INFORMATION ON DESIGN POSITION OF PROJECTS.

SL Name of the Work District/ A/A amount Agreement Agency Date of Target date Cumulative Span Arrangement Present Position Design issue.
No. Division in lakh value commence of expenditure
in lakh ment / completion ending
Stipulated 31.03.2022
date of in lakh
completion
1 2 3 4 5 6 7 8 9 10 11 12
1 Construction of Balasore 4266.67 2930.26 Prahalad Ch. 02-03-2019 01.02.2023 415.09 a)OT Road side - 167 mtr Pile Cap P-11 pier cap &
approaches along with Balasore-I Baug 01.02.2021 i) span-9 Superstructure.
ROB N0.268/A at nos.x19.08mtr=171.72
232/5-7 in lieu of Level mtr , 1no x19.14= 19.04
Crossing L.C. No.80 mtr, 1 nox 19.143
with 10.5m =19.143, 2nos x
carraigeway width(3 19.147=38.294 mtr (P13
lane carriage width) in to P25) & A(R) 248.197
between Balasore- mtr & Railway portion 1
Nilagiri Road Station Span (P12 & P-13) 51.40
on Kharagpur-Bhadrak mtr (b) Bampada
section. side - 228.857 mtr ii) 10
nos x19.08 mtr.= 190.80
mtr & P12 to P1 & A(R)
1x19.015 = 19.015 mtr &
1X19.042 = 19.042 mtr

2 Construction of Portal Sonepur 5860.06 5130.62 ARSS 11.06.2020 10.12.2022 0.00 46x25.00 Design of foundation Design of the open
Frame Bridge at Subarnpur Infrastructure 10.12.2022 (Pile) foundation for which the
Sonepur (Sonepur Project Ltd, One Test Pile Design bore log report is avilable
Division, ARSS) Super Class P4, P6 Foundation Test Pile has been put up for
Contractor/ completed. approval.

3 H.L. Bridge over Kalahandi 3842.02 5400.99 M/S Brijesh 05.02.2021 04.08.2023 424.538 16X25.24M (Revised Revised GAD submitted to Revised GAD & Foundation
Indravati Reservoir Kalahandi Agrawal, Super 04.08.2023 10x40 mt) C.E. (Designs) for approval Design pending
Mahulpatna Class
Kenduaguda Contractor
(Bhawanipatna
Division, Brijesh
Agrawal)
4 Construction of H.L. Design Data submitted on Open Foundation Design
Bridge over Mathajore 15.04.2022 Pending.
Nallah at Ch. 8/400 Km
on Allujharan-
Bhalumunda Road in
the District of
Dhenkanal.
SL Name of the Work District/ A/A amount Agreement Agency Date of Target date Cumulative Span Arrangement Present Position Design issue.
No. Division in lakh value commence of expenditure
in lakh ment / completion ending
Stipulated 31.03.2022
date of in lakh
completion
5 Construction of H.L. Malkangir 1184.68 1212.78 Binodini 27-12-2017 31.12.2022 106.42 203 mtr. Confirmatory Boring Partly foundation design
Bridge over river Saberi Malkangir Infrastructure 26.06.2019 8 x 25.36 mtr Completed & Report receive & partly pending
at 16/000Km of Mathili- Pvt. Ltd. submitted
Kaliaguda Road

6 Construction of H.L Malkangir 1078.00 964.28 Binodini 28-11-2017 31.06.2022 459.92 101 mtr. Piling completed & test Design of pile cap wanting.
Bridge over river Malkangir Infrastructure 27.02.2019 4 x 25.24 mtr report submitted for Pier pile
Saptadhara at Km2/0 Pvt. Ltd. Cap of pier.
of Govindapalli-
Kamalapadar-Gajiaguda
road in Malkangiri.

7 Construction of H.L. Dhenkanal 665.27 474.55 Monalisa 10.01.2022 9.07.2023 3x24.30 Borelog data submitted Revised GAD for open
Bridge over Kantabeli Dhenkanal Construction 9.07.2023 foundation design
Nallah at 8/100 Km of pending.
Badajhara Barihapur
NH - 53 right side of
Rengali Left Canal up
to Siarimalia Road
(RIDF-XXVII)
8 Construction of H.L Formation level too high. Formation level to be
Bridge over river SONA Approach Road cannot be reduced.
at Joda in the district of negotiated.
Keonjhar under DMF
for the year 2018-19
SL Name of the Work District/ A/A amount Agreement Agency Date of Target date Cumulative Span Arrangement Present Position Design issue.
No. Division in lakh value commence of expenditure
in lakh ment / completion ending
Stipulated 31.03.2022
date of in lakh
completion
9 Construction of ROB in Balasore 6023.71 3988.94 Ashirbad 11.09.2018 30.09.2022 2706.81 (a) Jaleswar-Side Retaining wall pile P18 to A2 cap P28 pier cap.
lieu of LC No.45 at Km Balasore-II Construction 10.09.2020 P28 & A2 pier cap P18-P28, Design Pending.
182/10-12 between i)Span - 12 Nos x 19.25 A2 design of rataining wall
Jaleswar-Laxmannathh Mtr (A1 to P4 and P6 to
Road Railway Station of P14)
S.E Railway on ii)Span - 1 No x
Kharagpur - Bhadrak 10.00 Mtr (P4-P5A)
Railway Section in the
District of Balasore. iii)Span - 1 No x
15.60 Mtr (P5A-P5B)

iv)Span - 1 No x
12.90 Mtr

(P5B-P6)

b)Chandaneswar-
Side
i)Span - 11 Nos x
19.25 Mtr (P17 to P28)

ii)Span - 1 No x
28.25 Mtr (P28 to A2)

c) Railway Portion

i)Span - 1 x 19.08
Mtr (P14-P15)
10 Construction of HL HL Mayurbhanj 1147.97 1062.89 M/s Santosh 15.07.2018 31.12.2022 436.19 (3x25.32 Mtr) Well foundation in progress P2, AR well cap & shaft.
Bridge over URA Nallah Mayurbhanj Kumar 14.07.2019 =75.96m Design Pending.
of BPBM Road. Khandelwal
11 Construction of ROB in Jharsuguda 4130.94 3069.34 Sri Balaji 18-09-2018 31.07.2022 819.19 Sambalpur side Curve Portion Girder
Lieu of JT-1 & JT-2 Jharsuguda Engicons Pvt. 17.03.2020 19.080+19.034+18.857+ Design pending.
near Sarbahal in Ltd. 18.925+3x19.080+18.34
Jharsuguda Town 9+2x16.815+18.333=11
under State Plan spans
Jharsuguda side
19.391+17.050+16.700+
18.031+3x19.080+19.02
5+18.848+18.844=10
spans
Total=21 spans

12 ROB at LC No-Cp-2 Cuttack. 4444.04 3526.45 M/s Y.B. 28.12.2018 26.02.2022 2430.1 25x19m+1x37.28m Nayabazar side Pile P4-P16
Nuapatana-Cuttack Cuttack-II Construction 27.06.2020 Total=512.28m pile Cap Design.
Gosala
SL Name of the Work District/ A/A amount Agreement Agency Date of Target date Cumulative Span Arrangement Present Position Design issue.
No. Division in lakh value commence of expenditure
in lakh ment / completion ending
Stipulated 31.03.2022
date of in lakh
completion
13 ROB AT LC No-178 at Cuttack. 8357.48 4875.68 M/s Rajalaxmi 05.07.2019 25.12.2022 2081.81 26 span of 24.6m+ Pile & Cap Retaining Wall Design
Gopalpur Cuttack-II Construction 04.07.2021 (Railway Superstructure in Progress pending.
1x37.28m+2x25.08m)
14 Construction of H. L. Phulbani 261.24 256.31 Subash ku 05.10.2021/ 04.09.2022 3 x 10.76 =32.28 mtr Confirmatory Boring data Foundation Design
Bridge over Nandangi Kandhamal Jena 04.09.2022 submitted. pending.
Nallah at 39.190km of
Mishrapada – Kelapada
– Sidngia –
Balandapada road in
the District of
Kandhamal under
NABARD Assistance
RIDF-XXV
15 Construction of HL Malkangir 1071.03 Sri Samarendra 02.11.2020 31.03.2023. 10x19.36m=193.60 mtr. Work in progress for P5,P6, Design of AR, P8, P9
bridge over river Sileru Malkangir Prasad Bisoi 01.03.2022 P7 pending
near Poluru on
Manyamkunda-Poluru
road
16 Balangir 1424.17 1858.74 Shreeman and 28-01-2020 31.12.2022 390.06 10x25.36 mtr=253.60 Foundation and substructure Superstructure Design
Construction of HL
Balangir aman 27.07.2021 mtr. in progress . same as Marzakud may be
bridge over Sonegarh
Infra.Pvt.Let. approved.
at Ch 1/845 Km on
Tusra-Rusuda Chhak to
Kharda Likjirla Chhack

17 Construction of HL Panikoili 1991.31 vide 4339.99 M/s Biraja 08.02.2021 07.08.2023 0.00 2x26.08M+2x62.08M = Test pile result submitted working pile already
bridge over river Jajpur letter Construction 07.08.2023 176.32 M long H.L Bridge approved
Baitarani at Dattpur no.16500/20.
12.16
R.E 4842.00
18 Construction of HL Panikoili 2320.29 2095.67 M/S Biraja 26.08.2021 25.08.2023 0.00 1 span x63Mtr= 63Mtr Test pile result submitted working pile already
bridge on Atharnalla Jajpur Const. 25.08.2023 approved
on Jajpur Bye pass
19 HL bridge over Mayurbhanj 2846.62 3057.38 Iron Triangle 12.05.2017 31.08.2022 1955.76 (8x36.50 Mtr)= 292.0 mtr Change of Superstructure Change of Superstructure
Budhabalanga on Mayurbhanj Ltd 11.01.2019 from cast in Situ to lunching design pending for
SNKUBN Road girder submitted to Launching prestressed
EIC(Designs) girder.
20 HL Bridge over Phulbani P1 foundation work in Revised design of AL
Godiapada Nallah on Kandhamal progress AL excavation in foundation pending .
BMKPS Road progress.

21 HL bridge over Phulbani 364.25 329.93 Subhash 31.12.2020/ 30.06.2022 3 X 19.36 = 58.08 mtr Foundation work in progress Cap, Superstructure design
Dindabali Nallh on G. Kandhamal Kumar S.Jena/ 30.11.2021 pending
Udayagiri Paburia
sarangiguda Road
SL Name of the Work District/ A/A amount Agreement Agency Date of Target date Cumulative Span Arrangement Present Position Design issue.
No. Division in lakh value commence of expenditure
in lakh ment / completion ending
Stipulated 31.03.2022
date of in lakh
completion
22 HL bridge over local Malkangir 2275.00 Sri Birendra 02.11.2020 31.03.2023 105.23 9x25.36m=228.240mtr. Pile work of AL, P1, P4 in Bore log report at P5
nalah on Chitrakonda Malkangir Kumar Nayak 01.05.2022 progress received on
Aringi Road 20.04.2022 .Bore log
report at p6 & P7 have not
been received .P5 working
Pile design under progress
.