela Cruz
Site Architect Project Manager Contractor
Footnotes:
PO - Project Owner
AoR - Architect-of-Record
PM - Project Manager
CM - Construction Manager
SA/SE - Site Architect/Engineer
Additional Notes:
WEATHER: SUNNY (SU) FAIR (F) LIGHT RAIN (LR) RAINY (R) HEAVY R (HR) STORMY (S)
F
6 7 8 9 10 11 12 13 14 15 16 17 18 19
PO AoR PM CM SA/E
MANPOWER:
✔ ✔ ✔
Name Position Present Absent
1 Arnelito Igna Foreman ✔
TEAM 2
18 Mark Villa Foreman ✔
29 Kevin Cudia ✔
Total Manpower: 26
WORK PERFORMED:
WBS %P Work Packages Description Location Remarks
Installation of Beam Runners for Attic Side
Installation of formworks for Master’s
Concrete & Bedroom Toilet & Bath
Reinforcement Preparation of Ground Floor Column for
Finishing – D2, B2, B3 respectively
Fixing of Beam Stirrups for 3F Side- 3B01,
3B21 respectively
EQUIPMENT USED:
CONSULTANTS’ COMMENTS:
To be completed by the Architect-of-Record /
Allied Consultants
VISITORS:
Name Position Company Purpose
BDO personnel BDO Site Survey
Arch. Reynold De Leon Arch. Joramae Balbin Arch. Alvin Paul Dela Cruz
Site Architect Project Manager Contractor
Footnotes:
PO - Project Owner
AoR - Architect-of-Record
PM - Project Manager
CM - Construction Manager
SA/SE - Site Architect/Engineer
Additional Notes:
NOVEMBER 8, 2022 | TUESDAY
PHOTO DOCUMENTATION:
Installation of Beam Runners - 4B13, 4B10, 4B15, 4B19, 4B16, 4B20, 4B03, 4B06, 4B17, 4B21 respectively
Installation of formworks for Master’s Bedroom Toilet & Bath
WEATHER: SUNNY (SU) FAIR (F) LIGHT RAIN (LR) RAINY (R) HEAVY R (HR) STORMY (S)
F
6 7 8 9 10 11 12 13 14 15 16 17 18 19
PO AoR PM CM SA/E
MANPOWER:
✔ ✔ ✔ ✔ ✔
Name Position Present Absent
1 Arnelito Igna Foreman ✔
TEAM 2
18 Mark Villa Foreman ✔
19 Jay Carlo Abino Carpenter/ Steelman ✔
29 Kevin Cudia ✔
Total Manpower: 26
WORK PERFORMED:
WBS %P Work Packages Description Location Remarks
Installation of Beam Runners for Attic Side
Concrete &
Reinforcement Splicing of column main bar for 3rd floor side-
B4, B5, D3, F3, F5, F5’,
EQUIPMENT USED:
CONSULTANTS’ COMMENTS:
To be completed by the Architect-of-Record /
Allied Consultants
VISITORS:
Name Position Company Purpose
Sab Briones Design Intern Nana X Co Site Visit
Architect-of-
Diana Dela Victoria Nana X Co Site Visit
Record
Joramae Balbin Project Manager Polybuild Site Visit
Arch. Reynold De Leon Arch. Joramae Balbin Arch. Alvin Paul Dela Cruz
Site Architect Project Manager Contractor
Footnotes:
PO - Project Owner
AoR - Architect-of-Record
PM - Project Manager
CM - Construction Manager
SA/SE - Site Architect/Engineer
Additional Notes:
NOVEMBER 9, 2022 | WEDNESDAY
PHOTO DOCUMENTATION:
Installation of Beam Runners - 4b02, 4b04, 4b05, 4b07, 4b08, 4b09 respectively
Splicing of column main bar for 3rd floor side- D3, F3 respectively
Splicing of column main bar for 3rd floor side- F5, F5’ respectively
DAILY FIELD
POLYBUILD CONSTRUCTION SERVICES
INSPECTION /
+63 917-547-2388 / polybuild.ph@gmail.com PROGRESS REPORT
Architect-of-Record:
PROJECT TITLE: DVP Residence - Proposed Three-Storey Split Type Residence w/ Attic
Nana & Co Architecture
L2-3 B1 Waterwood Park Village, Brgy. Sto. Cristo & Concepcion, 11-10-2022
PROJECT SITE:
Baliuag, Bulacan
MM/DD/YYYYY
PROJECT OWNER: Angelo B. Polinario and Sophie Arianne C. Dela Victoria Su M T W TH F Sa
WEATHER: SUNNY (SU) FAIR (F) LIGHT RAIN (LR) RAINY (R) HEAVY R (HR) STORMY (S)
SU
6 7 8 9 10 11 12 13 14 15 16 17 18 19
PO AoR PM CM SA/E
MANPOWER:
✔ ✔
Name Position Present Absent
1 Arnelito Igna Foreman ✔
29 Kevin Cudia ✔
Total Manpower: 26
WORK PERFORMED:
WBS %P Work Packages Description Location Remarks
Splicing of Column Main Bars for 3F & 2F
side
Concrete &
Reinforcement Installation of Column Ties for 3F Side
Fabrication of Beam Stirrups
EQUIPMENT USED:
CONSULTANTS’ COMMENTS:
Architect-of-Record / Allied
To be completed by the
Consultants
VISITORS:
Name Position Company Purpose
Mark Jabat Sales Consultant Multi-Line Product demo
Arch. Reynold De Leon Arch. Joramae Balbin Arch. Alvin Paul Dela Cruz
Site Architect Project Manager Contractor
Footnotes:
PO - Project Owner
AoR - Architect-of-Record
PM - Project Manager
CM - Construction Manager
SA/SE - Site Architect/Engineer
Additional Notes:
NOVEMBER 10, 2022 | THURSDAY
PHOTO DOCUMENTATION:
WEATHER: SUNNY (SU) FAIR (F) LIGHT RAIN (LR) RAINY (R) HEAVY R (HR) STORMY (S)
F
6 7 8 9 10 11 12 13 14 15 16 17 18 19
PO AoR PM CM SA/E
MANPOWER:
✔ ✔ ✔
Name Position Present Absent
1 Arnelito Igna Foreman ✔
TEAM 2
18 Mark Villa Foreman ✔
19 Jay Carlo Abino Carpenter/ Steelman ✔
29 Kevin Cudia ✔
Total Manpower: 26
WORK PERFORMED:
WBS %P Work Packages Description Location Remarks
Splicing of Column Main Bars for 3F Side
Installation of Column Ties for 3F Side
Concrete &
Fabrication of Beam Stirrups
Reinforcement
Installation of Column Formworks for 3F side
Installation of Beam Rebars for Attic Side
EQUIPMENT USED:
CONSULTANTS’ COMMENTS:
Architect-of-Record / Allied
To be completed by the
Consultants
VISITORS:
Name Position Company Purpose
BELINK/UNICRETE Submission of test result- compressive strength of
BELINK/UNICRTE
REPRESENTATIVE cylindrical concrete specimen.
Arch. Reynold De Leon Arch. Joramae Balbin Arch. Alvin Paul Dela Cruz
Site Architect Project Manager Contractor
Footnotes:
PO - Project Owner
AoR - Architect-of-Record
PM - Project Manager
CM - Construction Manager
SA/SE - Site Architect/Engineer
Additional Notes:
WEATHER: SUNNY (SU) FAIR (F) LIGHT RAIN (LR) RAINY (R) HEAVY R (HR) STORMY (S)
S
6 7 8 9 10 11 12 13 14 15 16 17 18 19
PO AoR PM CM SA/E
MANPOWER:
✔
Name Position Present Absent
1 Arnelito Igna Foreman ✔
TEAM 2
18 Mark Villa Foreman ✔
29 Kevin Cudia ✔
Total Manpower: 25
WORK PERFORMED:
WBS %P Work Packages Description Location Remarks
Installation of Beam Runners 4F
Concrete & Installation of Column Ties for 3F Side 3F
Reinforcement Installation of Column Formworks for 3F side 3F
Installation of Beam Rebars for Attic Side 4F
EQUIPMENT USED:
VISITORS:
Name Position Company Purpose
Arch. Reynold De Leon Arch. Joramae Balbin Arch. Alvin Paul Dela Cruz
Site Architect Project Manager Contractor
Footnotes:
PO - Project Owner
AoR - Architect-of-Record
PM - Project Manager
CM - Construction Manager
SA/SE - Site Architect/Engineer
Additional Notes: