Professional Documents
Culture Documents
W1 & W2 - Lesson 1 Introduction - MODULE
W1 & W2 - Lesson 1 Introduction - MODULE
W1 & W2 - Lesson 1 Introduction - MODULE
Engineering Economy
Interest and Money Time Relationship
This module deals with complex numbers, its forms and the operations
that can be performed on complex numbers.
Illustrative Examples:
1. An electrical contractor has a job which should be completed in 100 days.
At present, he has 80 men on the job and it is estimated that they will
finish the work in 130 days. If of the 80 men, 50 are paid P190 a day, 25
at P220 a day, and 5 at P300 a day and if for each day beyond the original
100 days, the contractor has to pay P2, 000 liquidated damages:
Solution:
(a) Let x = number of men to be added to complete the job on time
Equating man-days, we have
(x + 80)(100) = (80) (130)
X = 24 men
(b) With 80 men on the job and liquidated damages:
Wages: (50) (190) (130) = P1, 235, 000
3
Engineering Economy
Interest and Money Time Relationship
2. The monthly demand for ice cans being manufactured by Mr. Cruz is 3,
200 pieces. With a manually operated guillotine, the unit cutting cost is
P25.00. An electrically operated hydraulic guillotine was offered to Mr.
Cruz at a price of P275, 000 and which will cut by 30% the unit cutting
cost. Disregarding the cost of money, how many months will Mr. Cruz be
able to recover the cost of the machine if he decides to buy now?
Solution:
Manually Operated Guillotine
Monthly cutting cost = (3, 200) (P25)
= P80, 000
Electrically Operated Hydraulic Guillotine
Monthly cutting cost = (3, 200) (P25) (1 – 0.30)
= P56, 000
Savings = P80, 000 – P56, 000
= P24, 000 per month
𝑃275,000
No. of months to recover cost of machine = 𝑃24,000
No. of months to recover cost of machine = 11.5 months
(a) If all other costs are assumed equal, what is the total costs for each
machine for 6, 000 holes, assuming the total cost of each machine to
be charged to these holes?
Solution:
(a) Drill Press:
6,000
Time to drill 6, 000 holes = 30 = 200 hours
Wage of machinist = (P35) (200) = P7, 000
Cost of drill press = P30, 000
Total cost P37, 000
4. The volume of the raw material required for a certain machine part is
2.02 cu. Cm. The finished volume is 1.05 cu cm. the time for machining
each piece is 45 seconds for steel and 30 seconds for brass. The cost of
steel is P32.50 per kg and the value of steel scrap is negligible. The cost
of the brass is 60. 00 per kg and the value of brass scrap is P25.00 per kg.
The wage of the operator is P40.00 per hour and the overhead cost of the
machine is P50.00 per hour. The weight of steel and brass are 0.0081 and
0.0088 kg per cu cm, respectively. Which material will you recommend?
Solution:
Steel:
Weight per piece = (2.02) (0.0081) = 0.01636 kg
Cost per piece:
Material = (0.01636) (32.50) = P0.5317
45
Wage of operator = (3,600) (P40.00) = 0.5000
45
Overhead = (3,600) (P50.00) = 0.6250
Brass:
Weight per piece = (2.02) (0.0088) = 0.01778 kg
Cost per piece:
Material = (0.01778) (P60.00) = P1.668
30
Wage of operator = (3,600) (P40.00) = 0.3333
30
Overhead = (3,600) (P50.00) = 0.4167
P1.8168
Less cost of scrap = (2.02 – 1.05) (0.0088) (P25.00) = 0.2134
Total cost P1.6034
Use steel.
5. High carbon steel or alloy steel can be used for the set of tools on a table.
The tools must be sharpened periodically. Data for each are as follows:
High carbon steel Alloy steel
Output per hour 60 pcs 70 pcs
Time between tool grinds 4 hours 6 hours
Time required to change tools 1 hour 1 hour
The wage of the lathe operator is P50.00 per hour, based on actual
working hours. The tool changer costs P60.00 per hour. Overhead costs for the
lathe are P45.00 per hour, including tool-change time. A set of unsharpened high
carbon steel costs P500 and can be ground ten times; a set of unsharpened alloy
steel costs P850 and can be ground five times. Which type of steel should be
used?
Solution:
High carbon steel:
Cycle time = 4 + 1 = 5 hours
Number of pieces per cycle = (4) (60) = 240
Cost per cycle:
Operator = P50 (4) ` = P200
Tool changer = (P60) (1) = 60
Overhead = (P45) (5) = 225
6
Engineering Economy
Interest and Money Time Relationship
𝑃500
Unsharpened tool = = 50
10
Total P535
𝑃535
Cost per piece = = 𝑷𝟐. 𝟐𝟑
240
Alloy steel:
Cycle time = 6 + 1 + 7 hours
Number of pieces per cycle = (6) (70) = 420
Cost per cycle:
Operator = P50 (6) = P300
Tool changer = (P60) (1) = 60
Overhead = (P45) (7) = 315
𝑃850
Unsharpened tool = = 170
5
Total P845
𝑃845
Cost per piece = 420