VSL India Pvt.

Ltd RFI Summary

Project MG Setu Project

Project Code VT2104 Submission Date 14.12.2022

Sl.no RFI no. RFI Issue Date Date of Inspection Segment ID Description of works Time of Inspection VSL Engineer SPS Engineer Remarks

1 VSL/MGSP/VT2104/RE/497 13.11.2022 14.11.2022 P18-A16-R Reinforcement checking for Segment casting 4.00 PM Mr.Mahesh Kondala Mr.Vivek

2 VSL/MGSP/VT2104/RE/498 13.11.2022 14.11.2022 P26 B2-F Reinforcement checking for Segment casting 4.00 PM Mr.Mahesh Kondala Mr.Vivek

3 VSL/MGSP/VT2104/RE/499 13.11.2022 14.11.2022 P28-A7-F Reinforcement checking for Segment casting 4.00 PM Mr.Mahesh Kondala Mr.Vivek

4 VSL/MGSP/VT2104/ST/500 13.11.2022 14.11.2022 S33(A33,B33,C33) Concreting of 2nos. of Strut in Bay 01 4.00 PM Mr.Mahesh Kondala Mr.Vivek

5 VSL/MGSP/VT2104/ST/501 13.11.2022 14.11.2022 S6(A6,B6,C6) Concreting of 2nos. of Strut in Bay 01 4.00 PM Mr.Mahesh Kondala Mr.Vivek Revised

6 VSL/MGSP/VT2104/ST/502 13.11.2022 14.11.2022 S9(A9,B9,C9) Concreting of 2nos. of Strut in Bay 02 4.00 PM Mr.Mahesh Kondala Mr.Vivek

7 VSL/MGSP/VT2104/MC/503 13.11.2022 14.11.2022 Mould Cell 04 Checking of Mould comissioning of Bay 01 Cell 04 4.00 PM Mr.Ravi Teja Mr.Vivek

8 VSL/MGSP/VT2104/RE/504 13.11.2022 14.11.2022 P28-B8-R Reinforcement checking for Segment casting 5.00 PM Mr.Mahesh Kondala Mr.Vivek

9 VSL/MGSP/VT2104/RE/505 13.11.2022 14.11.2022 P19-B24-F Reinforcement checking for Segment casting 5.00 PM Mr.Mahesh Kondala Mr.Vivek

10 VSL/MGSP/VT2104/PT/506 13.11.2022 14.11.2022 P26-B1-F Profile checking of Segment in Bay 2 Cell 01 8.00 PM Mr.Saurabh Roy Mr.Vivek

11 VSL/MGSP/VT2104/SC/507 13.11.2022 14.11.2022 P26-B1-F Concreting of Segment in Bay 2 Cell 01 8.00 PM Mr. Sharda Tiwari Mr.Vivek

12 VSL/MGSP/VT2104/PT/508 14.11.2022 14.11.2022 P18-B28-F Profile checking of Segment in Bay 2 Cell 06 6.00 PM Mr.Saurabh Roy Mr.Vivek Spot RFI

13 VSL/MGSP/VT2104/SC/509 14.11.2022 14.11.2022 P18-B28-F Concreting of Segment in Bay 2 Cell 06 6.00 PM Mr. Sharda Tiwari Mr.Vivek Spot RFI