Risk Plan
Risk Plan
Potential Risk/Hazard Assess Risk (use Action to be taken to reduce the risk (Control) Monitor Evaluate
(Identify) matrix)
Supply of White Sugar Critical High Risk Stock sugar as much as possible but make that The manager must Increase the cake and
the sugar will be stored in appropriate room check the sugar cupcakes price. Cannot
storage with the correct temperature. expiration date and find sugar to buy in the
validity to avoid market
contamination.