Professional Documents
Culture Documents
Dorji Article 1
Dorji Article 1
Dorji Article 1
net/publication/352674064
Article in IEEE Parallel and Distributed Technology Systems and Applications · April 2015
CITATION READS
1 70
7 authors, including:
Some of the authors of this publication are also working on these related projects:
Solar Food: Reducing post-harvest losses through improved solar drying View project
Analysis on implementation of low cost thermal insulation material in Bhutan View project
All content following this page was uploaded by Sonam Dorji on 23 June 2021.
Abstract—This paper presents system design and Different simulation and modelling softwares are being
performance analysis of a grid-tied solar photovoltaic power used to study the performance of solar PV systems. Hybrid
system with battery backup. The system was designed to supply Optimization Model for Electric Renewables (HOMER) is
10.5 kW lighting load of a library building at the College of one such simulation model developed by National Renewable
Science and Technology in Bhutan. The performance was Energy Laboratory USA [6]. HOMER is a computer model
simulated using HOMER model. From the simulation, it was that simplifies the task of evaluating design options for both
found that the PV system is able to supply more than 31% of off-grid and grid-tied power systems for remote, stand-alone
the load in a year. The cost of PV energy generation over 25 and distributed generation applications. It enables the users to
years project life term was found to be 0.13 US$/kWh which is
evaluate the economic and technical feasibility of a large
six times higher than the current average cost of hydropower
number of technology options and to account for uncertainty
generation. The proposed system is financially not viable at the
current subsidized electricity tariff in Bhutan as the payback
in technology costs, energy resource availability, and other
period is more than the project life term and the net cash flow is variables. It can model both conventional and renewable
negative. energy technologies. Several studies have been carried out in
the past using HOMER. Varshney, Sharma and Khatod [7]
Keywords— HOMER; Solar PV; Cost of energy; Bhutan used HOMER to size a hybrid energy system consisting of
solar, micro hydro, biomass, diesel and battery for a rural
I. INTRODUCTION Narendra Nagar block, Tehri Garhwal of Uttarakhand. The
Bhutan, located in the Himalayas has a significant authors also also carried out the environmental aspects of
hydropower potential from the rivers flowing from north to different configuration. The total annual optimum cost and the
south. The total hydropower potential is estimated to be 30 cost of energy using HOMER was found to be US$ 39 919
GW of which 16 GW is said to be techno-economically and US$ 0.11/kWh respectively. A similar study by Roy,
viable. Out of which only 1488 MW has been developed [1]. Basu and Paul [8] also used HOMER to design and analyze a
Another 2910 MW hydropower plant is under solar PV system with battery storage in two modes, grid-tied
implementation, which is scheduled to complete by the end of and a standalone for electrification of a residential area
2017 [2]. Bhutan exported 5648 GWh electricity to India in located near Siliguri, West Bengal. The climate data was
2013 which is more than 75% of total generation [3]. Energy obtained from NASA surface meteorology and solar energy
demand in Bhutan is steadily increasing as it develops and website. From the analysis, the cost of energy was found to be
modernizes. Annual domestic consumption of electricity US$ 0.87/kWh for a standalone system compared to
increased from 338 GWh in 1995 [4] to 1901 GWh in 2013 $0.08/kWh for a grid-tied system.
[5]. During summer the energy production far exceeds its Salam, Aziz, Alwaeli and Kazem [9] carried out the
need, however it is unable to meet its need during the dry design and analysis of photovoltaic system to supply lighting
seasons. With this concern and also to further increase load for Renewable Energy Lab at Sohar University, Oman
electricity export to India, the Royal Government of Bhutan using HOMER. The solar energy utilization was found to be
targets to develop 10 000 MW of hydropower capacity by an attractive option with initial and energy cost of US$ 3425
2020 [3]. At the same time Bhutan also plans to harness and 0.561 US$/kWh respectively. Kazem, Qasim Ali,
another 20 MW through a mix of other renewable energy Alwaeli, Mani and Tariq [10] used HOMER to design and
technologies by 2025. Among the many renewable energy analyze a PV system for electrifying a health clinic in Oman
technologies, solar photovoltaic (PV) system has been with an average daily load of 42.307 kWh/day. The analysis
identified as one of the feasible options in Bhutan. showed the cost of energy as 0.418 US$/kWh. Similarly,
Globally, solar PV systems, both off-grid and grid-tied are Damanhuri, Othman, Ibrahim, Radzali and Mohd [11]
being developed as an alternative to conventional systems performed system design and cost analysis simulation of
using fossil fuels. This paper presents performance analysis of small scale dual-tariff solar photovoltaic system in UiTM
a grid-tied solar PV power system designed to supply lighting Pulau Pinang Malaysia using HOMER. Givler and Lilienthal
load of a library building at the College of Science and also used HOMER to determine the threshold load size at
Technology, Phuentsholing, Bhutan. The proposed system is which it is more cost-effective to include a diesel than to
envisaged to be used as a demonstration and training project increase the size of the battery bank or PV array [12]. Thus it
in order to encourage development of solar PV power system was observed that several authors used HOMER to design
in Bhutan. It is worthwhile to note that there are no similar and analyze performance of a solar PV system. Therefore,
studies conducted in the past in Bhutan. The current study HOMER was used as a simulation model in this paper. The
was conducted using simulation model HOMER. inputs to the HOMER model were extracted from the
manufacturer’s data submitted by the supplier.
20
15
Load (kW)
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
B. System configuration
The basic components of a grid-tied solar PV system with
battery backup consists of solar PV panels, tubular deep
charge batteries, an inverter and a charge controller. Fig. 2
depicts the block diagram of the proposed grid-tied solar PV
power system in HOMER. The proposed system is planned
to be installed on the roof of a three storeyed library building.
The building orientation and layout details of the PV panles Fig. 4. Layout of solar PV panels on roof
is presented in Fig. 3 and Fig. 4 respectively.
a. PV array
A total of 44 PV panels, each of 250 Wp and 24 V were used
for the proposed system simulation. The initial cost inlcuding
the mounting racks, delivery, installation and commissioning
is US$ 25 383. The operation and maintenance cost per year
was assumed to be 0.5% of the initial cost and its lifetime is
25 years. A derating factor of 90% was applied to each panel
to compensate for the degrading factors which is caused by
wiring losses, temperature, ageing, wind etc. The PV panels
are to be flush mounted on the existing roof which has a
slope of 13°. Thus the solar PV panels will have a slope of
13° with an azimuth of 29° as shown in Fig. 3. The effects of
temperaure on the PV output were also considered. The
Fig. 2. Block diagram of the proposed grid-tied PV system
average monthly solar radiation and clearness index for
Phuentsholing is shown in Fig. 5 and average ambient air
temperature and wind speed in Fig. 6.
539
6 0.8 The SSE data set is a set of global climatology from data
Daily radiation spanning 22 year period from July 1, 1983 through June 31,
Solar irradiation (kWh/m2/day)
Clearness Index
However, in 1989, the World Climate Research Program
0.4 estimated that most solar radiation ground sites has
uncertainties from 6 to 12% due to measurement
2 uncertainties from calibration drift, operational uncertainties,
0.2
or data gaps are often unknown or unreported for many
ground site data sets. The reliability of most of SSE data as
compared to ground measured data is in the range ±16%.
Moreover, a comparative analysis of long term climate data
0 0 from NASA and typical meterological year (TMY) data by
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Lhendup and Lhundup found variation of upto 7% only [14].
Hence, by using SSE data, there may not be significant
Fig. 5. Monthly solar radiation profile difference between the actual output and the simulated
output. Nevertheless, the longterm climate data was
30 5 compared with the ground measured data.
In order to check the usability of climate data obtained
24 4 from the NASA and SSE website, the climate data was
compared with the measured data obtained from the
Wind speed (m/s)
Temperature (°C)
20
30 tubular dry charge batteries of 200AH, 12V each were
used for the system which results in 5 hours autonomy. The
capital cost of the batteries is US$ 7960 and its life term was
assumed to be 10 years. The maintenance cost per year was
10
presumed to be 1% of the initial cost.
NASA MoEA
c. Inverter
An inverter was used to convert the DC output from the
PV array and the battery into AC output. A solar inverter of 0
20kVA/360V was chosen for the simulation whose 1 2 3 4 5 6 7 8 9 10 11 12
efficiency as per the manufacturer’s data is 96%. The capital
cost of the inverter if US$ 5900 and its life term is 10 years. Months
The maintenance cost was assumed to be same as the battery Fig. 7. Monthly minimum temperature (NASA vs MoEA)
maintenance cost.
III. CLIMATE DATA EVALUATION
Climate data is one of the most important factor which
determines the output power generated by a PV system.
Without proper assessment of the available renewable solar
energy resources, PV is set to disappoint the end users.
Therefore ground measurement stations are a useful assets
for the development of solar PV system. But due to absence
of the ground measurement stations in most part of Bhutan
the climate data for the simulation was obtained from NASA
Surface Meteorology and Solar Energy (SSE) website [13].
540
40 100%
80%
30
60%
Grid
20
40% PV
NASA MoEA
10
20%
0 0%
1 2 3 4 5 6 7 8 9 10 11 12
Months
Fig. 8. Monthly maximum temperature (NASA vs MoEA) Fig. 10. Monthly average electricity production
100 12
9
60
6
40
NASA MoEA
20 3
0
0
1 2 3 4 5 6 7 8 9 10 11 12
Months Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Fig. 9. Average monthly relative humidity (NASA vs MoEA) Fig. 11. Average monthly PV power generation
541
Nations Development Programme, Bhutan. Along with the [10] H. A. Kazem, S. Q. Ali, A. H. A. Alwaeli, K. Mani, and M. Tariq,
proposed system, a weather station is also being installed. "Life-cycle cost analysis and optimization of health clinic PV system
for a rural area in Oman," in World Congress on Engineering, London,
The proposed system will also be connected to a remote United Kingdom, 2013.
monitoring unit. The simulated results will be compared with [11] N. S. Damanhuri, N. A. Othman, I. R. Ibrahim, R. Radzali, and M. N.
the actual measurements and the results will be reported Mohd, "System design and cost analysis simulation of small scale dual-
elsewhere. tariff solar photovoltaic (PV) system in UiTM Pulau Pinang Malaysia,"
in World Congress on Engineering, London, United Kingdom, 2010.
TABLE II. COST COMPONENTS [12] T. Givler and P. Lilienthal, "Using HOMER® software, NREL’s
micropower optimization model, to explore the role of gen-sets in
Capital Replace- O&M Salvage Total
Comp. small solar power systems case study: Sri Lanka," National Renewable
($) ment ($) ($) ($) ($)
Energy Laboratory, 1617 Cole Boulevard, Golden, Colorado, United
PV
25 383 0 3 173 0 28 556 States of America Technical Report NREL/TP-710-36774 May 2005,
module
2005.
Battery 7 960 6 579 1 990 881 15 648 [13] NASA. (2014, April). NASA surface meteorology and solar energy.
Inverter 5 900 5 134 1 475 687 11 822 Available: http://eosweb.larc.nasa.gov
[14] T. Lhendup and S. Lhundup, "Comparison of methodologies for
Total 39 243 11 713 6 638 1 568 56 026 generating a typical meteorological year (TMY)," Energy for
Sustainable Development, vol. 11, pp. 5-10, 2007.
[15] BPC, "Tariff revision proposal July 2013 - June 2016," Bhutan Power
Corporation, Thimphu, Bhutan2013.
[16] BEA. (2014, September). Bhutan Power Corporation Tariff.
V. CONCLUSIONS (September), Bhutan Electricity Authority. Available:
The proposed grid-tied solar PV system for the library at http://www.bea.gov.bt/?page_id=28
College of Science and Technology, Phuentsholing was
simulated using HOMER model. From the analysis, it was
found that the simple payback period is more than the project
life term at the current subsidized electricity tariff. The total
cost of the system including the initial cost, replacement cost,
operation and maintenance cost and salvages is US$ 56 026.
The proposed system will be able to supply more than 31%
of the load at the generation cost of US$ 0.13/kWh which is
six times higher than the cost of hydropower generation.
ACKNOWLEDGEMENT
Yangchen Dolkar, Dawa Jamtsho, Rozal Adhikari,
Tshering Wangdi and Sonam Dorji would like to thank the
College of Science and Technology for the support rendered
while conducting this study.
Tshewang Lhendup and Cheku Dorji would like to thank
the Global Environment Facilty through the United Nations
Development Programme, Bhutan for generously sponsoring
the proposed project.
REFERENCES
[1] BEA. (2014, September). Druk green power corporation. (September),
Bhutan Electricity Authority. Available:
http://www.bea.gov.bt/?page_id=28
[2] DGPC. (2014, September). Updates from Projects Department.
Available: http://www.drukgreen.bt/index.php/projects-updates
[3] DGPC, "Druk Green Power Corporation Annual Report 2013,"
Thimphu, Bhutan2013.
[4] PCS, "Ninth five-year plan," The Planning Commission Secretariat,
Royal Government of Bhutan, Thimphu, Bhutan2002.
[5] BPC, "Bhutan Power Corporation Annual Report 2013," Thimphu,
Bhutan2013.
[6] HOMER, "Hybrid Optimization Model for Electric Renewables
(HOMER)," ed: National Renewable Energy Laboratory (NREL) USA,
2014.
[7] N. Varshney, M. P. Sharma, and D. K. Khatod, "Sizing of hybrid
energy system using HOMER," International Journal of Emerging
Technology and Advanced Engineering, vol. 3, pp. 436-442, 2013.
[8] B. Roy, A. K. Basu, and S. Paul, "Optimal design of a grid connected
solar photovoltaic power system for a residential load," International
Journal of Recent Advances in Engineering and Technology, vol. 1, pp.
2347-2812, 2013.
[9] M. A. Salam, A. Aziz, A. H. A. Alwaeli, and H. A. Kazem, "Optimal
sizing of photovoltaic systems using HOMER for Sohar, Oman,"
International Journal of Renewable Energy Research, vol. 3, pp. 301-
307, 2013.
542