PEPERIKSAAN AKHIR
SESI DISEMBER 2017
SULIT
SULIT DCQ5083: BUILDING WORKS MEASUREMENT 4
Notes:
Nota-nota:
3. Marks will be given for the knowledge of the subject, clear and systematic setting
of dimensions, adequacy and accuracy of description and dimensions.
Markah akan diberi untuk pengetahuan tentang subjek, tata atur yang sistematik,
kecukupan dan ketepatan dimensi dan keterangan.
2
SULIT DCQ5083: BUILDING WORKS MEASUREMENT 4
SECTION A: 50 MARKS
BAHAGIAN A: 50 MARKAH
INSTRUCTION:
This section consists of TWO (2) structured questions. Answer ALL the question.
ARAHAN:
Bahagian ini mengandungi DUA (2) soalan berstruktur. Jawab SEMUA soalan.
QUESTION 1
SOALAN 1
CLO1 (a) Referring to SMM2, identify the THREE (3) clauses that explain the sheet piles.
C2 Merujuk kepada SMM2, kenal pasti TIGA (3) klausa yang menerangkan tentang cerucuk
kepingan.
[3 marks]
[3 markah]
CLO1 (b) Based on the Drawing No. DCQ5083/PILING/01, carry out the quantities measurement
C3 for the interlocking sheet pile.
Berpandukan Lukisan No. DCQ5083/PILING/01, ukur kuantiti bagi cerucuk kepingan
saling kekunci.
[14 marks]
[14 markah]
CLO1 (c) Conclude all the measured quantities in question 1 (b), as the bill of quantities.
C4 Rumuskan semua kuantiti terukur dalam soalan 1(b) sebagai senarai kuantiti.
[8 marks]
[8 markah]
3
SULIT DCQ5083: BUILDING WORKS MEASUREMENT 4
QUESTION 2
SOALAN 2
Diagram A/ Rajah A
CLO1 (a) Based on Diagram A, list the complete taking off list for the reinforced concrete counter
top.
C2
Berdasarkan Rajah A, sediakan senarai kerja pengukuran lengkap untuk kerja-kerja
kaunter atas konkrit
[3 Marks]
[3 markah]
CLO1 (c) Conclude all the measured quantities in question 2(b) as the bill of quantities.
C4 Rumuskan semua kuantiti terukur dalam soalan 2(b) sebagai senarai kuantiti.
[8 marks]
[8 markah]
4
SULIT DCQ5083: BUILDING WORKS MEASUREMENT 4
SECTION B : 50 MARKS
BAHAGIAN B: 50 MARKAH
INSTRUCTION:
This section consists of FOUR (4) questions. Answer TWO (2) questions only.
ARAHAN:
Bahagian ini mengandungi EMPAT (4) soalan berstruktur. Jawab DUA (2) soalan sahaja.
QUESTION 1
SOALAN 1
CLO1 (a) Based on Clause Q.32 (1) SMM2, explain the measurement requirement for excavation in
C2
building services works.
Berdasarkan Klausa Q.32 (1) SMM2, terangkan keperluan pengukuran bagi penggalian
dalam kerja kemudahan bangunan.
[3 marks]
[3 markah]
CLO1 (c) Conclude all the measured quantities in question 1 (b) as the bill of quantities.
C4 Rumuskan semua kuantiti terukur dalam soalan 1(b) sebagai senarai kuantiti.
[8 marks]
[8 markah]
5
SULIT DCQ5083: BUILDING WORKS MEASUREMENT 4
QUESTION 2
SOALAN 2
CLO1 (c) Conclude all the measured quantities in question 2(b) as the bill of quantities.
C4 Rumuskan semua kuantiti terukur dalam soalan 2(b) sebagai senarai kuantiti.
[8 Marks]
[8 markah]
QUESTION 3
SOALAN 3
CLO1 (a) Based on the Clause E.5.7 (b) in SMM2, explain the measurement requirement for piling
C2 works.
Berdasarkan Klausa E.5.7(b) dalam SMM2, terangkan keperluan pengukuran bagi
kerja-kerja cerucuk.
[3 marks]
[3 markah]
6
SULIT DCQ5083: BUILDING WORKS MEASUREMENT 4
(b) Based on the Drawing No. DCQ5083/Timber Pile/01, carry out the quantities
CLO1
C3 measurement for Timber pile EXCEPT item for test pile.
Berdasarkan Lukisan No. DCQ5083/Timber Pile/01, ukur kuantiti bagi Cerucuk kayu
KECUALI item untuk ujian cerucuk.
[14marks]
[14 markah]
CLO1 (c) Conclude all the measured quantities in question 3(b) as the bill of quantities.
C4 Rumuskan semua kuantiti terukur dalam soalan 3(b) sebagai senarai kuantiti.
[8 marks]
[8 markah]
QUESTION 4
SOALAN 4
CLO1 (a) Referring to the SMM2, identify and explain the clause related to the testing of plumbing
C2 works.
Merujuk SMM2, kenalpasti dan terangkan fasal berkaitan pengujian terhadap kerja-
kerja perpaipan.
[3 marks]
[3 markah]
CLO1 (b) Based on the Drawing No. DCQ5083/ SERVICES/ 01 and DCQ5083/ SERVICES/ 02,
C3
carry out the quantities measurement for plumbing work from water tank to Bath 1.
Berpandukan Lukisan No. DCQ5083/SERVICES/01 dan DCQ5083/SERVICES/02, ukur
kuantiti bagi kerja perpaipan dari tangki air ke Bilik Air 1.
[14 marks]
[14 markah]
7
SULIT DCQ5083: BUILDING WORKS MEASUREMENT 4
CLO1 (c) Conclude all the measured quantities in question 4(b) as the bill of quantities.
C4
Rumuskan semua kuantiti terukur dalam soalan 4(b) sebagai senarai kuantiti.
[8 marks]
[8 markah]
SOALAN TAMAT
8
NOTES:
1. Timber pile cross section = 150mm X
150mm
2. Initial Pile Length = 3.0 metre
3. Extension Pile Length = 3.0 metre
4. Penetration Depth = 26.0 metre
A B C D 5. Mild Steel piles sleeve extension joint
= 160mm x 160mm x 450mm long
6. Working Load = 50 Tonne
3P 3P 3P 3P 7. Load Test = Twice Working Load
X X X X X X X
1 X
X X X X TITLE:
PILE FOUNDATION LAYOUT
SCALE: NOT TO SCALE
DRAWING. NO:
DCQ5083/Timber Pile/01
Side cast
Length
No Heading Description Unit location x (m)/ no Width (m) Height (m) Qtty Mark
Supply and install TNB meter box approved by TNB all
no 1 4
1 in accordance with TNB regulation 1
Supply and install main distribution board complete
with fuse current or voltage operated and circuit no 1 1 4
breaker (ELBC) all in accordance with TNB regulation
2
3