Professional Documents
Culture Documents
Analytical Instrument System Qualification
Analytical Instrument System Qualification
Analytical Instrument System Qualification
Printed by: HB U
Commenting open for 69 more days
Published On: 01-Sep-2022
Open for Commenting as of: 22-Sep-2022
Document Type: ---NONE---
DocId: GUID-147CE940-25BE-47AC-BC3B-7AD1441EDF7B_10201_en-US
Printed from: https://online.uspnf.com/uspnf/document/2_GUID-147CE940-25BE-47AC-BC3B-7AD1441EDF7B_10201_en-US
© 2022 USPC
T
ABSTRACT
All analytical instruments and systems for compendial use must be qualified
to be "fit for intended use" using the guidance provided in the
EN
currently official
general chapter Analytical Instrument Qualification 〈1058〉.
Qualifying the operation and performance of an analytical instrument
or system
is a
critical part of a robust quality management system and is required in a current
good
manufacturing practice (CGMP) environment.
In pharmacopeial applications, the
performance of an instrument or system directly impacts the data reported by
establishing the reportable value
of an analytical test characteristic specified
in a
monograph.
In an earlier Stimuli article, Analytical Instrument and System (AIS) Qualification to Support Analytical
Procedure Validation over the Life Cycle (1),
NT
the overall aims and objectives of the Analytical Instrument and System
Qualification Joint Subcommittee (AISQ JSC) to enhance 〈1058〉 were
described (2). The purpose of this article is to explore in more detail the AIS life
cycle process published as Figure 5 of that article (republished
here as Figure 1). The process presented in this
article is not a formal proposal for revision of 〈1058〉, but
rather a deeper dive into the current
thinking and position of the AISQ JSC on
analytical instrument qualification and its relationship to the analytical procedure
life cycle management
framework. As with the previous articles published in PF on this topic (2–3), USP seeks stakeholder feedback on the concepts presented within.
CO
INTRODUCTION
The AIS qualification process provides the procedural and metrological performance
framework for an instrument or system with a maintained
qualified state of control
and calibration over its life cycle, as shown in Figure 1, in accordance with the operational ranges of
measurement as
specified in the user requirement specifications (URS). The framework
in Figure 1 also gives guidance on the roles and responsibilities
of vendors
AL
At the heart
of this process flow is the risk assessment and traceability matrix. A traceability
matrix, which forms part of the final qualification
NT
report, is the mapping of
each
requirement in the URS to an operational procedure, document, or test with
acceptance criteria so that all
qualification activities are completed. It is
clear
that the extent of the qualification effort required to assure "fitness for use"
depends both on the
complexity of the AIS and, critically, the use to which it
is
being put within a specific laboratory environment. There is no "one size fits
all"
approach
and some examples across the range of AIS are illustrated in Figure 2.
CO
AL
CI
FI
OF
UN
T
Figure 3. Extension of the AIS qualification life cycle process.
EN
LIFE CYCLE PROCESS
DESCRIPTIONS
User Requirement
Specifications
functionality, operation,
performance, data storage and processing, among other functions, while the DQ
evaluates the vendor capabilities for
post-installation support. The FS and DS
may take many forms, such as an instrument specification, manual, or
drawing.
Design Qualification
the
alignment of the URS, FS and DS, and other engineering technical documents, as
appropriate, as well as the compliance with critical ("good
practice"-relevant)
user requirements.
Purchase Order
OF
Once in agreement, the user will deliver a purchase order (PO), and
the vendor should provide, if appropriate, the site preparation requirements
for
the installation of the AIS. This site preparation should be completed before
the AIS is installed, according to a proper agreement between the
user and
vendor.
After purchase, the AIS is delivered with an AIS delivery note and,
if appropriate, a factory acceptance test (FAT) document.
UN
Installation Qualification
The vendor will manufacture the AIS, perform any necessary tests in
accordance with their quality system, and upon approval, deliver the AIS to
the
user in an appropriate manner. Start-up and commissioning may be done either
by
the vendor, a designated third party, or the user on the
installed AIS, and may
include system testing during installation. Data from commissioning may be
leveraged to support qualification activities if
the documentation practices
for
test generation, execution, and documentation meet CGMP.
AIS should be properly installed, and the installation qualification
(IQ) should be carried out and documented to verify that the AIS, as delivered,
complies with the approved DS. This may include initial adjustments,
calibration, preventive maintenance, training, and documentation.
Operational Qualification
OQ is done to verify that, at the user's facility, the AIS meets its
specifications, focusing on the URS. In this way, OQ verifies that the AIS meets
the URS. OQ should be performed using appropriate holistic and modular AIS
functional tests.
For example, the following OQ functional tests can be adopted for a
near-infrared spectrometer, where the intended use of AIS is both
quantitative
and qualitative applications (Near-Infrared Spectroscopy 〈856〉):
Qualitative: Wavelength
accuracy using NIST SRM 2036, signal-to-noise ratios, or NIST SRM
2065 compliance
Quantitative: Same as
above, but also include standards for photometric linearity (e.g.,
Spectralon, or NIST SRMs 1928 and 1929)
Performance Qualification
T
New Analytical Procedures
EN
If the comparison of the new URS to the existing AIS FS and DS shows
agreement, the AIS may be accepted for the new procedure. If the
comparison does
not show agreement for that specific analytical procedure, the instrument may
be
updated, upgraded, or a new instrument may
be considered for purchase. A risk
analysis should always be done to evaluate any impact on previously implemented
procedures using that AIS. If
use outside of the qualified conditions is needed,
the appropriate tests should be repeated at the new operating conditions.
NT
Ongoing Performance Verification
of the Qualified State
read the
archived data); and AIS disposal—should be documented.
ABBREVIATIONS
AIS: Analytical Instrument and System
CI
CONFLICT OF INTEREST
DISCLAIMER
The authors did not declare any conflicts of interest related to the
subject matter of this Stimuli article.
UN
REFERENCES
a
Burgess Analytical Consultancy
Limited, ‘Rose Rae’, The Lendings, Startforth, Barnard Castle, Co. Durham, DL12 9AB,
United Kingdom.
b
SYRUS Solutions, Inc.,
Danbury, CT, United States.
c
Training and Consultant at
D´Amico Sistemas S.A., Buenos Aires, Argentina.
d
Independent Consultant,
Winnipeg, Manitoba, Canada.
e
Consultant, Macon,
France.
f
Ermer Quality Consulting,
Bensheim, Germany.
g
Tecnometrix, Ciutadella de
Menorca, Spain.
h
Gustavus Adolphus College,
Saint Peter, MN, United States
i
United States Pharmacopeia,
Rockville, MD, United States.
T
Auxiliary Information
-
Please
check for your question in the FAQs
before contacting USP.
EN
Topic/Question Contact Expert Committee
Not Applicable
NT
DocID: GUID-147CE940-25BE-47AC-BC3B-7AD1441EDF7B_10201_en-US
CO
AL
CI
FI
OF
UN