Sequence or step

1 Determine the Elevations

2 Calculate the Slope

3 Dig the Trench and Lay the Bedding

4 Install the Pipe

5 Backfill the Trench


 scrapers or motor graders for leveling of the drainage machine’s track, drain route after its
laying and backfilling;
 dump trucks for transportation of drainge pipes, filtering materials, assemblies of outlet and
head structures, as well as surface inlets;
 bulldozers for sliding apart of spoil banks from the collector and drain outfall, backfilling of
drain trenches, grooves, and excavation pits;
 loaders for loading of sand & gravel filters onto dump trucks when transporting those from a
storehouse next to the site to a continuously operating drainage machine;
 truck cranes for mounting of the surface inlets, outlet and head structures;
 excavators for excavation of outlet recesses and bottom-hole trench, installation of a
drainage machine on the collector slope.

 machines for compacting the drain backfilling soil to full depth;


 machines for leveling the tracks of drainage machines at the specified slope grade of the
drain under construction, i.e. scraper DZ-20, DZ-77С, DZ-12 , bulldozer motor grader D-557-
1, DZ-98, DZ-1 leveling excavator EP-301 ;
 machines for the installation of outfall structures in drain trenches;
 drainage machines with a bunker folding during transportation D-301, ED-3, ED-3А, ETTs-
406, ETTs-252А