Professional Documents
Culture Documents
Project Plan Project Reporting
Project Plan Project Reporting
Project Plan Project Reporting
Submitted by:
Monsalud, Ma. Teresa
Piliin, Ericka Mae
Presillas, Alexandra Shawn
Ribon, Charlotte
Rivera, Valerie Joy
Submitted to:
Prof. Louvelle Formentera
It provides a shared vision for what the project will accomplish – this common
understanding can bind the team together in completing actions that satisfy the
project’s goals.
It gives clarity on the responsibilities of team members and other organizations in
contributing to the goals of the project.
It organizes the work of the project and can be used to prevent extraneous work
from crowding out legitimate project activities.
It can be a very powerful communication mechanism, supplementing verbal
interactions. This is an important written reference for the team, and can also be
used with other stakeholders.
OPTIONAL PARTS
There are no generically defined “optional parts”
Certain parts of project plan may be simplified depending on project size, scope,
requirements for project resources and scheduling risk.
Good discipline to include the part but have only limited statements; this confirms
that you have assessed the requirements for the plan component.
Examples:
1. Risk Management Plan can be simplified if the project classed as “low risk” i.e., long
schedule, small scope, 3 to 6-month project, available resources for construction,
testing and implementation, good support for client, single-unit client organization
(client is controlled by one manager)
2. Quality Plan is always required but can be simplified
3. Communication Plan is required- even though the Project Manager may be the same
as the communications lead
4. Test Plan is always required but can be simplified
5. Activity Plan is always required but can be simplified
6. Resource Plan can be simplified if the resources requirements are limited (2 man
effort), skill required is commonly available internally or from existing service providers,
equipment/ facilities are available.
Additional
1. Executive Summary – the executive summary captures the essence of the report.
It summarizes everything without focusing specifically on any one part. That is, it
includes the background, analysis, and conclusions.
2. Introduction – the introduction serves to tell them what you’re going to say in the
future (the body). Introductions are the part of the report that generates interest in the
report and makes the reader want to read it. A strong introduction has the following 5
parts:
3. Main Body – The main body is where the contents and essence of the report are
told. These five components of a project report should be present, in this order:
c. Analysis of Options
Conservative Measures
Possible Approaches
1. “Task-Binary” Measure
-This is done by marking a completed task 100%, and ongoing or unfinished task
0%.
- It is easy judgment whether task is done or not versus subjective “% done”.
2. “Time to completion”
- Project Manager is asked to estimate the time needed to complete project tasks.
Project Manager needed to completion:
Essentially a “re-forecast” of effort required given all factors (resource skill,
availability of inputs, effectiveness of tools, quality of work)
Conservative because most PMs will add a buffer
Stringent and good measure if the project manager is highly experienced and
professional
RISK SECTION
Common Internal Business Risks
Stability - The ability of a business to manage its finances; meet its debt
obligations and return capital to its investors is integral to its success. A business
which is financially stable can grow its profits more easily than one which is not;
furthermore, investors, lenders and employees are more willing to engage with
and invest in a financially stable company. The reverse is true for businesses
which are unstable; instability can quickly lead to decreasing profits and,
ultimately, bankruptcy.
When putting together the project report, you have to identify specific mitigation
action for each risk identified. This will allow the project stakeholders to assess if the
mitigations are correct or sufficient.
https://www.pinnacleprojects.com/index.php/the-project-plan-sp-
1739577267/109-the-importance-of-a-project-plan
https://www.thebalancecareers.com/what-needs-to-be-in-a-project-plan-1669741
Project Report: Meaning: Contents of a Project Report. (2017, April 3). Retrieved from
https://accountlearning.com/project-report-meaning-contents-project-report/.
(n.d.). Retrieved from https://www.projectengineer.net/the-4-vital-parts-of-
a- project-report/.