Professional Documents
Culture Documents
PM Module2 ProjectPlanning 21-23
PM Module2 ProjectPlanning 21-23
PM Module2 ProjectPlanning 21-23
1
NLDIMSR
Project Management
Agenda
• Project Planning
• Network Analysis
• Critical Path Method
Project Planning
• Planning means predicting or forecasting the future activities and jobs in advance.
• Basic reason is to develop model, so as to aid Project Manager to identify critical
tasks which require timely completion
• In Project planning following needs to be defined:
1. Goals of project and respective activities for accomplishing them
2. Documentation of various estimates for controlling and correcting
3. Documentation of the agreements by the affected groups and individuals
4. Presence of alternatives and substitutes for constraints in the project
1. Identification of Project
2. Project Formulation
3. Project Appraisal
4. Project Selection
Estimating Projects
• Estimating
• The process of forecasting or approximating the time and cost of completing
project deliverables.
• The task of balancing expectations of stakeholders and need for control while
the project is implemented.
• Types of Estimates
• Top-down (macro) estimates: analogy, group consensus, or mathematical
relationships
• Bottom-up (micro) estimates: estimates of elements of the work breakdown
structure
Estimating Projects
Preferred Approach
• Make rough top-down estimates.
• Develop the WBS/OBS.
• Make bottom-up estimates.
• Develop schedules and budgets.
• Reconcile differences between top-down and bottom-up estimates
Cost Estimates
Project cost budgeting involves allocating the project cost estimate to individual
work items overtime. Estimation of Project Cost involves:
1. Estimation of Capital Cost of Project
2. Estimation of Cost of Production/Operating cost of Project
3. Estimation of Working Capital requirement
1. Direct Cost
i. Material cost
ii. Labour cost
iii. Sub-contractors and consultants
iv. Equipment and Facilities Rental
2. Overhead Costs
i. Direct Overhead Costs
ii. General and Administrative ( G&A) Overhead costs
Network Analysis
• Network Analysis is the tool used for planning, scheduling, and monitoring
project progress.
• The network is developed from the information collected for the WBS and is a
graphic flow chart of the project job plan.
• The network depicts the project activities that must be completed, the logical
sequences, the interdependencies of the activities to be completed, and in most
cases the times for the activities to start and finish.
• The network can be constructed through series of arrows and nodes
conveniently expressing the sequential nature of the project.
Terminology
Path: a sequence of connected, dependent activities.
Critical path: the longest path through the activity network that allows for the completion
of all project-related activities; the shortest expected time in which the entire project can
be completed. Delays on the critical path will delay completion of the entire project.
C
A B D
Terminology
Event: a point in time when an activity is started B
or completed. It does not consume time.
Burst Activity: an activity that has more than one activity
immediately following it (more than one dependency arrow
flowing from it). A C
Two Approaches
• Activity-on-Node (AON)
• Uses a node to depict an activity. D
• Activity-on-Arrow (AOA)
• Uses an arrow to depict an activity.
10. Use dummy activity freely in rough graph but final network should have only
reluctant dummy.
Activity-on-node Fundamentals
A comes before B,
(a) A B C which comes
before C A B C
A A
A and B must both be
(b) C completed before C
can start C
B B
B
B and C cannot
(c) A begin until A is B
completed A
C C
Title / Author: Project Management/Anand Dhutraj Page No. 36
NLDIMSR
A Comparison of AON and AOA
Network Conventions
Activity on Activity Activity on
Node (AON) Meaning Arrow (AOA)
C and D cannot
A C begin until A and
A C
(d) B have both been
completed
B D B D
B and C cannot
begin until A is
completed. D
A B D cannot begin until A B D
both B and C are
(f) completed. A Dummy C
C dummy activity is activity
again introduced in
AOA.
Locate 2 setup
facilities
Remodel
1 5 6
Move in
Interview
Hire and
train
3
Title / Author: Project Management/Anand Dhutraj Page No. 39
NLDIMSR
AON Locate
facilities
2 setup
1 6
Move in
Remodel
S 5 7
Hire and
Interview
train
3 4
In Fig above the activity 5 to 8, 6 to 7 are known as dangling error. These are not last
activities in the network.
Ei Lj Time (t) Ei Lj
T H
Network Information
Activity-on-node Network
• Subtract activity times along each path in the network (LF - Duration = LS).
• Carry the late start (LS) to the next activity where it becomes its late finish
(LF) unless
• The next succeeding activity is a burst activity, in which case the smallest LF
of all preceding activities is selected.
Problem 1
A project has the following times schedule
Problem 1 Solution 18 18
4 12
Solution The
network is
11 16
5 13
25 25
17 17
0 0
1 1 7 7 15 15
Problem 1 Solution
1-3-5-6-8-9-10 20
1-2 4 0 4 8 12
1-3-4-9-10 14
1-3 1 0 1 0 1
1-3-5-7-8-9-10 25
2-4 1 4 5 12 13
1-3-5-7-8-10 25
3-4
3-5
The two critical paths are 4-9
i. 1 → 3 → 5 →7 → 8 → 9 →10 1
ii. 1 → 3 → 5 → 7 → 8 →10
Problem 2
• A small project consists of following eight activities:
Activity Preceding Activity Duration (days)
• Draw network diagram and find
A - 20
critical path and project
B A 25
completion time.
C A 5
D B 15 • Find EST, EFT, LST and LFT for all
E C 30 the activities.
F D 35 • Calculate Slack and Float of all
G E 5 activities.
H F, G 2
Problem 2 Solution
Problem 2 Solution
Problem 2 Solution
Problem 3
• A small project consists of following eight activities:
Activity Preceding Activity Duration (days)
• Draw network diagram and find
A - 4
critical path and project
B - 5
completion time.
C - 7
D A 6 • Find EST, EFT, LST and LFT for all
E B 7 the activities.
F C 6 • Calculate Slack and Float of all
G D 5 activities.
H E 8
I F 5
Problem 3 Solution
Problem 3 Solution
Problem 3 Solution
Crashing Concepts
• Project duration can be reduced by assigning more resources to project
activities.
Project Costs
• The total project costs are the sum of direct costs, indirect costs, and
penalty costs.
• Direct costs include labor, materials, and any other costs directly
related to project activities.
• Indirect costs include administration, depreciation, financial, and
other variable overhead costs that can be avoided by reducing total
project time.
• The shorter the duration of the project, the lower the indirect costs will be.
Cost to Crash
To assess the benefit of crashing certain activities, either from a cost or a schedule
perspective, the project manager needs to know the following times and costs.
Normal time (NT) is the time necessary to complete an activity under normal
conditions.
Normal cost (NC) is the activity cost associated with the normal time.
Crash time (CT) is the shortest possible time to complete an activity.
Crash cost (CC) is the activity cost associated with the crash time.
= $2000/5 = $400/wk
Example
Sharon Lowe, Vice President for Marketing for the Electronic
Toys Company, is about to begin a project to design an
advertising campaign for a new line of toys. She wants the
project completed within 47 days in time to launch the
advertising campaign at the beginning of the Christmas
season.
Sharon has identified the six activities (labeled A, B, …, F)
needed to execute this project. Considering the order in
which these activities need to occur, she also has
constructed the following project network.
NLDIMSR
Example (Contd.)
A C E F
START F IN IS H
B D
NLDIMSR
Example (Contd.)
To meet the deadline of 47 days, Sharon has decided to crash the project, using the CPM method of
time-cost trade-offs to determine how to do this in the most economical way. She has gathered the data
needed to apply this method, as given below.
Time (days) Cost Maximum Crash
Activity Reduction in Cost per
Normal Crash Normal Crash Time day saved
Example - Solution
The upper path is A-C-E-F with a path length of 51 days which is the critical path.
Of the activities on the path, activity C has the smallest crash cost per day saved ($10,000) and
activity E is next ($15,000). Activity C can only be reduced by 3 days, so activity E also will need to
be crashed somewhat. Therefore, we find that the most economical way of reducing the length of
this path to 47 days is to shorten activity C by 3 days and activity E by 1 day with an additional total
cost of $45,000.
A C E F Activity to Crash Cost Maximum
12 15 18 6 crash Crash
C $10,000 3
START F IN IS H E $15,000 4
23 27 A $20,000 3
F $25,000 2
B D
NLDIMSR
Example - Solution
The lower path is B-D with a path length of 50 days now becomes critical path
From the time-cost trade-off data, both activities B and D have a crash cost per day saved of
$10,000, and both can be reduced by more than 3 days. Therefore, using marginal cost analysis,
we find that the most economical way of reducing the length of this path to 47 days is to shorten
either activity (it doesn’t matter which one) by 3 days with an additional total cost of $30,000.
B D
NLDIMSR
Example - Solution
Combining both the results, the total
crashing cost for the optimal way of
meeting the deadline of 47 days is
$30,000 + $45,000 = $75,000.
NLDIMSR
Example 2
For the data given in the below table, draw the network. Crash systematically the
activities and determine the optimal project duration and cost.
Example 2 - Solution
Activity 1-2 1-3 2-4 2-5 3-4 4-5
Normal Time (days) 8 4 2 10 5 3
Normal Cost (Rs) 100 150 50 100 100 80
Crash Time (days) 6 2 1 5 1 1
Crashed Cost (Rs) 200 350 90 400 200 100
Critical path
Example 2 - Solution
S No Path Duration
1 1-2-5 18 days
2 1-2-4-5 13 days
3 1-3-4-5 12 days
Critical Path : 1-2-5
Normal Project Completion time = 18 days
Direct Cost = Sum of normal cost of all activities
= 100+150+50+100+100+80
DC = Rs 580
Indirect Cost (IC) = 70 x 18 = Rs. 1260
Total Normal cost = DC + IC
Total Normal cost = 580+1260= Rs 1840
Example 2 – Solution
Activity
(Contd)
Paths (Days) Cost (Rs)
1-2-5 1-2-4-5 1-3-4-5 Direct Indirect Total
Maximum Crash Rank Before 18 13 12 580 1260 1840
Activity Reduction Cost per Crashin
in Time day saved
g
1-2 2 50 4
1-3 2 100 6 1-2 6+10=16 6+2+3=11 12 580+2*50 70*16 680+1120
2-4 1 40 3 =680 =1120 =1800
2-5 5 60 5 2-5 6+5=11 11 12 680+5*60 70*12 980+840
3-4 4 25 2
=980 =840 =1820
4-5 2 10 1
4-5 11 11 4+5+2=11 980+1*10 70*11 990+770
=990 =770 =1760
Example 3
For the data given in the below table, draw the network. Crash systematically the
activities and determine the optimal project duration and cost.
Example 3 - Solution
Activity 1-2 1-4 2-4 2-3 2-5 3-4 4-6 5-6
Normal Time (weeks) 8 10 5 6 8 0 12 5
Normal Cost (Rs) 1500 2000 800 1100 900 0 300 500
Crash Time (weeks) 6 7 4 4 5 0 8 4
Crashed Cost (Rs) 2000 3000 1400 1500 1500 0 400 800
Example 3 - Solution
S No Path Duration
1 1-2-5-6 21 weeks
2 1-2-4-6 25 weeks
3 1-2-3-4-6 26 weeks
4 1-4-6 22 weeks
Critical Path : 1-2-3-4-6
Normal Project Completion time = 26 weeks
Direct Cost = Sum of normal cost of all activities
DC= Rs 7100
Indirect Cost (IC) = 26*200 = Rs5200
Total Normal cost = DC + IC
Total Normal cost = Rs 12300
Activity Reduction per week 1-2-5-6 1-2-4-6 1-2-3-4-6 1-4-6 Direct Indirect Total
in Time saved Before Crashing 21 25 26 22 7100 5200 12300
1-2 2 250 3 1st Crashing 4-6 by 21 25-4=21 26-4=22 22-4=18 7100+100 22*200= 11600
1-4 3 333.3 5 4day =7200 4400
Thank you!