Professional Documents
Culture Documents
Applsci 12 00567
Applsci 12 00567
sciences
Article
Stability Improvement Method for Embankment Dam with
Respect to Conduit Cracks
Young-Hak Lee 1 , Jung-Hyun Ryu 2 , Joon Heo 3 , Jae-Woong Shim 3 and Dal-Won Lee 2, *
1 Institute of Agricultural Science, Chungnam National University, Daejeon 34134, Korea; fulia_cate@cnu.ac.kr
2 Department of Agricultural and Rural Engineering, Chungnam National University, Daejeon 34134, Korea;
ryoujh1155@naver.com
3 Rural Research Institute, Korea Rural Community Corporation, Ansan 15634, Korea; jheo01@ekr.or.kr (J.H.);
dskk@paran.com (J.-W.S.)
* Correspondence: dwlee@cnu.ac.kr; Tel.: +82-042-2821-5793
Featured Application: In this study, the inside of a conduit was monitored to visually reproduce
the erosion phenomenon caused by a crack in the conduit in an embankment. In addition, a
model that can dramatically reduce erosion based on the dispersion principle of water pressure
is proposed. The dispersion effect of water pressure was verified via pore water pressure mea-
surements and 3D FEM analysis.
Abstract: In recent years, as the number of reservoir embankments constructed has increased,
embankment failures due to cracks in aging conduits have also increased. In this study, a crack in a
conduit was modeled based on the current conduit design model, and the risk of internal erosion
was analyzed using a large-scale model test and three-dimensional deformation–seepage analysis.
The results show that when cracks existed in the conduit, soil erosion and cavitation occurred near
the crack area, which made the conduit extremely vulnerable to internal erosion. Herein, a model is
proposed that can reduce internal erosion by applying a layer of sand and geotextiles on the upper
Citation: Lee, Y.-H.; Ryu, J.-H.; Heo, part of the conduit located close to the downstream slope. In the proposed model, only partial erosion
J.; Shim, J.-W.; Lee, D.-W. Stability occurred inside the conduit, and no cavitation appeared near the crack in the conduit. The results
Improvement Method for suggest that internal erosion can be suppressed when the water pressure acting intensively on the
Embankment Dam with Respect to crack in the conduit is dispersed by the drainage layer. To validate these results, the pore water
Conduit Cracks. Appl. Sci. 2022, 12, pressure, seepage line, and hydraulic gradient were investigated to confirm the erosion phenomenon
567. https://doi.org/10.3390/
and reinforcement effect.
app12020567
Academic Editor: Bernhard Schrefler Keywords: conduit crack; embankment dam; hydraulic gradient; internal erosion; pore water pressure
phenomenon in which soil and water in the embankment zone are discharged to the slope
as erosion gradually develops inside the embankment [11].
A failure due to a conduit crack occurred at the Sandae Reservoir in Korea in April
2013 [12]. The failure, due to internal erosion caused by a conduit crack, resulted in a
concave circular shape being dug out around the conduit on the downstream slope, which
gradually expanded to the top of the embankment. The failure width of the embankment,
which started on the slope around the conduit, was approximately 12.2 m. The time that
elapsed between the leaked water appearing on the downstream slope and the failure
occurring was approximately 3 h, which is extremely short. An embankment failure due
to conduit cracks is a rare case, but since conduits continue to deteriorate, these failures
suggest that measurement strategies to deal with conduit cracks and failure problems will
be important in the future.
The conduits of small reservoirs are mostly circular in shape and have a small diameter.
This type of structure is a poor environment for reinforcing the inside of a conduit because
access by personnel and equipment is restricted. Therefore, reinforcement is carried out
outside the conduit. Currently, the reinforcement of conduits is based on the results of
investigating the leakage using photographic equipment, and a full or partial repair and
reinforcement are conducted according to the level of damage [13]. There are various
methods for reinforcing a conduit, such as grouting, waterproof mortar, and high-density
polyethylene (HDPE) slip lining of the pipe [14], and drilling is required in many cases.
However, reinforcement by drilling requires a careful approach, as it can affect the reinforce-
ment effectiveness by introducing new problems due to hydrofracturing, internal erosion,
and the contamination of filters and drainage materials in the embankment zone [15,16].
Therefore, in this study, an improvement model was developed as a way to minimize
the uncertainty of reinforcement due to drilling and maintain the reinforcement effect in the
long term. The improvement model aims to delay internal erosion by applying a drainage
layer (geotextile and sand layers) that can distribute the water pressure on the upper and
downstream slopes of the conduit without drilling. In order to evaluate the effectiveness
of the improvement model, the current model was constructed based on a conduit with a
circular shape and a small diameter. For the current model and the improvement model,
the erosion characteristics due to cracks occurring in the conduit were evaluated by a
large-scale indoor model test and three-dimensional deformation–seepage analysis. The
results discussed in this study provide basic data that can be put into practical use on the
embankment site of an old reservoir in the future.
𝑷𝑰 𝑾𝒐𝒑𝒕 𝜸𝒎𝒂𝒙 𝒄 𝒌𝒗
Sample 𝑮𝒔 ∅° USCS
(%) properties
Table 1. Physical and mechanical (%) of(kN/m 3)
samples (kPa)
used in the model. (m/s)
Clay layer 2.76 8.6 - 13.66 29.43 0 3.70 × 10−9 CL
PI W γmax c kv
Sample Gs Embankment opt
2.65 9.2 8.6 17.75 ∅◦
16.70 24 2.37 × 10−7 SC
USCS
(%) (%) (kN/m3 ) (kPa) (m/s)
Sand layer 2.65 NP 12.7 17.00 0 33 7.82 × 10−4 SP
Clay layer 2.76 8.6 - 13.66 29.43 0 3.70 × 10−9 CL
Embankment 2.65 Geotextile 8.6 -
9.2 - 17.75 - 16.70- - 24 - 2.371.00 7 −3
× 10×−10 SC-
Sand layer 2.65 𝐺 NP 12.7 𝑃𝐼 = plasticity
= specific gravity, 17.00 index, 𝑊 0 = optimum moisture33 content, 𝛾 −4 = maximum
7.82 × 10 SP
Geotextile - dry density,
- 𝑐 = cohesion,
- ø° = internal
- friction angle,
- kv = coefficient
- 1.00 × 10−3 USCS =- uni-
of permeability,
fied
Gs =soil classification
specific gravity, PIsystem.
= plasticity index, Wopt = optimum moisture content, γmax = maximum dry density,
c = cohesion, ∅◦ = internal friction angle, kv = coefficient of permeability, USCS = unified soil classification system.
2.2. Measurement Location and Experimental Conditions
2.2. Measurement Location and Experimental Conditions
In this study, the experimental model was designed to be 1/30 of the prototype. The
heightIn(H),
thiswidth
study,(W),
the experimental
and length (L)model
of the was
model designed to250,
were 51, be 1/30 of the
and 270 cm,prototype. The
respectively.
height (H), width (W), and length (L) of the model were 51, 250, and
The embankment model was equipped with a pore water pressure gauge (rated capacity:270 cm, respectively.
The
50 embankment
kPa) that can bemodel was
applied to equipped
the scale ofwith a pore water
a reduced pressure
model, gauge
and it was (rated capacity:
installed in each
50 kPa) that can be applied to the scale of a reduced model, and it was installed
section (P1, P2, and P3) of the upper part of the conduit. Figure 1 shows the cross-section in each
section (P1, P2, and P3) of the upper part of the conduit. Figure 1 shows the
of the experimental model and the installation location of the pore water pressure gauge. cross-section
of the
The experimental
model conduit wasmodel and theofinstallation
composed a pipe withlocation
a lengthof
ofthe
250pore
cm andwater pressureof
a diameter gauge.
φ50
The model conduit was composed of a pipe with a length of 250 cm and
mm based on design criteria [13], where the width of the crack area for the pipe wasϕ50a diameter of 10
mm based on design criteria [13], where the width of the crack area for the pipe was 10 cm,
cm, and the diameter of the crack was φ8–10 mm.
and the diameter of the crack was ϕ8–10 mm.
Experimentalmodel
Figure1.1.Experimental
Figure modeland
andmeasurement
measurementlocation.
location.
Figure 2. Comparison
Figurebetween conduit models:
2. Comparison between(a)conduit
currentmodels:
model, (b)
(a)proposed improvement
current model, model. improve
(b) proposed
model.
In this context, the improved model presented in this study is a method of applying a
layer of sand and geotextiles on top
In this context, theofimproved
the clay layer
modelinpresented
the current model.
in this The
study is purpose
a method of app
of this additional layer is to install a sand layer on the downstream slope to prevent
a layer of sand and geotextiles on top of the clay layer in the current model. the The pur
leaking water from
of thisrising to the downstream
additional embankment
layer is to install zoneonand
a sand layer thetodownstream
apply geotextile
slopetoto preven
prevent the loss of soil particles.
leaking water from rising to the downstream embankment zone and to apply geote
In a general embankment
to prevent the lossdam, a drainage
of soil particles. structure such as a toe drain or filter is
located at the end ofInthe downstream slope
a general embankment of the embankment
dam, a drainage to stably drain
structure such the
as aseepage
toe drain or fil
water. However, when erosion starts at a crack in the conduit, the drainage
located at the end of the downstream slope of the embankment to stably structure
drain the see
installed at the end of the downstream slope induces rapid drainage of the seepage water,
water. However, when erosion starts at a crack in the conduit, the drainage structur
which may increase the risk of internal erosion.
stalled at the end of the downstream slope induces rapid drainage of the seepage w
Here, the general premise of the improvement model is that when a sand layer and
which may increase the risk of internal erosion.
geotextile are placed on the upper part of the conduit, the water pressure concentrated on
Here, the general premise of the improvement model is that when a sand layer
the crack surface of the conduit is dispersed into the sand layer to induce a delay of internal
geotextile are placed on the upper part of the conduit, the water pressure concentrate
erosion. The improved model differs from the general embankment dam drainage structure
the crack surface of the conduit is dispersed into the sand layer to induce a delay of i
in that it is designed in consideration of the prevention of potential piping due to conduit
nal erosion. The improved model differs from the general embankment dam drai
cracks. Table 2 lists the experimental cases for the current model and the improvement
structure in that it is designed in consideration of the prevention of potential piping
model.
to conduit cracks. Table 2 lists the experimental cases for the current model and th
provement
Table 2. Experimental model.
cases for the current model and the improvement model.
Figure 3.
Figure 3. Crack
Crack conditions
conditionsin
incurrent
currentmodel
model(Case
(Case1—Crack):
1—Crack):(a)(a)
soil particle
soil lossloss
particle inside conduit,
inside (b)
conduit,
surface conditions of downstream slope, (c) erosion in near-conduit-filling zone.
(b) surface conditions of downstream slope, (c) erosion in near-conduit-filling zone.
In
In general, it is believed
the condition that by
reinforced if the embankment zone
a geomembrane (Casehas a high degree of compaction,
1—Reinforcement), no soil loss
cavitation
or erosionisoccurred
less likely to occur
inside owing to
or outside theconduit,
the high density of soil.
as shown in The model
Figure 4a,b.embankment
However, a
constructed
wide wet area in this
in a study had awas
loose state compaction
observeddegree
on theofdownstream
approximately 95%,
slope, as similar
shown toin that of
Figure
the actual embankment dam. Experimental results clearly show that even
4b. This indicates that the seepage line inside the embankment was formed on the top of if the compaction
or
thestrength of theThese
clay layer. embankment is high,
results show structural
that the claydefects, suchfunctioning
layer was as conduit cracks, can create
normally, but it
ashould
specialbeenvironment wherein cavitation can occur. Cavitation is suggested as
noted that over a long period of time, structural defects occurred in the conduit, one of the
causes that can failure
and a potential lead to might
the failure
form ofin an
theembankment
downstream dam slope.[19]. Generally, the causes of
embankment accidents and failures are investigated, but they are difficult to specify because
they are diverse. However, the results obtained in this study are considered important for
the field of embankment dams, as cavitation due to conduit cracks was identified.
Consequently, Case 1—Cracks did not lead to the failure of the embankment, but the
current model clearly showed that the cavitation risk due to the internal erosion of the
embankment zone could be high once conduit cracks occur.
In the condition reinforced by a geomembrane (Case 1—Reinforcement), no soil loss or
erosion occurred inside or outside the conduit, as shown in Figure 4a,b. However, a wide
wet area in a loose state was observed on the downstream slope, as shown in Figure 4b.
This indicates that the seepage line inside the embankment was formed on the top of the
clay layer. These results show that the clay layer was functioning normally, but it should
Appl. Sci. 2022, 12, x FOR PEER REVIEW 6 of 12
be noted that over a long period of time, structural defects occurred in the conduit, and a
potential failure might form in the downstream slope.
Reinforcementcondition
Figure 4. Reinforcement conditionofofcurrent
current model
model (Case
(Case 1—Reinforcement):
1—Reinforcement): (a) loss
(a) no no loss of par-
of soil soil
ticles inside
particles conduit,
inside (b)(b)
conduit, formation of of
formation wide
widewet
wetarea
areaoutside
outsidethe
theconduit,
conduit,(c)
(c)reinforced
reinforced crack
crack area
using membrane.
using membrane.
Figures 55 and
and66depict
depictthe
theleakage
leakageofof soil
soil into
into thethe conduit,
conduit, the the downstream
downstream slope,
slope, and
and the erosion
the erosion of soilofaround
soil around the cracked
the cracked area of area of the conduit.
the conduit. In the
In the crack crack condition
condition (Case 2—
Crack), the amount of soil loss inside the conduit was markedly smaller than that in the
current model (Case 1—Crack), as shown in Figure 5a. For the erosion area at the bottom of
the conduit, the improvement model was found to have approximately 1.7 times less ero-
sion than the current one; this proved it to be effective in reducing internal erosion. Mean-
Figure 4. Reinforcement condition of current model (Case 1—Reinforcement): (a) no loss of soil par-
Figure 4. Reinforcement
ticles inside conduit, (b)condition
formationofofcurrent model
wide wet (Case
area 1—Reinforcement):
outside the conduit, (c)(a) no loss ofcrack
reinforced soil par-
area
Appl. Sci. 2022, 12, 567 ticles inside conduit, (b) formation of wide wet area outside the conduit, (c) reinforced crack 6 of 12
area
using membrane.
using membrane.
Figures 5 and 6 depict the leakage of soil into the conduit, the downstream slope, and
(Case Figures
the erosion of5 soil
2—Crack), andthe 6 depict
amount
around thecracked
the leakage
of of soil
soil loss
area of into
inside
the thethe conduit
conduit,
conduit. thecrack
was
In the downstream
markedly
condition slope,
(Caseand
smaller than
2—
the
that erosion
Crack),in the of soil
the current around
amountmodel the
of soil (Case cracked area
1—Crack),
loss inside of the conduit.
as shown
the conduit was in In the crack
Figure 5a.
markedly condition
For the
smaller that in2—
(Case
thanerosion area
the
Crack),
at
current the amount
the bottom
model of theof
(Case soil lossthe
conduit,
1—Crack), inside the in
asimprovement
shown conduit
Figure was
model
5a. Formarkedly
was thefound smaller
erosion to area
have than that
atapproximately
the in theof
bottom
current
1.7
thetimes model
lessthe
conduit, (Case
erosion 1—Crack),
than the current
improvement as shown
model one;infound
was Figure
this to5a.
proved For
haveit tothe
beerosion
effective
approximately area at times
in1.7 the bottom
reducing of
internal
less ero-
the conduit,
erosion. the
sion thanMeanwhile, improvement
the currentlocallyone; this model
wetproved was
areas were found
it to beobservedto have
effectiveinin approximately
the downstream
reducing 1.7
internal times
slope, less
as shown
erosion. ero-
Mean- in
sion
Figure than
5b.the
Thiscurrent
shows one;
that this
the proved
seepage it to be
water effective
concentrated in reducing
in
while, locally wet areas were observed in the downstream slope, as shown in Figure 5b. This the internal
crack areaerosion.
of the Mean-
conduit
while,
was
shows locally
partially
that the wet areas were
dispersed
seepage in
water observed
the sand in theIndownstream
layer.
concentrated contrast
in the crack to slope,
Case
area of asthe
shown
1—Crack, in
noFigure
conduit was 5b.
cavitation This
was
partially
shows
observed that
dispersed in the seepage
in the sand
vicinity water
layer.of In concentrated
thecontrast
conduittoin Casein
Case the crack
2—Crack,
1—Crack, area of
no despitethe
cavitation conduit
thewas was
erosion
observed partially
inside the
in the
dispersedasinshown
conduit, the sand inlayer.
Figure In contrast
Thesetoresults
Case 1—Crack, no cavitation was observed in the
vicinity of the conduit in Case5c. 2—Crack, despiteare theassociated
erosion inside withthe the layers
conduit, of shown
as sand and
in
vicinity of the
geotextiles in conduit
theresults in Case
cracked 2—Crack, despite the erosion inside the conduit, as shown in
Figure 5c. These are area of thewith
associated conduit suppressing
the layers of sand and the erosion
geotextiles rates.
in the Under
cracked the
Figure 5c. These
condition results are associated with the layers of sand and geotextiles in theno cracked
area of theof geomembrane
conduit suppressing reinforcement
the erosion (Case 2—Reinforcement),
rates. Under the condition of there was
geomembrane lossre-of
area
soil of the
inside conduit
the suppressing
conduit, and the the erosion
area around rates.it Under
was the
stable condition
against of geomembrane
erosion, as shown re-in
inforcement (Case 2—Reinforcement), there was no loss of soil inside the conduit, and the
inforcement
Figure (Case
6a,c. In 2—Reinforcement),
addition, there was no the
losswetof soil inside the conduit, and theas
area around it was stableon the downstream
against erosion, as shownslope, in Figure area
6a,c.decreased
In addition, considerably,
on the down-
area
the around
seepage it was stable against erosion, as shown in Figure 6a,c. In addition, on theasdown-
stream slope,water
the wetin the
areaembankment was dispersed
decreased considerably, as thethroughout
seepage water the sand
in thelayer,
embankment shown
stream
in Figure slope, the wet area decreased considerably,
6b. throughout the sand layer, as shown in Figure 6b. as the seepage water in the embankment
was dispersed
was dispersed throughout the sand layer, as shown in Figure 6b.
Figure 5. Crack
Figure Crack conditions
conditions in the
in the improved
the improved model
improvedmodel (Case
model(Case 2—Crack):
(Case2—Crack): (a)
2—Crack):(a) modest
(a)modest loss
lossofof
modestloss soil
ofsoil particles
soilparticles
particles
Figure 5.
5. Crack conditions in
in the
in the conduit,
conduit, (b)
(b) sand
sand and
and geotextile
geotextile layers
layers in
in the
the downstream
downstream slope,
slope, and
and (c)
(c) minimal
minimal soil
soil loss
lossnear
near
sand and geotextile layers in the downstream slope, and (c) minimal soil loss near
the conduit-filling zone.
the conduit-filling zone.
Figure 6.
Figure 6. Reinforced
Reinforced conditions
Reinforced conditions of
conditions of improvement model
of improvement
improvement model (Case
model(Case 2—Reinforcement):
(Case2—Reinforcement):
2—Reinforcement):(a) (a) zero
(a)zero loss
lossofof
zeroloss of
soil particles
soil particles due
particles due to reinforced geomembrane, (b) reduced wet area in the downstream slope, and
soil due to
to reinforced
reinforced geomembrane,
geomembrane,(b) (b)reduced
reducedwet
wetarea
areaininthe
thedownstream
downstreamslope,
slope,and
and
(c) stability
(c) stability against
against erosion
erosion in the
the fillingzone
zone nearthe
the conduit.
(c) stability against erosion in
in the filling
filling zone near
near theconduit.
conduit.
The improvement model analyzed in this study used the combined effect of the sand
and geotextile layers in the downstream slope to suppress cavitation, even in the presence
of other structural defects (such as cracks in the piping). Therefore, it can be concluded
that the improvement model is a reliable method to improve the safety of an embankment
compared to the current method. Furthermore, applying the improvement model to the
downstream slope is simple and does not require drilling, which can be a great advantage
in terms of constructability.
PWP (kPa)
0.5 0.5
0 0
-0.5 -0.5
0 10 20 30 40 50 0 10 20 30 40 50
Time (hr) Time (hr)
7. Changes
Figure 7.
Figure Changesininpore
porewater
waterpressure duedue
pressure to conduit cracking:
to conduit (a) current
cracking: modelmodel
(a) current (Case 1—Crack),
(Case 1—
(b) improvement
Crack), model (Case
(b) improvement model2—Crack).
(Case 2—Crack).
In Case
In Case 1—Crack,
1—Crack,the theupstream
upstream pore
porewater pressure
water (P1)(P1)
pressure shows a continuous
shows decrease,
a continuous de-
which indicates that the crack in the conduit was affected by leakage. The
crease, which indicates that the crack in the conduit was affected by leakage. The changechange in the
downstream pore water pressure (P3) was insignificant because the leak from
in the downstream pore water pressure (P3) was insignificant because the leak from the the conduit
crack escaped
conduit to the lower
crack escaped to thepart
lowerofpart
the of
point
the where the pore
point where the water pressure
pore water gauge
pressure was
gauge
installed, and the effect of the water pressure was not observed. This trend
was installed, and the effect of the water pressure was not observed. This trend providedprovided the
same measurement results in all cases. In addition, the water pressure change
the same measurement results in all cases. In addition, the water pressure change was was small
at the center pore water pressure (P2). The results show that leakage was extensive in the
small at the center pore water pressure (P2). The results show that leakage was extensive
downstream conduit cracks, and thus, the seepage water did not reach the pore pressure
in the downstream conduit cracks, and thus, the seepage water did not reach the pore
gauge located in the center of the embankment zone. The embankment cross-section with
pressure gauge located in the center of the embankment zone. The embankment cross-
these conditions suggests that the risk of internal erosion around the downstream conduit
section with these conditions suggests that the risk of internal erosion around the down-
crack area may increase because the seepage water proceeds at the conduit crack area.
stream conduit crack area may increase because the seepage water proceeds at the conduit
In Case 2—Crack, the pore water pressure trends on both the upstream side (P1) and
crack area.
downstream side (P3) were similar to those of Case 1—Crack, but only the pore water
In Case 2—Crack, the pore water pressure trends on both the upstream side (P1) and
pressure (P2) at the center side increased. The increase in the central pore water pressure
downstream side (P3) were similar to those of Case 1—Crack, but only the pore water
(P2) indicates that water leakage is induced by the sand layer and geotextile installed on
pressure (P2) at the center side increased. The increase in the central pore water pressure
the downstream slope.
(P2) indicates that indicate
These results water leakage is sand
that the induced byand
layer the geotextile
sand layerdisperse
and geotextile installed
the water on
pressure
the downstream slope.
acting intensively on the conduit crack area and show that these additional layers are
These
effective in results
reducingindicate
the riskthat the sanderosion
of internal layer and geotextilethe
by delaying disperse the velocity.
leakage’s water pressure
acting intensively on the conduit crack area and show that these additional layers are ef-
fective in reducing
3.3. Seepage Line andthe risk of internal
Hydraulic Gradient:erosion by delaying
Numerical Analysis the leakage’s velocity.
3.3.1. Analysis Conditions
Seepage analysis in embankment dams provides useful information for estimating
the influence of seepage behavior according to the shapes of substructures inside the
embankment and the physical properties of their materials, water level conditions, and
soil–water characteristic curve. In this study, three-dimensional transient analysis was con-
ducted to identify the effects of conduit cracks and reinforced conduits on the embankment.
Transient analysis provides information supporting the validity of experimental results
by evaluating the erosion potential of the seepage line and the hydraulic gradient. The
analysis was performed using the elastic model (Geotextile) and Mohr–Coulomb model
(Clay, Embankment, Sand) of GTS NX 3D with the finite element method applied [20].
The dimensions, analysis parameters (Table 2), water level (H: 35 cm), and time boundary
(1 day = 86,400 s) of the cross-section of the embankment dam were the same as those of
the experimental model in this study. Additionally, the foundation of an impermeable
layer was configured to allow the leak to flow only in the embankment zone due to cracks
in the conduit. The mesh used Delaunay triangulation. The mesh size was about 0.03 m,
Appl. Sci. 2022, 12, 567 8 of 12
and 357,027 elements were generated. Tables 3 and 4 show the input parameters used for
3D transient analysis. The soil–water characteristic curves were applied to silty clay (clay
layer), sandy clay (embankment zone), and sand (sand layer) based on the van Genuchten
data [21]. At the present stage, only the cavitation potential in the experiment is presented,
and cavitation modeling was not included in this analysis.
c kx
Sample ν e0 ∅◦
(kPa) (m/s)
Clay layer 0.40 0.98 29.43 0 3.70 × 10−9
Embankment 0.35 0.48 16.70 24 2.37 × 10−7
Sand layer 0.33 0.50 0 33 7.82 × 10−4
Geotextile 0.30 - - - 1.00 × 10−3
ν = Poisson’s rate, e0 = initial void ratio, c = cohesion, ∅◦ = internal friction angle, k x = horizontal coefficient
of permeability.
Sample θs θr α n m(1−1/n)
Clay layer 0.38 0.007 0.8 1.09 0.083
Embankment 0.46 0.034 1.6 1.37 0.270
Sand layer 0.43 0.045 14.5 2.68 0.627
θr = residual water content, θs = saturated water content, α, n, m = curve fitting parameters.
Figure 8. 8.
Figure Changes
Changesininseepage
seepage line in current
line in currentand
andimprovement
improvement models:
models: (a) Case
(a) Case 1—Crack,
1—Crack, (b) Case
(b) Case
1—Reinforcement,
1—Reinforcement,(c) (c)Case
Case 2—Crack,
2—Crack, (d)(d)Case
Case2—Reinforcement.
2—Reinforcement.
Figure8c,d
Figure 8c,dshow
show the
the improvement
improvement model,
model,ininwhich thethe
which sand layer
sand and and
layer geotextile
geotextile
were applied to minimize internal erosion in this study. The seepage line of Case 2—Crack
were applied to minimize internal erosion in this study. The seepage line of Case 2—Crack
(Figure 8c) was formed at the crack site of the conduit for the initial 3 h, but the seepage
line dropped to the end of the downstream slope under the water level condition at 24 h.
These results show that the model not only reduces erosion due to the promotion of drain-
age in the sand layer above the clay layer but also provides a useful function to stably
Appl. Sci. 2022, 12, 567 9 of 12
(Figure 8c) was formed at the crack site of the conduit for the initial 3 h, but the seepage line
dropped to the end of the downstream slope under the water level condition at 24 h. These
results show that the model not only reduces erosion due to the promotion of drainage
in the sand layer above the clay layer but also provides a useful function to stably drain
the seepage water inside the embankment. Case 2—Reinforcement (Figure 8d) is the
condition in which the crack area of the conduit was reinforced by the geomembrane
in the improvement model. Unlike Case 1—Reinforcement, the seepage line of Case
2—Reinforcement appeared to gather at the end of the downstream slope under all of the
time conditions (0–24 h), which was interpreted as the condition in which the embankment
is in its most stable state. The seepage lines analyzed in this study are considered to be valid
data that can support the reliability of the internal erosion results in the model experiments.
Figure 9.
Figure 9. Location of hydraulic-gradient evaluation.
4 safety conditions for the internal erosion suggested in this study. In the current model,
3.5 0.2
3
if a crack occurs in a conduit, erosion may be inevitable regardless of fluctuations in
the water level, and 0.15
2.5 Caseit1-Crack
was determined that the possibility of1-Reinforcement
Case it developing into a piping
2 phenomenon is high. Case 2—Crack
Case 2-Crack (improvement model) had a hydraulic gradient of
Case 2-Reinforcement
0.1
1.5 0.42–0.44 and satisfied the safety conditions for internal erosion. Despite the small scale
1 0.05
0.5 of the cross-section of the drainage layer in Case 2—Crack, the hydraulic gradient was
0 0
0 5 10 15 20 25 0 5 10 15 20 25
Time (hr) Time (hr)
Figure 10. Time histories of variations in hydraulic gradients under (a) crack and (b) reinforcement
Appl. Sci. 2022, 12, 567 10 of 12
reduced compared to Case 1—Crack; thus, the improvement model was confirmed to be
effective for increasing
Figure 9.the resistance
Location to internal erosion.
of hydraulic-gradient evaluation.
(a) (b)
4.5 0.25
ment. These data explain the relationship between conduit cracks and the stability of the
embankment and can be used as fundamental data for the reduction in internal erosion.
Despite the small crack scale of the conduit, piping may occur due to internal erosion
under low water level conditions. The improvement model proposed in this study is a
useful method that can improve the safety of the embankment compared to the current
method because it can suppress the development of cavitation and piping, even if structural
defects, such as cracks, occur in the conduit.
Author Contributions: Software, J.-H.R.; investigation, J.H. and J.-W.S.; writing—review and editing,
Y.-H.L.; project administration, supervision, and conceptualization, D.-W.L. All authors have read
and agreed to the published version of the manuscript.
Funding: This work was supported by the Basic Science Research Program through the National Research
Foundation of Korea (NRF), funded by the Ministry of Education (grant no. 2019R1I1A3A01058517),
and the National Research Foundation of Korea (NRF) grant funded by the Ministry of Science, ICT
& Future Planning of the South Korean Government (grant no. 2019R1C1C1007100). In addition,
this work was supported by the Korea Institute of Planning and Evaluation for Technology in Food,
Agriculture and Forestry (IPET) through the Agricultural Infrastructure and Disaster Response
Technology Development Project, funded by the Ministry of Agriculture, Food and Rural Affairs
(MAFRA) (grant no. 320002-01).
Institutional Review Board Statement: Not applicable.
Informed Consent Statement: Not applicable.
Data Availability Statement: The study did not report any data.
Acknowledgments: We would like to thank the Rural Research Institute and Korea Rural Commu-
nity Corporation for their support (data and administrative) to prevent disasters caused by cracks
in conduits.
Conflicts of Interest: The authors declare no conflict of interest.
References
1. Skempton, A.W. Embankments and cuttings on the early railways. Constr. Hist. 1996, 11, 33–49.
2. Coleman, S.E.; Andrews, D.P.; Grant Webby, M.G. Overtopping breaching of noncohesive homogeneous embankments. J. Hydraul.
Eng. 2002, 128, 829–838. [CrossRef]
3. Fell, R.; Wan, C.F.; Cyganiewiewicz, J.; Foster, M. Time for development of erosion and piping in embankment dams. J. Geotech.
Geoenviron. Eng. 2003, 129, 307–314. [CrossRef]
4. Flores-Berrones, R.; Ramírez-Reynaga, M.; Jose Macari, E. Internal erosion and rehabilitation of an earth-rock dam. J. Geotech.
Geoenviron. Eng. 2011, 137, 151–160. [CrossRef]
5. Fox, G.A.; Felice, R.G.; Midgley, T.L.; Wilson, G.V.; Al-Madhhachi, A.T. Laboratory soil piping and internal erosion experiment:
Evaluation of a soil piping model for low-compacted soils. Earth Surf. Process. Landf. 2014, 39, 1137–1145. [CrossRef]
6. Lee, D.W.; Noh, J.J. Behavior of failure on agricultural reservoirs embankment by riprap reinforcement method. J. Korean Soc.
Agric. Eng. 2014, 56, 63–73. (In Korean)
7. Lee, Y.H.; Lee, T.H.; Lee, D.W. Overtopping model experiments and 3-D seepage characteristics of the embankment of deteriorated
homogeneous reservoirs. J. Korean Soc. Agric. Eng. 2019, 61, 13–23. (In Korean)
8. Ngambi, S.; Nakano, R.; Shimizu, H.; Nishimura, S. Cause of leakage along the outlet conduit underneath a low fill dam with
special reference to hydraulic fracturing. Trans. Jpn. Soc. Irrigation Drain. Reclam. Eng. 1997, 188, 263–272.
9. Tran, D.Q.; Nishimura, S.; Senge, M.; Nishiyama, T. Research on cause of dam failure from viewpoint of hydraulic fracturing—
Case study of a dam failure in Vietnam. Int. J. GEOMATE 2018, 14, 86–94. [CrossRef]
10. Tran, D.Q.; Nishimura, S.; Senge, M.; Nishiyama, T. Effects of culvert shapes on potential risk of hydraulic fracturing adjacent to
culverts in embankment dams. Int. J. GEOMATE 2018, 15, 38–44. [CrossRef]
11. Wan, C.F.; Fell, R. Investigation of rate of erosion of soils in embankment dams. J. Geotech. Geoenviron. Eng. 2004, 130, 373–380.
[CrossRef]
12. Korea Rural Community Corporation (KRC). Report on the Failure of the Embankment of the Angang Sandae Reservoir; Report of
Korea Rural Community Corporation; KRC: Naju-si, Korea, 2013. (In Korean)
13. Ministry of Agriculture, Food and Rural Affairs (MAFRA). Agricultural Infrastructure Design Standards; MAFRA: Sejong, Korea,
2002. (In Korean)
14. Cesare, J.A.; Brauer, D.J. Pinery Dam Outlet Conduit Repair, Biennial Geotechnical Symposium 2004. 26 April 2012. Available
online: https://doi.org/10.1061/40758(151)13 (accessed on 6 December 2021).
Appl. Sci. 2022, 12, 567 12 of 12
15. Federal Energy Regulatory Commission (FERC). Guidelines for Drilling in and near Embankment Dams and Their Foundations, Version
3.1; Division of Dam Safety and Inspections; FERC: Washington, DC, USA, 2016.
16. US Army Corps of Engineers (USACE). Engineering and Design—Drilling in Earth Embankment Dams and Levees; ER 1110-1-1807;
USACE: Washington, DC, USA, 2014.
17. Lee, Y.H.; Park, S.Y.; Tokida, K.I.; Lee, D.W. Three-dimensional seepage characteristics of reservoir embankment considering
interval of horizontal filter. Int. J. Offshore Polar Eng. 2018, 28, 80–86. [CrossRef]
18. Foster, M.A.; Fell, R.; Spannagle, M. The statistics of embankment dam failures and accidents. Can. Geotech. J. 2000, 37, 1000–1024.
[CrossRef]
19. Federal Emergency Management Agency (FEMA). Technical Manual: Conduits through Embankment Dams: Best Practices for
Design, Construction, Problem Identification and Evaluation, Inspection, Maintenance, Renovation, and Repair; FEMA: Washington, DC,
USA, 2005.
20. MIDAS IT. Midas Geotechnical and Tunnel Analysis System (Midas GTS). 2020. Available online: https://www.midasgeotech.
com/blog/tag/geotechnical-engineering (accessed on 20 October 2020).
21. Carsel, R.F.; Parrish, R.S. Developing joint probability distributions of soil water retention characteristics. Water Resour. Res. 1988,
24, 755–769. [CrossRef]
22. Ojha, C.S.P.; Singh, V.P.; Adrian, D.D. Influence of porosity on piping models of levee failure. J. Geotech. Geoenviron. Eng. 2001,
127, 1071–1074. [CrossRef]
23. Ojha, C.S.P.; Singh, V.P.; Adrian, D.D. Determination of critical head in soil piping. J. Geotech. Geoenviron. Eng. 2003, 129, 511–518.
[CrossRef]
24. United States Society on Dams (USSD). The Aging of Embankment Dams. 2010. Available online: https://www.ussdams.org/
wp-content/uploads/2016/05/aging.pdf (accessed on 20 October 2020).
25. Ke, L.; Takahashi, A. Strength reduction of cohesionless soil due to internal erosion induced by one-dimensional upward seepage
flow. Soils Found. 2012, 52, 698–711. [CrossRef]
26. Terzaghi, K.; Peck, R.B. Soil Mechanics in Engineering Practice, 2nd ed.; John Wiley and Sons, Inc.: New York, NY, USA, 1967; p. 729.