INDEX OF CHECK LISTS - Fire Fighting

SL.NO DESCRIPTION
1 Hydrant External
2 Hydrant External Yard
3 Hydrant Internal
4 Sprinkler External
5 Sprinkler Internal
6 Sprinkler External Yard

Project Management Group


CB Richard Ellis
Inspection Report
( Hydrant External )

Client WeWork Inspection Report No


Consultant : Date
Package : Fire Fighting Inspection Request No
Vendor : Date
Description of Work :
Wing : Dwg.Ref.No Rev : Inspection Request
Floor : Details : Inspected by By Time
Location
Sl.
Description YES NO Remarks
No
1.0 Check Hydrant Valves
2.0 Check Gate Valves
3.0 Check Butterfly Valves
4.0 Check the approved shop Drawing

Observations if any :

The above works have been completed and checked and are ready for inspection

Vendor : Consultant : CBRE :


Signature : Signature : Signature :
Name : Name : Name :

Project Management Group


CB Richard Ellis
Inspection Report
( Hydrant External Yard )

Client WeWork Inspection Report No


Consultant : Date
Package : Fire Fighting Inspection Request No
Vendor : Date
Description of Work :
Wing : Dwg.Ref.No Rev : Inspection Request
Floor : Details : Inspected by By Time
Location
Sl.
Description YES NO Remarks
No
1.0 Check the approved drawing
2.0 Check the piping
3.0 Check the Butterfly Valves
4.0 Check the Hydrant Valves
5.0 Check the Fire Hose Cabinet
6.0 Check the Hose / Branch Pipe
7.0 Check the Gate Valves

Observations if any :

The above works have been completed and checked and are ready for inspection

Vendor : Consultant : CBRE :


Signature : Signature : Signature :
Name : Name : Name :

Project Management Group


CB Richard Ellis
Check list for Sprinkler System Hydro Test
Wework, Futura, Pune
Client WeWork Inspection Report No
Consultant/PMC CBRE Date
Package Inspection Request No
Vendor Date
Description of Work fire fighting -sprinkler pipe line hydrostatic test
Wing : Dwg.Ref.No Rev : Inspection Request
Floor : Details : Inspected by By Time
Location
Sl.
Description YES NO Remarks
No
1.0 Check the approved drawing
2.0 Check the Piping
3.0 Check the Butter fly Valves
4.0 Check the Test Drain Valves
5.0 Check the Air vent lines
6.0 Check the Flushing Outlet
7.0 Check PRV
8.0 Check the Sprinkler Head & branch piping
9.0 Check the all Dummie plugs
10.0 testing pipe sketch attached
11.0 testing team identification
12.0 testing area barrication
13.0 sign boards / signs
14.0 pressure gauge calibaration certificate
15.0 pump machinary third party certificate

Observations

Vendor CBRE-PjM Consultant

Signature
Name
Date

Format No. F037-QC-Ch-143/Rev01/Oct2013

CBRE South Asia Pvt. Ltd. Project Management, India 5 of 5