KPTCL for Line Clear proposal for the month of September -2022

Duration of LC request

Name of the Name of the KPTCL Name of the BESCOM Name of the BESCOM Date on which last
Sl no
KPTCL Circle Division Circle Division
Sub Division Name of the station/Line Feeder Date Time Reason for availing LC
LC was approved
Areas Affected Load Affected (MW) Wheather alteranate Power Supply Arranged or not Remarks Consent

From To From To Duration

Nagasandra, Kantahalli, Hulivana, Jiddigere, Gunnagare, Hosuru,


1 Tumkur K.B Cross Tumkur K.B Cross 66/11KV MUSS Jiddigere 9/2/2022 9/2/2022 10:00 16:00 6:00 Quarterly Maintenance
Shettibeedu, Bommadiagere,

stringing of conductor between Loc. No. 02 & 03 required for


2 BRAZ Ramanagar Kanakapura 66/11kV Achalu S/s, F-4, industrial feeder, 9/4/2022 9/4/2022 10:00 16:00 6:00 the work of SC line on DC towers from existing T.K Halli to
Kanakapura line-2 to proposed 66/11kV Shivanhalli S/s

F-14, Urban feeder, stringing of conductor between Loc. No. 02 & 03 required for
66/11kV Kanakapura
3 BRAZ Ramanagar Kanakapura F-5, IP feeder, 9/4/2022 9/4/2022 10:00 16:00 6:00 the work of SC line on DC towers from existing T.K Halli to
S/s
F-16 NJY Kanakapura line-2 to proposed 66/11kV Shivanhalli S/s

Construction of 220kV DC line from 400kV HM Hole to


66kV Chitradurga- 220kV SRS Chitradurga.For erection of MCMV towers in the
Chitradurga Major Chitradurga Major Chitradurga Urban All Feeders from the said All areas coming under the 66kV Chitradurga- Turuvanur line
4 Davanagere Davanagere Turuvanur line @ 220kV 9/5/2022 9/30/2022 10:00 16:00 6:00 existing corridor.
Works Division Works Division and Rural MUSS from the 220KV SRS Chitradurga.
SRS Chitradurga (Loc:29/1,31/2, 32/4,32/5,32/6, 30/0)
Construction of 66kV DC line from Bagur tap point to Loc.
No. 169 of 66 kV Ramagiri-Hosadurga line Near Ramagiri
HSD
Chitradurga Major Chitradurga Major Hosadurga & 66kV Line From Ramagiri .All Feeders from the sub-station in the existing corridor of 66 kV Ramagiri-
5 Davanagere Davanagere 9/5/2022 9/5/2022 11:00 16:00 5:00 Exp,Illapura,Bagur,Hebballi,Sanihalli,Srirangapura,Anival,HSD 8.6
Works Division Works Division Holalkere - Hosadurga – Baguru. Baguru MUSS Hosadurga SC line for a distance of 16.183 kms in
RURAL and the surrounding areas.
Chitradurga District.To remove existing old towers btwn Loc
9 to 11 in pond area.

110/11KV MUSS
6 Tumkur K.B cross Tumkur K.B cross 9/5/2022 9/5/2022 10:00 16:00 6:00 Quarterly Maintenance Kadehalli, Dabbeghatta,Mavinkere, Gonitumkur, karadigere
Kadehalli
Construction of 66 kV SC Line on DC towers by using coyote
ACSR conductor from 220 KV SRS Davanagere to four pole
structure Chitradurga in the existing corridor of 66KV
7 Saraswathi Nagar 9/5/2022 9/5/2022 10:00 16:00 6:00 Davangere -Chithragurga SC Line-1 for adistance of 55.697 9/1/2022 Daba stop to Jayanagara Church back side,(Loc 4-8).
Davangere Davangere Davangere Davangere 66/11kV SRS
Kms in Davanagere/Chitradurga District and Buy back of
66kV Somanahalli- released materials on Total Turnkey Basis—Availing Line
Subramanyapura line 2 For
clearcarrying out periodical maintenance works as per
bay [66/11kV maintenance schedule for 2nd quarter. Load of 66/11kV
No load will be
8 BMAZ South Somanahally BMAZ[S] Kengeri, HSR Kaggalipura, 66/11kV 9/6/2022 9/6/2022 10:00 15:00 5:00 Kaggalipura, 66/11kV Shobha Forest view will be changed No load will be affected. No load will be affected.
affected.
Shobha Forest View] at over to 220kV Subramanyapura station. No load will be
220/66/11kV R/S, affected. Consent given for availing the LC on 06.09.2022
Somanahalli, Bengaluru.
66/11kv harihara-new,
9 Davanagere Davanagere Davanagere Davanagere Harihara 220kV SRS Davanagere 9/6/2022 9/6/2022 10:00 14:00 4:00 2nd Quarter maintenance 10
harihara-hospate Muss

Harihar-Hospet MUSS,
66/11kv harihara-new, Harihar-Hospet MUSS, Harihar city MUSS, 66kV Guttur MUSS &
10 Davanagere Davanagere Davanagere Davanagere Davangere Harihar city MUSS, 66kV 9/6/2022 9/6/2022 10:00 14:00 4:00 2nd Quarter maintenance 18.26
harihara-hospate Line Polyfibers
Guttur MUSS & Polyfibers Sannapapainahatti, Bhadrappana Thopu, Netranahally,
Marammanahally, Nerlahally, Sunkadarahatti, Kuntobainahatti,
Kappad Bande Hatti, Yenimegalahatti, Kengobainahatti,
Bosaiahnahatti, Jungli Surainahattikonasagara, Udevu,
11 Davanagere Hiriyuru Davanagere Hiriyuru Molakalmuru Konasagara_66 All Feeders 9/6/2022 9/6/2022 10:00 16:00 6:00 1&2nd quarterly maintenance work. 3.8
Kumbara Kaple, Chowdipura, Bhadrappana Thopu,
Netranahally, Sannapapainahatti, Nerlahally, Kuntobainahatti,
Odnobaianahatttichowdipura, Kumbara Kaple, Patri Male Kaple,
Ballaji Kaplekonasagara, Udevu
66/11KV MUSS Chowdanakuppe, Chikkonahalli, Akkimaripalya, R.Byadrahalli,
12 Tumkur K.B Cross Tumkur K.B Cross 9/6/2022 9/6/2022 10:00 16:00 6:00 Quarterly Maintenance
Chowdankuppe Hangarahalli, Ankanahalli, Neelasandra, Tavarekere, M.H Palya

Hunaseghatta,jayapura, Kamparahalli, J Mallenahalli,


110/11KV MUSS
13 Tumkur K.B Cross Tumkur K.B Cross 9/6/2022 9/6/2022 10:00 16:00 6:00 Quarterly Maintenance Virupakshipura,Sasaluhalli,ganganaghatta,Sooguru, M
Hunseghtta
Gollarahatti, Kannughatta,Masavaghatta,
For carrying out periodical maintenance works as per
66/11kV, 12.5MVA Power maintenance schedule for 2nd quarter. Load on the Power
Transformer-1 & 2 at Transformer-1 can be taken over Power Transformer-2
No load will be
14 BMAZ South Somanahally BMAZ[S] Kengeri 66/11kV Sub-station, 9/7/2022 9/7/2022 10:00 15:00 5:00 through 11kV Bus coupler. No load will be affected. No load will be affected.
affected.
Kaggalipura [Brigade Load on the Power Transformer-2 can be taken over Power
Meadows] Transformer-1 through 11kV Bus coupler. No load will be Consent given for availing the LC on 7.09.2022(
affected.
RR Nagara Division, 66/11 kV Chandralayout Consent given Peak load of the station is 26
15 BMAZ North NRS West 9/7/2022 9/7/2022 10:00 15:00 5:00 Quarterly maintenance 12/18/2021 Areas feeding from 66/11kV Chandra layout S/s 15 Load changeover will be done by BESCOM
Rajajinagara MUSS MW, 14 MW load change over will be done by
BESCOM authority & about 7 MW load will be
affected during LC period

Mellekatte, Rudranakatte, Kandanakovi, Mallapura, Anaji and


16 Davanagere Davanagere Davanagere Davanagere Anagodu Mellekatte 66/11kV All 11kV feeders 9/7/2022 9/7/2022 10:00 16:00 6:00 2nd Quarter maintenance 7
surrounding villages

CSD 1, CSD2 and


17 Davanagere Davanagere Davanagere Davanagere yaragunta 66/11kv all 11kv feeders 9/7/2022 9/7/2022 10:00 16:00 6:00 2nd Quarter maintenance 10
RSD Davangere

CSD 1, CSD2 and 66/11kv Davangere,


18 Davanagere Davanagere Davanagere Davanagere 220kV SRS Davanagere 9/7/2022 9/7/2022 10:00 14:00 4:00 2nd Quarter maintenance 66/11kv Davangere, yaragunta Muss 16
RSD Davangere yaragunta Muss

Construction of 66kV DC line from Bagur tap point to Loc.


No. 169 of 66 kV Ramagiri-Hosadurga line Near Ramagiri
HSD
Chitradurga Major Chitradurga Major Hosadurga & 66kV Line From Ramagiri .All Feeders from the sub-station in the existing corridor of 66 kV Ramagiri-
19 Davanagere Davanagere 9/7/2022 9/7/2022 11:00 16:00 5:00 Exp,Illapura,Bagur,Hebballi,Sanihalli,Srirangapura,Anival,HSD 8.6
Works Division Works Division Holalkere - Hosadurga – Baguru. Baguru MUSS Hosadurga SC line for a distance of 16.183 kms in
RURAL and the surrounding areas.
Chitradurga District.To remove existing old towers btwn Loc
9 to 11 in pond
Construction of area.
66kV DC line from Bagur tap point to link
66kV Mathod-Panchanahalli line near Kerehalli village limits in
Chitradurga Major Chitradurga Major All Feeders from the NEERAGUNDA,ADRIKATTE,SRI MATA,ALADAHALLI AND
20 Davanagere Davanagere Hosadurga Madhure(Hosadurga) to 9/7/2022 9/7/2022 10:00 16:00 6:00 the existing corridor of 66 kV Mathod-Hosadurga-Ramagiri 4.63
Works Division Works Division Neergunda MUSS SURROUNDING AREAS
Neeragunda Line. SC line for a distance of 24.696 kms in Chitradurga
District.For stringing work btwn Loc No:6 to 10

Huliyar Town, Tammadihalli, Kenkere,Yalanadu,keshavapura,


21 Tumkur K.B Cross Tumkur K.B Cross 110/11KV MUSS Huliyar 9/7/2022 9/7/2022 10:00 14:00 4:00 For replacement 110KV CT koragere, Somanahalli, Nandihalli, Sigebagi, Lakshmipura,
Doddabidare,Avalagere,Ballekatte, Singapura, rangapura,belaguli

Establishing 2X100MVA, 220/66/11KV Station at Sira and


No area will be affected (alternate power supply source available
construction of 220KV Double LILO on MC Towers, 66KV
22 Tumkur Tumkur Tumkur Tumkur 66KV Sira-P.N Halli Line 9/7/2022 9/23/2022 10:00 16:00 6:00 66/11KV P.N.Halli Sub Station and 66/11KV C.B.Gere Sub
Line on MC/DC/SC Towers, stringing on 66KV DC Towers,
Station fro m Hiriyuru 220/66KV R/s
Construction of 1No. TB & Dismantling works.

Ramanagara 66/11kV Honniganahalli


23 Kanakapura Ramanagara Kanakapura 9/8/2022 9/8/2022 10:00 15:00 5:00 Quaterly maintenance work 11/12/2021 Honniganahalli, Acchalu, Sathnur Town & sorrounding villages 14 NO Quaterly maintenance work
Circle & Acchalu S/s
Consent is given to avail LC on 08.09.2022.
Construction of 66kV DC line from proposed 220 kV Duration as 10:00 TO 15:00 hours.
Hosadurga Station to link existing 66 kV
220KV Hosadurga to Vedavathi Water works,Kappagere, Koratigere, Siddaramanagara ,
Halurameshwara-Mathod SC line near Honnenahalli limits
Chitradurga Major Chitradurga Major Halurameshwara Tap All Feeders from the Kanguvalli, Kellodu, Rangavvanahalli , Peelapura, Devigere,
24 Davanagere Davanagere Hosadurga 9/8/2022 9/8/2022 11:00 16:00 5:00 for a distance of 8.553 kms in Chitradurga District.For 8.5
Works Division Works Division Point to 66KV Hosadurga Hosadurga MUSS Kobbaripete UrbanB.V.NagaraMavinkatteAttighatta and
Opening of jumps at Halurameshwara Tap Point.
Line. surrounding areas
For Power supply Re-arrangement to 66/11kVHosadurga.
V.V.Pura, Rangavanahally, Bharamsagar Lambanihatti V.Vpura,
Karikere, Rangavanahally, Bharamsagar Lambanihatti, Durgavara,
25 Davanagere Hiriyuru Davanagere Hiriyuru Challakere Vishweshwarapura_66 All Feeders 9/8/2022 9/8/2022 10:00 16:00 6:00 1&2nd quarterly maintenance work. 5
Kerehindlahatty Doddaullarthi Yadalaghatta, Kaluvehalli,
Construction of 66 kV SC Line on DC towers by using coyote Kyathagondanahalli, Gowdarahatti, Janammanahlli
ACSR conductor from 220 KV SRS Davanagere to four pole Concurrence given Sadashivanagara Change
structure Chitradurga in the existing corridor of 66KV over from IISc F-11 feeder and RMV F- 6
26 Saraswathi Nagar 9/8/2022 9/8/2022 10:00 16:00 6:00 Davangere -Chithragurga SC Line-1 for adistance of 55.697 9/1/2022 Daba stop to Jayanagara Church back side,(Loc 4-8). feeder
Davangere Davangere Davangere Davangere 66/11kV SRS F-2 Dhobighat Change over from IISc F-4
Kms in Davanagere/Chitradurga District and Buy back of feeder and Hebbal F- 19 feeder
released materials on Total Turnkey Basis—Availing Line F-1 Sadshivnagar
The LC on Bank-1 and related feeders required F-3 SSLC Board Change over from IISc F-4
clear F-2 Dhobighat
from 09.09.2022 @11:00 Hrs to 12.09.2022 feeder, C Station F-18 and Brigade F- 4 feeder
Replacement existing 11kV SIEMENS make Bank-1 F-3 SSLC Board F-7 Mysore Lamps Change over from Nandini
Malleswaram(C2,C6 Alternate supply will be arranged by BESCOM O&M staff for @22:00 Hrs and For disconnecting Bus F-4 feeder, Brigade F7 and IISc F7 feeder
27 BMAZ NORTH SRS Peenya North 66/11kV IISC MUSS 9/9/2022 9/12/2022 11:00 22:00 11:00 switchgears by new 11kV MEI make switchgears at _ F-7 Mysore Lamps _
Sub division) the feeders which have change overs from other stations coupler from Bank-1 and Bank-2 entire station F-5 Sri Ganesha Temple Change over from
66/11kV IISc MUSS, RMSD, SRS Peenya. Bangalore. F-5 Sri Ganesha Feeder RMV F-1 feeder, 'A' Station F9
load will be affected for Three Hours on
10.09.2022
Channasamudra,Kappagere,Koratigere,Madhure,Kanguvahalli,Kell
66/11 kV MUSS All Feeders from the said
28 Davanagere Chitradurga 220 SRS Davanagere Chitradurga 220 SRS Holalkere 9/9/2022 9/9/2022 10:00 16:00 6:00 Quarterly maintenance work odu,Hagalagere,Rangavalli,Pilapura,Devigere,Vedavathi,B V 6
Hosadurga MUSS
Nagara, Mavinakatte palya, Attighatta and the surrounding areas.

All Feeders from the said


29 Davanagere Chitradurga 220 SRS Davanagere Chitradurga 220 SRS Hosadurga 220 kV MUSS MADURE 9/9/2022 9/9/2022 10:00 16:00 6:00 Half Yearly maintenance work Madhure Station Limits 6.6
MUSS

Sanikere, Vijayapura Gate, Gopanahally, Kammathmarikunte,


30 Davanagere Hiriyuru Davanagere Hiriyuru Challakere Sanikere_66 All Feeders 9/9/2022 9/9/2022 10:00 16:00 6:00 1&2nd quarterly maintenance work. Ganjigunte, Hottappanahally, Hottappanahally Gollarhatti, 7
Somaguddu, Chikkenahally, Kurumaradi, Malligere, Jammankaple

110/11KV MUSS AM Kavalu,Halenahalli,Ghatanikere, Chowlihalli,muddenahalli,


31 Tumkur K.B Cross Tumkur K.B Cross 9/9/2022 9/9/2022 10:00 16:00 6:00 Quarterly Maintenance
Halukurke Halukurke,Kodigehalli,
Duration of LC request

Name of the Name of the KPTCL Name of the BESCOM Name of the BESCOM Date on which last
Sl no
KPTCL Circle Division Circle Division
Sub Division Name of the station/Line Feeder Date Time Reason for availing LC
LC was approved
Areas Affected Load Affected (MW) Wheather alteranate Power Supply Arranged or not Remarks Consent

From To From To Duration

Alternate supply to 11 kV feeders can be


32 BRAZ BIAL Begur BRC Hoskote 66/11 kV Pillagupa 9/10/2022 9/12/2022 10:00 15:00 5:00 11 kV Breaker replacemnet work Pillagumpa and surrounding areas 28MW No arranges if any possible from BESCOM side
only Consent is given to avail LC on 10.09.2022 to
11.09.2022. Duration as 10:00 TO 15:00 hours.

F5 Mauneshwara, F6
CSD 1, CSD2 DCM, F7 G&S, F8 KTJ, F9 Iron pole Structure replacement work in 11kV Bank-2 & F5 Mauneshwara, F6 DCM, F7 G&S, F8 KTJ, F9 PJ, F10 CGH, F11
33 Davanagere Davanagere Davanagere Davanagere 66kV MUSS Davanagere 9/10/2022 9/10/2022 10:00 16:00 6:00 7
Davangere PJ, F10 CGH, F11 LF11, Bank-3 & providing released good breakers in 11kV Bank-3 LF11, F12 basaveshwara
F12 basaveshwara

Construction of 220kV DC line from 400kV HM Hole to


Chitradurga Major Chitradurga Major 220kV Guttur- 220kV Guttur-
34 Davanagere Davanagere Chitradurga Urban 9/10/2022 9/16/2022 10:00 16:00 6:00 220kV SRS Chitradurga.For Erection of 220kV DC towers in All areas coming under the 220kV Guttur-Chitradurga line
Works Division Works Division Chitradurga line Chitradurga line
the existing corridor (Loc:4/0,11/0)

F1-CIPSA,F2-Honnenahalli,F3-Haraluru,F5-Industrial,F6-KM
halli,F7-Carmobiles,F8-Hirehalli,F9-Maranayakanapalya,F10-
35 Tumkur Tumkur Tumkur Tumkur 66/11kV S/S Hirehalli 9/10/2022 9/11/2022 10:00 16:00 6:00 DP replacement work
Siddaganga mataF11-Raitharapalya,F12 Nandihalli NJY,F14
Ranevalves

66/11kV S/S Jigani,( Jigani surrounding area, Haragadde,


Ramanagara To carry out Quarterly maintenance and OLTC overhauling
36 Yerrandanahalli Ramanagara Chandapura 66/11kV S/S Jigani 9/11/2022 9/11/2022 10:00 15:00 5:00 5/28/2022 Madapattana, Gollahalli, Nandnavana layout, Bukkasagara, 22 NO
Circle of TR-1 Consent is given to avail LC on 11.09.2022,
Kallabalu. Ashrama Road). Duration for LC Approved from 10:00 to 15:00
hours (5 Hours)

Ramanagara For station maintenance works, Overhauling of 66kV 66kV Attibele Line, 66kV Samandur line, Areas feeding from No, but only Attibele S/S can switch over load from Anekal
37 Yerrandanahalli Ramanagara Chandapura 66/11kV Anekal 9/11/2022 9/11/2022 10:00 15:00 5:00 5/31/2022 38 MW
Circle isolators and other scheduled works at 66/11kV S/s Anekal Anekal S/S such as Anekal Town and its surrounding rural areas S/S to 220 kV Sarjapura Consent is given to avail LC on 11.09.2022,
Instead of 12.09.2022,,Duration for LC
Approved from 10:00 to 15:00 hours (5 Hours)

For station maintenance works, Tan Delta test of power


66kV Bagganadoddi line, Areas feeding from Kumbaranahalli S/S
Ramanagara transformers and other scheduled works at 66/11kV S/s
38 Yerrandanahalli Ramanagara Chandapura 66/11 kV Kumbaranahalli 9/11/2022 9/11/2022 10:00 15:00 5:00 5/31/2022 such as Haragadde, Kumbaranahalli, Jigani and its surrounding 15 MW No
Circle Kumbaranahalli Consent is given to avail LC on
areas. 11.09.2022,Duration for LC Approved from
10:00 to 15:00 hours (5 Hours)

For station maintenance works, Replacement of 11kV Bank


Ramanagara CT's and other scheduled works at at 66/11kV S/S Areas feeding from Bagganadoddi S/S such as Indlawadi,
39 Yerrandanahalli Ramanagara Chandapura 66/11 kV Bagganadoddi 9/11/2022 9/11/2022 10:00 15:00 5:00 5/31/2022 3 MW No
Circle Bagganadoddi Bagganadoddi, Kadujakkanahalli and its surrounding areas Consent is given to avail LC on
11.09.2022,Duration for LC Approved from
10:00 to 15:00 hours (5 Hours)

66/11kV S/S Jigani, 66/11kV S/S Kumbarana halli, 66/11kV


1)To carry out 2ND Quarterly maintenance at
Ramanagara S/S Bagganadoddi, and areas industries, Nisarga,Harpanahalli,
40 Yerrandanahalli Ramanagara Chandapura 220/66/11kV R/S Jigani 9/11/2022 9/11/2022 10:00 15:00 5:00 220/66/11kV R/s Jigani. 5/28/2022 45 NO
Circle Koppagate,Kalbalu,H.manchanahalli feeding from 220/66/11kv Consent is given to avail LC on
2)For attending Hot line obseravation. 11.09.2022,Duration for LC Approved from
R/s Jigani.
10:00 to 15:00 hours (5 Hours)

F5 Mauneshwara, F6
CSD 1, CSD2 DCM, F7 G&S, F8 KTJ, F9 Iron pole Structure replacement work in 11kV Bank-2 & F5 Mauneshwara, F6 DCM, F7 G&S, F8 KTJ, F9 PJ, F10 CGH, F11
41 Davanagere Davanagere Davanagere Davanagere 66kV MUSS Davanagere 9/11/2022 9/11/2022 10:00 16:00 6:00 7
Davangere PJ, F10 CGH, F11 LF11, Bank-3 & providing released good breakers in 11kV Bank-3 LF11, F12 basaveshwara
F12 basaveshwara

F1-Kolala,F2-Mavathur,F3-Byragundlu,F4-Chikkadoddavadi,F5-
Saggere,F6-Pathaganahalli,F7-Urdigere,F8-Katenalli,F9-
42 Tumkur Tumkur Tumkur Tumkur 66/11kV S/S Kolala 9/11/2022 9/11/2022 10:00 16:00 6:00 Antharasanahalli incoming line breaker overhaling
Yelachagere,F10Hanumanthagiri,F11-Vajanakurke,F12-
Construction of 66 kV SC Line on DC towers by using coyote Doddasaggere,F13-Chinnahalli
ACSR conductor from 220 KV SRS Davanagere to four pole
structure Chitradurga in the existing corridor of 66KV
43 Saraswathi Nagar 9/11/2022 9/11/2022 10:00 16:00 6:00 Davangere -Chithragurga SC Line-1 for adistance of 55.697 9/1/2022 Daba stop to Jayanagara Church back side,(Loc 4-8).
Davangere Davangere Davangere Davangere 66/11kV SRS
Kms in Davanagere/Chitradurga District and Buy back of
released materials on Total Turnkey Basis—Availing Line
clear
220 kV Guttur-Davangere- 220 kV Guttur-Davangere-
44 Davanagere Davangere Davanagere Davangere Davangere 1 Line, 66 kV Harihar- 1 Line, 66 kV Harihar- 9/12/2022 9/12/2022 10:00 16:00 6:00 NHAI Work - 16
Hospet & 66 kV Industrial Hospet & 66 kV Industrial

Chikkanakatte,Hirekandavadi,Gunjiganuru,B.Durga,Filter
66/11 kV MUSS All Feeders from the said
45 Davanagere Chitradurga 220 SRS Davanagere Chitradurga 220 SRS Holalkere 9/12/2022 9/12/2022 10:00 16:00 6:00 Quarterly maintenance work House,Kadur,Kotehal,Chikkandavadi,Chikkajajuru,Hireemmiganu 5.96
Chikkajuru MUSS
ru ,Arasanagatta ,K N Halli and surrounding areas.

Gyarhalli,T.B.Nagara,Muttugaduru,Kalghatta,Udegere ,Sirigere
66/11 kV MUSS All Feeders from the said Water
46 Davanagere Chitradurga 220 SRS Davanagere Chitradurga 220 SRS Holalkere 9/12/2022 9/12/2022 10:00 16:00 6:00 Quarterly maintenance work 5.43
Sasaluhalla MUSS works,Andanur,Dandiganahalli,Hireemmiganuru,Toppenahalli and
surrounding areas.
Neralagunte, Battaiahnahatti, Nayakanakere,
Yarmanchiahanahatti, Yarmanchenahatti, Katavvanahalli,
Karthikenahatti, Nerlagunte Kurabarahatti, Nerlagunte ,
47 Davanagere Hiriyuru Davanagere Hiriyuru Thallak Neralagunte_66 All Feeders 9/12/2022 9/12/2022 10:00 16:00 6:00 1&2nd quarterly maintenance work. 6
Battaiahnahatti Hosahalli, Marenahatti, N.Devarahalli,
Bheemanakerehosahalli, Marenahatti, N.Devarahalli,
Chowluru, Chikkachallur,
Bheemanakere, Oblapura,
Katavvanahalli, T.N.Kote, Melukote,
Karthikenahatti
Obanahalli. Doddchalluru, Doddagollarahatti, Hullikatte,
Chowluru Gate, Vishvanatha Pura, Choluru, Allapura, , T.N.Kote,
48 Davanagere Hiriyuru Davanagere Hiriyuru Challakere PR Pura_66 All Feeders 9/12/2022 9/12/2022 10:00 16:00 6:00 1&2nd quarterly maintenance work. 12
Oblapura, Chikkachallur, Obanahlli, Doddabeeranahalli,
Doddachallur

Ramanagara 100 MVA Transformer -2 Alternate power supply can be arranged through bus
49 TKHalli Ramanagara Ramanagara 9/13/2022 9/13/2022 10:00 15:00 5:00 Quarterly maintenance work 6/25/2022 No load effected
Circle at 220 kV R/S T K Halli coupler Consent is given to avail LC on 13.09.2022,
Duration for LC Approved from 10:00 to 15:00
hours (5 Hours)

Peak load-7MW,
2nd Quarterly/Half Yearly maintenance work of Incoming Devarabisanahalli,Adarsha,Sai Shrustii,Sterling Ascentia,Samvi J
HSR Layout & 66/11kV Global Tech Park Load change over-
50 BMAZ South HSR Layout South 9/13/2022 9/13/2022 10:00 14:00 4:00 Line, Power Transformers, 66kV PT, 66kV Main BUS, 66kV 2/24/2022 V Hotel Load Changeover-3MW
Koramangala S/s 3MW,
Breakers and Maintenance of 11kV Breakers
Load affected-4MW
Consent given for availing the LC on 13.09.2022
For carrying out periodical maintenance works as per
220kV Somanahalli-
maintenance schedule for 2nd quarter. Load of 220kV
BWSSB Tataguni line bay No load will be
51 BMAZ South Somanahally BMAZ[S] Kengeri 9/13/2022 9/13/2022 10:00 15:00 5:00 BWSSB Tataguni station may be fed from 220kV No load will be affected. No load will be affected.
at 220/66/11kV R/S, affected.
Vrushabhavathi through PGCIL Bidadi - Kumabalagodu Tuppadakkanahalli, Iynahalli, Matadajogihally, Siddainakote,
Somanahalli, Bengaluru.
station. No load will be affected. Kombehalli(G), Yarapothajogihalli, Gowdrahatti, Kampal Consent given for availing the LC on 13.09.2022
Devarahatti(B.G.Kere)Yarrenahalli, Tumkurnahalli,
RR Nagar,Rajaji Adavimallapura, Odnobainahatti, Nerlahally, Akhatti,
66/11 kV Kengeri satellite Consent given Peak load of the station is 12
52 BMAZ North NRS East,West,South nagar,Kengeri,Jayanag 9/13/2022 9/13/2022 10:00 15:00 5:00 Quarterly maintenance 9/20/2021 Areas feeding from 66/11kV Kengeri Sateelite Town S/s 10 Load changeover will be done by BESCOM
Town station Kudligarahatti, Sunkadrarahatti, Belavina Maradahatti MW, 05 MW load change over will be done by
ar,Vidhanasoudha Odnobainahatti, Kuntobainahatti, Badasuraianahatti, Marlahalli, BESCOM authority & about 7 MW load will be
affected during LC period
Muddainahatti, Gollara Nagenahatti, Adavil Obaina Kaple,
Gundlururayapura, Myasarahatti, Maliyammanhatti,
Sulenahalli, Kakpalaiahnahatti, Gundluru, Somenahalli,
53 Davanagere Hiriyuru Davanagere Hiriyuru Hiriyuru Hiriyur_66 All Feeders 9/13/2022 9/13/2022 10:00 16:00 6:00 1&2nd quarterly maintenance work. 10
Marlahalli, Yarrenahalli, Siddainakote, Iynahalli,
For carrying out periodical maintenance works as per Matadajogihalli, Tuppadakkanahalli Tanda, Yarapothajogihali,
66/11kV, Kampaldevarahatti, Tumkurlahalli.Rayapura, Mysarahatti,
maintenance schedule for 2nd quarter. Load on the Power
20MVA,12.5MVA Power Maliyamanahatti, Somenahalli, Sulenahalli, Gundluruhangal,
Transformer-1 can be taken over Power Transformer-2
Transformer-1&2 at Somenahally, No load will be
54 BMAZ South Somanahally BMAZ[S] Kengeri 9/14/2022 9/14/2022 10:00 15:00 5:00 through 11kV Bus coupler. No load will be Molakalmuru
affected. Town, Eddulabommanahatti, No load will be affected.
220/66/11kV R/S, Byrapura, Guddadahalli, Huchangidurgahangal, affected.
Load on the Power Transformer-2 can be taken over Power
KPTCL, Somanahalli, Tuppadakkanhali, Bommalinganhalli, Kommanapatti, Rangaina
Transformer-1 through 11kV Bus coupler, consequently. No Consent given for availing the LC on 14.09.2022
Bengaluru. Durga Dammbyrapura, Guddadahalli, Huchangidurga, Jayanthi
load will be affected.
Nagara
55 Davanagere Davanagere Davanagere Davanagere RSD Davangere Obajjihalli 66/11kv All 11kV feeders 9/14/2022 9/14/2022 10:00 16:00 6:00 2nd Quarter maintenance Obajjihalli
66KV Lines:and surrounding area 9
1.Madhugiri
2.Pulamaghatta
3.Koratagere 1& 2
All 11 KV Feeders of 4.Sira 1 & 2
56 Davanagere Davanagere Davanagere Davanagere Benkikere Sowlanga 9/14/2022 9/14/2022 10:00 16:00 6:00 2nd Quarter maintenance All 11 KV Feeders
5.Koratagere 1& 2 of Savalanga Station 5
Savalanga Station\
6.Nitrahalli
Downstream stations,
1. Madhugiri
Bank-I and II 66kV
&
220/66/11KV R/S 2. Badavanahalli
F1- Arenahally 66KV
57 Tumkur Madhugiri Tumkur Madhugiri 9/14/2022 9/14/2022 10:00 16:00 6:00 Quarterly Maintenance
Madhugiri 3. Hosakere
F2- Town 66kV
4. Medigeshi 66kV
F3-Nirantara Jyothi
5. I D Halli 66kV
F4-Bhoothanahally
Bank-I
6. and II & 66kV
Kodigenahalli
F5-Chinakavajra
F1-Rangapura
66/11 kV MUSS 7. Nitrahalli
58 Tumkur Madhugiri Tumkur Madhugiri 9/14/2022 9/14/2022 10:00 16:00 6:00 Quarterly Maintenance F6- D.V.Hally66kV
F2-kavanadala
Madhugiri (OLD) 8. Puravara 66kV
F8- Kambathnahally
F3-sidadaragallu
9. Pulamatta
F9- Siddapura66kV
F7-Jayanagara
10. Holavanahalli (Agri)
66kV
F10-Dabeghatta
F8-J.V.N
11. 220kV palya
Madhugiri power Transformer &2
66/11 kV MUSS F11-Jadegondanahalli
F10-koonahalli
59 Tumkur Madhugirii Tumkur Madhugirii 9/14/2022 9/14/2022 10:00 16:00 6:00 Quarterly Maintenance Bank-I and II &
F12-Timlapura
Badavanahally F11-Badavanahalli (Town)
F1-Rantavalalu
F4-dodderi
F2-Kotagaralahalli
F5-karpenahalli
F3-Basavanahalli
F6 chandragiri
Bank-I and II &F1-CHIKKAVALLI
F4-Sajjemmanahalli
66/11 kV MUSS F9-banagarahalli
66KV Lines
F2-HOLAVANAHALLY
60 Tumkur Madhugiri Tumkur Madhugiri 9/14/2022 9/14/2022 10:00 16:00 6:00 Quarterly Maintenance F9-Badigondanahalli
Pulamaghatta F12-Poojarahalli
MADHUGIRI
F3-THAGARIGHATTA-1
F5-Shivanagere
MIDEGESHI
F4-HULIKUNTE
F6-Thonachagondanahalli
PAVAGADA
F7-Kittagali L-1
F9-Suvarnamukki (NJY)
PAVAGADA
F8-B Betta L-2
F11-Godrahalli(NJY)
66/11 kV MUSS
61 Tumkur Madhugiri Tumkur Madhugiri 9/14/2022 9/14/2022 10:00 16:00 6:00 Quarterly Maintenance NAGALAMADIKE
F12-Kemenahalli(NJY)
Holavanahalli Y N HOSAKOTE
F5-SOMPURA
SHYLAPURA
F6-KODALAHALLI
NAGALAMADIKE
F7-B.D.PURA -1
Bank-I
F8-H.V and
NAGALAMADIKE
PalyaII & -2
220/66/11 kV R/S
62 Tumkur Madhugiri Tumkur Madhugiri 9/14/2022 9/14/2022 10:00 16:00 6:00 Quarterly Maintenance F1-K.T. HALLY
Downstream
F10-B.D.Pura stations:
(NJY)
Pavagada F2- DEVALAKERE
1.Shylapura 66KV
F4-
2.Y NVADANAKAL
Hosakote 66KV
F5- C. H. PALYA 66KV
3.Nagalamadike
F6-KOTAGUDDA
4.Lingadahalli 66KV
66/11 kV MUSS
63 Tumkur Madhugiri Tumkur Madhugiri 9/14/2022 9/14/2022 10:00 16:00 6:00 Quarterly Maintenance F7- MARIDASANAHALLY
5.Mangalawada 66KV
Shylapura
F8- BUDIBETTA
6.Pavadgada 66kv
F9-BELLIBATLU
7.Venkatapura 66Kv
F10- B.HOSAHALLY
8.Theriyur 66KV
F11-
9.12.5YETTINAHALLY
MVA Tr -1 & 2
F12- GUJJANADU
Duration of LC request

Name of the Name of the KPTCL Name of the BESCOM Name of the BESCOM Date on which last
Sl no
KPTCL Circle Division Circle Division
Sub Division Name of the station/Line Feeder Date Time Reason for availing LC
LC was approved
Areas Affected Load Affected (MW) Wheather alteranate Power Supply Arranged or not Remarks Consent

Bank-I and II -
F6-HANUMANTHANAHALLY
F7- BHIMANAKUNTE
From To From To Duration
F8-HOSADURGA
F9- DODDAHALLY
Bank-I
F10-S.N.and II -
HALLY
F-1 Hussenpura NJY
F11-HOSADURGA
66/11 kV MUSS Y.N F-2 Kodamodagu
F1-THIPAGANAHALLY
64 Tumkur Madhugiri Tumkur Madhugiri 9/14/2022 9/14/2022 10:00 16:00 6:00 Quarterly Maintenance F-3
Hosakote F2- Water Supply
Y N HOSAKOTE
F-4
F3- S.R
G T Pura
HALLY
INTEROCEAN
F4- JALOD 3MW
PGP 1MW
F5- STATION AUXLARY
66/11 kV MUSS Bank-I
PVP
F12-1MW and II -
BHIMANAKUNTE NJY
65 Tumkur Madhugiri Tumkur Madhugiri 9/14/2022 9/14/2022 10:00 16:00 6:00 Quarterly Maintenance F1-k k
Nagalamadike F-5 H hally
F-17Hosahalli
V Stone crusher
F2-Harasikere
F-6 B.K Hally
F4
F-7Manglawada
THIRUMANI
Bank-I
F5-Marurand II -
F-9 Bhupur
66/11 kV MUSS F-4
F-10Bommathanahalli
F6-Kirarlahalli
Valluru
66 Tumkur Madhugiri Tumkur Madhugiri 9/14/2022 9/14/2022 10:00 16:00 6:00 Quarterly Maintenance F-5
Mangalawada F-11Neelammanahalli
F7-Kannamadi
Ryapte
F-6
F-12Chikkanayakanahalli
F8-Hanumasagara
kodamodugu
F-7
F9-CPalavalli
K pura
F-8
F10-Byrapura
NJY Arasikere
F-9 Byadnur
F11-Uddagatte
67 Tumkur Madhugiri Tumkur Madhugiri 66/11 kV MUSS Pavagada 9/14/2022 9/14/2022 10:00 16:00 6:00 Quarterly Maintenance
F-10 Buddareddyhalli
Bank-I and II -
F-11 Ponnasamudra
F1-Chandrabhavi
F-12 KHB Colony
F2-Reddyhalli
F-1 Pavagada
F3-Medigeshi
F-2 C.K.Pura
68 Tumkur Madhugiri Tumkur Madhugiri 66/11 kV MUSS Midigeshi 9/14/2022 9/14/2022 10:00 16:00 6:00 Quarterly Maintenance
F4-Mallanayaknahalli
F-3 Gangasagara
F5-Hanumanthpura(NJY)
F6-Laxmipura(NJY)

69 Tumkur Madhugiri Tumkur Madhugiri 66/11 kV MUSS Hosakere 9/14/2022 9/14/2022 10:00 16:00 6:00 Quarterly Maintenance Bank-I and II -Related feeders

70 Tumkur Madhugiri Tumkur Madhugiri 66/11 kV MUSS I D halli 9/14/2022 9/14/2022 10:00 16:00 6:00 Quarterly Maintenance Bank-I and II -Related feeders

66/11 kV MUSS
71 Tumkur Madhugiri Tumkur Madhugiri 9/14/2022 9/14/2022 10:00 16:00 6:00 Quarterly Maintenance Bank-I and II -Related feeders
Kodigenahalli
Construction of 66 kV SC Line on DC towers by using coyote
F1-Kolkunte IP ACSR conductor from 220 KV SRS Davanagere to four pole
structure Chitradurga in the existing corridor of 66KV
F2-Giriyapura IP Jayanagara Church to Shakthi Nagar over head water tank,(Loc-8-
72 66/11kV Avaragere S/s DCM IP
F3-Kaidal 9/14/2022 9/14/2022 10:00 16:00 6:00 Davangere -Chithragurga SC Line-1 for adistance of 55.697 9/1/2022
Davangere Davangere Davangere Davangere 12)
Kms in Davanagere/Chitradurga District and Buy back of
F4-Hadadi IP
F5-Kalbande NJY released materials on Total Turnkey Basis—Availing Line
F6-Kukkuwada IP clear Kolkunte,Giriyapura, Kaidal, Hadadi, Kalbande,
Kukkuwada F8-Lokikere IP Kukkuwada, Lokikere ,Kanagondanahalli
73 Davanagere Davanagere Davanagere Davanagere Davanagere 9/15/2022 9/15/2022 10:00 16:00 6:00 Half Yearly Maintenance Work 10
66/11 Kv F9-Kanagondanahalli IP Matti, Nagarasanahalli,Hoovinamadu
F10-Matti IP Kollenahalli,Balluru,Kalkere And Surrounding Villages.
F11-Nagarasanahalli IP
66/11kV NJY
F12-Hoovinamadu
Kukkuwada,Shyagale,
F13-Kollenahalli NJY 66/11 kv Kukkuwada,Shyagale, thyavangi, santhebennur ,
74 Davanagere Davangere Davanagere Davangere Kukkuwada 220kV SRS Davanagere 9/15/2022 9/15/2022 10:00 14:00 4:00 2nd quarter maintenance 35
thyavangi, santhebennur
F14-Balluru NJY , Basavapattana Muss
Basavapattana Muss
F15-Kalkere NJY

Harihara Town, Water


Supply, KHB Colony, Replacement of inspection chaimber & re-alignment of Harihara Town, Water Supply, KHB Colony, Industrial Area,
75 Davanagere Davanagere Davanagere Davanagere Guttur 66/11KV MUSS Guttur 9/15/2022 9/15/2022 10:00 16:00 6:00 NEERAGUNDA,ADRIKATTE,SRI 9
Industrial Area, Karlahalli, MCVCB Bus Bar 11kV Bus Coupler of Transformer-1 Karlahalli, Harihara Rural, Doggalli
Harihara Rural, Doggalli MATA,ALADAHALLI,HUNAVINODU,DODDAGHATTA,JANKAL,THA
Construction of 220 kV DC line from proposed 220/66 kV NEGEKALLU,KANTAPURA,DEVAPURARA,MAJJANAHALLI,ATTIMA
Baguru , Neergunda,
Benkikere station to proposed 220/66 kV GE,HONNENAHALLI,DUGGAVARA,GULIHATTI,BOCHENAHALLI,S
Hosadurga,
Chitradurga Major Chitradurga Major Hosadurga & 220KV Line From 220KV Hosadurga(Madure) sub-station for a distance of 41.104 EERANAKATTE,RANGAPPA TEMPLE,S K
76 Davanagere Davanagere Halurameshwara & 9/15/2022 9/15/2022 11:00 16:00 5:00 38.9
Works Division Works Division Holalkere Benkikere to Hosadurga kms in Hosadurga Taluk, Chitradurga District.For providing HALLI,KENKERE,NAKIKERE,POOJARAHATTI ,MADADAKERE ,Ved
Madadakere All Feeders
double suspension
Construction /double
of 66kV DC linetension insulators
from Bagur at road
tap point to link avathi Water works,Kappagere, Koratigere, Siddaramanagara ,
from the said MUSS
crossing in 4 Locations.line near Kerehalli
Mathod-Panchanahalli village limits in Kanguvalli, Kellodu, Rangavvanahalli , Peelapura, Devigere,
the existing corridor of 66 kV Mathod-Hosadurga-Ramagiri Kobbaripete UrbanB.V.NagaraMavinkatteAttighatta AND
SOMENAHALII,SRIRAMPURA,SNERALAKER,KABBLA,BALLALASA
Chitradurga Major Chitradurga Major 66kV Mathod to All Feeders from the SURROUNDING AREAS
77 Davanagere Davanagere Srirampura 9/15/2022 9/15/2022 10:00 16:00 5:00 SC line for a distance of 24.696 kms in Chitradurga MUDRA,GARGA,BELAGUR,KODIHALLI,KALKERE,THONACHENAH 8.8
Works Division Works Division Panchanahalli Line Garaga MUSS
District.Stringing of conductor btwn Tower No. 100 and 101 ALLI,GAVIRANGAPURA AND SURROUNDING AREAS
in Mathod–Panchanahalli Line & for Interconnection
Arrangements.

78 Tumkur Madhugiri Tumkur Madhugiri 66/11 kV MUSS Sira 9/15/2022 9/15/2022 10:00 16:00 6:00 Quarterly Maintenance Bank-I and II -Related feeders

66/11kV MUSS
79 Tumkur Madhugiri Tumkur Madhugiri 9/15/2022 9/15/2022 10:00 16:00 6:00 Quarterly Maintenance Bank-I and II -Related feeders
Tavarakere

66/11kV Harobele, Line maintenance work & Quaterly


Ramanagara Kodihalli, Kunur, Quaterly maintenance work of Transmission line & 66/11kV Harobele, Kodihalli, Kunur, Hukunda, Bijjahalli, maintenance work of Harobele, Kodihalli,
80 Kanakapura Ramanagara Kanakapura 9/16/2022 9/16/2022 10:00 15:00 5:00 1/5/2022 40 NO
Circle Hukunda, Bijjahalli, Substations Hunasanahalli S/s & surounding Villages. Kunur, Hukunda, Bijjahalli, Hunasanahalli
Hunasanahalli S/s. S/s Consent is given to avail LC on 16.09.2022.
Concurrence givenTO 15:00 hours.
Duration as 10:00 F-6 Mathikere
Change over from RMV F-5 feeder,
F-4 Malleshwaram Change over from IISc F2 &
F17 - Cool joint,F18-Food Complex,F19-Safina plaza,F-20 Prestige F3 feeder,Brigade F-4 feeder, 'C'station F-18
LC required for 2nd Quarterly Maintenance of 20 MVA TR-3 Full load change over can be made on NGEF , EDC and C
81 BMAZ South Hoody East Indiranagar Division 66/11kV B-Station 9/16/2022 9/16/2022 10:00 15:00 5:00 9/22/2022 central,F21-Prestige dynasty,F22-Manipal R.M.U,F23-City bank NO load affected MOM Enclosed. feeder
at 66/11 kV B Station MUSS Station F- 8 Water supply Change over from IISc F2
MG road, F-24 PM street LC MAYRMVBE APPROVED,CHANGE OVER CAN
feeder, F-1 & F-8 feeder,
F-6 Mathikere BE9ARRANGED
F- Yeswanthpur Change over from IISc F7
F-4 Malleshwaram The LC on Bank-2 and related feeders required feeder, Mathikere F-6 feeder,
F2-Honnur, F3- Replacement existing 11kV SIEMENS make Bank-2 F- 8 Water supply from 16.09.2022 @11:00 Hrs to 19.09.2022 F-10 BHEL Change over can be given from
Malleswaram(C2,C6 Basavanalu, F4-Industry, Alternate supply will be arranged by BESCOM O&M staff for RMV F8 feeder with ristricted load.
82 BMAZ NORTH SRS Peenya North 66/11kV IISC MUSS 9/16/2022 9/19/2022 11:00 22:00 11:00 switchgears by new 11kV MEI make switchgears at _ F- 9 Yeswanthpur _ @22:00 Hrs and For connecting Bus coupler
Sub division) the feeders which have change overs from other stations F- 11 Brain Center Change over from IISc F1
F5-Malleshattihalli, F6- 66/11kV IISc MUSS, RMSD, SRS Peenya. Bangalore. F-10 BHEL from Bank-1 and Bank-2 entire station load feeder, RMV F-6 feeder,
Kadajji, F7-Avaragere, F8- F- 11 Brain Center will be affected for Three Hours on 18.09.2022
Anagodu, F9-Bethur, F10-
Honnur, Basavanalu, Industry,Malleshattihalli, Kadajji, Avaragere,
Putaganalu, F11-Igooru,
Anagodu, Bethur, Putaganalu, Igooru, Chikkanahalli, NJY
83 Davanagere Davangere Davanagere Davangere CSD 2 and RSD Avaragere 66/11kV F12-Chikkanahalli, F13- 9/16/2022 9/16/2022 10:00 16:00 6:00 Half Yearly Maintenance Work 12
Rampura, Anekonda, Mahaveera, Ravi, Goshale, Lingadahalli and
Anaekonda, F14-
STP Avaragere Industry and Surrounding Area
Mahaveera, F15-Ravi,
F16-Goshale, F17-NJY
66/11 kV MUSS Lingadahalli, F18-NJY
84 Tumkur Madhugiri Tumkur Madhugiri Rampura, F19-STP 9/16/2022 9/16/2022 10:00 16:00 6:00 Quarterly Maintenance Bank-I and II -Related feeders
Guligenahalli
Avaragere Industry.

66/11 kV MUSS
85 Tumkur Madhugiri Tumkur Madhugiri 9/16/2022 9/16/2022 10:00 16:00 6:00 Quarterly Maintenance Bank-I and II -Related feeders
Bukkapatna

66/11 kV MUSS
86 Tumkur Madhugiri Tumkur Madhugiri 9/16/2022 9/16/2022 10:00 16:00 6:00 Quarterly Maintenance Bank-I and II -Related feeders
Kallambella

220/66/11KV hoody- Qaurterly Maintenance Work of transformers -1 and 11kV Load of transformer 1 is 10MW , TR2 is 11MW & TR3 is 7
87 BMAZ South Hoody East White field 9/17/2022 9/17/2022 10:00 15:00 4:00 2/5/2022 NGEF Estate (F-9 feeder , Gardacharpalya) 1 (one) Load change over will
MWbe , done by BESCOM MOM Enclosed.
31.5MVA trf-1 Switchgears 1.5MW load will be
1. During Transformer-1 LC, load will be catered through
1. To carry out Tan-Delta Test of Transformer-1, affected for 1.5 Hour Concurrence given
bus-coupler on Transformer-2 with 5MW load affected.
Transformer-2 and Transformer 3. during Transformer 1
2. During Transformer-2 LC , load will be catered through
2. To carry out quaterly/half yearly maintenance works of Kempapura,Agrahara L/o,Defence L/o,Fortune,A block ,Pai house, Maintenance work .
66/11kv Sahakarnagar bus-coupler on Transformer-3 with 4MW load change over
88 BMAZ NORTH HEBBAL North C8,C9,C4 sub division 9/17/2022 9/17/2022 10:00 15:00 5:00 Transformer Bays, 66kV Line Bays, 11kV Bus maintenance. 9/3/2022 Byatrayanapura , UAS layout , Telecom layout ,Milstone and 2. 24 MW load will be
muss from BESCOM and hence no load affected.
3. For carrying out IR test of all equipements like CT's, PT's, hiranandani appartement affected for 3 Hours
3.During Transformer-3 LC , load will be catered through
LA's, Transformers, 66kV Breakers, 11kV Breakers, Wall during 11kv Bus and Consent is given work can be taken
bus-coupler on Transformer-2 with 4MW load change over
entry bushings and 11kV Bus. Adugodi,Salapuria Tower,Big Bazar,Accenture,KMF 66kv Bus GOS
Peak load-20MW, from BESCOM and hence no load affected.
2nd Quarterly/Half Yearly maintenance work of Incoming maintenance
HSR Layout & 66/11kV Primal Tech Park Godown,Nanjappa Layout,New
12th block,7thBlock,11th mico road,Chikkalakshmi
Block,RGA Infrastructure 1 & 2,9th A Load change work.
over- 4.During 11kv Bus and 66kv Bus Gos maintenance , station
89 BMAZ South HSR Layout South 9/17/2022 9/17/2022 10:00 14:00 4:00 Line, Power Transformers, 66kV PT, 66kV Main BUS, 66kV 2/10/2022 Layout,Mahalingeshwara badavane,bangalore Load Changeover-2MW
Koramangala S/s block,9Th B block,Intel,Station auxillary. 2MW, load of 24MW will be affected for 3 hrs.
Breakers and Maintenance of 11kV Breakers consent is given for availing the LC on
dairy,Forum,Rangadasappa layout, Lakkasandra,Wilson Load affected-18MW
17.09.2022
Garden,Chinnayyana Palya,Chandrappa Nagara,Nimhans
Administrative block,Bande slum,Sunnakal Forum,Brundavana Peak load-33MW,
Jayanagara and 66/11kV Adugodi Sub- 2nd Quarterly/Half Yearly maintenance work of 66kV PT, 20-12-2021 Slum, NDRI-police quarters, 8th block, 7th block adugodi, NDRI Load change over-
90 BMAZ South HSR Layout South 9/17/2022 9/17/2022 10:00 15:00 5:00 Load Changeover-18MW
Koramangala Station 66kV Main BUS,31.5MVA Transformer-3 Only for Tr-3 NIANP, St Johj Hospital, 5th block industrial layout, Mico Bosch, 18MW,
JNC Sorronding, 5th Block KHB colony, Industrial Area 5th block, Load affected-15MW
Consent given for availing the LC on 17.09.2022
7th block khb colony, Industrial Area 3rd block, 8th to 11th main,
100MVA, 220/66kV Power For carrying out periodical maintenance works as per Industrial area 5th block, Koramangala 3rd, 4th, 5th, 6th Block,
Transformer-2 at maintenance schedule for 2nd quarter. Load of Transformer Maruthi nagara, Dabas colony, OLd Madivala,, Oracle, Madivala, No load will be
91 BMAZ South Somanahally BMAZ[S] Kengeri 9/17/2022 9/17/2022 10:00 15:00 5:00 No load will be affected.
NEERAGUNDA,ADRIKATTE,SRI No load will be affected.
220/66/11kV R/S, will be changed over to 150MVA Power Transformer-1&3 Chikka Adugodi, Krishna nagara Industrial Area, Davanam affected.
Somanahalli, Bengaluru and other 220kV Stations. No load will be affected. MATA,ALADAHALLI,HUNAVINODU,DODDAGHATTA,JANKAL,THA
Jewellers. Consent given for availing the LC on 17.09.2022
Construction of 220 kV DC line from proposed 220/66 kV NEGEKALLU,KANTAPURA,DEVAPURARA,MAJJANAHALLI,ATTIMA
Baguru , Neergunda,
Benkikere station to proposed 220/66 kV GE,HONNENAHALLI,DUGGAVARA,GULIHATTI,BOCHENAHALLI,S
Hosadurga,
Chitradurga Major Chitradurga Major Hosadurga & 220KV Line From 220KV Hosadurga(Madure) sub-station for a distance of 41.104 EERANAKATTE,RANGAPPA TEMPLE,S K
92 Davanagere Davanagere Halurameshwara & 9/17/2022 9/17/2022 11:00 16:00 5:00 38.9
Works Division Works Division Holalkere Benkikere to Hosadurga kms in Hosadurga Taluk, Chitradurga District.For providing HALLI,KENKERE,NAKIKERE,POOJARAHATTI ,MADADAKERE ,Ved
Madadakere All Feeders
double suspension
Construction /double
of 66 kV tension
SC Line on DCinsulators
towers byatusing
road coyote avathi Water works,Kappagere, Koratigere, Siddaramanagara ,
from the said MUSS
crossing in 4 Locations.
ACSR conductor from 220 KV SRS Davanagere to four pole Kanguvalli, Kellodu, Rangavvanahalli , Peelapura, Devigere,
structure Chitradurga in the existing corridor of 66KV Kobbaripete UrbanB.V.NagaraMavinkatteAttighatta AND
Jayanagara
SURROUNDING Church to Shakthi Nagar over head water tank,(Loc-8-
AREAS
93 66/11kV Avaragere S/s DCM 9/17/2022 9/17/2022 10:00 16:00 6:00 Davangere -Chithragurga SC Line-1 for adistance of 55.697 9/1/2022
Davangere Davangere Davangere Davangere 12)
Kms in Davanagere/Chitradurga District and Buy back of
released materials on Total Turnkey Basis—Availing Line
clear
66/11 kV
94 BMAZ WEST WEST WEST Hanumanthanagara 9/17/2022 9/17/2022 10:00 16:00 6:00 Maintenance works like tree trimming, jump works etc 9/16/2022 HANUMANTHANAGAR AND SURROUNDING AREAS
substation

66/11 kV
95 BMAZ WEST WEST WEST Hanumanthanagara 9/18/2022 9/18/2022 10:00 16:00 6:00 Maintenance works like tree trimming, jump works etc 9/16/2022 HANUMANTHANAGAR AND SURROUNDING AREAS
substation
Duration of LC request

Name of the Name of the KPTCL Name of the BESCOM Name of the BESCOM Date on which last
Sl no
KPTCL Circle Division Circle Division
Sub Division Name of the station/Line Feeder Date Time Reason for availing LC
LC was approved
Areas Affected Load Affected (MW) Wheather alteranate Power Supply Arranged or not Remarks Consent

From To From To Duration

Ramanagara 1. 2nd Quarterly maintenance at 66/11 kV Attibele.


96 Yerrandanahalli Ramanagara Chandapura 66/11 kV Attibele 9/18/2022 9/18/2022 10:00 15:00 5:00 3/20/2022 Attibele, Attibele industrial area, Maisandra, Yaduvinahalli areas. 25 No
Circle 2. For replacing Bank-2 CTs. Consent is given to avail LC on
18.09.2022,Duration for LC Approved from
10:00 to 15:00 hours (5 Hours)

1)To carry out 2ND Quarterly maintenance at 66/11kV S/s


Ramanagara 66/11kV S/s Jigani Link
97 Yerrandanahalli Ramanagara Chandapura 9/18/2022 9/18/2022 10:00 15:00 5:00 Jigani Link Road 2/5/2022 Industries and areas feeding from 66/11kv Jigani Link Road S/s . 15 NO
Circle Road Consent is given to avail LC on
2)For attending Hot line obseravation 18.09.2022,Duration for LC Approved from
10:00 to 15:00 hours (5 Hours)
66kV Kanakapura-
Somanahalli Line-1 Line maintenance work & Quaterly
Ramanagara Industries of near at Yedamadu S/s, Hanumanthanagara Raising
98 Kanakapura Ramanagara Kanakapura (Partial) & 66/11kV 9/18/2022 9/18/2022 10:00 15:00 5:00 Quaterly maintenance work & Transmission line 2/15/2022 14 NO maintenance work of Yadamadu &
Circle sun IPP & sorrounding villages
Yadamadu & Hanumanthanagara S/s. Consent is given to avail LC on 18.09.2022.
Hanumanthanagara S/s. Duration as 10:00 TO 15:00 hours.

31.5MVA power
transformer -02 of For attending hot spots at Transformer LV side and Bank-2 Aletrnative power supply for 4.1MW will be arranged and
99 BMAZ South GIS DIVISION North Peenya 2nd stage 9/18/2022 9/18/2022 10:30 15:30 5:00 Peenya industrial area 4MW MOM attached
Brindhavana side remaining 4.1MW have no alternative source.
220/66/11kV GIS station
Consent is given work can be taken

31.5MVA power
transformer -01 of Aletrnative power supply for 7.9MW will be arranged and
100 BMAZ South GIS DIVISION North Peenya 9/18/2022 9/18/2022 10:30 15:30 5:00 To avoid induction at bank-2 of 31.5 MVA transformer -02. Peenya industrial area 3MW MOM attached
Brindhavana remaining 3MW have no alternative source.
220/66/11kV GIS station
Consent is given work can be taken

220/66/11kV HSR Layout


R/s 2nd Quarterly/Half Yearly maintenance work of 220kV No load will be
101 BMAZ South HSR Layout South HSR Layout 9/18/2022 9/18/2022 10:00 15:00 5:00 1/13/2022 No load will be affected No load will be affected
(220kV Mylsandra-HSR Mylsandra-HSR Line-1 Bay affected
Line-1 Bay) Consent is given for availing the LC on
18.09.2022

Chitradurga Urban 220/66/11 kV MUSS SRS, All Feeders from the said
102 Davanagere Chitradurga 220 SRS Davanagere Chitradurga 220 SRS 9/18/2022 9/18/2022 10:00 14:00 4:00 Half Yearly maintenance work All 66KV Line Outgoing from the said MUSS. 168
and Rural Chitradurga MUSS

66kV O/G line Baddihalli, F-1 Shanthinagara,F-2 Devanuru,F-10


GVR,F-11 Gandhinagara,F-12 VHB,F-14 Gulur NJY,F-4 AK kaval
103 Tumkur Tumkur Tumkur Tumkur 66/11kV S/S Melekote 9/18/2022 9/18/2022 10:00 16:00 6:00 DP structure work
F-5 Melekote,F-6 Banavara,F-7 Dairy,F-8 Kumkumanahalli, F-
9 Guluru

Peak load-21MW,
2nd Quarterly/Half Yearly maintenance work of 66kV PT, Wilson Garden, Hombegowda Nagara, Sampagi Nagara, J.C. road, Load Changeover-14.3MW, 66kV National college loads (Load
Jayanagar & Load changeover-14.3
104 BMAZ South HSR Layout South 66/11kV BMTC S/s 9/19/2022 9/19/2022 10:00 15:00 5:00 66kV Main BUS, 66kV Breakers and Maintenance of 11kV 10/21/2021 Shanti Nagar, BTS Road, Richmond Circle,Residency of 16MW) to be change over to 220kV NIMHANS R/S or to
Indiranagar MW
BUS. Road,sudhamanagara, K.H. Road 66kV Victoria S/s
66kV Kaggalipura- Load affected-6.7MW
Consent given for availing the LC on 19.09.2022
For carrying out periodical maintenance works as per
Somanahalli line bay And
maintenance schedule for 2nd quarter. Load of 66/11kV
66kV Kaggalipura-Shobha
Kaggalipura [Brigade Meadows] and 66/11kV Shobha Forest No load will be
105 BMAZ South Somanahally BMAZ[S] Kengeri Forest view line bay at 9/19/2022 9/19/2022 10:00 15:00 5:00 No load will be affected. No load will be affected.
View Sub-stations may be changed over to 220kV affected.
66/11kV Sub-station,
Subramanyapura station. And LC will be availed after
Kaggalipura [Brigade Consent given for availing the LC on 19.09.2022
completing the bay consequently. No load will be affected.
Meadows], Bengaluru.
66kV Kanakapura-T.K Basaveshwara nagar, Vijayanagar, Govindaraja Nagar,
Ramanagara Kamshipalaya, RPCJewellers
Layout, Binny
106 Kanakapura Ramanagara Kanakapura Halli Line-2, 66/11kV 9/20/2022 9/20/2022 10:00 15:00 5:00 Quaterly maintenance work & Transmission line 11/9/2021 Doddalahalli, GRT IPP & Layout, Prashant
sorrounding Nagar,
villages 9 NO Quaterly maintenance work
Circle
Doddalahalli S/s. Hosahalli vijaynagar, RPC layout, Service Road, Vijayanagar 7th Consent is given to avail LC on 20.09.2022.
Main to 13th Main, Ist Stage Thimmenahally, Part of MC Layout, Duration as 10:00 TO 15:00 hours.
Binny Layout, Marenahally Layout, Part of Vinayaka Layout, PC
Industrial Area, Kaveripura, Ranganathapura, KCG Ind. Area, During LC Period 21MW load will be affected after
NRS Consent given Peak load of the station is 40
107 BMAZ North NRS North 66/11 kV Vijayanagar 9/20/2022 9/20/2022 10:00 15:00 5:00 Quarterly maintenance 12/28/2021 Nanjappa Ind. Estate, Sunnadagodu, Selvam Industrial Estate, 21 rearranging of loads on other stations as per concerned
Division,Rajajinagar. MW, 22 MW load change over will be done by
Ballayana Kere, Syndicate Bank Colony, Kaveripura 1st Block, 2nd BESCOM officials. BESCOM authority & about 18 MW load will be
Block, 3rd Block, 5th Block, 6th Block, 7th Block, 8th Block, affected during LC period
Nagarbhavi 11th block, KHB Colony, HVR Layout, Syndicate Bank
Anagodu, RSD Colony and surrounding area, Siddaiah Puranika Road, Papaiah
108 Davanagere Davanagere Davanagere Davanagere Kadajji. 66/11kV All 11kV feeders 9/20/2022 9/20/2022 10:00 16:00 6:00 2nd Quarter maintenance Beturu, KHB
Garden Basavanal,
Colony,Nagarakatte
KHB Colony,kadajji
Magadiand surrounding
main road , Partvillages
of 7
Davanagere
Agrahara Dasara halli
Construction of 66 kV SC Line on DC towers by using coyote
ACSR conductor from 220 KV SRS Davanagere to four pole
structure Chitradurga in the existing corridor of 66KV
Jayanagara Church to Shakthi Nagar over head water tank,(Loc-8-
109 66/11kV Avaragere S/s DCM 9/20/2022 9/20/2022 10:00 16:00 6:00 Davangere -Chithragurga SC Line-1 for adistance of 55.697 9/1/2022
Davangere Davangere Davangere Davangere 12).
Kms in Davanagere/Chitradurga District and Buy back of
released materials on Total Turnkey Basis—Availing Line
Srinagara , hosakerehalli , pes engg college , veerbhadranagara ,
Jayanagar and RR clear Bank colony , Hanumanthnagara , girinagara , seetha circle ,
nagara (W1,W2,W6, vidhyapeeta circle , pramod layout , muneshwara block ,nagendra 08 MW load can be shifted on nearby stations by BESCOM at
110 BMAZ South Subramanyapura West & South 66/11kV Banashanakari 9/21/2022 9/21/2022 10:00 15:00 5:00 Periodic maintainance works 8/4/2021 45
W7 & S15 block , Bull temple Road , kathriguppe , Avalahalli ,Sterling the time of Line clear.
Subdivisions) apartment ,NTY Layout , Thyagarajanagara , Basavangudi , BSK
Consent given for availing the LC on 21.09.2022
3rd stage

All Feeders from the said G.N kere,Bukkasagara,Mathod,Nagatihalli,Menasinodu,Mathod


111 Davanagere Chitradurga 220 SRS Davanagere Chitradurga 220 SRS Srirampura 66/11 kV MUSS Mathod 9/21/2022 9/21/2022 10:00 16:00 6:00 Half Yearly maintenance work 7.7
MUSS urban,D T Vatti,Vajra and the surrounding areas.

Kanchipura,Kittidal,Kadavigere,Obbalapura,Vengalapura,N N
66/11 kV MUSS All Feeders from the said
112 Davanagere Chitradurga 220 SRS Davanagere Chitradurga 220 SRS Srirampura 9/21/2022 9/21/2022 10:00 16:00 6:00 Half Yearly maintenance work Katte,D K Katte,Shivanagara,J S Pura,C B Gere and the 4.08
Kanchipura MUSS
surrounding areas.

chillahally, vk gudda, hoovinaholehariyabbe, shravanagere,


Somenahalli,Shrirampura,Neralakere,Kabbala,Ballalasamudra,Gar
All Feeders from the said dharmapura, Aralikere, Krishnapurachillahally, Eshwaragere,
113 Davanagere Chitradurga 220 SRS Davanagere Chitradurga 220 SRS Srirampura 66/11 kV MUSS Garga 9/21/2022 9/21/2022 10:00 16:00 6:00 Half Yearly maintenance work ga,Belaguru,Kodihalli,Kalkere,Thonachenahalli,Gavirangapura. 8.92
MUSS Hoovinahole, Devarakotta,
And the surrounding areas.Eshwaragere, Hoovinahole,
Devarakotta, chillahally, vk gudda, Yalagondanahalli,
Abbinnahole, T Gollahalli, Mungasavalli, Krishnagiri, Suguru,
1)Replacement of 66KV BUS Coyote to Drake conductor 12 Bagganadu,
Burudukunte, B Gulya,
G Kaval, Kolatadahallianesidri,
Saluhunase, Krihnagiri, K T N
Hosahallyharyabbe,
114 Davanagere Hiriyuru Davanagere Hiriyuru Hiriyuru Hariyabbe_66 All Feeders 9/21/2022 9/21/2022 10:00 16:00 6:00 nos of main/cross bays at Hariyabbe MUSS. Halli, K T N Halli
kanajanahally, Tanda, Beturu
Bethuru, K T Halli Onihatti, Kariyala,
palya, 14
2) 1&2nd quarterly maintenance work. Maradihatty, Murumane Hatty,
kuridasanahattiMungasavalli, Mudlahatty,
Krishnagiri, Gayath
Suguru, Ripura, B K
Saluhunase,
Hatti, Benne Erappanahatty,
kanajanahally, Bethuru, Beturu JG Halli.kuridasanahatti,
palya, Julaiahnahattyanesidri,
Krihnagiri,
chillahally, K
vkTgudda,
N Halli,T Gollahalli,
K T N HalliShravanagere,
Tanda, K T Halli
Benakanahalli,
Gollarahally1.Oabalapura
Sakkara, Hariyabbehariyabbe, .2.Obalapura Tandadharmapura,
shravanagere,
115 Davanagere Hiriyuru Davanagere Hiriyuru Hiriyuru JG Hally_66 All Feeders 9/21/2022 9/21/2022 10:00 16:00 6:00 1&2nd quarterly maintenance work. 3.Mavinamadu.4.Pilali.5.Surappanahatty 6.Saraswthihatty
Aralikere, Krishnapura, Benakanahalli, SakkaraHariyabbe, 18
7.Kilaradahally
kanajanahalli, 8.Lambanitanda .1.Pilali.2.Surappanahatty
3.Saraswthihatty 4.Kilaradahally
5.Lambanitand1.Oabalapura .2.Obalapura Tanda
Ramanagara 66/11kV Allimaranahalli 3.Kiladahallyonihatti, Kariyala, Maradihatty, Murumane Hatty, Line maintenance work & Quaterly
116 Kanakapura Ramanagara Kanakapura 9/22/2022 9/22/2022 10:00 15:00 5:00 Quaterly maintenance work 1/12/2022 66/11kV Substation
Mudlahatty, Allimaranahalli
Gayath Ripura, & surounding
B K Hatti, Villages.
Benne Erappanahatty, J 3 NO
Circle S/s. maintenance work of Allimaranahalli S/s
G Halli. Julaiahnahattyj.G.Hally Consent is given to avail LC on 22.09.2022.
Duration as 10:00 TO 15:00 hours.

220kV Somanahalli-
For carrying out periodical maintenance works as per
Mylasandra line-1 bay at No load will be
117 BMAZ South Somanahally BMAZ[S] Kengeri 9/22/2022 9/22/2022 10:00 15:00 5:00 maintenance schedule for 2nd quarter. No load will be No load will be affected. No load will be affected.
220/66/11kV R/S, affected.
affected as both are source stations.
Somanahalli, Bengaluru.
Consent given for availing the LC on 22.09.2022

F1-Kandagallu IP
Shyagale F2-Kodihalli IP Kandagallu ,Kodihalli,Goniwada,Shyagale
118 Davanagere Davanagere Davanagere Davanagere Davanagere 9/22/2022 9/22/2022 10:00 16:00 6:00 Half Yearly Maintenance Work 5
66/11 Kv F3-Goniwada IP And Surrounding villages.
F4-Shyagale NJY

CSD 1, CSD2 and


119 Davanagere Davanagere Davanagere Davanagere 220kV SRS Davanagere 66/11kV 20MVA BBL 9/22/2022 9/22/2022 10:00 16:00 6:00 2nd Quarter maintenance 11kV belavnnurru and JHP-2 and IP feeders 12
RSD Davangere

Maddihalli, Halagaladdi, Pd Kote, Khandenahally, Hosakerepd


120 Davanagere Hiriyuru Davanagere Hiriyuru Hiriyuru PD kote_66 All Feeders 9/22/2022 9/22/2022 10:00 16:00 6:00 1&2nd quarterly maintenance work. Kote, Khandenahally, Hosakere, Maddihalli, Halagaladdi, 7
Hosakere, Khandenahlli Palyamaddihalli, Halagaladdi,

121 Davanagere Hiriyuru Davanagere Hiriyuru Hiriyuru Hariyabbe_66 All Feeders 9/22/2022 9/22/2022 10:00 16:00 6:00

220kV Somanahalli-
For carrying out periodical maintenance works as per
Mylasandra line-2 bay at No load will be
122 BMAZ South Somanahally BMAZ[S] Kengeri 9/23/2022 9/23/2022 10:00 15:00 5:00 maintenance schedule for 2nd quarter. No load will be No load will be affected. No load will be affected.
220/66/11kV R/S, affected.
affected as both are source stations.
Somanahalli, Bengaluru.
Consent given for availing the LC on 23.09.2022

Byrohalli, Ramohalli, Kengeri Town, Bidadi Rural, Devikiran,


220kV Kengeri(K1
123 BMAZ South West 66/11kV Kumbalagodu 9/23/2022 9/23/2022 10:00 15:00 5:00 Periodic maintainance works 1/28/2022 Deccan Herrald, KAIDB 1st phase,KAIDB 2nd phase, Geruplaya 30 No
Subramanyapura subdivision)
industrial area, ISRO. Consent given for availing the LC on
23.09.2022( As per Mom)

Thimmalapura, Konehalli, Bidaregudi, Naguthihalli,


124 Tumkur K.B Cross Tumkur K.B Cross 110/11KV MUSS Honnvali 9/23/2022 9/23/2022 10:00 16:00 6:00 Quarterly Maintenance hulihalli,Honnavalli, Hosapatna,Baluvaneralu,Patrahalli,
Rudrapura, gudigondanahalli

Boralinganapalya, Kunigal Town, Kenkere, Bilidevalaya,


125 Tumkur K.B Cross Tumkur K.B Cross 66/11KV MUSS Kunigal 9/24/2022 9/24/2022 10:00 16:00 6:00 Quarterly Maintenance
Kalasipalya, Janagere, Heruru, Bhaktharahalli IP, Bidanagere

220 KV R/s Nittur (220kV 110KV Gubbi, 110KV Kadaba, 110kV KG temple, 110kV Kallur,
126 Tumkur Tumkur Tumkur Tumkur 9/24/2022 9/24/2022 10:00 16:00 6:00 Half Yearly -01 maintenance
and 110kV side) 110kV Doddaguni, 110kV Somalpura and 220kV Nittur R/S

20 MVA Tr-1, 20 MVA Tr-2, F1-Kodihally, F2-YELLAPURA, F3-


SAGARANAHALLY, F4-M.S Hally, F5-Hemavathi, F6- Thyagatoor,
220 KV R/s Nittur (11kV F7-Benachigere,F8- Hesarahally, F9-Belavattha, F11 - Matthigatta,
127 Tumkur Tumkur Tumkur Tumkur 9/24/2022 9/24/2022 10:00 16:00 6:00 Half Yearly -01 maintenance
side) F12-Bandihalli,F13-M.N Kote, F14-Rampura, F15- Nittur, F16-
Sopanahally NJY, F17- CNNL Water supply, F18-PURA NJY,F19-
Bommanahalli NJY,
Duration of LC request

Name of the Name of the KPTCL Name of the BESCOM Name of the BESCOM Date on which last
Sl no
KPTCL Circle Division Circle Division
Sub Division Name of the station/Line Feeder Date Time Reason for availing LC
LC was approved
Areas Affected Load Affected (MW) Wheather alteranate Power Supply Arranged or not Remarks Consent

From To From To Duration

110kv gubbi line, 110kv bidare line at Gubbi S/S, F1-Gopalapura,


F2-G.Hosahalli, F3-Tippuru NJY, F4-singonahalli, F5-Torehalli
GH&MH, F7-Kodigehalli, F8-Koppa, F9-Heruru, F10-M.H Patna,
128 Tumkur Tumkur Tumkur Tumkur 110/11 KV S/s Gubbi 9/24/2022 9/24/2022 10:00 16:00 6:00 Half Yearly -01 maintenance F11-Uddehosakere, F12-Honnavalli, F13-Bidare, F14-
Ammanaghatta, F15-Gubbi Town, F16-KMF, F17-Thonganahalli
NJy, F18-Doddakattigenahalli NJY, F20-Bescom subdivision, F24-
Madapura NJY
F1-Guddadahally NJY, F2- Kaggere, F3- Bidare, F4-
Ranganatahapura, F5- Gowripura, F6- JAINIGARAHALLY, F6B-
129 Tumkur Tumkur Tumkur Tumkur 110/11 KV S/s Bidare 9/24/2022 9/24/2022 10:00 16:00 6:00 Half Yearly -01 maintenance
Mannammatemple, F7- M.S Pallya, F8- Kashimath, F9-
Muniyappanapallya

130 Tumkur Tumkur Tumkur Tumkur 110/11 KV S/s Kadaba 9/24/2022 9/24/2022 10:00 16:00 6:00 Half Yearly -01 maintenance F9-Bennur NJY..F10-DKhalli NJY, F11-BelavathaNJY

110/11 KV S/s KG
131 Tumkur Tumkur Tumkur Tumkur 9/24/2022 9/24/2022 10:00 16:00 6:00 Half Yearly -01 maintenance F6-Nagasandra NJY, F12-konanakere NJY
Temple

132 Tumkur Tumkur Tumkur Tumkur 110/11 KV S/s Ungra 9/24/2022 9/24/2022 10:00 16:00 6:00 Half Yearly -01 maintenance F5-CSpura NJY... F6-watersupply

,F-11 BENAKANGONDI ,F12- NJY B.G Halli,F13- NJY


133 Tumkur Tumkur Tumkur Tumkur 110/11 KV S/s Kallur 9/24/2022 9/24/2022 10:00 16:00 6:00 Half Yearly -01 maintenance
Madapatna ,F-15 NJY T.palya,F5-Kallur (Urban)

110/11 KV S/s
134 Tumkur Tumkur Tumkur Tumkur 9/24/2022 9/24/2022 10:00 16:00 6:00 Half Yearly -01 maintenance 110kV doddaguni all 11kV feeders
Doddaguni

F9-Raghadevanahalli NJY, F10-Basavapura NJY, F11-


135 Tumkur Tumkur Tumkur Tumkur 110/11 KV S/s Sampige 9/24/2022 9/24/2022 10:00 16:00 6:00 Half Yearly -01 maintenance
Machenahalli NJY

110kv Somalapura line, F1-H Nagenahalli, F2-M.N kote, F3-


110/11 KV S/s
136 Tumkur Tumkur Tumkur Tumkur 9/24/2022 9/24/2022 10:00 16:00 6:00 Half Yearly -01 maintenance Gollahalli, F4-Mattikere, F5-Uddehosakere, F6-Somalapura Town,
Somalapura
F7-Baguru NJY, F8-Sankapura, F9-Gyarehalli

66/11 KV S/s Nandihally


137 Tumkur Tumkur Tumkur Tumkur 9/24/2022 9/24/2022 10:00 16:00 6:00 Half Yearly -01 maintenance 66kV Nandihalli all 11kV feeders
Cross

138 Tumkur Tumkur Tumkur Tumkur 66/11 KV S/s Ankasandra 9/24/2022 9/24/2022 10:00 16:00 6:00 Half Yearly -01 maintenance 66kV Ankasandra all 11kV feeders

F1-Thalekoppa,F2-Thonasanahally,F3-Ennekatte,F7-H palya,f9-
139 Tumkur Tumkur Tumkur Tumkur 66/11 KV S/s Chelur 9/24/2022 9/24/2022 10:00 16:00 6:00 Half Yearly -01 maintenance
madenahallyF10-Idakanahally

20 MVA Tr-1 , 12.5 MVA Tr-2, and 11KV feeders F1- Shivapura,
F2- Hagalawadi, F3- Manchaladore, F4- Hoovinakatte, F5-
140 Tumkur Tumkur Tumkur Tumkur 66/11 KV S/s Hosakere 9/24/2022 9/24/2022 10:00 16:00 6:00 Half Yearly -01 maintenance Kallanahally, F6-Hosakere, F7-ALILUGATTA, F8-BETTADAHALLY,
F9-KALINGANAHALLY, F10-SOMALAPURA, F11-GANESHAPURA,
F12-BANDIHALLI

8 MVA Tr-1, F1- Matthikere, F2- Kurehally, F3- Hagalawadi NJY,


141 Tumkur Tumkur Tumkur Tumkur 66/11 KV S/s Hagalawadi 9/24/2022 9/24/2022 10:00 16:00 6:00 Half Yearly -01 maintenance
F4- Guddenahally, F4B- G Rangapura

66/11 KV S/s
142 Tumkur Tumkur Tumkur Tumkur 9/24/2022 9/24/2022 10:00 16:00 6:00 Half Yearly -01 maintenance F3-Mallasandra Town, F6-Gollahalli NJY and F9-KMF
Mallasandra

Ramanagara For station maintenance works, Tan Delta test of 66kV CT's
143 Yerrandanahalli Ramanagara Chandapura 66/11 kV Bommasandra 9/25/2022 9/25/2022 10:00 15:00 5:00 5/29/2022 All Areas and industries feeding from Bommasandra S/S 25 MW No
Circle and other scheduled works at 66/11kV S/s Bommasandra Consent is given to avail LC on
25.09.2022,Duration for LC Approved from
10:00 to 15:00 hours (5 Hours)

Bhaktharahalli, Bagenahalli, Bannimaradakatte, Vanigere,


66/11KV MUSS
144 Tumkur K.B Cross Tumkur K.B Cross 9/28/2022 9/28/2022 10:00 16:00 6:00 Quarterly Maintenance Kuruduhalli, Vaddarakuppe, Teradakuppe, Kallupalya,
Bhakthrahalli
Gidadapalya

Ramanagara 220/66kV Kanakapura


145 Kanakapura Ramanagara Kanakapura F2 -Upkar Layout 9/29/2022 9/29/2022 10:00 15:00 5:00 TR2 Quaterly maintenance work 3/29/2022 Kanakapura Town & surounding Villages. No load affected Partial load will take on existing 100MVA Tr-1 Tr-2 Quaterly maintenance work
Circle S/s. Strengthening of existing transmission line passing
F1-Sunkadakatte Consent is given to avail LC on 29.09.2022.
Govt.School/Colleges Duration as 10:00 TO 15:00 hours.
F3-Ullal
Herohalli a) To provide double sting insulator in between tower no. 10
F10-Nedikerappa Indl Areas affected:Mahadeshwaranagara, Prasanna layout, Hosahalli, Approximately 4MW load can be changed over
srigandakaval & 11 which is passing over the premises of 22-05-2022
Area Kempegowda nagar, Gollarahatti, Nedikerappa industrial area, to 66/11kV N.G.Halli Sir M. V. Layout and
146 BMAZ NORTH SRS Peenya KPTCL Bangaluru NORTH Sunkadakatte K2, N8 & N6 66/11kV Byadarahalli 9/11/2022 9/11/2022 10:00 15:00 5:00 Anganavadikendra Lakshmidevinagara B'lore(Govt school) LC availed by 18MW
F11- Anjajanagara Herohalli, Tunganagara, Vigneshwaranagara, Anjanagara, Vijanagara MUSS as per confirmation from
K2, N8, N6 Sub Strengthening of existing
b) To provide double stingtransmission line passing
insulator in between tower no.- TLM Staff
F5-Tunganagara
F6 -Niligiri Thopu Govt.School/Colleges Annapoorneshwari nagara & Sunkadakatte BESCOM official after conducting MOM
Division)
Papareddy palya 5,6 &7 which is passing over the premises of Nammoora
F6-Balaji Layout
F7-Hegganahalli a) To provide double sting insulator in between tower no. 10 Approximately 7MW load can be changed over
School, Sanjayagandhinagara Nandini layout post,
Pategar Palya F8-Annapoorneshwari
F10-Annapoorneshwari & 11 whichschool).
Blore(Govt is passing over the premises of 22-05-2022 to 66/11kV Vijanagara MUSS, 66/11kV
srigandakaval nagar Areas affected: Annapoorneshwari, Niligiri Thopu, Hegganahalli &
147 BMAZ NORTH SRS Peenya KPTCL Bangaluru NORTH N8, N6 & N10 66/11kV Srigandakaval nagar 9/11/2022 9/11/2022 10:00 15:00 5:00 Anganavadikendra Lakshmidevinagara B'lore(Govt school) LC availed by 6MW Chandra layout MUSS, and 66/11kV Sir M.V.
Sunkadakatte Sunkadakatte
F2-Sunkadakatte b) To provide double sting insulator in between tower no.- TLM Staff MUSS as per confirmation from BESCOM
(N8, N6 & N10 Sub
Industrial area 5,6 &7 which is passing over the premises of Nammoora official after conducting MOM
Division) F-4 Thugani feeder
F13-Saltava (IP), F-
developers School, Sanjayagandhinagara Nandini layout post,
66/11 kV 12 Yedanahalli feeder conversion of existing 220 kV SC Somanahalli-TK Halli line
Blore(Govt school). F-4 Thugani feeder (IP), F-12 Yedanahalli feeder (NJY), F-5
148 BRAZ kanakapura Ramanagara Harohalli Hanumanthanagara (NJY), F-5 9/17/2022 9/17/2022 10:00 16:00 6:00 to DC line from existing 220/66 kV TK Halli to existing
Hanumanthanagara (IP), F-6-KIADB
substation, Hanumanthanagara (IP), 220/66 kV Somanahalli Substation
F-6-KIADB
F-4 Thugani feeder (IP), F-
66/11 kV 12 Yedanahalli feeder conversion of existing 220 kV SC Somanahalli-TK Halli line
F-4 Thugani feeder (IP), F-12 Yedanahalli feeder (NJY), F-5
149 BRAZ kanakapura Ramanagara Harohalli Hanumanthanagara (NJY), F-5 9/18/2022 9/18/2022 10:00 16:00 6:00 to DC line from existing 220/66 kV TK Halli to existing
Hanumanthanagara (IP), F-6-KIADB
substation, Hanumanthanagara (IP), 220/66 kV Somanahalli Substation
F-6-KIADB
KPTCL for Line Clear proposal for the month of August-2022

Duration of LC request

Name of the Name of the KPTCL Name of the BESCOM Name of the BESCOM Date on which last
Sl no
KPTCL Circle Division Circle Division
Sub Division Name of the station/Line Feeder Date Time Reason for availing LC
LC was approved
Areas Affected Load Affected (MW) Wheather alteranate Power Supply Arranged or not Remarks Consent

From To From To Duration

New Tower: Erection of Tower No-2 MD+3 (NBT) Vikas Tech


Park design up to Cross Arm level up to Existing 220kV NBT
incomung line of 66/11kV
1 CTAZ Davanagere Chitradurga NN NN 8/1/2022 8/1/2022 9:00 16:00 7:00 bottom of conductor. ii) New Tower: Erection of Tower No-3 NN NN NN
Bharamasagar Sub-Station
MD+6 (NBT) Vikas Tech Park design up to Cross Arm level
up to Existing 220kV NBT bottom of conductor.

Exinting 66kV Erection of Towers and stringing work between


279 CTAZ Byadarnhalli-Kodigehalli 8/1/2022 8/17/2022 9:00 16:00 7:00 location 1 and 17, Dismantling of towers and No load affected No load affected alternate supply arranged
line. Coyote conductor.

existing 220kV SC existing 220kV SC Somanahalli – T.K. Halli to DC line from


280 CTAZ Somanahalli – T.K. Halli to 8/1/2022 8/12/2022 10:00 16:00 6:00 existing 220/66kV T.K.Halli to existing 220/66kV
DC line Somanahalli Sub-station

66 kv Antharasanahalli
2 CTAZ Tumkur choluru Hosakere line
All feeder 8/2/2022 8/2/2022 7:00 16:00 11hrs Constructoion 11kv DC line chelur,Hoskere ,Nandihalli,Hagalawadi

114 CTAZ K.B Cross 66/11KV S/s, Yediyuru, 8/2/2022 8/2/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance

Gowribidanur-
stringing from tapping point to Tower no-02. Areas fed from
Doddaballapura-2 line and
281 CTAZ 8/2/2022 8/2/2022 9:00 16:00 7:00 66/11kV Thondebhavi and 11kV feeders F-15 Alkapura and Kurubarahalli surrounding areas and EHT consumer.
66kV Gowribidanur ACC
F-11
lin

single suspension/Tension insulators has to be replaced by


66kv Antharsnalli-
double suspension/Tension insulators in
282 CTAZ Melekote &66kv Antharsn 8/2/2022 8/2/2022 10:00 14:00 4:00 near Govt. School, Betthaluru 
66kV Antharasanahalli-Bellavi and 66kV Antharasanahalli -
alli-Bellavi
Melekote  DC line

66kV Kanakapura-
Chikkenahalli &
Quaterly maintenance work of Transmission line & Consent is given to avail LC on
283 Ramanagara Kanakapura Kanakapura Kanakapura Channapatna Line & 8/2/2022 8/2/2022 10:00 16:00 6:00 7/30/2022 Allimaranahalli, Chikkenahalli S/s & surounding Villages. 27 NO
Substations 02.08.2022
66/11kV Allimaranahalli
& Chikkenahalli S/s.

Consent is Given to avail LC on


Channapattana Urban, Kodamaballi, Bevoor sub division of 02.08.2022.( Note: if any exams &
66/11 kV Channapttana
Channapattana Taluk area feeding from 66/11 kV Channapattana emergency programs comes near to
284 Ramanagara TKHalli Ramanagara Ramanagara and Vandaraguppe 8/2/2022 8/2/2022 10:00 16:00 6:00 station Quarterly maintenance work 7/30/2022 22 MW No alternate power supply
substation and Channapattana Urban, Bevoor feeding from 66/11 that date I,e 02.8.2022 , the LC
substations
kV Vandaraguppe substation date should change /postpone to
another date )
66/11kV Devarabisanahalli sub-station for:
1)TAN-Delta of 31.5MVA Power Transformer 1 by R&D
Peak load-20MW,
2)Quarterely Maintenance work of 66/11kV Transformers,
HSR Layout & 66/11kV Bellandur,RMZ,Devarabisanahalli,Kariyammanapalya,Akme load changeover- LC was requested on in the month of May but LC may be availed, Interuption
285 BMAZ South HSR Layout South 8/2/2022 8/2/2022 10:00 16:00 6:00 66kV Isolators,66kV CT's & PT's. 7/30/2022 Load Changeover-15MW
Koramangala Devarabisanahalli S/s projects,Anupama,Total Mall,Shobha IRIS 15MW, was not approved paper notification to be given
3) Erection and Commission of NCT
Renovation and load affected-5MW
4)11kV Breaker maintanance
Modernization works at Following worksTest
5)CRM & Timer will be carried
of 66kV out under
Breakers R&M project.
by RT
220/66/11kV Receiving 1) Removal of the jumper which connects the CT and line
Station, Hoody, GR TECH PARK,PRESTIGE SHANTINIKETAN COMMERCIAL AND
side jack bus
RESIDENTIAL,EPIP FEW AREA,WHITEFIELD FEW AREA.
Bangalore East Taluk, Dismantling of the 3 Nos of CT equipments , structure and
O&M Whitefield Division Load will be affected. Load management has to be done by Concurrence given by AEE E-12
286 BMAZ 400kv SSC Division Bangalore Urban 8/2/2022 8/4/2022 10:00 16:00 6:00 foundation. 7/30/2022 26 MW
East BESCOM TL&SS KPTCL and BESCOM. Sub-division
District on Total Erection of the 3 Nos of new CT structure and foundation
Note: IT and Techpark loads will be taken on DG and balace load
Turnkey Basis and existing CT equipments.
will be affected
Removing from old C&R Panel and connecting to new C&R
66kV Prestige panel and relay and equipment testing
Shantiniketan
KONANUR, HALAUDARA, OBALAPURA, ALAGWADI, PALAKIHALLY,
3 CTAZ Chitradurga Chitradurga Rural 66/11 kV MUSS Sirigere 8/3/2022 8/3/2022 10:00 16:00 6:00 Emergency Quarterly maintenance work 7/30/2022 MADAKARIPURA, SIDDAPURA, SIRIGERE, MEL(BBH), CHIKKENAHALLI, NO
ALAGHATTA & CHEELANGI

115 CTAZ K.B Cross 66/11KV S/s, Thippur 8/3/2022 8/3/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance

116 CTAZ K.B Cross 66/11KV s/s, Nidasale 8/3/2022 8/3/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance

HUNASEKATTE, KODAGAVALLI, CHIKPURA.


HIPEOUNTANUR,BHEMASAMUDPA VADDARAPALYA,
66/11 kv MUSS
117 CTAZ 8/3/2022 8/3/2022 10:00 16:00 7 hrs emergency quarterly maintainance work BHEEMESHWARATEMPLE, TUREBAILU CAMP. un maintenance
Hireguntanuru
SEEBARANJY, BERAVARA-NJY, N BALLEKATTE,HOSAHALLI &
MALALI
HEGGERE, YEMMEHATTI, NALLIKATTE,
work
KOLAHAL NJY, HEGDEHAL,VIJAPUR,SHIVANAKERE,
66/11 kv MUSS NANDIHALU, BHADURGATTA,ADAVIGOLLARAHALLI NJY,
118 CTAZ 8/3/2022 8/3/2022 10:00 16:00 7 hrs emergency quarterly maintainance work
bharamasagara BHARAMASAGARA PAMERAHALLI, KOGUNDE SKM INDUSTRIAL
PEEDER
& KODIHALLI

66/11 kv MUSS KALGUNTE,BHALIGHATTE,LAKSHMISAGARA,VIJAYAPURA


119 CTAZ 8/3/2022 8/3/2022 10:00 16:00 7 hrs emergency quarterly maintainance work
Vijayapura NJY,MARADI ANJANEYA & CHIKKALAGHATTA

HUNASEKATTE, KODAGAVALLI, CHIKPURA,


66/11 kV MUSS HIREGUNTANUR,BHEMASAMUDRA,VADDARAPALYA,
120 CTAZ Chitradurga Chitradurga Rural
Hireguntanuru
8/3/2022 8/3/2022 10:00 16:00 6:00 Emergency Quarterly maintenance work 7/30/2022 BHEEMESHWARATEMPLE, TUREBAILU CAMP, SEEBARANJY,
NO
BERAVARA—NJY, N BALLEKATTE, HOSALLI & MALALI

HEGGERE,YEMMEHATTI, NALLIKATTE,
KOLAHAL NJY, HEGDEHAL, VIJAPUR, SHIVANAKERE, NANDIHALLI,
66/11 kV MUSS BHADURGATTA, ADAVIGOLLARAHALLI NJY, BHARAMASAGARA,
121 CTAZ Chitradurga Chitradurga Rural
Bharamasagara
8/3/2022 8/3/2022 10:00 16:00 6:00 Emergency Quarterly maintenance work 7/30/2022 PAMERAHALLI, KOGUNDE NJY, SKM INDUSTRIAL FEEDER
NO
& KODIHALLI

KALKUNTE, BALIGHATTE, LAKSHMISAGARA, VIJAPURA NJY, MARADI


122 CTAZ Chitradurga Chitradurga Rural 66/11 kV MUSS Vijapura 8/3/2022 8/3/2022 10:00 16:00 6:00 Emergency Quarterly maintenance work 7/30/2022 ANJANEYA & CHIKKALAGHATTA
NO

i) NHAI overhead Crossing New line Stringing and


incomung line of 66/11kV completion of balance bracing work including earthing. ü)
229 CTAZ Davanagere Chitradurga Bharamasagar Sub- 8/3/2022 8/3/2022 9:00 16:00 7:00 New Tower: - Erection of Tower No-4 MD+0 (NBT) Vikas
Station Tech Park design up to Cross Arm level up to Existing
220kV NBT bottom of conductor.

66 kv Antharasanahalli
4 CTAZ Tumkur All feeder 8/4/2022 8/4/2022 7:00 16:00 11hrs Constructoion 11kv DC line chelur,Hoskere ,Nandihalli,Hagalawadi
choluru Hosakere line

66/11KV S/s,
123 CTAZ K.B Cross 8/4/2022 8/4/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance
Santhemavathur

HanbarHoepet MUSS Harhar city MUSS, 66kV Gutnur MUSS a


5 CTAZ Davangere Davangere 8/5/2022 8/5/2022 11:00 16:00 7hrs Emergency maintainance work
Polyilbers
Duration of LC request

Name of the Name of the KPTCL Name of the BESCOM Name of the BESCOM Date on which last
Sl no
KPTCL Circle Division Circle Division
Sub Division Name of the station/Line Feeder Date Time Reason for availing LC
LC was approved
Areas Affected Load Affected (MW) Wheather alteranate Power Supply Arranged or not Remarks Consent

From To From To Duration

220KV Nelamangala -2 Consent is given to Avail LC on


124 BRAZ DBPura BRC Kengeri Nelamangala 8/5/2022 8/5/2022 11:00 15:00 4:00 Quarterly maintenance works of the station. 7/30/2022 No Load Affected - Load will be Taken on 220KV Nelaqmangala-1 line
Line 05.08.2022

66kV Guttur Industrial


TLM Sub-Division, Harihar-Hospet MUSS, Harihar city MUSS, 66kV Guttur MUSS &
125 CTAZ Davangere line & 66kV Harihar- 8/5/2022 8/5/2022 11:00 16:00 5:00 Emergency Maintenance work 7/30/2022
KPTCL,Davangere Polyfibers
Hospet line

i) NHAI overhead Crossing New line Stringing and


incomung line of 66/11kV completion of balance bracing work including earthing.
230 CTAZ Davanagere Chitradurga Bharamasagar Sub- 8/5/2022 8/5/2022 9:00 16:00 7:00 ii) New Tower: - Erection of Tower No-4 MD+0 (NBT) Vikas
Station Tech Park design up to Cross Arm level up to Existing
220kV NBT bottom of conductor.
Renovation and Following works will be carried out under R&M project.
Modernization works at 1) Removal of the jumper which connects the CT and line
Vishweshwaraiah Industrial Area, Asraya Lay out, Green Domain
220/66/11kV Receiving side jack bus
lay out. Brigade Metropolis Apartments,
Station, Hoody, Bangalore Dismantling of the 3 Nos of CT equipments , structure and
Transmission O&M Whitefield Division Load will be affected. Load management has to be done by Concurrence given by AEE E-12
287 400kv SSC Division East Taluk, Bangalore 8/5/2022 8/7/2022 10:00 16:00 6:00 foundation. 7/30/2022 17 MW
(Works) Circle East BESCOM TL&SS KPTCL and BESCOM. Sub-division
Urban District on Total Erection of the 3 Nos of new CT structure and foundation
Note: IT and Techpark loads will be taken on DG and balace load
Turnkey Basis and existing CT equipments.
will be affected
Removing from old C&R Panel and connecting to new C&R
66kV Brigade Metropolis panel and relay and equipment testing 6 MW of 66/11 kV
Divyasree Tech park
For Carrying out Quarterly Maintenance work. Attending MUSS
East circle , South Whitefield Division 66/11kV Divyashree Tech MRS Tech park,HUAWEI, Divyasree tech park and Minor
6 BMAZ SOUTH Hoody 8/6/2022 8/6/2022 10:00 15:00 5:00 hot spots observation on 66kV EPIP line bay and 66kV 7/30/2022 2 MW of 66/11 kV
Circle and Koramangala Park MUSS irrigation.
minor irrigation line bay. Minor irrigation.
23 MW of 66/11 kV
kachmaranahalli

66 kv Antharasanahalli
7 CTAZ Tumkur All feeder 8/6/2022 8/6/2022 7:00 18:00 11hrs Constructoion 11kv DC line chelur,Hoskere ,Nandihalli,Hagalawadi
choluru Hosakere line

66/11KV S/s,
126 CTAZ K.B Cross 8/6/2022 8/6/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance
Kempanhalli

AIMANGALA,BARAMPURA,MARADIDEVIKERE,KOVERAHATTI,KAL
66/11 kv MUSS
127 CTAZ 8/6/2022 8/6/2022 10:00 16:00 7 hrs emergency quarterly maintainance work VATTI,I, MARADIHALL,
Aimangala
BURUJINAROPPA AND SURROUNDING AREAS

66/11 kv MUSS J N N Kote,Gollanakatte, PallavagereJ C hali and the Burounding


128 CTAZ 8/6/2022 8/6/2022 10:00 16:00 7 hrs emergency quarterly maintainance work
KOTTE areas.

Consent is Given to avail LC on


06.08.2022.( Note: if any exams &
WONDERALLA, HEJJALLA, BANNIKUPPE, GOMTHI, KADUMANE,
66/11kV Sub station emergency programs comes near to
129 BRAZ Somanahalli Ramangara Ramanagara 8/6/2022 8/6/2022 10:00 16:00 6:00 To carry out periodical 2nd quarterly maintenance work 7/30/2022 MANCHANAYAKANAHALLI, HOSSADODDI, AVAREGERE, KHB 10MW No
HEJJALLA that date I,e 06.8.2022 , the LC
HAMPAPURA
date should change /postpone to
another date )

Load will be Taken on 220KV Nelaqmangala-1 line and Consent is given to Avail LC on
130 BRAZ DBPura BRC Kengeri Nelamangala 220KV Begur Line 8/6/2022 8/8/2022 11:00 16:00 5:00 Quarterly maintenance works of the station. 7/30/2022 No Load Affected
Nelamangala-2 Line 08.08.2022

31.5MVA power
Whitefield and transformer -02 of 2MW load will be affected and Alternative power suplly
131 BMAZ South GIS DIVISION East and South 8/6/2022 8/6/2022 13:00 16:00 3:00 Quarterly Maintenace work 7/30/2022 F14-Hoody 2MW MOM attached
indirangara 220/66/11kV ITI GIS arranged for remaining feeders from BESCOM
station

Chilur, Malali, Kuruva, TG Halli, Kengatte, Gadekatte, Givinkovi,


132 CTAZ Benkikere Channagiri Chilur 8/6/2022 8/6/2022 10:00 16:00 6:00 Quarterly maintenance works 7/30/2022 4 MW No LC approval not issued since April
Kadadkatte, MG Halli and 66 kV Mallapura line

AIMANGALA, BARAMPURA, MARADIDEVIKERE, KOVERAHATTI,


133 CTAZ Chitradurga Hiriyuru Rural 66/11 kV MUSS Aimangala 8/6/2022 8/6/2022 10:00 16:00 6:00 Emergency Quarterly maintenance work 7/30/2022 KALVATTI, MARADIHALLI, BURUJINAROPPA AND SURROUNDING NO
AREAS

134 CTAZ Chitradurga Chitradurga Urban 66/11 kV MUSS J N KOTE 8/6/2022 8/6/2022 10:00 16:00 6:00 Emergency Quarterly maintenance work 7/30/2022 J N Kote,Gollanakatte,Pallavagere,J C halli and the surrounding areas. NO

For Carrying out Quarterly Maintenance work. Attending Whitefield, Gunjur, Ramgundanahalli, Kachmaranahalli, Varthur-
East circle , South Whitefield Division, 66/11kV
231 BMAZ SOUTH Hoody 8/6/2022 8/6/2022 10:00 15:00 5:00 hot spots observation on 31.5MVA Transformer-1 & 2 and 7/30/2022 gunjur main road, Alasahalli road, Balegere, Hagadur, 14 MW
Circle HSR, Koramangala Kachamaranahalli MUSS
66kV Divyashree Tech Park line. Madhuranagar, Trisul build tech

Wind Tunnel Road, Murugeshpalya, SR Layout, Runway Transformer1 - 2 MW,


LC may be availed, Interuption
232 BMAZ SOUTH Hoody BMAZ(South) Koramangala 66/11KV Golf Link 8/6/2022 8/6/2022 10:00 13:00 3:00 Quarterly maintenance of Bank-1 & feeders 7/30/2022 coumpound road, Vinayaka Nagara, Ashok Avenue road, KR Transformer2 - 2.9 Change overs available for all feeders.
paper notification to be given
Garden, Domlur Outer ring road, Amarjyoti Layout west wing. MW

Fidelity, Philips, Icubator, IBM D4 Block, IBM D1 & D2 Block, IBM


1. To carry out Maintenance work of incoming line, outgoing
D3 Block, F2 Block, L6 Siemens, Manyatha Residency, B.T.S
line, Transformer Bays, 66kV bus Gos,11kV bus and
Loucent, Anz H Block, C4 Block, Godrej apartment, Hebbal
breaker maintenance. Peak Load of Station during weekend is 20MW, Load change
Shivajinagar Kempapura, Vinyaka Layout, Chirranjeevi Layout, Venkategowda
66/11kV Manyatha Tech 2. For attending Hotspot works. over of 4MW shall be done by BESCOM to neighboring
234 BMAZ North Hebbal East & North division & Hebbal 8/6/2022 8/6/2022 10:00 16:00 6:00 7/30/2022 Layout, JNC, L5 Nokia Block, G1 Block, MFAR, Madhuvana M2 16MW Consent is given work can be taken
Park 3. For carrying out IR test of all equipements like CT's, PT's, stations. 1) During LC peroid 16MW of load will be effected
division Block, Rachenahalli, Srirampura, Chamundeshwari Layout, Rayal
LA's, Transformers, 66kV Breakers, 11kV Breakers, Wall for 7:30 hrs during 66kV & 11kV bus & PT maintainence
Enclave, Mestri Palya, Thanisandra, SNN Clermont apartment,
entry bushings and 11kV Bus.
karle, B.Narayanapura Cross, BDS Layout, Mantri Lithos, Coffee Load on 20MVA Tr1- 5 MW, Tr2 -15MW, Tr3 - 7MW
4. For conducting Tan-Delta.
Board layout, fathima layout, Amarjhothi layout, Mariyanna Palya. `
To arrest oil leakage from top cover bolts and nuts of 20MVA
2MW of Tr-2 load and 2MW of Tr-1 load will be shifted on
Shivajinagar Tr-2 by replacing top gasket.
66/11kV Manyatha Tech 66kV Yellarbande by Bescom during LC
235 BMAZ North Hebbal East & North division & Hebbal 8/6/2022 8/10/2022 10:00 16:00 6:00 work order no: 926/L11/HBL/74-116/813 dtd 23.03.2022 7/30/2022 NIL NO LOAD AFFECTED Consent is given work can be taken
Park 13 MW of Tr-2 load will be taken on Tr-1 using Bus Coupler
division Work Award No : SEE/Tr(M)/BMAZ(N)/EE(O)/AEE-2/F-
71(6)/21-22/13517-20 Dtd 23.03.2022.
Total load on Tr-1 will be 16 MW after changeover, Tr3 -
7MW

1) CRM & Timer Test of all 66kV Breakers Peak load-20MW,


Sarjapura, Cessana garden, Outer ring road, Central mall,Exora
HSR Layout & 66/11kV Shobha 2)Quarterly maintenance of 2x31.5MVA Transformers, load changeover- LC was requested on in the month of May but LC may be availed, Interuption
288 BMAZ South HSR Layout South 8/6/2022 8/6/2022 10:00 16:00 6:00 7/30/2022 Business park, Shobha Apartments, Salarpuria Softzone, Load Changeover-12MW
Koramangala Apartment S/s 66kV Islators, 66kV Bays & 66kV Breakers. 12MW, was not approved paper notification to be given
Thakshasheela Health care
3)19Nos of 11kV Switchgears. load affected-8MW

66kV Somanahalli-
For carrying out periodical maintenance works as per
ISCKON
O&M Division, maintenance schedule for 2nd quarter. Load of 66kV No load will be
289 BMAZ SOUTH Somanahally BMAZ[S] [Subramanyapura line-1] 8/6/2022 8/6/2022 10:00 16:00 6:00 7/30/2022 No load will be affected. No load will be affected.
BESCOM, Kengeri ISCKON station may be changed over to 220kV affected.
bay at 220/66/11kV R/S,
Subramanyapura station. No load will be affected.
Somanahalli, Bengaluru.

31.5MVA power
Whitefield and transformer -01 of 1) Quarterly Maintenace work . 2) For attending 2MW load will be affected and Alternative power suplly
290 BMAZ South GIS DIVISION East and South 8/6/2022 8/6/2022 10:00 13:00 3:00 7/30/2022 F-11 Devasandra 2MW MOM attached
indirangara 220/66/11kV ITI GIS Thermography observations arranged for remaining feeders from BESCOM
station

Yes. 220kV 'A' station will be shifted to 220kV NRS, 66kV


To carry out Condition Monitoring works on 220kV and
BMTC will be shifted to 220kV NIMHANS, 66kV B station will
Sir M V 22/66/11kV EDC 66kV GIS Modules (4 line bays+2 Transformer bays+ 2 PT No load will be
291 BMAZ South GIS DIVISION EAST Indiranagar 8/6/2022 8/6/2022 10:00 16:00 6:00 7/30/2022 No load will be affected. be shifted on 220kV HAL and 66kV Austin will be shifted on MOM attached
station bay+1 BC bay in 220kV GIS side and 11 bays in 66kV GIS affected.
220kV Koramangala. All 11kV Loads will be changed over at
side).
BESCOM side.
Consent is given work can be taken
Consent is given work can be
Duration of LC request taken F 2 LG Halli 100% Change
over from RMV F14 feeder
F 4 80ft Road Adithya Kalyana
Name of the Name of the KPTCL Name of the BESCOM Name of the BESCOM Date on which last Mantapa 100% Change over from
Sl no
KPTCL Circle Division Circle Division
Sub Division Name of the station/Line Feeder Date Time Reason for availing LC
LC was approved
Areas Affected Load Affected (MW) Wheather alteranate Power Supply Arranged or not Remarks RMV F1Consent
& F8 feeder
F 7 SBM Colony 100% Change over
from IISc F6 and RMV F4 feeder
From To From To Duration F 5 Pampa Nagar No change over.
Fdr 4: Hesarghata Exp
Pampa Nagara, Mohan Kumar
Fdr 5:Chikkabanavara
Nagara, B K Nagara Akkiyappa
Fdr 6:Bagalakunte
Garden Mathikere F5, F6 & F9
Fdr 8:S.Gatta
For carrying out Yearly maintenance works for attending feeders change over is not possible,
Fdr 9: BWSSB During the LC Period, Total 12MW Loads will
Jalahalli Division, maintenance and alignment of Bus GOS-7 Nos, 11kV Soladeveanhalli, Hesarghatta, Byalkere, Acharya college if Incoming change over is provide
292 BMAZ North SRS Peenya, KPTCL BMAZ North Soladavenahalli 8/6/2022 8/6/2022 11:00 15:00 4:00 7/30/2022 F10-Mallige Solar feeder 12MW be affected as no feeders have changeover
N9 Sub-division Switchgear, 66kV CT & PT, 66kV Breakers, Cpacitor Bank surrounding areas. by KPTCL, from hebbala station
Fdr 1:St Auxiliary option.
maintenance. C/o of F5, F6 & F9 can be done.
Fdr 2: Hesarghatta
F 6 Yeshwanthpura No change
Fdr 3:Shivakote
over. K N Extension, Gokula, HMT
Fdr 7:Silvepura
main road, Yeshwantha pura main
Fdr 11: Soladevanhalli Express
road, Mathikere
220/110/11KV R/S KB F 9 VR Layout No change over. V R
135 CTAZ K.B Cross 8/7/2022 8/7/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance
Cross lay out, HMT Lay Out, JP Park, MK
Nagara, SBM Colony, Gokula F8
Bandappa Garden No Change over,
MF 10 Sundarnagar change over to
GF 11 MSR Hotel, MF11 Sriram
sadana change over to GF 7 MES
136 CTAZ K.B Cross 66/11KV S/s, Anchepalya 8/7/2022 8/7/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance Road)

Ramanagara & Magadi & 66/11kV Tavarekere Tavarekere and Nelamangala Subdivision areas feeding from Consent is given to avail LC on
137 BRAZ Nelamangala 8/7/2022 8/7/2022 10:00 16:00 6:00 2nd Quarterly & Half Yearly maintenance work 7/30/2022 12MW No
Bangalore Rural Nelamangala Substation 66/11kV Tavarekere Substation 07.08.2022

Ramanagara & 66/11kV Kodigehalli Tavarekere and K4 Subdivision areas feeding from 66/11kV Consent is given to avail LC on
138 BRAZ Nelamangala Magadi & Kengeri 8/7/2022 8/7/2022 10:00 16:00 6:00 2nd Quarterly & Half Yearly maintenance work 7/30/2022 12MW No
Bangalore West Substation Kodigehalli Substation 07.08.2022

Alur, Makali, Dasanpura, Madanyakanahalli, Mantri Layout,


Consent is given to Avail LC on
139 BRAZ Nelamangala BRC Nelamangala 66/11kv Substation Alur 8/7/2022 8/7/2022 10:00 16:00 6:00 Second Quarterly and Annual maintenance 7/30/2022 Gowdarahalli, Siddanahalli, BDA Flats, Nagarur,APMC, TATA 12MW No Consent is given to Avail LC on 07.08.2022
07.08.2022
Housing,Dedicated feeder to Himalaya drug company.

66/11kv Substation 11kV feeders Evacuating from 66/11kV Nelmangala Substation Consent is given to Avail LC on
140 BRAZ Nelamangala BRC Nelamangala 8/7/2022 8/7/2022 10:00 16:00 6:00 Second Quarterly and Annual maintenance 7/30/2022 18MW No
Nelmangala coming under Nelamangala and Dabaspet Subdivisions, BESCOM 07.08.2022

66/11kv Substation 11kV feeders Evacuating from 66/11kV Thyamagondlu Consent is given to Avail LC on
141 BRAZ Nelamangala BRC Nelamangala 8/7/2022 8/7/2022 10:00 16:00 6:00 Second Quarterly and Annual maintenance 7/30/2022 18MW No
Thyamagondlu Substation coming under Dabaspet Subdivisions, BESCOM 07.08.2022

31.5MVA power
Whitefield and transformer -03 of Alternative power suplly arranged for all feeders from
142 BMAZ South GIS DIVISION East and South 8/7/2022 8/7/2022 11:00 16:00 5:00 Quarterly Maintenace work 7/30/2022 Nil Nil MOM attached
indirangara 220/66/11kV ITI GIS BESCOM
station

143 CTAZ Benkikere Channagiri Kattige 8/7/2022 8/7/2022 10:00. 16:00 6:00 Quarterly maintenance works 7/30/2022 Kattige and IPP solar 20 MW & 2 MW 5 MW LC approval not issued since April

Savalanga, Ganjeenahalli, Machigondanahalli, Chinnikatte,


144 CTAZ Benkikere Channagiri Sowlanga 8/7/2022 8/7/2022 10:00 16:00 6:00 Quarterly maintenance works 7/30/2022 4 MW No LC approval not issued since April
Mussenalu, Madhapura, Jayanagara, Kodthalu, Kyathinkoppa

i) New Tower: - Erection of Tower No-5 MD+6(NBT)


Vikas Tech Park design up to Cross Arm level up to Existing
incomung line of 66/11kV
220kV NBT bottom of conductor.
236 CTAZ Davanagere Chitradurga Bharamasagar Sub- 8/7/2022 8/7/2022 9:00 16:00 7:00
ii) Dismantling of Existing 220kV NBT & 66kv tower and
Station
New tower-05 & 04 Erection of Balance Portion. iii) and
NHAI Crossing Stringing of Existing line conductor.

incomung line of 66/11kV


i) New line Stringing and completion of Balance Bracing
237 CTAZ Davanagere Chitradurga Bharamasagar Sub- 8/7/2022 8/7/2022 9:00 16:00 7:00
work including earthing.
Station

66/11kV Ranganadoddi Consent is given to avail LC on


293 BRAZ Kanakapura Kanakapura Kanakapura 8/7/2022 8/7/2022 10:00 16:00 6:00 Quaterly maintenance work 7/30/2022 Harohalli Town, Harohalli Industrial area & surounding villages. 24.6 NO
S/s 07.08.2022

66kV TG Halli Line and


66/11kV 12.5MVA Power
2nd Quarterly
Second & Half
Quarterly andYearly
Annual maintenance work
maintenance and for
of 220/66/11kv Consent is given to avail LC on
294 BRAZ Nelamangala Ramanagara Magadi Transformer at 8/7/2022 8/7/2022 10:00 16:00 6:00 7/30/2022 66/11kV TG Halli, VG Doddi and Tavarekere Substations 20MW No
attending
R/S hotline
Dabaspet for observations
FY-2022-23. 07.08.2022
220/66/11kV Magadi
Substation 1. 220kv and 66kv bus-preventive Maintenance and A. Areas feeding from Down streams of 220/66/11kv R/s
attending critical hotspots. Dabaspet.
2. 100MVA TR1 & TR2- 1st Quaterly and Annual preventive 1.66/11 kv Nelamangala
maintenance and attending critical hotspot observation. 2. 66/11 kv Thyamagondlu
3. 31.5MVA TR1 & TR2- 1st Quaterly and Annual preventive 3. 66/11 kv T Begur
220/66/11 kv R/S Consent is given to Avail LC on
295 BRAZ Nelamangala BRC Nelamangala 8/7/2022 8/7/2022 10:00 16:00 6:00 maintenance and attending critical hotspot observation. 7/30/2022 4. 66/11 kv Hirehalli 130MW No Consent is given to Avail LC on 07.08.2022
Dabaspet 07.08.2022
4. 220kv and 66kv Line bays-1st Quaterly and Annual 5. 66/11 kv Averahalli
preventive maintenance and attending critical hotspot 5. 66/11 kv S K Steel(EHT)
observation. 6. 66/11 kv Jindal(EHT).
Vidhana soudha 5. 11kv GOS- 1st Quaterly and Annual preventive B. Dabaspet
City Market, Sub Division
Avenue road, Area
BVK feeding
iyengarfrom
road, RT street, CT street,
Division (W5, W3, maintenance and attending critical hotspots, replacement of 1.220/66/11kv R/s Dabaspet
Chikkapet, Nagarathpet, SP road, Town hall, JC road, Minerva
Quarterly maintenance
11kv feeders workweaken
GOS contacts, of 66kVjumps
Line, Bus and 11kV
and pothead
West, East and W4), RR nagar Circle, KG road, Gandhi nagar, Masidi, Mysore road police During LC period, 8MW of load will be changed over to other 4MW load will be affected after changeover of
296 BMAZ North NRS 66/11 kV Victoria Station 8/7/2022 8/7/2022 10:00 16:00 6:00 Bus bar
repair and to attend hot spot in 66kV Transformer 2
work. 7/30/2022 4 LC may be availed
South Circle Division (W2), quarters, Gori palya, Binny pet, New tharagu pet, Chamarajpet, Stations by BESCOM loads to other Stations
isolator at 66/11kV Victoria Station.
Jayanagar Division AM road, Kalasipalya, Victoria Hospital, KIMS, Shankarpuram,
(S2) Dental college RMU, SJ park RMU

150MVA Power Transformer 1& 2 GOS


150MVA Power Transformer 1& 2 GOS Overhauling for Total Naganathapura
Overhauling for 220kV Somanahalli Line BUS
220kV Somanahalli Line BUS GOS & Line GOS , 220kV Peak load-166MW,
GOS & Line GOS , 220kV Side HSR Line BUS LC may be availed, Interuption
297 BMAZ South HSR Layout South HSR Layout 220kV Naganathpura RS 8/7/2022 8/7/2022 10:00 16:00 6:00 Side HSR Line BUS GOS, 150MVA Power Transformer -1 7/30/2022 Nil Load changeover- Load Changeover-68MW
GOS, 150MVA Power Transformer -1 Bus GOS, paper notification to be given
Bus GOS, CRM for Somanahalli Bay .Periodical Bay 68MW
CRM for Somanahalli Bay .Periodical Bay
Maintenance Load affected -nil
Maintenance

20 MVA power
transformer -03 of To carry out Quarterly Maintenace work and attending Alternate power arranged for 2.8 MW, remaining 3.1 MW
298 BMAZ South GIS DIVISION North N4 BESCOM 8/7/2022 8/7/2022 10:30 14:30 4:00 7/30/2022 F-11 (Bajaj packers) and F-9 (SLV Industrial area) 3.1 MW MOM attached Consent is given work can be taken
220/66/11kV Brindhavan Thermovision hotspots observation have no alternate source.
GIS station
During the time of LC, 16MW of load can be
F4 - New BEL Road
changed over to other stations by BESCOM
F5-MSR Ind. Estate
staff and 10MW load will be affected at RMV
Malleswaram,Jalah F8-ISRO & LG Halli
MUSS Consent is given work can be taken
alli,Hebbal Replacement of flashed over 66kV incoming line "R" Phase F9-IISC Layout Alternate supply will be arranged for around 13MW by
BMAZ North Only F12 feeder feeding to c9 sd
299 SRS Peenya, KPTCL Bangalore North Additional central 66/11kV RMV MUSS 8/7/2022 8/7/2022 11:00 15:00 4:00 current transfomrer and also for carrying out Yearly 7/30/2022 F12-Devinagara 10MW BESCOM O&M staff for the feeders which have change overs
Circle Also during LC period replacement of load change is possible from Attur
(C2,C6,C4,C9 Sub maintenance works F14-New feeder Chikkamarenahalli from other stations
flashedover CT and station maintenance work yelahanka Stn
division) Partial loads of the above mentioned feeder will be affected as per
will be carried out viz Bus GOS 6Nos, 11kv
BESCOM officials.
Switchgear, 66kV PT, 66kV CT, 66kV Breaker,
66kV IISc load will be affected
at 66/11kV RMV MUSS

RSD Davangere & srs yaragunta &


8 CTAZ Davangere 8/8/2022 8/8/2022 10:30 16:00 5:30 2nd quarter maintenance 7/30/2022 surrounding Obajjihalli village
Telagi neelagunda line

Anaji, Kandanakom, Aluru, Rudranakntte nakntte


9 CTAZ Davangere All 11kv feeders 8/8/2022 8/8/2022 10:30 16:00 7hrs 2nd quarter Maintainence
surroundings area

10 CTAZ Davangere All 11kv feeders 8/8/2022 8/8/2022 10:30 16:00 7hrs 2nd quarter Maintainence surroud ing Obanhalli vilage
Duration of LC request

Name of the Name of the KPTCL Name of the BESCOM Name of the BESCOM Date on which last
Sl no
KPTCL Circle Division Circle Division
Sub Division Name of the station/Line Feeder Date Time Reason for availing LC
LC was approved
Areas Affected Load Affected (MW) Wheather alteranate Power Supply Arranged or not Remarks Consent

From To From To Duration

11 CTAZ Davangere All 11kv feeders 8/8/2022 8/8/2022 9:30 16:00 7hrs 2nd quarter Maintainence Surrounding attigere village

12 CTAZ Davangere All 11kv feeders 8/8/2022 8/8/2022 9:30 16:00 7hrs 2nd quarter Maintainence Surrounding angodu village

13 CTAZ Davangere All 11kv feeders 8/8/2022 8/8/2022 9:30 16:00 7hrs 2nd quarter Maintainence Surrounding Maykonda village Limits

56kV Bilichodu, 66kV


Plagate, 66kV Sokke, 56kV Bilichodu, 66kV Plagate, 66kV Sokke, 66kV Mellelatte, 66kV
14 CTAZ Davangere 8/8/2022 8/8/2022 10:30 16:00 7hrs Emergency maintainance work
66kV Mellelatte, 66kV K»daji sub-statio
K»daji sub-statio

15 CTAZ Davangere shyagnle MUS 8/8/2022 8/8/2022 10:30 14:30 4hrs Emergency maintainance work shyagnle MUS

145 CTAZ K.B Cross 66/11KV S/s, Jiddigere 8/8/2022 8/8/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance

Consent is given work can be


taken F-28 BYRAPPA RMU 30 %
Change Over from Shobha F5 and
F12 Rajkumar Road, Suguna
Load will be Taken on 220KV Nelaqmangala-1 line and Consent backside
Hospital is given to Avail6th
road, LCand
on
146 BRAZ DBPura BRC Kengeri Nelamangala 220KV KIADB Line 8/8/2022 8/8/2022 11:00 15:00 4:00 Quarterly maintenance works of the station. 7/30/2022 No Load Affected
Nelamangala-2 Line 5th cross08.08.2022
Prakash Nagara.
F-26 SAI MANDIR RMU 60 %
Change Over from IISc F7 and
Nandini F4 VV School Road,
Manjunathnagara, Shivanagara, Gayithrinagara, Prakash nagara, Mariyappana Palya.
LN pura Subramanyanagara, Vijayanagara, Rajajinagara 2nd During LC Period 35MW 1oad will be affecte 35MW load will be affected after changeover of F7 - II Block & C1 100% Change
220/66/11 kV NRS R/s over from Nandini F9 feeder
147 BMAZ North NRS West and North Rajajinagara 8/8/2022 8/8/2022 10:00 16:00 6:00 Quarterly maintenance 7/30/2022 block, 6th Block Rajajinagar, Amarjyothi |Nagara, Saraswati 35 after rearranging of loads on other stations as per concern= loads to ot
station F11 - Prakashnagara 100% Change
Nagara, Vinayaka layout, Agrahara, dasarahali, Indranagara, BESCOM officials. stations
Sankarmata over from IISc F5 and Shobha F6
feeders.
F10 - SUBRAMANIYA NAGAR 100%
Change over from Nandini F4
Vidhana soudha During LC Period 20MW 1oad will be affecte feeder
Telecom layout, RPC Layout, Hampi Nagar, Agrahara, dasarahali,
148 BMAZ North NRS West and North Division (W5, W3, 66/11 kV Telecom layout 8/8/2022 8/8/2022 10:00 16:00 6:00 Quarterly maintenance 7/30/2022 20 after rearranging of loads on other stations as per concern= Radial sourse from NRS F4 - DEVAIAH PARK 100% Change
Indranagara
W4), Rajaji nagar BESCOM officials. over from IISc F7, Shobha F6,
Nandini Lay put F4, A station F23
feeders.
F25 - TVS SUJUKI SHOW ROOM
100% Change over from IISc F7,
Nandini Lay put F4 feeders.
149 CTAZ Davangere Angodu Mellekatte 8/8/2022 8/8/2022 10:30 16:00 5:30 2nd quarter maintenance 7/30/2022 Anaji, Kandanakovi, Aluru, Rudranakatte surrounding areas Brigade Station F1,F2,F5,F6,F9,F1
No change over. Brigade Gate Way
Appartments
Brigade F7 100% Change over from
IISc F7,
Brigade F4 100% Change over from
TLM Sub-Division, 66kV Ucchangidurga 66kV Bilichodu, 66kV Pallagatte, 66kV Sokke, 66kV Mellekatte, IISc F4 and IISc F3,
150 CTAZ Davangere 8/8/2022 8/8/2022 10:30 16:00 5:30 Emergency Maintenance work 7/30/2022 Brigade F3 75 % Change Over
KPTCL,Davangere Outgoing line 66kV Kadajji sub-stations
From Shobha F6 Prakasha Nagara,
1 st, 2nd, 3rd cross Suguna
Hospital back side road,
F-28 BYRAPPA RMU

151 CTAZ Davangere Angodu Attigere 8/8/2022 8/8/2022 9:30 16:00 6:30 2nd quarter maintenance 7/30/2022 surrounding Attigere village

152 CTAZ Davangere Angodu Angodu 8/8/2022 8/8/2022 9:30 16:00 6:30 2nd quarter maintenance 7/30/2022 surrounding Angodu village

153 CTAZ Davangere Angodu Mayakonda 8/8/2022 8/8/2022 9:30 16:00 6:30 2nd quarter maintenance 7/30/2022 surrounding Mayakonda village limts

Peak load-24MW,
Replacement of old ERL make 11kV switchgears with New load changeover will
HSR Layout & 66/11kV Electronic City 10-08-2022 11kV DAS/SCADA compatible MEI make switchgears Electronic City Ph-2, Veersandra, Ananth Nagara, be arranged by LC may be availed, Interuption
238 BMAZ South HSR Layout South 8/8/2022 10:00 16:00 6:00 7/30/2022 Load Change Over-24MW GCW Work
Chandapura Ph-2 Sec-2 (Malgudi) S/s ( pertaining to Trf-1 i.e. Bank-1, F1, F2, F3, F4, F5, F6, F14 Doddanagamangala BESCOM as per paper notification to be given
along with Bus Coupler) MOM. No load will be
affected

220kV Nelamangala- For Quarterly Maintenance works & To clear the emergency No load will be 220kV Anchepalya have alternate feeding from 220kV Consent is given to avail LC on
300 Ramanagara Nelamangala Ramanagara Magadi 8/8/2022 8/8/2022 11:00 14:00 3:00 7/30/2022 ---
Anchepalya Jungles grown in the line corridor. affected Magadi receiving station. 10.08.2022

66 kv Antharasanahalli
16 CTAZ Tumkur All feeder 8/10/2022 8/10/2022 7:00 16:00 11hrs Constructoion 11kv DC line chelur,Hoskere ,Nandihalli,Hagalawadi
choluru Hosakere line

Harihara Town, Water Supply, KHB Colony,


66/11kV MUSS Caryingout 2nd
154 CTAZ Harihara 8/10/2022 8/10/2022 10:00 16:00 7hrs Industrial Area, Karlahali, Harhara Rural, Deeturu. arath,
Guttur Quarter Maintenance
Ganganarasi, Doggalli

Harihara Town,Water Supply,KHB coloney,Industrial Area


155 CTAZ Davanagere Davanagere Harihara 66/11kv MUSS Guttur 8/10/2022 8/10/2022 10:00 16:00 7hrs Quaterly maintenance works
Karulhalli,Harihara Rural,Deeturu

66/11KV S/s,
156 CTAZ K.B Cross 8/10/2022 8/10/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance
Huliyurdurga

MADANAYAKANAHALLI, C G HALLI, YELAVARTHI, MUDDAPURA,


66/11 kv MUSS
157 CTAZ 8/10/2022 8/10/2022 10:00 16:00 7 hrs emergency quarterly maintainance work HOSAGALLAHATTI RAYANAHALu,SUARANAHALLY,INAHALLI AND
madanayakanahalli
SURROUNDING APPAS

BOMMAKKANAHALLI,Kunaberu ,u Avalenahalli,
66/11 kv MUSS
158 CTAZ 8/10/2022 8/10/2022 10:00 16:00 7hrs emergency quarterly maintainance work Doddaghatta,Turuvanuru,kariyammanashetti,kotehatti,hunasekat
turuvanur
te,Pelaraharty, and the surrounding area

Consent is Given to avail LC on


10.08.2022.( Note: if any exams &
66/11kV Sub station Ramanagara Town, Janapadaloka, Hunsenahalli, K.P.Doddi, emergency programs comes near to
159 BRAZ Somanahalli Ramangara Ramanagara 8/10/2022 8/10/2022 10:00 16:00 6:00 To carry out periodical 2nd quarterly maintenance work 7/30/2022 14MW No
RAMANAGARA Vaderahalli, Bilagumba. that date I,e 10.8.2022 , the LC
date should change /postpone to
another date )
Duration of LC request

Name of the Name of the KPTCL Name of the BESCOM Name of the BESCOM Date on which last
Sl no
KPTCL Circle Division Circle Division
Sub Division Name of the station/Line Feeder Date Time Reason for availing LC
LC was approved
Areas Affected Load Affected (MW) Wheather alteranate Power Supply Arranged or not Remarks Consent

From To From To Duration

Consent is given to avail LC on


160 BRAZ Nelamangala Ramanagara Magadi 66/11kv Hullenahalli 8/10/2022 8/10/2022 10:00 16:00 6:00 Preventive quartely maintainance 7/30/2022 Kudur subdivison 7 MW Not
10.08.2022

Consent is given to avail LC on


161 BRAZ Nelamangala Ramanagara Magadi 66/11kv Kudur 8/10/2022 8/10/2022 10:00 16:00 6:00 Preventive quartely maintainance 7/30/2022 Kudur subdivison 8 No
10.08.2022

Consent is given to avail LC on


162 BRAZ Nelamangala Ramanagara Magadi 66/11kv Srigiripura 8/10/2022 8/10/2022 10:00 16:00 6:00 Preventive quartely maintainance 7/30/2022 Kudur subdivison 5 No
10.08.2022

MADANAYAKANAHALLI,C G
66/11 kV MUSS
163 CTAZ Chitradurga Chitradurga Urban 8/10/2022 8/10/2022 10:00 16:00 6:00 Emergency Quarterly maintenance work 7/30/2022 HALLI,YELAVARTHI,MUDDAPURA,HOSAGOLLARAHATTY,RAYANAHALLI, NO
Madanayakanahalli
SURANAHALLY,INAHALLI AND SURROUNDING AREAS.

Bommakkanahalli, Kunabevu,Avalenahalli,Doddaghatta,
164 CTAZ Chitradurga Chitradurga Rural 66/11 kV MUSS Turuvanur 8/10/2022 8/10/2022 10:00 16:00 6:00 Emergency Quarterly maintenance work 7/30/2022 Turuvanur,Kariyammanahatti,Kotehatti,Hunasekatte,Pelarahatty and the NO
surrounding areas.

Harihara Town, Water Supply, KHB Colony, Industrial Area,


165 CTAZ Guttur Division Harihara 66/11KV MUSS Guttur 8/10/2022 8/10/2022 10:00 16:00 6:00 Carryingout 2nd Quarter Maintenance 7/30/2022 Karlahalli, Harihara Rural, Deeturu, Sarathi, Ganganarasi,
Doggalli

220kV R/s Gowribidanur and connected stations (AFTL IPP)


1.6611kV
V G Doddi,S/s Thondebhavi
Dabguli, 2. 66/11kV
Gavinagamangala, S/s Manchenahalli
Ajjanahalli, Gerehalli, 3. Consent is given to avail LC on
301 BRAZ Nelamangala Ramanagara Magadi 66/11kv V G Doddi 8/10/2022 8/10/2022 10:00 16:00 6:00 Quaterly Maintenance 7/30/2022 66/11kV S/s Gundlukottur 4.66/11kV S/s Gudibande 4MW No
Atthimgere 10.08.2022
5.66/11kV S/s D palya 6.66/11kV S/s
Vidhurashwatha(Greenergy solar) 7.66/11kV S/s Ramapura 8.
66/11kV S/s Mandikal9. 66/11kV S/s Theriyur,
220Kv R/s Mittemari R/s and connected
stations 1.66/11kV S/s Somanathapura, 2.66/11kV S/s
110-140MW(GBDR) Alternate power supply will not be arranged as the
220/66/11kV R/s peresandra,3.66/11kV S/s somenahalli, 4.66/11kV S/s Consent is given to Avail LC on
302 BRAZ GBNUR KOLAR Chikkaballapura 8/10/2022 8/10/2022 10:00 16:00 6:00 For quarterly maintenance work. 7/30/2022 +80-90 maintenance of the above mentioned 66kV Sub stations will
Gowribidanur sadali ,julpalya,6.66/11kV S/s chelur(Solar),7.66/11kV S/s 10.08.2022
MW(Mittemari) be carried out.
chakavelu, 8.66/11kV S/s pathapalya, 9.66/11kV S/s
thimmampalli,,10.66/11kV S/s bagepalli,11.66/11kV S/s
Vatadahosahalli. 66/11kV Kodigenahalli(alternate
supply can be arranged from 220kV R/s Madhugiri)
1. Periodical Maintenance work of 1x20MVA Tr's, Bus GOS, 66/11kV Sadali(alternate supply can be arranged from 220kV R/s Peak load-7.0MW,
66/11kV Jakkasandra line GOS, 66kV Breakers, 66kV CT's and 66kV PT's. BWSSB, Jakkasandra, HSR 5th Sector 66/11kV
Chinthamani) teachers colony,
Muss part of Load change over- LC was requested on 18.05.2022 and LC may be availed, Interuption
303 BMAZ South HSR Layout South HSR Layout 8/10/2022 8/10/2022 10:00 16:00 6:00 7/30/2022 Load Change Over-4.0MW Consent
S/s 2. Periodical Maintenance work of 11kV switchgears Venkatapura, Greenage supply
Gundamagere(alternate Apartment
can be arranged from 220kV NRS 4.0MW, 06.07.2022 but was not approved paper is given worktocan
notification be taken
be given
3. Attending Hot Line observations Dbpura during this time) , 66kV ACC EHT Load affected-3.0MW 1.66kv IISC station load 15MW can be shifted on to NRS,ITI-
1 banasawadi station load 33MW can be shifted on to 220kv F1 Vyalikaval -
To carry out quaterely and half yearly maintenance
ITI station,iti-2 yellarbande station load 30mw is already on
1.To carry out Maintenance work of incoming line,
220kv HBR,,66kv C1and C2 load C Stn 40mw can be shited 100% change over on RMV
outgoing line, Transformer Bays, 66kV bus Gos,11kV bus
c4 subdivisionand RT nagar, ganga nagar,cholanagar, outer ring on to 220KV A station . 2. during lc period only 66kv hebbal load partially F8,
and breaker maintenance.
c5 road ,kariyappalayout,ashram road, 1st blockanand nagar During the lc period 66kv hebbal do not have alternate can be shifted by BESCOM staff of around 2.F9 A station Change over: 30%
304 BMAZ NORTH Hebbal north and east 220/66/11kv,R/S Hebbal 8/10/2022 8/10/2022 10:00 16:00 6:00 2. For attending Hotspot works. 7/30/2022 25mw
subdivision,E1subd guddappa reddy layout,hebbal ,jayamahal1st block ,nandi durga source ,66kv hebbal station load is around 35mw but 10mw by near by station hence 25mw will be from 'C' station F18 and 20 % IISC
3. For carrying out IR test of all equipements like CT's, PT's,
ivion road, marappa garden, jc nagar,millers road etc around 10mw can be changed over by bescom staff and all affected F8,
LA's, Transformers, 66kV Breakers, 11kV Breakers, Wall
the 11kv feeders ,banks,and also bus coupler maintanenace 3.F -19 C V Raman Road Change
entry bushings and 11kV Bus.
will be done during the lc period ,The total station load over:40% IISC F2 and C Station F
4. For conducting Tan-Delta.
130mw 3. 25MW of load will be effected for 7:30hrs 18 - 20% and 30% IISC F1
during 66kV & 11kV bus & PT maintainence Sadashivanagara
17 CTAZ Davangere All 11kv feeders 8/11/2022 8/11/2022 10:30 16:00 7hrs 2nd quarter Maintainence AT Ikv Feners emanating lrom Kukhwada SS

All 11kvFeeden emanatng írom SRS Davanagere


LeFl-ada (un. F-oamnaseu). F
Kukkurada(IP). F4-Yalhmma(U), F>-Beanunu, FF13-Industrial
18 CTAZ Davangere All 11kv feeders 8/11/2022 8/11/2022 10:00 16:00 7hrs 2nd quarter Maintainence
F14+Vidyanaara PIS
Kanganat Fl6-JHP-2, F17-JHP-1, F21-N J
Taraabah, F22-S S Hi-tech F3-Vvelananda

19 CTAZ Davangere Davangere 8/11/2022 8/11/2022 10:00 16:00 4hrs Emergency maintainance work 20kV SRS Davanagere

166 CTAZ Davangere RSD Davangere Kukkuwada 8/11/2022 8/11/2022 10:30 16:00 5:30 2nd quarter maintenance 7/30/2022 All 11kV Feeders emanating from Kukkuwada SS

All 11kV Feeders emanating from SRS Davanagere i.e., F1-Hadadi


(IP), F2-Tholahunase(IP), F3-Kukkuwada(IP), F4-Yallamma(IP), F5-
Belevanuru, F6-Naganuru(IP), F7-Jarikatte(IP), F8-
167 CTAZ Davangere Davangere 220kV SRS Davanagere 8/11/2022 8/11/2022 10:00 16:00 6:00 2nd quarter maintenance 7/30/2022 Turchaghatta(IP), F9-Shamanuru, F10-Saraswathi, F11-Water
Works, F12-Attigere, F13-Industrial, F14-Vidyanagara, F15-
Ranganatha, F16-JHP-2, F17-JHP-1, F21-N J Taralabalu, F22-S S
Hi-tech, F23-Vivekananda

Tavarakere, Durvigere, mugulihalli, Nellihankalu, Masanikere,


168 CTAZ Benkikere Channagiri Tavarekere 8/11/2022 8/11/2022 10:00 16:00 6:00 Quarterly maintenance works 7/30/2022
Gangagondanahalli, Jaipura, jaggi water supply

169 CTAZ Benkikere Channagiri Tyavanagi 8/11/2022 8/11/2022 10:00 16:00 6:00 Quarterly maintenance works 7/30/2022

Honnali all feeders, Arakere, Belimalluru, Hiregonigere,


170 CTAZ Benkikere Channagiri Honnali 66 kv 8/11/2022 8/11/2022 10:00 16:00 6:00 Quarterly maintenance works 7/30/2022
Balleshwara, Hanumasagara and Marikoppa

TLM Sub-Division,
171 CTAZ Davangere 220kV Guttur-DVG-1 Line 8/11/2022 8/11/2022 10:00 14:00 4:00 Emergency Maintenance work 7/30/2022 220kV SRS Davanagere
KPTCL,Davangere

Peak load-24MW,
Replacement of old ERL make 11kV switchgears with New load changeover will
HSR Layout & 66/11kV Electronic City 13-08-2022 11kV DAS/SCADA compatible MEI make switchgears Shakambari
Electronic CityNagara,
Ph-2, Pipe line road,
Veersandra, Ragavendra
Ananth Nagara,swamy matta, JP be arranged by LC may beonavailed, Interuption
239 BMAZ South HSR Layout South 8/11/2022 10:00 16:00 6:00 7/30/2022 Load Change Over-24MW LC request 11.08.2022 shall be
Chandapura Ph-2 Sec-2 (Malgudi) S/s ( pertaining to Trf-2 i.e. Bank-2, F7, F8, F9, F10, F11, F12, nagar 1st phase, 14th cross, Salarpuria Appt, nagarjuna Appt,
Doddanagamangala BESCOM as per paper notification to be given
considered. 
F13) Puttenahalli area, Jayangara 8th Block, Jayanagara 5Th Block , MOM. No load will be
Jayangara 7th Block , ITI layout, SBI colony, Near RV dental, affected S6 Subdivision - F4 SARAKKI
college surroundings, 24th main, Behined LIC office , LIC colony, K
MUSS LOAD CAN BE SHIFTED TO
R Layout, Venkatadri Layout, JP nagar 5th Phase, Sai narsary
1) OLTC Overhauling of 66/11kV Transformers-1 and F5 JAYANAGAR MUSS. F13
Road, JP nagar 6th phase, 15th cross, 16th & 12th cross ,Adarsha Peak load-18MW,
periodic maintenance work. SARAKKI MUSS LOAD CAN BE
residency apt,Adarsha garden,Sindhura convention hall & Load change over- LC was requested on 18.05.2022, 15.06.2022
240 BMAZ South HSR Layout South HSR Layout 66/11kV Sarakki S/s 8/11/2022 8/11/2022 10:00 16:00 6:00 2)Quarterly Maintenance work of 66/11kV Transformers-2, 7/30/2022 Load Change Over-11MW SHIFTED TO ELITE F2 FEEDER.
surround,JP nagar Metro and surrounding,Indira Gandhi 11MW, but was not approved
66kV Isolators,66kV CT's & PT's. F2 SARAKKI MUSS LOAD CAN BE
circle,Aster hospital,15th
A.K.Ashram crossRoad,
Road, Devagowda underpass road,Actor
R.T.Nagar Sudeep
1st Block, Load affected-7MW
3)11kV Breaker maintanance SHIFTED TO RBI F1 FEEDER. NO
house surrounding,24th main Nandini
Thimmaiah Garden, Modi Garden, Military Area,hotel signal junction,Green
1. To carry out Maintenance work of incoming line, outgoing OTHER FEEDER C/O IS POSSIBLE
city hospital.Central mall, KR layout,Venkatadri
Veerannapalya,Lumbini Garden,BWSSB Sewage layout,Kalyani
line, Transformer Bays, 66kV bus Gos,11kV bus and (F1,F14,F6,F18)
Magnum road,DS palya,Vaishnavi
plant,Mariyannaplaya,Coffee boardTerrace apt, JP nagar-
breaker maintenance. 2nd,3rd,4th,5th phase,Marenahalli,Manjunath colony,Tank Bund Peak Load of Station is 26 MW, Load change over of 6MW
Shivajinagar L/O,Kempapura,Dasarahalli,maruthi L/O,Buvaneshwari S14 Subdivision - Change over
66/11kV Yellarbande 2. For attending Hotspot works. road,Bannerghatta
Manjunath road,Dollars
Nagar, Thimmiah layout,Kalyani
Road, Bhovi magnum
Colony, apt,
Mahaganapati shall be done by BESCOM to neighboring stations
305 BMAZ NORTH Hebbal East & North division & Hebbal 8/11/2022 8/11/2022 10:00 16:00 6:00 7/30/2022 nagar.BEL Corporate OfficeChankya L/O,Nagawara,M.S.Ramaiah 20 MW Consent is given work can be taken
arranged.
MUSS 3. For carrying out IR test of all equipements like CT's, PT's, Kalyani
Nagar, Krishna magnum.
Pushpanjali Apartment, Shivanahalli Park, Adarsha 1) 20MW of load will be effected for 7:30hrs during 66kV &
division North city,Thanisandra main road,Ashirwad nagar,amarjyothi
LA's, Transformers, 66kV Breakers, 11kV Breakers, Wall Nagar,Adarsha Layout,Unix Colony,Indira Nagar, Manjunath 11kV bus & PT maintainence
L/O,Rachen halli main road,Mestry palya,Royal enclave,Sri
entry bushings and 11kV Bus. Nagar, 3rd stage 1st Block0
rampura villageVHBCS L/O,,B-Nagar, Lakshmi
Veeranaapalya, Nagar,L/O, 17th
Jojappa
4. For conducting Tan-Delta. H.V.K.Layout, Kirloskar Colony, Karnataka Layout, Kamala Nagar,
cross Govindpura, veerannapalya Main Road, Byrappa L/O and
V.J.S.S.Layout,
surrounding areas Ward Office surrounding, Gruhalakshmi Layout
NRS 1st Stage, Nagapura, Mahalakshmi Puram, Mhodi Hospital Road, Most of the 11kV load will be changed over to
66/11 kV Mahalakshmi Quarterly maintenance work of 66kV Lines,Bus and 11kV During LC period,10MW of load will be changed over to other
306 BMAZ North NRS North Division,Rajajinagar 8/11/2022 8/11/2022 10:00 16:00 6:00 7/30/2022 Punjab National Bank, Hamsaleka Home Surrounding, 8 neighbouring stations and only 8MW load will F-26 SAI MANDIR RMU
Layout Bus bar isolator at 66/11kV Mahalakshmi Layout station. Stations by BESCOM
. Shankarmata, Pipe Line road, J.C.Nagar, Kurabaralli, Rajaji Nagar be affected during LC period.
2nd Block, E.S.I.Hoaspital. Kamala Nagar Main road,
Gruhalakshmi Layout 2nd Stage, Bovi Palya, Gelayara Balaga,
Mico Layout, G.D.Naidu Halli, West of chord road, Mahalakshmi
Layout, ESCON-Opp.SIT.road, B.N.E.S.College, BELL Apartment,
Sandal Soap Factory, Yeshvanth pura Indl.Area, Toyoto Show
room, Esteem Classic Apartment,Lumos Apartment.
Duration of LC request

Name of the Name of the KPTCL Name of the BESCOM Name of the BESCOM Date on which last
Sl no
KPTCL Circle Division Circle Division
Sub Division Name of the station/Line Feeder Date Time Reason for availing LC
LC was approved
Areas Affected Load Affected (MW) Wheather alteranate Power Supply Arranged or not Remarks Consent

From To From To Duration

Consent is Given to avail LC on


12.08.2022.( Note: if any exams &
66/11kV Sub station Madarasabaradoddi, Lakkasandra, Gungarahalli, Sugganahalli, emergency programs comes near to
172 Ramanagara Somanahalli Ramangara Ramanagara 8/12/2022 8/12/2022 10:00 16:00 6:00 To carry out periodical 2nd quarterly maintenance work 7/30/2022 10 MW No
Melehalli Lakshmipura that date I,e 12.8.2022 , the LC
date should change /postpone to
another date )

173 CTAZ Benkikere Honnali Honnali 220/66/11KV 8/12/2022 8/12/2022 10:00 16:00 6:00 Quarterly maintenance work 7/30/2022 bidaragadde holemadapura govinakovi 3 MW No there was no approval for LC since April LC request on 12.08.2022 shall be
considered. 

S6 Subdivision - F4 SARAKKI
MUSS LOAD CAN BE SHIFTED TO
F5 JAYANAGAR MUSS. F13
J.P nagar 2nd,3rd,4th,6th phases,Bannerghatta road,KR Layout Peak load-11MW,
SARAKKI MUSS LOAD CAN BE
1)OLTC Overhauling of 66/11kV Transformers-3 and 15th cross,Rose garden,Sarakki garden,JP nagar 1st Load change over- LC was requested on 18.05.2022, 15.06.2022
241 BMAZ South HSR Layout South HSR Layout 66/11kV Sarakki S/s 8/12/2022 8/12/2022 10:00 15:00 5:00 7/30/2022 Load Change Over-8.5MW SHIFTED TO ELITE F2 FEEDER.
periodic maintenance work phase,Sarakki gate,SBI colony,Sangam circle 47th 8.5MW, but was not approved
F2 SARAKKI MUSS LOAD CAN BE
cross,Jayanagar 8th block,Arya nagar,Jayanagar 4th & 5th block. Load affected-2.5MW
SHIFTED TO RBI F1 FEEDER. NO
OTHER FEEDER C/O IS POSSIBLE
66kV Somanahalli- (F1,F14,F6,F18)
T.K.Halli line. 1. For interchange of 66kV line bays at 66/11kV
Major Works Doddalahalli S/s and stringing of conductor from Loc No:01 Harobele, Kodhihalli, Kunur, Hukunda, Bijjalli, Hunasanahalli, S14 Subdivision - Change over
Transmission
307 Division, Ramanagara Kanakapura 66kV Kanakapura - Tk 8/12/2022 8/12/2022 10:00 16:00 6:00 to 04. 7/30/2022 Achalu, Doddalahalli, Honahaganahalli, Haluguru and 66kV Solar 60MW No Consent is given
arranged.
(Works) Circle
Ramanagara Halli Line 1 & 66kV 2. For removal of Jumps near 220kV T. K Halli station of plant at Doddalahalli substation
Kanakapura - TK Halli Kanakapura - Tk Halli Line1 & 2
Line 2

220kV Somanahalli- For carrying out periodical maintenance works as per


O&M Division, BWSSB Harohalli line bay maintenance schedule for 2nd quarter. Load of 220kV No load will be
308 BMAZ SOUTH Somanahally BMAZ[S] 8/12/2022 8/12/2022 10:00 16:00 6:00 7/30/2022 No load will be affected. No load will be affected.
BESCOM, Kengeri at 220/66/11kV R/S, BWSSB Harohalli, 220kV Kanakapura stations may be fed affected.
Somanahalli, Bengaluru. from 220kV TK Halli station. No load will be affected.

Benkikere, Maadapura, Honnebagi, benakanahalli, Hebbalagere,


309 CTAZ Benkikere Channagiri Benkikere 8/12/2022 8/12/2022 10:00 16:00 6:00 7/30/2022 10MW No
NST kavalu etc

310 CTAZ Benkikere Channagiri 220kV Benkikere 8/12/2022 8/12/2022 11:00 16:00 5:00 7/30/2022 Benkikere and Malladihalli 66kV lines 25MW No

31.5MVA power
Whitefield and No load will be Alternative power suplly will be arranged for all feeders from
20 BMAZ South GIS DIVISION East and South transformer -02 of EPIP 8/13/2022 8/13/2022 14:00 16:00 2:00 To carry out Tan Delta Test and Quarterly Maintenace work 7/30/2022 No load will be affected. MOM attached
Koramangala affected. BESCOM
220/66/11kV GIS station

31.5MVA power
Whitefield and No load will be Alternative power suplly will be arranged for all feeders from
21 BMAZ South GIS DIVISION East and South transformer -01 of EPIP 8/13/2022 8/13/2022 10:00 13:00 3:00 To carry out Tan Delta Test and Quarterly Maintenace work 7/30/2022 No load will be affected. MOM attached
Koramangala affected. BESCOM
220/66/11kV GIS station

gandi nagara, ambedkar circle, chaukipete, doddapete, kalikadevi


road, bashanagara, shivanagara, razakcircle, Mustafa nagara, sto
surrounding, vijayanagara badavane, Rajivgandi badavane, sps
srs yaragunta &
22 CTAZ Davangere CSD1, CSD2, RSD 8/13/2022 8/13/2022 10:30 16:00 5:30 2nd quarter maintenance 7/30/2022 nagara, smk nagara, valmiki circle, shivali theatre surrounding,
Neelagunda line
kondajji road, ajm nagara, bjm school, RTO office, surrounding
area, yaragunta, DC office, industrial area, bathi, avaragolla,
kakkaragolla surrounding area,

andi nagara, ambedkar circe, chaukipete Odapete, kalikadevi road


23 CTAZ Davangere All 11kv feeders 8/13/2022 8/13/2022 10:30 16:00 7hrs 2nd quarter Maintainence razakcrcie, Mustafa nagara, stourrounding vijayanagara badavane,
Rawgandi

24 CTAZ Davangere Davangere 8/13/2022 8/13/2022 10:30 16:00 4hrs Emergency maintainance work Yarangunta MUSS& Deavanngere MUSS

Lakkampura, Gadimakunte, Gopalapura, Chikka


ujini, Tumminakatte, Marlkatte, kyasanahali,Ounpun,
Quarterly
25 CTAZ Hiremallanahole All 11kv feeders 8/13/2022 8/17/2022 10:00 16:00 8hrs Chikkabantanahali, Yarlakatte, | 8MW No approval for
maintenance work
Venkateshapura, Gurusiddapura, Agasanahalli, LC since Aprl.
Malemachikere, Hlire bannihatn, Jadanakarte,Sokke, Hosakere,

66 kv Antharasanahalli
26 CTAZ Tumkur All feeder 8/13/2022 8/13/2022 7:00 18:00 11hrs Constructoion 11kv DC line chelur,Hoskere ,Nandihalli,Hagalawadi
choluru Hosakere line

TLM Sub-Division, SRS yaragunta &


174 CTAZ Davangere 8/13/2022 8/13/2022 10:30 14:30 4:00 Emergency Maintenance work 7/30/2022 Yaragunta MUSS & Davanagere MUSS
KPTCL,Davangere Neelagunda 66kV line

All 110 KV Outgoing lines:-Total Load affected: 140 MW 110/11


KV S/s Nittur, Gubbi, Bidare, Doddaguni, Kadaba, Kallur, K.G
242 CTAZ 220 KV R/s Nittur 8/13/2022 8/13/2022 10:00 16:00 8hrs a1/1st Half Year Maintenancea1/1st Half Year Maintenance 140 MW
Temple,
Ungra, Somalapura.

* Attending Hotline Observations of 66kV Bus


66/11kV Electronic City * Quarterly maintenance of 66/11kV, 20MVA Power
Peak load-37MW,
S/s Transformers.
Electronic City Ph-1, Neeladri Road, Hebgodi, Veersandra, load changeover- LC was requested on 16.04.2022, 21.05.2022,
HSR Layout & (66/11kV Hulimangala * Quarterly Maintenance of Bus Isolators and 66kV Drake LC may be availed, Interuption
311 BMAZ South HSR Layout South 8/13/2022 8/13/2022 10:00 16:00 6:00 7/30/2022 Golahalli,EHT Infosys, 66/11kV Hulimangala station feeding 15MW, Load Changeover-15MW 11.06.2022 & 09.07.2022, but was not
Chandapura S/s since it is radially fed conductor Bus. paper notification to be given
areas. load affected-22MW approved.
from 66/11kV Electronic * Quarterly maintenance of 66kV Bays & 38Nos 11kV
City S/s) Switchgears

220kV Somanahalli- For carrying out periodical maintenance works as per


BWSSB Tataguni- maintenance schedule for 2nd quarter. Load of 220kV
O&M Division, No load will be
312 BMAZ SOUTH Somanahally BMAZ[S] Vrushabhavati line bay at 8/13/2022 8/13/2022 10:00 16:00 6:00 Vrushabhavati station and 220kV BWSSB Tataguni station 7/30/2022 No load will be affected. No load will be affected.
BESCOM, Kengeri affected.
220/66/11kV R/S, may be changed over to 220kV NRS station through Peenya
Somanahalli, Bengaluru. or to 400kV Bidadi PGCIL station. No load will be affected.
1. To carry out Maintenance work of incoming line, outgoing
Consent is given work can be taken
line, Transformer Bays, 66kV bus Gos,11kV bus and Vidha Soudha, Ganesh RMU, Miller’s Road,Jaymahal, M.K.
Peak Load of Station is 35MW, Load change over of 20MW 1. F18-P.G Halli. Change over: 35%
breaker maintenance. Street,Cunningham Road, Kemp Road, Benson Town, Spencer
Shivajinagar and shall be done by BESCOM to neighboring stations 1).10MW from IISc station F4 feeder and 35
2. For attending Hotspot works. Road, Sultanjigunta Road, RMZ Millenia , B&LC Hospital,
313 BMAZ North Hebbal East Vidhanasoudha 66/11kV ‘C’ Station 8/13/2022 8/13/2022 10:00 16:00 6:00 7/30/2022 10 MW+5 MW of load(feeders)along with 5 mw load of BMRCL will be % Brigade F4 feecer. Palace
3. For carrying out IR test of all equipements like CT's, PT's, Vasanthnagar, Chikkbazar, Geneva House, Timmaiyya Road,
division effected for 07:30hrs during 66kV & 11kV bus & PT Guttahalli. LC requested on Second
LA's, Transformers, 66kV Breakers, 11kV Breakers, Wall Tasker Town, P.G Halli, Haine’s Road, Chandrahas, Muneshwara
maintainence Saturday
entry bushings and 11kV Bus. Nagar
4. For conducting Tan-Delta.

31.5MVA power
Whitefield and 1MW load will be affected and Alternative power suplly
27 BMAZ South GIS DIVISION East and South transformer -03 of EPIP 8/14/2022 8/14/2022 10:00 13:00 3:00 To carry out Tan Delta Test and Quarterly Maintenace work 7/30/2022 EPIP area 1MW MOM attached
Koramangala arranged for remaining feeders from BESCOM
220/66/11kV GIS station

175 CTAZ Benkikere Channagiri Devarahalli 8/14/2022 8/14/2022 10:00 16:00 6:00 Quarterly maintenance work 7/30/2022 Devarahalli.Nuggihalli. Neethigere.Ganghuru.Gullehalli 8MW

176 CTAZ Benkikere Channagiri Goppenahalli 8/14/2022 8/14/2022 10:00 16:00 6:00 Quarterly maintenance works 7/30/2022 Pandomatti, Goppenahalli and sorrounding areas 15 MW No

Lingadahalli , Nallur, Asthapanalli, Galihalli, and sorroundings


177 CTAZ Benkikere Channagiri Lingadahalli 8/14/2022 8/14/2022 10:00 16:00 6:00 Quarterly maintenance works 7/30/2022 12 MW No
areas
Duration of LC request

Name of the Name of the KPTCL Name of the BESCOM Name of the BESCOM Date on which last
Sl no
KPTCL Circle Division Circle Division
Sub Division Name of the station/Line Feeder Date Time Reason for availing LC
LC was approved
Areas Affected Load Affected (MW) Wheather alteranate Power Supply Arranged or not Remarks Consent

From To From To Duration

Mavinakatte, Madal, Gururajpura, BRT colony,


178 CTAZ Benkikere Channagiri Mavinakatte 8/14/2022 8/14/2022 10:00 16:00 6:00 Quarterly maintenance works 7/30/2022 8 MW No
Hanchinasiddapura and sorrounding areas

179 CTAZ Benkikere Channagiri Nallur 8/14/2022 8/14/2022 10:00 16:00 6:00 Quarterly maintenance works 7/30/2022 Nallur 4 MW No

Channagiri, Narashettihalli, Honnebagi, Bannihatti, mudigere,


314 CTAZ Benkikere Channagiri Channagiri 8/14/2022 8/14/2022 10:00 16:00 6:00 7/30/2022 Mavinahole, Billahalli, Bussenahalli, Garaga, Ajjihalli, 20MW No
Chikkulikere, Haronahalli etc

66 kv Antharasanahalli
28 CTAZ Tumkur All feeder 8/16/2022 8/16/2022 7:00 16:00 11hrs Constructoion 11kv DC line chelur,Hoskere ,Nandihalli,Hagalawadi
choluru Hosakere line

110/11 Kv S/s
180 CTAZ K.B Cross 8/16/2022 8/16/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance
HUNASEGHATTA

Vishwapriya Layout , Begur koppa Road, devarachikkanahalli,


220kV HSR(S10,S12 LC may be availed, Interuption
181 BMAZ South South 66/11kV Soudella 8/16/2022 8/16/2022 10:00 16:00 6:00 Periodic maintainance works 7/30/2022 Akshyanagara, Prestige Song of South, tejaswini Nagara, 15 No Previous date of Station LC was on 09.03.2022
Subramanyapura subdivision) paper notification to be given
Hirnadani Aparatent and surrounding Areas

LC request on 16.08.2022 shall be


considered. 
Peak load-12.5MW,
ONLY ST.JOHN F1 AND F4
66/11kV St John Wood Replacement of old CGL make switchgears of Bank-2 and St John Hostel,Tavarekere,Accenture,St John Wood load changeover-
243 BMAZ South HSR Layout South Koramangala 8/16/2022 8/18/2022 10:00 16:00 6:00 7/30/2022 Load Changeover-11.5MW - FEEDER FEEDING S14
S/s feeders apartment,Oracle,Junction TC,Christ College 11.5MW,
SUBDIDVISION OF btm UNIT,
load affected-1.5MW
ONLY F1 CAN BE CHANGE OVER
ON JAYADEVA STATION, F4 feeder
feeding only 10 %
66kV Kanakapura-
Somanahalli Line-1
Chathra Sunishka Solar Power plant (IPP), Maralawadi Town, Consent is given to avail LC on
315 Ramanagara Kanakapura Kanakapura Kanakapura (Partial) & 66/11kV 8/16/2022 8/16/2022 10:00 16:00 6:00 Quaterly maintenance work & Transmission line 7/30/2022 15.9 NO
Godur & surounding villages 16.08.2022
Chathra, Maralawadi,
Godur S/s.

Consent is Given to avail LC on


220 kV R/S T K Halli, 66
Kodambahalli sub division of Channapattana Taluk area feeding 16.08.2022.( Note: if any exams &
kV Harohalli-2 line Bay,
from 66/11 kV B V Halli/ Guruvinapura substation and Sathnur emergency programs comes near to
316 Ramanagara TKHalli Ramanagara Ramanagara 66/11 kV Guruvinapura 8/16/2022 8/16/2022 10:00 16:00 6:00 Line and station Quarterly maintenance work 7/30/2022 13 MW No alternate power supply
subdivision area of Kanakapura Taluk feeding from 66/11 kV that date I,e 16.8.2022 , the LC
and 66/11 kV B V Halli
Guruvinapura. date should change /postpone to
substations
another date )

Weavers coloney, Gottigere, Mantapa, Purvankara, AMC College,


Ramanagara and HSR and 66/11kV Bannerghatta Ragihalli, Kasaraguppe, National Park, Basavanapura, Consent is given to avail LC on
29 BMAZ (S) Subramanyapura 8/17/2022 8/17/2022 11:00 14:00 3:00 Periodic maintainance works 7/30/2022 17 Previous date of Station LC was on 06.11.2022
South Chandapura station Mylasandra, Bytarayandoddi, Lakshmipura, Shivanahalli and 17.08.2022.
surrounding Areas

Guttedurga, Halekallu, Bilichodu, Chadaragolla,


Mugidaraghalli, Chikka arakere, Kurudi,
Madihalli,Tuppadahalli, Katenahalli, Asagodu,
Quarterly Benchekatte, Muchunuru, narasimharajapura,
30 CTAZ Hiremallanahole All 11kv feeders 8/17/2022 8/17/2022 10:00 16:00 8hrs
maintenance work Marenahalli, Medikerihalli, Mediginakere,
Koratikere, Kasturipurn,Vyasagondanahall,
Somanahali, Gokulatu, Halavadandi, Sagalagatte,h ireharakere,
Devikere Maharajanahatt.

alagatte, Kenchamma naguhali, urlulkatte,Diddig,


Quarterly Hosaduga,vadeyarahalli Siddayyanakote,basavankote
31 CTAZ Hiremallanahole All 11kv feeders 8/17/2022 8/17/2022 10:00 16:00 8hrs
maintenance work danudda,basavanapura,channapura addihalli,hosuru,marakunte,
Kamalapura.

182 CTAZ K.B Cross 110/11 Kv s/S TIPTUR 8/17/2022 8/17/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance

220/66/11KV R/S,
183 CTAZ K.B Cross 8/17/2022 8/17/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance
Anchepalya

66/11KV S/s,
184 CTAZ K.B Cross 8/17/2022 8/17/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance
Sanabaghatta

66/11KV S/s,
185 CTAZ K.B Cross 8/17/2022 8/17/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance
Thimmasandra

Consent is Given to avail LC on


17.08.2022.( Note: if any exams &
66/11kV Sub staion emergency programs comes near to
186 BRAZ Somanahalli Ramangara Ramanagara 8/17/2022 8/17/2022 10:00 16:00 6:00 To carry out periodical 2nd quarterly maintenance work 7/30/2022 Kootgallu, Yerehalli, Shanaboganahalli, Danayankanapura 5MW No
Kootgallu that date I,e 17.8.2022 , the LC
date should change /postpone to
another date )

100MVA Power
Devanahalli Taluk, Kundhana ,Doddabelavangala,D.Cross Consent is given to Avail LC
187 BRAZ DBPura BRC Kengeri Nelamangala Transformer-1 NRS 8/17/2022 8/17/2022 10:00 16:00 6:00 Quarterly maintenance works of the station. 7/30/2022 70MW No
Doddaballapura and local areas on17.08.2022
DBPura,

Consent is given to Avail LC


188 BRAZ DBPura BRC Kengeri Nelamangala 66/11kV S/s D.Cross 8/17/2022 8/17/2022 10:00 16:00 6:00 Quarterly maintenance works of the station. 7/30/2022 D.Cross, Doddaballapura and local areas. No
on17.08.2022

Consent is given to Avail LC


189 BRAZ DBPura BRC Kengeri Hosakote 66/11kV S/s Devanahalli 8/17/2022 8/17/2022 10:00 16:00 6:00 Quarterly maintenance works of the station. 7/30/2022 Devanahalli Taluk No
on17.08.2022

Consent is given to Avail LC


190 BRAZ DBPura BRC Kengeri Hosakote 66/11kV S/s Kundhana 8/17/2022 8/17/2022 10:00 16:00 6:00 Quarterly maintenance works of the station. 7/30/2022 Kundhana No
on17.08.2022

66/11kV S/s Consent is given to Avail LC


191 BRAZ DBPura BRC Kengeri Nelamangala 8/17/2022 8/17/2022 10:00 16:00 6:00 Quarterly maintenance works of the station. 7/30/2022 Doddabelavangala No
Doddabelavangala on17.08.2022

Guttedurga, Halekallu, Bilichodu, Chadaragolla, Mugidaragihalli,


Chikka arakere, Kurudi, Madihalli,Tuppadahalli, Katenahalli,
Asagodu, Benchekatte, Muchunuru, narasimharajapura,
192 CTAZ Hiremallanahole Jagaluru Bilichodu 8/17/2022 8/17/2022 10:00 16:00 6:00 Quarterly maintenance work 7/30/2022 8MW No There was no approval for LC since April.
Marenahalli, Medikerihalli, Mediginakere, Koratikere,
Kasturipura,Vyasagondanahalli, Somanahalli, Gokulatti,
Halavadandi,Sagalagatte,hireharakere, Devikere, Maharajanahatti.
Duration of LC request

Name of the Name of the KPTCL Name of the BESCOM Name of the BESCOM Date on which last
Sl no
KPTCL Circle Division Circle Division
Sub Division Name of the station/Line Feeder Date Time Reason for availing LC
LC was approved
Areas Affected Load Affected (MW) Wheather alteranate Power Supply Arranged or not Remarks Consent

From To From To Duration

Pallagatte, Kenchamma nagtihalli, urlukatte, Diddigi, Hosadurga,


Vadeyarahalli, Siddayyanakote, Basavanakote, tarehalli, Gode,
193 CTAZ Hiremallanahole Jagaluru Pallagatte 8/17/2022 8/17/2022 10:00 16:00 6:00 Quarterly maintenance work 7/30/2022 Guddadalinganahalli, inalli, Kodadagudda, Basavapura, 8MW No There was no approval for LC since April.
Channapura, Suraddihalli, Palanayakanakote, Kallenahalli,
Hosuru,marakunte, Kamalapura.

Lakkampura, Gadimakunte, Gopalapura, Chikka ujjini,


Tumminakatte, Marikatte, kyasanahalli, Gouripura,
194 CTAZ Hiremallanahole Jagaluru Sokke 8/17/2022 8/17/2022 10:00 16:00 6:00 Quarterly maintenance works 7/30/2022 Chikkabantanahalli, Yarlakatte, Venkateshapura, Gurusiddapura, 8MW No There was no approval for LC since April.
Agasanahalli, Malemachikere, Hirebannihatti, Jadanakatte, Sokke,
Hosakere, .

66/11kV MUSS Talagawara, 66/11kV MUSS Cheemangala, Consent is given to Avail LC


317 BRAZ CHN Kolar Chintamani 66/11kV S/s Talagawara 8/17/2022 8/17/2022 10:00 16:00 6:00 66/11kV MUSS Talagawara. 7/30/2022 28 MW NO _
66/11kV MUSS Y.Hunasenahalli on17.08.2022

66/11 kV Shoba Indra Quarterly Maintenance works of station equipments at During LC Period 1.3MW load will be affected as per
318 BMAZ North NRS North, West Vidhana Soudha 8/17/2022 8/17/2022 10:00 16:00 6:00 7/30/2022 Global mall, Sobha Indraprastha Apartment 1.3 LC may be availed
prastha Station 66/11kV Sobha Indraprastha Substation concerned BESCOM officials.

Bannerghatta may
66kV Somanahalli-Jigani For carrying out periodical maintenance works as per
be changed over to
line-2 bay [Somanahalli- maintenance schedule for 2nd quarter.Load of 66/11kV
O&M Division, Bannerghatta may be changed over to 220kV Station, Jigani or 220kV Station, Jigani Bannerghatta may be changed over to 220kV Station, Jigani
319 BMAZ SOUTH Somanahally BMAZ[S] Bannerghatta] at 8/17/2022 8/17/2022 10:00 16:00 6:00 Station, Bannerghatta may be changed over to 220kV 7/30/2022
BESCOM, Kengeri load of 66/11kV Station Bannerghatta may be affected. or load of 66/11kV or load of 66/11kV Station Bannerghatta may be affected.
220/66/11kV R/S, Station, Jigani or load of 66/11kV Station Bannerghatta
Station Bannerghatta
Somanahalli, Bengaluru. may be affected.
may be affected.

Somenahalli,Shrirampura,Neralakere,Kabbala,Ballalasamudra,Gar
32 CTAZ Chitradurga Srirampura 66/11 kV MUSS Garga 8/18/2022 8/18/2022 10:00 16:00 6:00 Emergency Quarterly maintenance work 7/30/2022 ga,Belaguru,Kodihalli,Kalkere,Thonachenahalli,Gavirangapura. NO
And the surrounding areas.

33 CTAZ Davangere All 11kv feeders 8/18/2022 8/18/2022 10:30 16:00 7hrs 2nd quarter Maintainence Au Tiv Feeders emana tng rom Shyagae Ss

Jagalur town, Hanumantapura, Kechenahalli,


Tmalehali, Rangapura, Toranagatte, Uddagatta,
Gogud, Jammapura, Marenahalli,
Bommakkanahalli, Toranagatte, Harishinagundi,
Lingannanahalli, Gopagondanahalli, Bistuvalli,Rastemakunte,
Quarterly
34 CTAZ Hiremallanahole All 11kv feeders 8/18/2022 8/18/2022 10:00 16:00 8hrs Yaranahati, Jyothipura, Anaburu,
maintenance work
Kelagote, Kanakuppe, Chikka bannihatti, Devikere,|
Guttidurga, Sagalagatte, Rastemachikere,
Malammanahalli, Rajanahatti, Giddanakatte,
Bullalli, Bairanayakanahalli, Gavimata,
Santemuddapura, Haladallí, Gandinagara
Quarterly Bidarakere, Nibguru, Kattigehalli, Nellikatte,
35 CTAZ Hiremallanahole All 11kv feeders 8/18/2022 8/18/2022 10:00 16:00 8hrs
maintenance work Bastihal, ulahalu, Kalgere. Hosahatti

195 CTAZ Davanagere Davanagere Harihara 66/11 kv Harihara 8/18/2022 8/18/2022 10:00 16:00 7hrs Quaterly maintenance works Harihara town

110/11 Kv S/s
196 CTAZ K.B Cross 8/18/2022 8/18/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance
MAYASANDRA

197 CTAZ K.B Cross 110/11 KV S/s KARADI 8/18/2022 8/18/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance

GN KERE,BUKKASAGARA,
198 CTAZ 66/11 kv MUSS Mathod 8/18/2022 8/18/2022 10:00 16:00 7hrs emergency quarterly maintainance work
MATHOD,NAGATIHALLI, ME NASINODU,MATHOD URBAN,D T
VATTI, VAJRA AND THE SURROUNDING AREAS

KanchipurnKittdal, Kadavigere, Obbalapura, Vengalapura, N N


66/11 kv MUSS
199 CTAZ 8/18/2022 8/18/2022 10:00 16:00 7hrs emergency quarterly maintainance work KATTE, D K KATTE, shivanagara, JS Pura,C BGERE and
Kanchipura
surrounding area

200 CTAZ Guttur Division Harihara 66/11KV Harihara 8/18/2022 8/18/2022 10:00 16:00 6:00 Carryingout 2nd Quarter Maintenance 7/30/2022 Harihara Town

201 CTAZ Davangere RSD Davangere Shyagale 8/18/2022 8/18/2022 10:30 16:00 5:30 2nd quarter maintenance 7/30/2022 All 11kV Feeders emanating from Shyagale SS

TLM Sub-Division, 66kV Kukkuwada to


202 CTAZ Davangere 8/18/2022 8/18/2022 10:30 14:30 4:00 Emergency Maintenance work 7/30/2022 Shyagale MUSS
KPTCL,Davangere Shyagale line

203 CTAZ Benkikere Channagiri Kundur 8/18/2022 8/18/2022 10:00 16:00 6:00 Quarterly maintenance works 7/30/2022 Hanumanahalli , kunduru, Koolambi, Singatgere,

Jagalur town, Hanumantapura, Kechenahalli, Tmalehalli,


Rangapura, Toranagatte, Uddagatta, Gogud, Jammapura,
Marenahalli, Bommakkanahalli, Toranagatte, Harishinagundi,
Lingannanahalli, Gopagondanahalli, Bistuvalli, Rastemakunte,
204 CTAZ Hiremallanahole Jagaluru Jagaluru 8/18/2022 8/18/2022 10:00 16:00 6:00 Quarterly maintenance work 7/30/2022 Yaranahatti, Jyothipura, Anaburu, Kelagote, Kanakuppe, Chikka 8MW No There was no approval for LC since April.
bannihatti, Devikere, Guttidurga, Sagalagatte, Rastemachikere,
Malammanahalli, Rajanahatti, Giddanakatte, Bullalli,
Bairanayakanahalli, Gavimata, Santemuddapura, Haladalli,
Gandinagara.

Bidarakere, Nibguru, Kattigehalli, Nellikatte, Bastihalli, ullihalu,


205 CTAZ Hiremallanahole Jagaluru Bidarakere 8/18/2022 8/18/2022 10:00 16:00 6:00 Quarterly maintenance work 7/30/2022 6MW No There was no approval for LC since April.
Kalgere. Hosahatti.

G.N
KERE,BUKKASAGARA,MATHOD,NAGATIHALLI,MENASINODU,MA
206 CTAZ Chitradurga Srirampura 66/11 kV MUSS Mathod 8/18/2022 8/18/2022 10:00 16:00 6:00 Emergency Quarterly maintenance work 7/30/2022 NO
THOD URBAN,D T VATTI,VAJRA AND THE SURROUNDING
AREAS.

Kanchipura,Kittidal,Kadavigere,Obbalapura,Vengalapura,N N
66/11 kV MUSS
207 CTAZ Chitradurga Srirampura 8/18/2022 8/18/2022 10:00 16:00 6:00 Emergency Quarterly maintenance work 7/30/2022 Katte,D K Katte,Shivanagara,J S Pura,C B Gere and the NO
Kanchipura
surrounding areas.

Kundalgura, Kodihalli, Uppalagere, Shivapura, Pitlali, Aluru, 34MW Generation


208 CTAZ Davanagere Davanagere Hiriyuru Ranganathapura_66 8/18/2022 8/18/2022 10:00 16:00 6:00 1&2nd quarterly maintenance work. 7/30/2022 NO
Aranakatte, Laxmipura and 7MW station load
Duration of LC request

Name of the Name of the KPTCL Name of the BESCOM Name of the BESCOM Date on which last
Sl no
KPTCL Circle Division Circle Division
Sub Division Name of the station/Line Feeder Date Time Reason for availing LC
LC was approved
Areas Affected Load Affected (MW) Wheather alteranate Power Supply Arranged or not Remarks Consent

From To From To Duration

Hindsghtta, chigalikatte, gowdanahally, yalladakere, somerahally, 12MW of stations


209 CTAZ Davanagere Davanagere Hiriyuru Hindusghatta_66 8/18/2022 8/18/2022 10:00 16:00 6:00 1&2nd quarterly maintenance work. 7/30/2022 NO
Mavinamadu load

210 CTAZ Davanagere Davanagere Hiriyuru Hiriyur_220/66/11 8/18/2022 8/18/2022 10:00 16:00 6:00 1&2nd quarterly maintenance work. 7/30/2022 All 66/11KV station coming undder Hiriyur Nodal 270MW generation NO

20 MW solar
211 CTAZ Davanagere Davanagere Hiriyuru Bharamagiri_66 8/18/2022 8/18/2022 10:00 16:00 6:00 1&2nd quarterly maintenance work. 7/30/2022 All areas pertaining to Bharamagiri station generation and 10 NO
MW station load

66/11kV Carryingout 2nd


320 CTAZ Harihara 8/18/2022 8/18/2022 10:00 16:00 7hrs Harihara Town
Hanharaa Quarter Maintenance

220/66kV S/s, Consent is given to avail LC on


321 Ramanagara Kanakapura Kanakapura Kanakapura 8/18/2022 8/18/2022 10:00 16:00 6:00 TR1 Quaterly maintenance work 7/30/2022 No load affected 0 NO
Kanakapura. 18.08.2022

HOSAKOTE , 66/11kV S/s Industries near Kondasapura ,Bidrahalli , Consent is given to Avail LC
322 BRAZ BIAL BRAZ 8/18/2022 8/18/2022 10:00 16:00 6:00 For quarterly maintenance work of 66/11KV Kondasapura 7/30/2022 30 NO
AVALAHALLI Kondasapura Medahalli,Kanamangala ,Bhatrahalli on18.08.2022

LC request on 18.08.2022 shall be


considered.
Gubbalala, Part of Uttarahalli, ISRO layout Ind. Area, Adarsha
S5 Subdivision- out of 8 feeders, 2
aprtments I & II, Mantri Tranquill apartments, Maruthi layout,
220kV Jayanagar(S5,S12 66/11kV Periodic maintainance works of 66kV BUS & 11kV Bus and 04 MW load (out of 14 MW) can be shifted on nearby stations (f4,f13) feeders no change over can
323 BMAZ South South 8/18/2022 8/18/2022 10:00 16:00 6:00 7/30/2022 Bharath layout, Doddakallasandra Ind,area, Agara and connected 14 Previous date of Station LC was on 9.10.2021
Subramanyapura subdivision) Subramanyapura painting of I beam structures by BESCOM at the time of Line clear. be done ,6 feeders change over can
areas, Kuamraswamy lyt, Vittal nagara, Yadalam nagar, Maruthi
be done Spura F6- isro F5, Spura
nagar.
F8-Isro F9,spura F9-Isro F10,
a) Erection of 6No's of 110KV and 66KV towers. spura F12-iscon F9,spura f14-iscon
EPIP Yarandanahalli F12, spura F16-iscon F9
South and B) Stringing of Double circuit Drake ACSR conductor from
Transmission 10MW load of 66KV Dommasandra s/s will be arranged Concurrence given by AEE E-4
324 BMWSD Ramanagra O&M Chandapura Dommasandra to 8/18/2022 8/20/2022 10:00 16:00 6:00 Loc No.53 to Loc No. 67. 7/30/2022 Dommasandra, Suligunte, Muttanallur 8 MW Concurrence given by AEE E-4 Sub-division
(Works) Circle through Kachamaranahalli s/s Sub-division
Circle Sarjapura single circuit
OverHead line c) Releasing of existing 66KV Single circuit tower & coyote F8 - BanadappaGarden
conductor.
F-7 SBM Colony
During the time of LC, 7MW of load can be
Malleswaram,Jalah
For carrying out Yearly maintenance works for attending changed over to other stations by BESCOM F09 F12 Anf F13 three feeders
alli,Hebbal F-5 Pamapanagar Alternate supply will be arranged for around 7MW by
BMAZ North 66/11kV Mathikrere maintenance and alignment of Bus GOS-8 Nos, 11kV staff and 9 MW load will be affected at feedering to C9 sd Load Change
325 SRS Peenya, KPTCL Bangalore North Additional central 8/18/2022 8/18/2022 10:00 16:00 6:00 7/30/2022 9 MW BESCOM O&M staff for the feeders which have change overs
Circle MUSS Switchgear, 66kV CT & PT, 66kV Breakers, Cpacitor Bank Mathikere MUSS provision is Feasible from
(C3,C6,C4 Sub F-9 VR Layout from other stations
maintenance. Sahakarnagr stn 100/%load
division)
Full loads of the above mentioned feeder will be affected as per
BESCOM officials.

36 CTAZ Guttur Division Harihara 66/11kV MUSS Nandigudi 8/19/2022 8/19/2022 10:00 16:00 6:00 Carryingout 2nd Quarter Maintenance 7/30/2022 All Feeders & NJY connected to 66/11kV MUSS Nandigudi

Caryingout 2nd
212 CTAZ Harihara 66/11kv Nandigudi 8/19/2022 8/19/2022 10:00 16:00 7hrs Al Feeders& NY connected to 66/11kV MUSS Nandigudi
Quarter Maintenance

66/11kV MUSS Caryingout 2nd


213 CTAZ Harihara 8/19/2022 8/19/2022 10:00 16:00 7hrs All Feeders& NY connected to 66/11kV MUSS Banuvali
Banuvali Quarter Maintenance

214 CTAZ Davanagere Davanagere Harihara 66/11kv Bennuvalli 8/19/2022 8/19/2022 10:00 16:00 7hrs Quaterly maintenance works All feeders and NJY connected to 66/11kv MUSS Bennvalli

110/11 Kv S/S
215 CTAZ K.B Cross 8/19/2022 8/19/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance
THANDAGA

Consent is Given to avail LC on


19.08.2022.( Note: if any exams &
66/11kV Sub staion emergency programs comes near to
216 BRAZ Somanahalli Ramangara Ramanagara 8/19/2022 8/19/2022 10:00 16:00 6:00 To carry out periodical 2nd quarterly maintenance work 7/30/2022 Jalamangala, Thadikavagilu, Akkur, Kysapura and 11kV IPP 5MW No
Jalamangala that date I,e 19.8.2022 , the LC
date should change /postpone to
another date )

217 CTAZ Guttur Division Harihara 66/11kV MUSS Banuvalli 8/19/2022 8/19/2022 10:00 16:00 6:00 Carryingout 2nd Quarter Maintenance 7/30/2022 All Feeders & NJY connected to 66/11kV MUSS Banuvalli

All 66/11KV station coming undder 220/66 KV SRS Thallak and


218 CTAZ Davanagere Davanagere Hiriyuru 220/66 KV SRS, Thallak 8/19/2022 8/19/2022 10:00 16:00 6:00 1&2nd quarterly maintenance work. 7/30/2022 50 MW Generation
IPP's connected to 220/66 KV SRS Thallak & down stream stations

LC request on 19.08.2022 shall be


considered. 
Peak load-12.5MW,
ONLY ST.JOHN F1 AND F4
Koramangala and 66/11kV St John Wood Replacement of old CGL make switchgears of Bank-1 and BTM 1st Stage,Majestic Aparment,AXA,BTM Layout,Asis load changeover-
244 BMAZ South HSR Layout South 8/19/2022 8/21/2022 10:00 16:00 6:00 7/30/2022 Load Changeover-7.9MW - FEEDER FEEDING S14
Jayanagara S/s feeders Bavan,Gurappana Palya 7.9MW,
SUBDIDVISION OF btm UNIT,
load affected-4.6MW
ONLY F1 CAN BE CHANGE OVER
ON JAYADEVA STATION, F4 feeder
feeding only 10 %

CM Hole, Kanakatte, Siddibali, Bennehal,kaleyarapur, Malapua, During LC period


Quarterly
37 CTAZ Hiremallanahole All 11kv feeders 8/20/2022 8/20/2022 10:00 18:00 8hrs sharamasamudr,Hole, Hosahatti, Sangenahali, 1. RR nagara Sation Load and Partial Load oF
maintenance work Alternate power supply will be arranged from following
Timmalapura,Kamandalagund. REMCO GIS (12 to 13 MW will be Changed over
220kV Stations:-RS
on V vvalley 220kV Station.) LC request on 20.08.2022 shall be
220/66kV R/S Khodays=6MW:
2. ISRO Layout substation load will be shifted considered.
66kV BMRCL (6MW);
on 220kV NIMHANS via sarakki Substation.
220kV Vrishabhavathi
3. BMRCL load will be shifted on KHODAYS S5 Subdivision- out of 8 feeders, 2
Arehalli, Ittamadu, AGS Layout, Chikalsandra, TG Layout, R/S=30.3MW:66kV RR Nagar
220kV Jayanagara( S5 and 220/66kV 220kV station (f4,f13) feeders no change over can
38 BMAZ South South 8/20/2022 8/20/2022 10:00 16:00 6:00 Periodic maintainance works 7/30/2022 Bhuvneshwarinagar and areas surrounding the sub-station. 16 66kV Global EHT-05 MW
Subramanyapura S18 subdivision) Subramanyapura 4. Consent letter from EEE, TL&SS HSR be done ,6 feeders change over can
220kV NIMHANS R/S=35MW:Sarakki SS - 35MW
Division and EEE NRS TL&SS Division is be done Spura F6- isro F5, Spura
ISRO- 15MW
enclosed. F8-Isro F9,spura F9-Isro F10,
220kV NRS
5. During 220kV Spura Line Clear, arranging spura F12-iscon F9,spura f14-iscon
24MW:REMCO-GIS - 24MW
Power supply to Arehalli Substatiton F12, spura F16-iscon F9
(VV valley to REMCO line cable fault hence load to be shifted
substation is difficult . Hence , it is proposed to
Sasvehalli, rampura, hotyapura birganahalli kyasinakere kulgatte on NRS RS)
39 CTAZ Benkikere Channagiri Sasvehalli 8/20/2022 8/20/2022 10:00 16:00 6:00 Quarterly maintenance works 7/30/2022 9MW avail LC for substation will be taken on the
inoor same day of 220kV Spura LC .

CM Hole, Kanakatte, Siddihalli, Bennehalli, Kalldevarapura,


40 CTAZ Hiremallanahole Jagaluru Hiremallanahole 8/20/2022 8/20/2022 10:00 16:00 6:00 Quarterly maintenance work 7/30/2022 Mallapura, Bharamasamudra, HM Hole, Hosahatti, Sangenahalli, 8MW There was no approval for LC since April.
Timmalapura, Kamandalagundi.

66kv HM Hole, 66KV Neralagunte Station, DRDO, Neralagunte,


Devarahatti, Nrlagethanahatti, Gowdagere, Gowripura,
66/11 kV MUSS
41 CTAZ Chitradurga Challakere Rural 8/20/2022 8/20/2022 10:00 16:00 6:00 Emergency Quarterly maintenance work 7/30/2022 Nsyakanahatti, Hale Jogihatti, Rekalagere, BG Halli, TK Halli, NO
Nayakanahatti
Mallurahalli, Madadevapura and Surrounding Areas, 66KV
Radiance Solar IPP, 11KV STGRS IPP
Duration of LC request

Name of the Name of the KPTCL Name of the BESCOM Name of the BESCOM Date on which last
Sl no
KPTCL Circle Division Circle Division
Sub Division Name of the station/Line Feeder Date Time Reason for availing LC
LC was approved
Areas Affected Load Affected (MW) Wheather alteranate Power Supply Arranged or not Remarks Consent

From To From To Duration

66/11 kV MUSS
42 CTAZ Chitradurga Challakere Rural 8/20/2022 8/20/2022 10:00 16:00 6:00 Emergency Quarterly maintenance work 7/30/2022 HOSAKALLAHALLI and Balenahally Surrounding Areas. NO
Balenahally

12MW of stations
43 CTAZ Davanagere Davanagere Hiriyuru Challakere_66 8/20/2022 8/20/2022 10:00 16:00 6:00 1&2nd quarterly maintenance work. 7/30/2022 Challakere town, Nannivala village, VD halli and Duggavara village NO
load

08MW of stations
Shivaganga, Amblagere, Bhagavathi, Siddeshwara, Obenahally,
44 CTAZ Davanagere Davanagere Challakere Rangenahally_66 8/20/2022 8/20/2022 10:00 16:00 6:00 1&2nd quarterly maintenance work. 7/30/2022 load and generation NO
Byadarahally.
of 16MW

110/11 Kv S/S
219 CTAZ K.B Cross 8/20/2022 8/20/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance
THALAKERE

66/11KV S/s,
220 CTAZ K.B Cross 8/20/2022 8/20/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance
Honnenahalli

66kv HM Hole, 66KV Neralngunte Stanon. DRDO, Neralagunte,


Devarahatt, Nrlagethanahatt,
66/11 kv MUSS
221 CTAZ 8/20/2022 8/20/2022 10:00 16:00 7hrs emergency quarterly maintainance work uoWpun Nayakanahatti, Hale jogihatti,Rekalagere, BG halli, TK
Nayakanshetti
halli , mallurahalli,, Madadeva and surrounding areas, 66kV
Radiance Solar IPP, 1 IKV STGRS IP

66/11 kv MUSS
222 CTAZ 8/20/2022 8/20/2022 10:00 16:00 7hrs emergency quarterly maintainance work HOSAKALLAHALL and Balenahaly Surrounding areas .
balenahalli

Load not affected to Consent is Given to avail LC on


Ramangara Town and 20.08.2022.( Note: if any exams &
220/66/11 KV R/S, 66kV feeding stations emergency programs comes near to
223 Ramanagara Somanahalli Ramangara Ramanagara 8/20/2022 8/20/2022 10:00 16:00 6:00 To carry out periodical 2nd quarterly maintenance work 7/30/2022 Yarabnagara In Ramanagara Town, Senapathy White Lay Industry NO ALTERNATE SOURCE
KOTHIPURA Ramanagara, Bevoor, that date I,e 20.8.2022 , the LC
Sankalagere and date should change /postpone to
Dashavara another date )

LC request on 20.08.2022 shall be


Arehalli, Ittamadu, AGS Layout, Chikalsandra, TG Layout, considered. 
220kV Jayanagara(S15, 03-04 MW load can be shifted on nearby stations by
224 BMAZ South South 66/11kV Arehalli 8/20/2022 8/20/2022 10:00 16:00 6:00 Periodic maintainance works 7/30/2022 Ramanjenayanagar, Bhuvneshwarinagar and areas surrounding 16 Previously LC approved on 19.02.2022
Subramanyapura S18 subdivision) BESCOM at the time of Line clear.
the sub-station. S15 Subdivision - No change over
arranged,

150MVA, 220/66kV Power For carrying out periodical maintenance works as per
O&M Division, Transformer-1 at maintenance schedule for 2nd quarter. Load of Transformer No load will be
245 BMAZ SOUTH Somanahally BMAZ[S] 8/20/2022 8/20/2022 10:00 16:00 6:00 7/30/2022 No load will be affected. No load will be affected.
BESCOM, Kengeri 220/66/11kV R/S, will be changed over to 150MVA Power Transformer-3 and affected.
Somanahalli, Bengaluru 100MVA Power Transformer-2. No load will be affected.

F-8- Ragigudda,
F2- BPO unit,
F4- swagath Main road,
Jayanagar 66/11 KV Jayanagara GIS To carry out Condition Monitoring works on GIS Modules (2 Aletrnative power supply for 12MW will be arranged and
246 BMAZ South GIS DIVISION SOUTH 8/20/2022 8/20/2022 10:00 16:00 6:00 7/30/2022 F5-Hanamantappa RMU, 6MW MOM attached
Divisioon staton line bays+2 Transformer bays+ 1 PT bay) Brenton Road, Shobha pearl, ICICI bank, Embassy heights, remaining 6MW have no alternative source.
F6-Geetha Colony,
Abharan
F9-KK Road,jewells, Herban life, RMZ, Ashok nagar, Garudamall, Air
Force
F14- RVHosp. ,Dommaluru, Austin Town, Vivek nagar, Trinity
Teachers.
Church, Vijaj bank, Hotel Taj,Victoria layout, Museum Road,
1. Periodical Maintenance work of 66kV EDC line, 3x20MVA
Albert street, king street, Museum cross road, Lavelle road, St.
Tr's, Bus GOS, line GOS, 66kV Breakers, 66kV CT's and Peak load=25.0MW LC request on 20.08.2022 shall be
Koramangala, mark road, Y.G.Palya, KSRP, ITC hotel, Richmond road,
66kV PT's. Load Change LC was requested on 04.06.2022, but was not considered. 
326 BMAZ South HSR Layout South & East Indiranagar and 66/11kV Austin Town S/s 8/20/2022 8/20/2022 10:00 16:00 6:00 7/30/2022 Vannerpet, Life Style, M.G.Road, Hayes Road, Convent Road, Load Change over=15MW by BESCOM
2. Periodical Maintenance work of 11kV switchgears over=15MW approved
Jayanagar S.L.Apartment, Richmond Town, Najappa circle, Stain garden,
3. Attending Hot line observations. Load affected= 10MW Change over arranged,
Richmond Park, Longford Road, Braight street, Foodworld road,
Johnson
220kV market,
Lines BWSSB
,All 66kV water lines,
outgoing supply, longford road,
F2-Swandenahalli, F3-
Ashoknagar,
Yellapura, F4.Shopper stop, Markam road, brigade road, commerce
college, , Richmond circle, Vittal malya road, Siddaiah
Handtool,FSNavilahalli,F6-Urkere,F7-Melehalli, road, wood
F8-Hebbaka, F9.
220 KV R/s street, castle strreet,
Bugudanahalli, Neelasandra,
F10-Industrial Anepalya, Bunglow,F12-KIADB,
Area,F11-DC BMRCL.
45 CTAZ 8/21/2022 8/21/2022 10:00 16:00 8hrs For Quarterly maintenance works 30 MW
Antharasanahalli F13-KIADB
Industrial area, F14-Narasapura, F15-Sathyamangala, F16-
Fitwell, F17-Indo
auto F20-KG Palya, F21-Tudalayout
220kV PGCIL Line, 220kV Madhugiri Line, 66kV TMTP O/G line,
11kv F1&F12
220/66/11kV R/s KIADB
46 CTAZ 8/21/2022 8/21/2022 10:00 16:00 8hrs For Quarterly maintenance works Station Auxiliary, F2- TMEIC, F7-Chamundi, F8-Sharada, F9, F10- 10mw
Vasanthanarasapura
mahalakshmi,
F11-Vigneshwara

F2,F3,F4-TMTP1,F5-TMTP2,F6-TMTP3,F7-TMTP4,F8-TMTPS,F9-
47 CTAZ 66/11KV S/s TMTP 8/21/2022 8/21/2022 10:00 16:00 8hrs For Quarterly maintenance works TMTP6,F10 &F11 0

F1-Nandihalli, F2-Doddasarangi, F3-Hosali(NJY), F4


66/11kv s/s Kambathanahalli/Adalapura,F5-KHB1,F6-KHB2,F7-
48 CTAZ 8/21/2022 8/21/2022 10:00 16:00 8hrs For Quarterly maintenance works 7mw
Doddasarangi Chikkasarangi(NJY), F8-
Hethenahalli

66/11kV Chandrappa Tavarekere Subdivision areas feeding from 66/11kV Chandrappa Consent is given to avail LC on
49 Ramanagara Nelamangala Ramanagara Magadi 8/21/2022 8/21/2022 10:00 16:00 6:00 2nd Quarterly & Half Yearly maintenance work 7/30/2022 12MW No
Circle Circle Substation 21.08.2022

nyamathi, surahonne,salbalu, kudurekonda, madanabhavi,


50 CTAZ Benkikere Channagiri Nymathi 8/21/2022 8/21/2022 10:00 16:00 6:00 Quarterly maintenance works 7/30/2022 7MW
arabagatte

10MW of stations
Budurukunte, Kalamarahally , Siddeshwara,Belagere, Goralattu,
51 CTAZ Davanagere Davanagere Challakere Kalamarahally_66 8/21/2022 8/21/2022 10:00 16:00 6:00 1&2nd quarterly maintenance work. 7/30/2022 load and generation NO
Siradarakapile
of 28MW

F1-Soorenshlli, F2 Kabbigere,F3 Kodihalli NJY,F4Dodderi,


FSThovinakere
rural,F6 Thovinakere Urban,F7 Kestur,F8 GG halli,F9 Sorekunte,
66kV Line Bay, Power TR-182, 11kv
247 CTAZ 66kV S/s Thovinakere 8/21/2022 8/21/2022 10:00 16:00 8hrs F10 9mw
Breakers and Isolators Maintenance
Siddarabetta,F11 Siddeshwara NJY,F12 Dandinamaramma NJY
work
F13
chowdeshwari NJY

66/11kV S/S Chandapura, Hale


66/11KV S/S, For periodical 2nd Quarterly chandapura, Neraluru, Kerthi layout, Muthanalluru and Partial Load can be shifted to Attibele, Yarandhalli & Consent is given to avail LC on
248 Ramanagara Yerrandanahalli Ramanagara Chandapura 8/21/2022 8/21/2022 10:00 16:00 6:00 7/30/2022 18 MW
Chandapura maintenance of Equipments surrounding areas Chokkasandra station by BESCOM 23.08.2022 instead of 21.08.2022
feeding from Chandpura station

150 MW (220/66kV
220kV R/S Malur along To attend critical hotspots in 220kV Bus-1&2 selector 66/11kV Downstream Stations of Malur R/S)
Alternate power supply can be arranged for downstream
with its connected 66kV isolators and also for re-conditioining of 220kV Bus-1&2 1. 220/66kV Malur R/S, 150MW(220/66kV Consent is given to Avail LC on
249 BRAZ Malur Kolar KGF 8/21/2022 8/21/2022 10:00 16:00 6:00 7/30/2022 stations of 220/66kV Sarjapura & VTP R/S from
downstream sub-stations selector isolators of 220kV Bus coupler Bay and Quarterly 2. 220/66kV Sarjapura R/S & Sarjapura & VTP R/S 21.08.2022
Yerandahally & HSR Layout Stations
and 220kV Bus-1&2 Maintenance 3. 220/66kV VTP R/S )
Total=300MW

220/66kV T.Gollahalli R/s


Nangali,Byrakuru,Kysambally,Doddakari,
along with its connected To Conduct Tan Delta test on 220kV Current Transformers Consent is given to Avail LC on
250 BRAZ Malur Kolar KGF 8/21/2022 8/21/2022 10:00 16:00 6:00 7/30/2022 Andersonpet,Mudiyanur, H.gollahalli,Tayaluru, N.G.Hulkur, 92 No
66kV downstream sub- by R&D and Quarterly Maintenance 21.08.2022
M.N.Halli, Avani, Mulbagal, KGF, Kamasmudra, BEML EHT
stations
Duration of LC request

Name of the Name of the KPTCL Name of the BESCOM Name of the BESCOM Date on which last
Sl no
KPTCL Circle Division Circle Division
Sub Division Name of the station/Line Feeder Date Time Reason for availing LC
LC was approved
Areas Affected Load Affected (MW) Wheather alteranate Power Supply Arranged or not Remarks Consent

From To From To Duration

Railway traction-1 &2, Kembodi, Tamaka, Yeldur, Dalsanur,


DRDO, T.D.Halli, Sugutur, S M Mangala, Bangarpet, Vemgal, Two dates have been proposed for carrying out of quarterly
251 BRAZ Kolar Kolar Kolar 220 kV R/s Kolar 8/21/2022 8/21/2022 10:00 16:00 6:00 Second quarterly maintenance works 7/30/2022 150 MW Consent is given
Talgunda, Kyalanur, Narsapura, Vokkaleri, Kolar urban and rural maintenance
areas

66kV Kaggalipura-Shoba
For carrying out periodical maintenance works as per
Forest View line bay at
O&M Division, maintenance schedule for 2nd quarter. Load of 66/11kV No load will be
252 BMAZ SOUTH Somanahally BMAZ[S] 66/11kV Sub-station, 8/21/2022 8/21/2022 10:00 16:00 6:00 7/30/2022 No load will be affected. No load will be affected.
BESCOM, Kengeri Shobha Forest View Sub-stations may be changed over to affected.
Kaggalipura [Brigade F8 ITI Aux and F-21 AKM BALLET total load of 5 MW can be
220kV Subramanyapura station. No load will be affected.
Meadows], Bengaluru. shifted to 31.5 MVA TRf No:1
Renovation and Following works will be carried out :
Feeders affected are: 7 MW
Modernization works at 1) Cable Laying, glanding and termination
F3 EPIP -1
220/66/11kV Receiving 2) Testing & Commissioning of yard side
F7 Kundalahalli
Station, Hoody, Bangalore 3) Relay Testing SAS integration of the line equipments and
Transmission O&M Whitefield Division F8 RHB Colony Concurrence given by AEE E-7 and
253 400kv SSC Division East Taluk, Bangalore 8/21/2022 8/30/2022 9:00 16:00 7:00 Charging 7/30/2022 7 MW Alternate arrangement shall be made by BESCM authorities
(Works) Circle East BESCOM F14 Manipal Hospital E-12 Sub-division
Urban District on Total
F16 MS L&T
Turnkey Basis
F22 Boruka Tech Park
Partial load on 31.5MVA Transformers will be affected Consent is given work can be taken
F23 Bushra Tech Park
Vidhana Soudha 31.5 MVA TRf No:2 during the above shut down period. 5 Robertson Block 100 % Change
F24 BEL Tower Hotel
Division (W-4 & W- F11 Phoenix Mall Over from NRS F 28, 'A' Station F3
During LC Period 20MW load will be affected after
East and North 5 Sub-division) and To carry out quarterly maintenance work of attending 20MW load will be affected after changeover of and NRS F 25 feeder
254 BMAZ North NRS 66/11 kV 'A' Station 8/21/2022 8/21/2022 10:00 16:00 6:00 7/30/2022 Areas feeding from 66/11kV A station 20 rearranging of loads on other stations as per concerned
Circle Malleshwaram hotspots at 66/11kV A Station loads to other stations. F6 Brahma Pura 100 % Change
BESCOM officials.
Division (C-1 & C-2 Over from NRS F 11, Brigade F3
Sub-division) feeder.
F5 Robertson Block

66/11KV Caryingout 2nd Dittur, vataganahali, sarathi, Chikkabidare,


52 CTAZ Harihara 8/22/2022 8/22/2022 10:00 16:00 7hrs
Kurubarahalli Quarter Maintenance kondaji and surrounding area

53 CTAZ Davanagere Davanagere Harihara 66/11kv Karaberehalli 8/22/2022 8/22/2022 10:00 16:00 7hrs Quaterly maintenance works Dittur

Consent is Given to avail LC on


22.08.2022.( Note: if any exams &
66/11kV Sub staion Akkur, Thalwadi, Veroopasandra, Chikkaganwadi and emergency programs comes near to
54 Ramanagara Somanahalli Ramangara Ramanagara 8/22/2022 8/22/2022 10:00 16:00 6:00 To carry out periodical 2nd quarterly maintenance work 7/30/2022 5MW NO
Chikkagangawadi Doddagangawadi that date I,e 22.8.2022 , the LC
date should change /postpone to
another date )

RR Nagar,Rajaji
nagar,Kengeri,Jaya 66/11 kV Sir M V Layout LC request on 22.08.2022
55 BMAZ North NRS East,West,South 8/22/2022 8/22/2022 10:00 16:00 6:00 Quarterly maintenance 7/30/2022 Areas feeding from 66/11kV Sir, M V Layout S/s 15 Load changeover will be done by BESCOM LC may be availed shall be
nagar,Vidhanasoud station considered. 
ha
S6 Subdivision - F4 RBI MUSS
LOAD CAN BE SHIFTED TO F4
KHODAYS MUSS. F1 FEEDER RBI
RBI layout,Kottanur,J.P Nagar 5th phase,Shreyas colony,Gaurav
MUSS LOAD CAN BE SHIFTED TO
HSR and nagara,Nataraja layout,Nrupathunga nagar,Jambusavare 07 MW load can be shifted on nearby stations by BESCOM at
56 BMAZ South Subramanyapura South 66/11kV RBI 8/22/2022 8/22/2022 10:00 16:00 6:00 Periodic maintainance works 7/30/2022 20 Previous date of Station LC was on 08.03.2022 F2 SARAKKI MUSS. F13 FEEDER
Jayanagara dinne,Chunchughatta,Brigade Millenium & Briagde Gardenia the time of Line clear.
RBI MUSS LOAD CAN BE SHIFTED
appartments and areas surrounding the sub-station.
TO F2 ELITE MUSS. NO OTHER
FEEDER IS POSSIBLE FOR C/O
(F2,F5,F12,F14,F15,F16)

Dittur, vataganahalli, sarathi, Chikkabidare, kondajji and S14 Subdivision- Change over
57 CTAZ Guttur Division Harihara 66/11KV Kurubarahalli 8/22/2022 8/22/2022 10:00 16:00 6:00 Carryingout 2nd Quarter Maintenance 7/30/2022 arranged,
surrounding area

12 MW of station load
F5-Purlahalli, F6-Jajur, F7-Baramsagara, F8-Ranikere, Total 25
58 CTAZ Davanagere Davanagere Hiriyuru Dyavarnahally-66 8/22/2022 8/22/2022 10:00 16:00 6:00 1&2nd quarterly maintenance work. 7/30/2022 and generation of NO
villages
around 16MW

Obalapura,Chitranayakanahally, Mylanahally, Gudihalli,


59 CTAZ Davanagere Davanagere Hiriyuru Mylanahally_66 8/22/2022 8/22/2022 10:00 16:00 6:00 1&2nd quarterly maintenance work. 7/30/2022 6 MW of stations load NO
Kamasamudra

Peak load-24MW,
Replacement of old AREVA make 11kV switchgears with load changeover will
66/11kV Electronic City
24-08-2022 New 11kV DAS/SCADA compatible MEI make switchgears Electronic City Ph-1, Hongasandra, Bommanahalli Main Road, be arranged by LC may be availed, Interuption
255 BMAZ South HSR Layout South HSR Layout Ph-2 Sec-1 (Velankani) 8/22/2022 10:00 16:00 6:00 7/30/2022 Load Change Over-24MW GCW Work
( pertaining to Trf-1 i.e. Bank-1, F1, F2, F3, F4, F5, F11 NGR Layout BESCOM as per paper notification to be given
S/s
with Bus Coupler) MOM. No load will be
affected

Load of 66/11kV Banashankari


RR Nagar,Rajaji To attend Hotspots and Maintenance works of all station station,66/11kV RRnagar will be shifted on
Down streams of Vrushabhavathi R/S: 66/11kV Chandra Layout During LC Period 65MW load will be affected after
nagar,Kengeri,Jaya 220/66/11 kV equipments at 220/66/11kV Vrushabhavathi RS and 220kV Spura.Load of BMRCL station will be
256 BMAZ North NRS East,West,South 8/22/2022 8/22/2022 10:00 16:00 6:00 7/30/2022 MUSS, 6611kV Sir MV Layout,6611kV Kengeri MUSS, Mysore 65 rearranging of loads on other stations as per concerned LC may be availed
nagar,Vidhanasoud Vrushabhavathi R/S downstream stations: 66/11kV Chandra Layout MUSS, shifted on BMRCL Byappanahalli station
Road surrounding area. BESCOM officials.
ha 6611kV Sir MV Layout,6611kV Kengeri MUSS (Source:Hoody).Load of 66/11kV Chandrappa
circle will be shifted on Kumbalagodu station.

For carrying out periodical maintenance works as per


66kV Somanahalli-Jigani
maintenance schedule for 2nd quarter. Load of 66kV
O&M Division, line 1 bay [RBI, South city] No load will be
257 BMAZ SOUTH Somanahally BMAZ[S] 8/22/2022 8/22/2022 10:00 16:00 6:00 Somanahalli-Jigani line 1 bay [RBI, South city] can be 7/30/2022 No load will be affected. No load will be affected.
BESCOM, Kengeri at 220/66/11kV R/S, affected.
changed over to 220kV Station, Khodays. No load will be
Somanahalli, Bengaluru.
affected.

110/11 KV S/s
60 CTAZ K.B Cross 8/23/2022 8/23/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance
TURUVEKERE

KSIT College,8th Block Anjanapura,weavers coloney,Purvankara


HSR (S12), Kengeri 4MW load can be shifted on nearby stations by BESCOM at LC may be availed, Interuption
61 BMAZ South Subramanyapura South 66/11kv Anjanapura 8/23/2022 8/23/2022 10:00 16:00 6:00 Periodic maintainance works 7/30/2022 Apartment,Amruthnagara,SP thota,Vaddarapalya,Kembathahalli 10 Previous date of Station LC was on 11.02.22
(K3) the time of line clear paper notification to be given
and area surronding sub-station.

30MW of Stations
All areas pertaining to Hangal, Rampura and Nagasamudra
62 CTAZ Davanagere Davanagere Hiriyuru Hangal_66 8/23/2022 8/23/2022 10:00 16:00 6:00 1&2nd quarterly maintenance work. 7/30/2022 Load and Generation NO
stations
of around 56MW

BG Kere, Abbenahally, Surammanahally, Mushtalagummi,


63 CTAZ Davanagere Davanagere Hiriyuru BG Kere_66 8/23/2022 8/23/2022 10:00 16:00 6:00 1&2nd quarterly maintenance work. 7/30/2022 8 MW of stations load NO
Kondlahally, Mogalahally

6MW of stations load


Gowrasamudra, Hanumanthanahally Obanahally, B.T Pura,
64 CTAZ Davanagere Davanagere Hiriyuru Gowrasamudra_66 8/23/2022 8/23/2022 10:00 16:00 6:00 1&2nd quarterly maintenance work. 7/30/2022 and generation of NO
Honnuru.
3.2MW

66kV T.K.Halli-Iggaluru
Line. Consent is Given to avail LC on
1. 66/11kV Akkurmole-15MW,
23.08.2022.( Note: if any exams &
Major Works 2. 66/11kV Iggalur-12MW,
Ramanagara (i) 66kV T.K Halli – Iggalur Releasing and restringing of conductor between Loc No:38 to (i)-31 MW emergency programs comes near to
258 BRAZ Division, Ramanagara 8/23/2022 8/23/2022 10:00 16:00 6:00 7/30/2022 3. 66kV EHT M/s CNNL at Iggalur-6MW --
Maddur line 43 (ii)-18MW that date I,e 23.8.2022 , the LC
Ramanagara 1. For carrying out replacement of jump connecting between 4. 66/11kV Yethambadi-3.2MW
(ii) 66kV T.K Halli – date should change /postpone to
Akkurmole line line isolator and breaker limb(Rph) in 220kV Malur another date )
incoming at 220kV R/s Sarjapura.
2. Attending Hot line observations in 220Kv incoming line
breaker and mainteance works of 11kv Switchgears 1. 220/66/11KV R/S, Sarjapura
220/66/11KV R/S, 3.To carryout alignment work of 66Kv Bus B isolators of 2. 66/11kV Dommasandra substation Consent is given to avail LC on
259 BRAZ Yerrandanahalli Ramanagara Chandapura 8/23/2022 8/23/2022 10:00 16:00 6:00 7/30/2022 45 MW No
Sarjapura 100MVA Tr-2 5. Some of the Sarjapura , dommasandra and Attibele Local & 23.08.2022
3. for conducting IR and PI tests on 2X100MVA surrounding Areas
transformers and 2X20MVA transformers at 220kV
Sarjapura Station.
4. To carryout 2nd quarterly maintenance works on all lines
and Equipments at 220KV Sarjapura All areas feeding from following station will be effected:
220kV R/s BIAL &
Hosakote ,Nandagu For quarterly maintenance work of 220kV R/s BIAL and its 1)66/11kV Vidyangar Consent is given to Avail LC on
260 BRAZ BIAL BRAZ Downstream stations 8/23/2022 8/23/2022 10:00 16:00 6:00 7/30/2022 80 NO
di,Devanhalli down stream 2)66/11kV Budigere 23.08.2022
EHT-BIAL-1&2 ,ITC
Duration of LC request

Name of the Name of the KPTCL Name of the BESCOM Name of the BESCOM Date on which last
Sl no
KPTCL Circle Division Circle Division
Sub Division Name of the station/Line Feeder Date Time Reason for availing LC
LC was approved
Areas Affected Load Affected (MW) Wheather alteranate Power Supply Arranged or not Remarks Consent

From To From To Duration

Indiranagar Quarterly mainatainance and OLTC Overhauling of


261 BMAZ SOUTH Hoody East circle 66/11KV B-station 8/23/2022 8/23/2022 10:00 16:00 6:00 7/30/2022 No load affected
Division Transformer-4 and maintainence of Trfr-4 bay equipments.

Malebennur, Halivana, Kumbaluru, Boodihal,


66/11kv Caryingout 2nd
65 CTAZ Harihara 8/24/2022 8/24/2022 10:00 16:00 7hrs Nanditavare, Kokkanuru, Govinahal, Kunebelakere, |
Malebennur Quarter Maintenance
Hindusgatta, Kumarahanahali, Guddadahali

66/11kv Caryingout 2nd


66 CTAZ Harihara 8/24/2022 8/24/2022 10:00 16:00 7hrs Devarabelakere Kadlegundi salakatte, mudahadadi Mittalakatte
Devarabelakere Quarter Maintenance

67 CTAZ Davanagere Davanagere Harihara 66/11kv Devarabelekere 8/24/2022 8/24/2022 10:00 16:00 7hrs Quaterly maintenance works Devarabelekere,kadlegundi,salakatte,mudahadodi,

68 CTAZ Davanagere Davanagere Harihara 66/11kv Malebennur 8/24/2022 8/24/2022 10:00 16:00 7hrs Quaterly maintenance works Malebennur

110/11 Kv S/s
69 CTAZ K.B Cross 8/24/2022 8/24/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance
BANDIHALLI

channasamudra Kappagere, Koratigere, Madhure,K


66/11 kv MUSS o00anguvahal,Kelodu, Hegalagere, Rangavali, Plapurn|
70 CTAZ 8/24/2022 8/24/2022 10:00 16:00 7hrs emergency quarterly maintainance work
hosadurga Devigere,Vedavathi.B V Nagara, Mavinakatte palva Attighatta and
the surrounding areas

H S D Exp,Illapura,Bagur, Hebballi, Sanihal, Srirangapura


71 CTAZ 66/11 kv MUSS begur 8/24/2022 8/24/2022 10:00 16:00 7hrs emergency quarterly maintainance work
Anival HSD RURAL and surrounding areaa

72 CTAZ 66/11 kv MUSS nergunda 8/24/2022 8/24/2022 10:00 16:00 7hrs emergency quarterly maintainance work NergundaAdrkatte, ShriMATA,Aladahali and the surrounding areas

All 66KV Stationa from Madure and 11 KV Feeders fed from


73 CTAZ 66/11 kv MUSS madure 8/24/2022 8/24/2022 10:00 16:00 7hrs emergency quarterly maintainance work
madure

Consent is Given to avail LC on


24.08.2022.( Note: if any exams &
Namdaari, Heggadagere, Urgahalli, Myganahalli, ABM billtech
66/11kV Sub staion Madapiura and Myganahalli load can be taken on emergency programs comes near to
74 BRAZ Somanahalli Ramangara Ramanagara 8/24/2022 8/24/2022 10:00 16:00 6:00 To carry out periodical 2nd quarterly maintenance work 7/30/2022 layout, Kenchanaguppe, chuncjaga NJYm Madapura and 10MW
Kempanahalli Ramangara MUSS that date I,e 24.8.2022 , the LC
sourraounding areas
date should change /postpone to
another date )

Consent is given to avail LC on


75 BRAZ Nelamangala Ramanagara Magadi 66/11kv Agalakote 8/24/2022 8/24/2022 10:00 16:00 6:00 Preventive quartely maintainance 7/30/2022 Kudur subdivison 7 MW Not
24.08.2022

Consent is given to avail LC on


76 BRAZ Nelamangala Ramanagara Magadi 66/11kv Mathikere 8/24/2022 8/24/2022 10:00 16:00 6:00 Preventive quartely maintainance 7/30/2022 Kudur subdivison 7 MW Not
24.08.2022

LC request on 24.08.2022 shall be


considered.

ISRO Layout, ISRO layout Ind. Area, Kumarswamy layout, Vittal S5 Subdivision- out of 11 feeders,
220kV Jayanagara(S5 04 MW load can be shifted on nearby stations by BESCOM at
77 BMAZ South South 66/11kV ISRO Layout 8/24/2022 8/24/2022 11:00 15:00 4:00 Periodic maintainance works 7/30/2022 nagara, Vikram nagar, Ilyaznagar, Yelchenahalli, surrounding 15 Previously LC approved on 26.05.2022 (f3, f4, f6, f7, f8, f10, f11, f12 )8
Subramanyapura Subdivision) the time of Line clear.
area. feeders no change over can be done
,3 feeders change over can be done
isro F2-Spura F4 , Isro F5-Spura
F6, isro F9 -spura F8

78 CTAZ Guttur Division Harihara 66/11KV Devarabelakere 8/24/2022 8/24/2022 10:00 16:00 6:00 Carryingout 2nd Quarter Maintenance 7/30/2022 Devarabelakere Kadlegundi salakatte, mudahadadi Mittalakatte

Channasamudra,Kappagere,Koratigere,Madhure,Kanguvahalli,Kell
79 CTAZ Chitradurga Hosadurga 66/11 kV MUSS Hosdurga 8/24/2022 8/24/2022 10:00 16:00 6:00 Emergency Quarterly maintenance work 7/30/2022 odu,Hagalagere,Rangavalli,Pilapura,Devigere,Vedavathi,B V NO
Nagara, Mavinakatte palya, Attighatta and the surrounding areas.

HSD
80 CTAZ Chitradurga Hosadurga 66/11 kV MUSS Bagur 8/24/2022 8/24/2022 10:00 16:00 6:00 Emergency Quarterly maintenance work 7/30/2022 Exp,Illapura,Bagur,Hebballi,Sanihalli,Srirangapura,Anival,HSD NO
RURAL and surrounding areas.

66/11 kV MUSS Neergunda,Adrikatte,ShriMATA,Aladahalli and the surrounding


81 CTAZ Chitradurga Hosadurga 8/24/2022 8/24/2022 10:00 16:00 6:00 Emergency Quarterly maintenance work 7/30/2022 NO
Neergunda areas.

All 66KV Stations from Madure and 11 KV Feeders Fed from


82 CTAZ Chitradurga Hosadurga 220 kV MUSS MADURE 8/24/2022 8/24/2022 10:00 16:00 6:00 Emergency Quarterly maintenance work 7/30/2022 NO
Madure

Thallak, Rudrammanahally, Banjigere, devarahalli, 10MW of stations


83 CTAZ Davanagere Davanagere Hiriyuru Thallak_66 8/24/2022 8/24/2022 10:00 16:00 6:00 1&2nd quarterly maintenance work. 7/30/2022 nayakanahatti, bedareddihalli, valase, hirehalli, load NO
chikkammanahalli, buklarahalli.

220kV Somanahalli-Bidadi For carrying out periodical maintenance works as per


O&M Division, line-1 bay at maintenance schedule for 2nd quarter. Load of 220kV No load will be
262 BMAZ SOUTH Somanahally BMAZ[S] 8/24/2022 8/24/2022 10:00 16:00 6:00 7/30/2022 No load will be affected. No load will be affected.
BESCOM, Kengeri 220/66/11kV R/S, Somanahalli-Bidadi line-1 will be taken on 220kV affected.
Somanahalli, Bengaluru. Somanahalli-Bidadi line-2. No load will be affected.

NRS Sunkadakatte, Kamakshipalya, Malathahalli, Niligiri thopu, Most of the 11kV load will be changed over to
66/11 kV Srigandhakaval Quarterly maintenance work of 66kV Lines,Bus and 11kV During LC period,10MW of load will be changed over to other
263 BMAZ North NRS North Division,Rajajinagar 8/24/2022 8/24/2022 10:00 16:00 6:00 7/30/2022 Hegganahalli, Annapoorneshwarinagara, Pattegarpalya, 2 neighbouring stations and only 2MW load will
MUSS Bus bar isolator at 66/11kV Srigandhakaval station. Stations by BESCOM
. Kottigepalya, Kengunte. be affected during LC period.

LC request on 25.08.2022 shall be


Banagirinagar, Jayanagar 7th block, BSK2nd stage,BDA
12 MW load can be shifted on nearby stations 66/11kV considered. 
220kV Jayanagara(S1,S9,S 66/11kV Complex,Channamanakere Achhakatu, Saroja Complex,
84 BMAZ South South 8/25/2022 8/25/2022 10:30 12:30 2:00 Periodic maintainance works 7/30/2022 19 Sarakki, Nimhans, Banashankari, ISRO Layout, by Bescom Previous date of Station LC was on 09.02.2022
Subramanyapura 14 subdivision), I Padmanabhanagara Rajivnagar, Padmanabhanagar, Yarabnagar, TATA Silkfarm,
at the time of line clear. S9 Subdivision - No change over
Shastrinagar, S9 Subdivision premises, 9th Main Batashowroom.
arranged,
Duration of LC request

Name of the Name of the KPTCL Name of the BESCOM Name of the BESCOM Date on which last
Sl no
KPTCL Circle Division Circle Division
Sub Division Name of the station/Line Feeder Date Time Reason for availing LC
LC was approved
Areas Affected Load Affected (MW) Wheather alteranate Power Supply Arranged or not Remarks Consent

From To From To Duration

LC request on 25.08.2022 shall be


considered. 
220kV Jayanagara(S1,S9,S 66/11kV 16 MW load of Tr-1 can be shifted on Trf-2 through Bus
85 BMAZ South South 8/25/2022 8/25/2022 13:30 16:00 2:30 Periodic maintainance works 7/30/2022 F1-Banagirinagara, F2-Jayanagar 7th block, F13-Saroja Complex. 2.5 Previous date of Station LC was on 09.02.2022
Subramanyapura 14 subdivision), I Padmanabhanagara coupler.
S9 Subdivision - No change over
arranged,

110/11 Kv S/s
86 CTAZ K.B Cross 8/25/2022 8/25/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance
KEREKODI

87 CTAZ K.B Cross 66/11KV S/s, Hebbur 8/25/2022 8/25/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance

All 66KV Stations from SRS and 11 kV Peedere Fed from SRS
Nagara ,kelagotte bank colony ,gONURU , belagatta, O R
66/11 kv MUSS SRS & SS
88 CTAZ Chitradurga 8/25/2022 8/25/2022 10:00 16:00 7hrs emergency quarterly maintainance work halli ,vidhyanagara , seebar, CG Halli , JC badavane , chandravally
division chitradurga
, PK HALLY, MILL AREAS
kwssb UNIVERSITY

All 66KV Stations from SRS and 11 KV Feeders Fed from SRS,
NAGARA,KELAGOTE,BANK COLONY,GONURU,BELAGATTA,G R
220/66/11 kv SRS &SS
89 CTAZ Chitradurga Chitradurga Urban 8/25/2022 8/25/2022 10:00 16:00 6:00 Emergency Quarterly maintenance work 7/30/2022 Halli,VIDHYANAGARA,SEEBAR,C G HALLY,JCR NO
Division Chitradurga
BADAVANE,CHANDRAVALLY,P K HALLY,MILL
AREA,KWSSB,UNIVERSITY

12MW of station load


90 CTAZ Davanagere Davanagere Hiriyuru Rampura_66 8/25/2022 8/25/2022 10:00 16:00 6:00 1&2nd quarterly maintenance work. 7/30/2022 All areas pertaining to Rampura station and generation of NO
24MW

Giddobanahalli and Mallappanahally,harthikote,


91 CTAZ Davanagere Davanagere Hiriyuru Mallappanahally_66 8/25/2022 8/25/2022 10:00 16:00 6:00 1&2nd quarterly maintenance work. 7/30/2022 7MW of stations load NO
Giddobanahally,industrial area,salabbonahalli,

Peak load-24MW,
Replacement of old AREVA make 11kV switchgears with load changeover will
66/11kV Electronic City
27-08-2022 New 11kV DAS/SCADA compatible MEI make switchgears Electronic City Ph-1, Hongasandra, Bommanahalli Main Road, be arranged by LC may be availed, Interuption
264 BMAZ South HSR Layout South HSR Layout Ph-2 Sec-1 (Velankani) 8/25/2022 10:00 16:00 6:00 7/30/2022 Load Change Over-24MW GCW Work
( pertaining to Trf-2 i.e. Bank-2, F6, F7, F8, F9, F10, F12, NGR Layout BESCOM as per paper notification to be given
S/s
F13) MOM. No load will be
affected

220kV Somanahalli-Bidadi For carrying out periodical maintenance works as per


O&M Division, line-2 bay at maintenance schedule for 2nd quarter. Load of 220kV No load will be
265 BMAZ SOUTH Somanahally BMAZ[S] 8/25/2022 8/25/2022 10:00 16:00 6:00 7/30/2022 No load will be affected. No load will be affected.
BESCOM, Kengeri 220/66/11kV R/S, Somanahalli-Bidadi line-2 will be taken on 220kV affected.
Somanahalli, Bengaluru. Somanahalli-Bidadi line-1. No load will be affected.

110/11 Kv S/s
92 CTAZ K.B Cross 8/26/2022 8/26/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance
NONAVINAKERE

Consent is Given to avail LC on


26.08.2022.( Note: if any exams &
66/11kV Sub staion Shivanahalli, Bannikuppe, Kadanakuppe, Kavanapura, emergency programs comes near to
93 Ramanagara Somanahalli Ramangara Ramanagara 8/26/2022 8/26/2022 10:00 16:00 6:00 To carry out periodical 2nd quarterly maintenance work 7/30/2022 10MW NO
Shivanahalli Ankanahalli, Lakkojanahalli that date I,e 26.8.2022 , the LC
date should change /postpone to
another date )

Consent is given to Avail LC on


94 BRAZ DBPura BRC Kengeri Nelamangala 66/11kV S/s Kanaswadi 8/26/2022 8/26/2022 10:00 16:00 6:00 Quarterly maintenance works of the station. 7/30/2022 Kanaswadi and surrounding areas No
26.08.2022

1. To carry out Maintenance work of incoming line, outgoing


line, Transformer Bays, 66kV bus Gos,11kV bus and
1. Peak Load of Station is 21MW, Load change over of 11MW
breaker maintenance.
Vidyaranyapura, Yelahanka New Town, KMF,Maruthi Nagar, shall be done by BESCOM to neighboring stations. 2. 10MW
Additional Central 66/11kV Attur Yelahanka 2. For attending Hotspot works.
266 BMAZ North Hebbal East 8/26/2022 8/26/2022 10:00 16:00 6:00 7/30/2022 M.S.Palya, L&T, NCBS, Attur Layout, Purvankara Block-1,2,3, 10MW LOAD WILL BE INTERRUPTED for 7:30hrs during 66kV &
Division Station 3. For carrying out IR test of all equipements like CT's, PT's,
RMZ , Judicial Layout. 11kV bus & PT maintainence
LA's, Transformers, 66kV Breakers, 11kV Breakers, Wall
entry bushings and 11kV Bus.
4. For conducting Tan-Delta.

F-1 Guddadahalli, F2- Kaggere, F3- bidare, F4- ranganathapura,


F5- Gowripura,
95 CTAZ 110/11kV Bidare 8/27/2022 8/27/2022 10:00 16:00 8hrs Q1/1st Quarter Maintenance 13mw
F6-Jainigarahally, F7- MS Pallya, F8- Kashimath, F9-
Muniyappanapallya

F-1 SG Palya,F-2 Habbathanahalli,F-3 Mallasandra, F-4


Mallasandra Rural,F5
(A) Kaggere,F-S (8) Asalipura,F-6 Gollahalli NUY,F-13 Gowdihalli,
96 CTAZ 66/11kV Mallasandra 8/27/2022 8/27/2022 10:00 16:00 8hrs Q2/Half Yeartly Maintenance works 15mw
F-14 KallipalyaF
7 Doddanaravangala
F-8 Chowkenahalli, F-9 KMF,F-11 Jogirahatti, F-12 Muddigere
10kV Renew Energy Solar Line,
F-1 Thovinakere, F-2 Sarigehalli, F-3 Byadarahall
F-4 Ramadihalli, F-5 Mallenahalli, F-6 Sampige,F-7
Angarekhanahalli,F-8
97 CTAZ 110/11kv sampige 8/27/2022 8/27/2022 10:00 16:00 8hrs Q2/Half Yeartly Maintenance works 17mw
Halesampige, F-9 Raghadevanahalli, F-10 Basavapura,F-11
machenahalli, F
12Doddahatti, F13-8.C.Kaval_
F-14-Yalladabhagi
Kodagihallichengavi and Kunnalapanchyat limits,F1- N.S.
Devarahatti (Rural),F2
Surigenahalli (Rural), F3-Ungra (Rural), F4- Kunnala (Rural),F5-
98 CTAZ 110/11kV KG Temple 8/27/2022 8/27/2022 10:00 16:00 8hrs a1/ 1st Quarter Maintenance Koppa (Rural), F6- 25mw
Nagasandra (NJY),F7- Kodigehalli (Rural),F8- Changavi (Rural), F9-
Hosapalya
(Rural), F10- Mallappanahalli (Rural), F12- Konanakere (NJY
F-1 Kodihalli, F-2 Kadashettyhalli, F-3 Belvatha, F-4 H.S.Hally, F-
9 Bennuru NJY,FS
B. Mallenahally, F-6 Gangasandra, F-7 Kadaba,F-8 Byalahalli, F-
99 CTAZ 110/11kv Kadaba 8/27/2022 8/27/2022 10:00 16:00 8hrs a1/ 1st Quarter Maintenance 25mw
10 D.k.Hally
NJY,F-11 Belvatha NJY,F-12 HAL water supply,F-13
Thogarighatta,F-14 Hosuru

F1-Chinnayanapalya, F2-chanahalli, F3- IdaguruF4- Ankalakoppa,


F5- C.S Pura
100 CTAZ 110/11kv Ungra 8/27/2022 8/27/2022 10:00 16:00 8hrs a1/ 1st Quarter Maintenance 15mw
NJYF6-WatersupplyF7-Naranhally.F8-Ungra, F9- Manekuppe
F10- Gaddehally
F1-C.S.Pura (Rural), F2-Peddanahalli (Rural),F3-Kadaba (Rural),
F4-Byadigere
(Rural),FS-Kallur (Urban), F6-Hindiskere (Rural),F7-K. Kallahalli
(Rural), F8
Ankalakoppa (Rural), F9- Manchihalli (Rural), F10- Kurubarahalli
101 CTAZ 110/11kv Kallur 8/27/2022 8/27/2022 10:00 16:00 8hrs Q1/1st Quarter Maintenance 24mw
(Rural),F-11
Benakanaguni(Urban), F12- NJY B.G Halli, F13- NJY Madapatna,
F14- NUY
F1-KORE,F2-KONDLY,F3-BADAVANAPALYA
Mallenahali, F-15 NJY T.palya, F-16 pendranahalli, F-17 NJY
F4-DODDAGUNI,FS-NERALEKERE,
Padugudi. F6-THAGGIHALLY
10:00 18:00 Q1/ 1st Quarter Maintenance
F7-BADENAHALLY(NJY),.F8-SHIVASANDRA(NJY), F9-
102 CTAZ 110/11kv Doddaguni 8/27/2022 8/27/2022 10:00 16:00 8hrs Q1/1st Quarter Maintenance 15mw
6.OBALAPURA(NJY), F10-
HARENAHALLY(NJY),F11-MAVINAHALLI,
GubbiTown,Herur, F12-kanchiganahali,
GHosahalli, MHPatna,Ammangatta Gram
F13-
panchyat Limits
DINDIGADAHALLI,F14-PERMASANDRA,F15-BENNEHALLA
F-1 Gopalapura,F-2 G.Hosahalli, F-3 NJY Tippur, F-4 KAVAL
Singonahalli, F-5 Torehalli
(GH),F-5 Torehalli (MH),F-6 NJY Madapura,F-7 Kodigenahalli, F-8
267 CTAZ 110/11kv Gubbi 8/27/2022 8/27/2022 10:00 16:00 8hrs a1/1st Quarter Maintenance Koppa,F-9 35mw
Herur,F10 M.H.Patna ,F11- Uddehosakere, F12- Honnavalli, F13-
Bidre,F14
Ammanagatta,F15- Gubbi Town,F16 -KMF,F-17 NY,F-18
21-Vadaluru Kere,F24
D.Kattigenahli, F20 (F6-Madapura NJY)
Nittur
Bescom and SomalapurGramaPanchayat Limits
subdivision_
|F1-H.Nagenahalli, F2-M.N.Kote,F3-Gollahalli, F4-Mathikere,F5-
110/11kv s/S
268 CTAZ 8/27/2022 8/27/2022 10:00 16:00 8hrs a1/ 1st Half Year Maintenance Uddehoskere, F6- 12mw
Somalapura
Somalapura Town
F7-Bagur (NJY), F8-Sankapura (NJY)
F9-Gyarahali
Duration of LC request

Name of the Name of the KPTCL Name of the BESCOM Name of the BESCOM Date on which last
Sl no
KPTCL Circle Division Circle Division
Sub Division Name of the station/Line Feeder Date Time Reason for availing LC
LC was approved
Areas Affected Load Affected (MW) Wheather alteranate Power Supply Arranged or not Remarks Consent

From To From To Duration

f1-ThalikoppaF2-Thonasanahally'F3-EnnekatteF4-Irksandra
FS-Town FeederF6- Jalaguni
F7-H palyaF8-Nimbaekatae
269 CTAZ 66/11KV Cheluru 8/27/2022 8/27/2022 10:00 16:00 8hrs Q2/Half Yearly Maintenance works F9- MadenahallyF10-Idakanahally 10mw
F11-C HarivaesandraF12 Water SupplyF13 NJY NallurF14 NJY
KodiyalaF15-NJY S
HALLI
Ankasandrapanchyat limits
F1-Gangayanapalya, F2-Kuntaramanahalli, F3-Nirantara
Jyothi,F4-Idle, F5-
270 CTAZ 66/11KV Ankasandra 8/27/2022 8/27/2022 10:00 16:00 8hrs a2/Half Yearly Maintenance works 14mw
Kallugudi, F6-Ankasandra, F7-Ranganahally, F8- ByadarahallyF9-
Devarahally, F10-
Sarigepalya,F11- Yarabally

271 CTAZ 66/11KV Hoskere 8/27/2022 8/27/2022 10:00 16:00 8hrs Q1/ 1st Half Year Maintenance F1,F2,F3,F4,F5,F6,F7,F8F9,F10,F11,F12 25mw

F1- Kurehalli, F2-MATTIKERE, F3-HAGALAWADI (NJY), F4-


272 CTAZ 66/11KV Hagalvadi 8/27/2022 8/27/2022 10:00 16:00 8hrs Q1/Half Yearly Maintenance works 6mw
GUDDENAHALLI

273 CTAZ 66/11KV Nandihalli cross 8/27/2022 8/27/2022 10:00 16:00 8hrs Q1/ 1st Quarter Maintenance F1 F2 F3 F4 4mw

11 KV Side-F1-Kodihali F2 -Yelapura F3-Sagaranahalli, F4- A


M.S.halli, F4 'B,FS-Hemavati, "f-12 Ban Ily (Y operated)". F18 -
Pura njy,F19
Bommenahalli niy.F6{A) - Tyagtur,F6(B) Tyagtur F7 -Benachigere,
274 CTAZ 220 KV R/s Nittur 8/27/2022 8/27/2022 10:00 16:00 8hrs Monthly Maintenance 30mw
F8 -
Hesarahalli, F9 - Belvatha,F11-Mattigatta ,F13- MN Kote F14-
Rampura, F15-
Nittur (urban).F 16-Sopanahalli NJY

220kV HSR(S10,S12s LC may be availed, Interuption


103 BMAZ South South 66/11kV DLF(Annabel) 8/28/2022 8/28/2022 10:00 16:00 6:00 Periodic maintainance works 7/30/2022 DLF Apartment 1 MW No Previous date of Station LC was on 15.03.2022
Subramanyapura subdivision) paper notification to be given

110/11 Kv S/s
225 CTAZ K.B Cross 8/29/2022 8/29/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance
GUNGURUMALE

Consent is Given to avail LC on


29.08.2022.( Note: if any exams &
66/11kV Sub staion Akkur, Thalwadi, Veroopasandra, Chikkaganwadi and emergency programs comes near to
226 Ramanagara Somanahalli Ramangara Ramanagara 8/29/2022 8/29/2022 10:00 16:00 6:00 To carry out periodical 2nd quarterly maintenance work 7/30/2022 5MW NO
URAGAHALLI Doddagangawadi that date I,e 29.8.2022 , the LC
date should change /postpone to
another date )

19MW of stations
104 CTAZ Davanagere Davanagere Hiriyuru Nagasamudra_66 8/30/2022 8/30/2022 10:00 16:00 6:00 1&2nd quarterly maintenance work. 7/30/2022 All areas pertaining to Nagasamudra and Rampura stations. load and generation NO
of 32MW

110/11 Kv S/s
227 CTAZ K.B Cross 8/30/2022 8/30/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance
AMMASANDRA

110/11 Kv s/s
228 CTAZ K.B Cross 8/30/2022 8/30/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance
KADEHALLY

Consent is given work can be taken


1. To carry out Maintenance work of incoming line, outgoing
line, Transformer Bays, 66kV bus Gos,11kV bus and Total 4 nos feeder belongs to c9
breaker maintenance. Peak Load of Station is 12 MW, Load change over of 8MW sd .F01,F02,F13,F07 feeders Partial
Yelahanka old Town, Yelahanka Newtown, Yelahanka Industrial
C7 Yelahanka new 66/11 kV KHB Colony 2. For attending Hotspot works. shall be done by BESCOM to neighboring stations. load will be shifted to other Stn(F01
327 BMAZ Northb Hebbal North 8/30/2022 8/30/2022 10:00 16:00 6:00 7/30/2022 Layout, Yelahanka 4th& 5th Phase, chikka bommasandra, 4MW
town MUSS, Yelahanka 3. For carrying out IR test of all equipements like CT's, PT's, 1. During LC peroid 4MW of load will be effected for 7:30hrs feeder to F11 Abbigere full
Anantha pura, Puttenahalli, Ramagondanahalli, Kempanahalli etc
LA's, Transformers, 66kV Breakers, 11kV Breakers, Wall during 66kV & 11kV bus & PT maintainence load ,F02 load F09 skn and F10
entry bushings and 11kV Bus. gokula stn 45 to 50% load change
4. For conducting Tan-Delta. over,F13 and F7 load KHB F12
partial load 30% change over)

105 CTAZ K.B Cross 110/11kv S/s C.N.Hali 9/7/2022 9/7/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance

110/11KV S/s
106 CTAZ K.B Cross 9/7/2022 9/7/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance
THIMANAHALLY

110/11KV S/s
107 CTAZ K.B Cross 9/7/2022 9/7/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance
HANDANAKERE

110/11KV S/s
108 CTAZ K.B Cross 9/7/2022 9/7/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance
SHETTIKERE

110/11KV S/s
109 CTAZ K.B Cross 9/7/2022 9/7/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance
Kathrikehal

110 CTAZ K.B Cross 110/11 Kv S/s Huliyar 9/7/2022 9/7/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance

110/11 kv S/s
111 CTAZ K.B Cross 9/9/2022 9/9/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance
HONAVALLI

112 CTAZ K.B Cross 66/11KV S/s Dasudi 9/14/2022 9/14/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance

113 CTAZ K.B Cross 110/11KV S/s Halkurke 9/23/2022 9/23/2022 10:00 16:00 7hrs Q2/ 1st Half Year Maintenance