Method Statement
of
Excavation Work
1
C.A.T. GROUP METHOD STATEMENT OF EXCAVATION WORK
HAWIYAH-UNAYZAH GAS RESERVOIR REVISION 1 DATE 10.08.2020
STORAGE PROJECTS
SAUDI ARAMCO
Table of Contents
2
C.A.T. GROUP METHOD STATEMENT OF EXCAVATION WORK
HAWIYAH-UNAYZAH GAS RESERVOIR REVISION 1 DATE 10.08.2020
STORAGE PROJECTS
SAUDI ARAMCO
1. SCOPE
2. REFERENCES
ASTM D 4253 Test method for maximum index density and unit weight of
soil using a vibratory table.
ASTM D 4254 Test method for maximum index density and unit weight of
Relative density.
ASTM D 422 Test method for Practical-Size of Soil
ASTM D 698 Test method for Moister – density relation of soil and soil
aggregation.
ASTM D 1556 Test method for Density and weight of soil in place by the
sand – cone method.
ASTM D 1557 Test method for compaction characteristics of soil using
modified method.
ASTM D 2922 Test method of density of soil and soil aggregate in place
by nuclear method. (Shallow depth).
ASTM D 5777 Standard guide for using the Seismic Refraction Method
for Subsurface Investigation.
3
C.A.T. GROUP METHOD STATEMENT OF EXCAVATION WORK
HAWIYAH-UNAYZAH GAS RESERVOIR REVISION 1 DATE 10.08.2020
STORAGE PROJECTS
SAUDI ARAMCO
3.1 Definitions
Client: Saudi Aramco
Contractor: Br. CAT International Co. Ltd.
3.2 Abbreviations
CM – Construction Manager
QM – Quality Manager
HSEM – HSE Manger
4. RESPONSIBILITIES
4
C.A.T. GROUP METHOD STATEMENT OF EXCAVATION WORK
HAWIYAH-UNAYZAH GAS RESERVOIR REVISION 1 DATE 10.08.2020
STORAGE PROJECTS
SAUDI ARAMCO
Site Foreman – is responsible to ensure that the work crew is familiar with the
safety requirement of the activity.
The safety of all personnel, equipment and plant operations will be the
responsibility of the Construction Manager in coordination with the Site Engineer.
5. PREPARATION OF EQUIPMENT
Contractor will ensure that all heavy equipment listed below will be certified and
their operators have the required licenses as Saudi Aramco requirements.
Excavators
Grader
Backhoes
Bulldozer
Dump Trucks
Compactors
Vibrating Roller
Rock Breakers
Lifting Equipment
Jack Hammer with Air Compressor
Generators
6. PROCEDURE
back into the excavated area or taken away through dump truck at the
same time to designated dumping area. Excavated edge must be
sloped, or step shaped.
If any dewatering system is required during or after excavation a
separate method statement shall be submitted for method of
dewatering as well as disposal.
Contractor responsibility to protect all the underground/ above ground
utilities. During excavation caution and care shall be taken to avoid
any underground facilities damages. Daily surveillance shall be
conducted for possible caving. The underground utilities, cable, pipes
etc. shall be verified with plan as-built drawing prior to start any
excavation. Advice from Saudi Aramco Utility department shall be
taken to locate the existing utilities. If any suspects of existing
underground, then the mechanical excavation shall be stopped &
excavation shall be continuing with manual.
Suitable detecting equipment but not limited to, cable detectors,
ground mapping etc. shall be arranged by the contractor to locate
underground utilities. If ground utilities are suspected, excavation
shall be done manually to identify these utilities. Contractor has to
excavate for trial pits if required by Client.
The contractor shall be responsible for preserving and avoiding
damage to reference points, property markers, benchmarks,
monuments, etc., during the excavation, the damages shall be
repaired or replaced with the satisfaction of Client.
Excavation Plan, including a Pre-Excavation checklist, as per the
Saudi Aramco Construction Safety Manual and Safety Management
Guide 06-002-2008 shall be submitted prior to beginning excavation.
Consulting Services Department review of the Excavation Plan shall
be submitted if excavation depth is greater than 6 meter or if the Plan
includes support or protection for existing structures, foundations, or
underground utilities.
Heavy equipment shall not be operated within 2 meter or 1 time the
depth of excavation.
Excavation operator and HSE staff will stop excavation in case of any
person present inside of zone being excavated.
Certified gas tester to conduct gas testing prior to start the excavation
and before every entry and recorded.
Rescue team to be identified and present at site.
7
C.A.T. GROUP METHOD STATEMENT OF EXCAVATION WORK
HAWIYAH-UNAYZAH GAS RESERVOIR REVISION 1 DATE 10.08.2020
STORAGE PROJECTS
SAUDI ARAMCO
The health and safety will perform a splendid role in all construction activities to
ensure that all the works are being carried out in a safe manner and creating a
healthy environment at site. All works performed by individuals will comply with
the Client health and Safety Standards.
8
C.A.T. GROUP METHOD STATEMENT OF EXCAVATION WORK
HAWIYAH-UNAYZAH GAS RESERVOIR REVISION 1 DATE 10.08.2020
STORAGE PROJECTS
SAUDI ARAMCO
Ensured that all site personnel involved make us of their PPE. Housekeeping
and safe access properly maintained all the time. All the signs install prior to
start the job.
Site Supervisor will conduct daily toolbox meetings and explain the
requirements of the Client and other special needs to make and maintain a safe
working environment.
If there is any unsafe condition, Workers/ Equipment shall not be allowed to
enter the area.
Hard barricades and lightings shall be placed.
All activities will be carried out safely in accordance with Contractor’s HS plan
approved by the Client.
Contractor shall provide fire extinguishers (if necessary) for all fuel operating
site equipment.
Ensure housekeeping is carried out every day before work begins or complete.
Excavation greater than 2.4 meter (8 ft.) deep in type B or C soil, an excavation
plan (e.g., shoring design calculation and drawings) that meets the
requirements of this chapter shall be developed by a degreed civil/ structural
engineer.
Excavations greater than 6 meter (20 ft) deep, regardless of soil type, an
excavation plan (e.g., shoring design calculations and drawings) that meets the
requirements of this chapter shall be developed by a degreed civil/ structural
engineer and reviewed by the SA Consulting Services Department (CSD).