Professional Documents
Culture Documents
Construction Project Management Mid Semester
Construction Project Management Mid Semester
Construction Project Management Mid Semester
the project is displayed in a single, easy-to-understand chart. The purpose of this chart is to
break down complex activities into smaller, more management constituents. It also describes
the deliverables needed to complete the project, i.e. the “what” of the project. It doesn’t
include timelines or resources. The goal of the WBS is to give the project team a hyper-
focused idea of what they need to achieve. An example of a work break down
The top of the hierarchy shows the project name which would be level 1, below that are the
sub divisions are level two and below that are the activities to be undertaken under each sub
divisions.
Prepare a WBS for a 1km water trunk main 32” Dia. with four Tee intersection supply
take off at 100 m equidistance.
Question 2
For the following table of information:
i. Draw the network diagram (10 marks)
ii. List the network paths (5 marks)
iv. Determine the float for each activity (10 marks)
Site clearance
excavate
foundation
columns
walls
floors
roof
plumbing
finishes
Electrical finishes
Practical
completion
Question 3
i. Explain what constitutes a contract and name and explain the Four (4) types
used in the Construction process.
A contract is an agreement between two parties that creates a legal obligation for both to
perform specific acts such as rendering payment or delivering goods.
Lump sum contract - contracts are the most frequently-used contract, particularly for
building construction. The idea is that all aspects of the project are pre-determined and laid
out in a fixed scope of work. The cost is known and upfront for the owner, and the contractor
Advantages
The amount of the project is known and upfront before the project begins.
Disadvantage
If any out-of-scope work is needed, a change order will be required, which could delay the
If the project goes out of scope as a result of the contractor’s poor time management, rework,
or weather, the contractor will suffer loss if a change order was not used
Unit price contract - contracts are necessary when the work materials can’t be measured
accurately ahead of time. These are most common with civil projects. For example, if a
contractor is tasked with building a highway, dirt removal would be something that can’t be
accurately quantified but would require time and heavy machinery. For this contract, owners
provide fixed quantities for the project materials, and contractors apply their personal unit
pricing. Contractors can then bid for the project, and the owner will choose whichever unit
price works best for them. Advantages of this type of contract is that the unit prices are fixed
thus making this a pro for the owners, in addition if the owners original unit estimate are
inaccurate, then they are responsible for covering any additional cost
The disadvantage of this type of contract is that If the owner’s original estimates are
inaccurate, they will need additional work from contractors and go over budget (for
contractors, this would be a pro, since more work = more money). The full price of the
Cost-plus contracts - does not require a predefined scope of work with a fixed cost. Instead,
the contractor keeps track of the time and materials spent throughout the project and the
owner is responsible for reimbursement, plus a fixed fee for the contractor.
Advantages
There is guaranteed profit for the contractor since they can add on work at any point in the
project, plus the percentage of the total cost is added at the end.
Disadvantages
There is significant risk for the owner, who is responsible for reimbursing all time and
A ton of paperwork is involved with these contracts because every receipt and time stamp
Target-cost contract - this contract is a combination of the lump sum and the cost-plus
contracts. The contractor is paid based on the actual project costs, plus a fee (fixed or
percentage of total cost). This fee makes provision for a case where the cost of the project
does not exceed certain target costs specified by the owner. The contractor faces risk if the
project cost increases; however, the contractor is rewarded a percentage of any savings
ii. Discuss eight (8) key elements that make up a standard construction contract
1). Termination clause - This is often included in construction contracts and considers the
terminating party and the cause of termination, if any. The method of termination and the
2). Warranties and Statute of limitations- The contractor should state any warranties clearly in
the contract. The warranties make provision for the correction of any issue caused by the
3). Mediation/arbitration and attorney’s fees - This element makes provision for disputes
surrounding the contract. Both parties may agree to settling disputes through mediation where
4). Project cost and payment terms - The project cost should be clearly stated in the contract.
It should also detail the payment schedule, that is, the specific dates and amounts for various
instalments.
5). Project Scope- The scope describes the construction project in clear details. It outlines the
precise tasks to be undertaken by the contractor. It also determines the amount of work
6). Contractor and owner information and signature - In any standard construction contract,
the contractor’s information must be clearly detailed. This includes the contractor’s name,
7). Owner’s information and signature- For the contract to be legally binding, the owner’s
name, address, signature, and other relevant details must also be included in the contract.
8). Contract documents - The contract documents must also be included in the contract. This
includes drawings, specifications, scope of works, conditions, bill of quantities, schedule, and
Tendering is the process by which bids are invited from interested construction contractors to
undertake specific packages of construction work. Tendering allows the owner of the project
to obtain a fair price and the best value possible for the project at hand. It ensures that true
service providers of non-consulting services which sets out terms and conditions under which
Closed Tendering - In this method a select group of contractors are invited to bid. Usually,
these contractors are prequalified for the specified works, or are specialists in the field of
work. The necessary bidding information and data are documented in the Request for
Quotation (RFQ) or Request for Proposal (RFP) and sent to the prospective bidders
Direct Contracting - This method is used only when there is a single known company that
that can provide the necessary services, goods, works or continuation of works or services for
the project.
Open Tendering - This method allows all eligible bidders the chance to bid competitively
v). The Contractor’s tender states that it is open for acceptance for six weeks from the
date of tender, but the contractor withdraws it after three weeks citing a suddenly
increased workload. Is the contractor liable to the employer for the additional cost of a
replacement contractor?
When a contractor submits a tender, it is an offer to carry out the required work for a certain
sum. The employer is free to accept the offer, reject it or to attempt to negotiate. Until the
offer is accepted there is no contract. The law is that an offer can be withdrawn at any time
before it is accepted and there are some rather awkward rules regarding acceptance by post.
Therefore, in normal circumstances the contractor can withdraw the tender before it is
accepted and, strictly, no reason need be given. The contractor has no liability for any
additional costs suffered by the employer. In addition to that the position is very different if
the employer pays the contractor to keep the tender open. Tenders often state that in
consideration of a payment the contractor agrees to keep the tender open for acceptance for a
period of 6 weeks from the signing date of the contract. The effect of that is to create a little
contract between employer and contractor whereby the consideration is the employer’s
payment and the contractor keeping the tender open. Effectively, the employer has bought an
option for a few weeks to decide whether or not to accept the contractor’s tender. A sum of
say $100,000.00 may not seem much, but the law does not require that adequate
consideration is given. It is sufficient if the consideration has some value. In this case, a
contractor who withdraws the tender after three weeks would be in breach of the little
contract and the employer would probably be able to bring an action for damages. The
damages would be likely to be the additional costs incurred by the employer in engaging
Vi). Explain in detail the various stages of a tender Review process and their Personnel.
The various stages of the tender review process and their personnel are as follows:
Opening and Recording Tenders- tenders should be opened and recorded in a way that
maintains security of the tenderers intellectual property and that offers no advantage to one
tenderer over another. It is ideal or a good practice to open ad summarise tenders as soon as
possible after the closing time. This process should be checked by at least two persons.
evaluation team is critical to the success of the tender process. Above all, a consistent
approach to the evaluation of all tenders is required. After receipt of tenders, submissions are
comparatively assessed against the Criteria for Selection defined in the tender documents.
Tenders are likely to contain significant differences, particularly in areas of design, time,
cost, risk allocation, durability and operation. Tenders may also differ in terms of certainty of
delivery and clarity of content. A tender that does not comply with the tender documents
should be rejected. If a tender is rejected, the reasons for such action are to be clearly
Tender Clarifications- The evaluation team may seek clarification of any issues from
applicants, verbally or in writing, but may not solicit new information. The tender
Tender selection and award- The lot feeder should ensure that unsuccessful tenderers are
advised in writing that their tenders have been unsuccessful. In the finalisation of the contract
documentation, the lot feeder and successful tenderer shall ensure that the contract
incorporates the tender submission of the successful tenderer and any qualifications during
the tender process. It is noted that this phase of the process is to settle all outstanding
technical, commercial and/or legal issues necessary for finalisation of the contract. It is not an
opportunity for either party to vary the final contract price or to materially alter the proposal.