Professional Documents
Culture Documents
PM Module3 ProjectSchedulingandRM 21-23
PM Module3 ProjectSchedulingandRM 21-23
1
NLDIMSR
Project Management
Agenda
• Project Scheduling and Risk Management
o Gantt Chart
o Splitting and Multitasking
o PERT Analysis
o Risk Management
Project Scheduling
• Project schedule is the tool that communicates what work needs to be
performed, which resources of the organization will perform the work and the
timeframes in which that work needs to be performed.
• The project schedule should reflect all the work associated with delivering project
on time.
• Scheduling is carried out in advance of the commencing the project and involves:
1. Identifying tasks that need to be carried out.
2. Estimating how long they will take
3. Allocating resources (mainly personnel) and
4. Scheduling when tasks will occur
Gantt Chart
Gantt charts provide a standard format for displaying project schedule information by
listing project activities and their corresponding start and finish dates in a calendar format
Purpose
• To illustrate the relationship between project activities & time.
• To show the multiple project activities on one chart
• To provide a simple & easy method to understand representation of project scheduling
• Easy to construct
• Gives earliest completion date.
• Provides a schedule of earliest possible start and finish times of activities.
Disadvantages
• Gives only one possible schedule (earliest).
• Does not show whether the project is behind schedule.
• Does not demonstrate the effects of delays in any one activity on the
start of another activity, thus on the project completion time.
Week Number
Activity
1 2 3 4 5 6 7 8
A
B
C
D
1. Using a Forward Schedule: starting with the list of activities and a given start
date follow them forwards in time until you hit given deadline.
2. Using a Backward Schedule: look at the deadline, from that date work in the
logical list of activities.
Both of these methods allow you to ensure that all necessary activities can possibly
be completed within the given project time frame.
Example
Consider the following:.
Example
Example
Splitting / Multitasking
• Splitting/Multitasking
• A scheduling technique for creating a better project schedule and/or increase
resource utilization.
• Involves interrupting work on an activity to employ the resource on
another activity, then returning the resource to finish the interrupted
work.
• Is feasible when startup and shutdown costs are low.
• Is considered the major reason why projects fail to meet schedule.
Splitting Activities
• The beta distribution is generally used to describe the inherent variability in time estimates
• The probabilistic approach involves three time estimates:
• The length of time required under optimal conditions
o Optimistic time, (a)
• The length of time required under normal conditions
• Most likely time, (m)
• The length of time required under the worst conditions
• Pessimistic time, (b)
Mean = E(T) = Sum of te for the activities on critical path and standard deviation
𝑏−𝑎 2
SD = √ Sum of Var of all the activities on critical path
6
Title / Author: Project Management/Anand Dhutraj Page No. 28
NLDIMSR
T−E T
Therefore, 𝑍= N(0,1)
V T
Z is called standard normal variable s.n.v., where probabilities of Z are calculated from the
normal area table.
Steps in PERT
1. Identify the optimistic, most likely and pessimistic times for each activity.
2. Calculate the Activity times using formula:
3. Draw the PERT Network
4. Identify the Critical Path by calculating EST, EFT, LST and LFT. Find total project
completion time using duration of critical path.
𝑏−𝑎 2
5. Calculate variance of each activity 𝜎𝑡2 =
6
6. Calculate variance of all the activities on the critical path.
7. Calculate standard deviation of critical path using the formula
Standard deviation (𝜎) = √ (sum of variance of critical activities)
Steps in PERT
8. Calculate the value of z using these values
𝑋 − 𝑇𝑒
𝑧=
𝜎
𝐷𝑢𝑒 𝑑𝑎𝑡𝑒 −𝐸𝑥𝑝𝑒𝑐𝑡𝑒𝑑 𝑝𝑟𝑜𝑗𝑒𝑐𝑡 𝑐𝑜𝑚𝑝𝑙𝑒𝑡𝑖𝑜𝑛 𝑡𝑖𝑚𝑒
i.e. 𝑧 = √ Variance
9. Calculate probability of the project completion for due date from the value of z and the
“Normal probability table”
Example 1
The details of 9 activities of a project are as follows, construct the network diagram.:
• Determine various paths and critical path
• Calculate probability of completion of project in 38 days.
• Calculate project duration if the probability of completion of project is 94.5%
• Calculate project duration if the probability of completion of project is 34.5%
Time in days
Activity
Optimistic (a) Most Likely (m) Pessimistic (b)
1-2 2 5 14
1-6 2 5 8
2-3 5 11 29
2-4 1 4 7
3-5 5 11 17
4-5 2 5 14
6-7 3 9 27
5-8 2 2 8
7-8 7 13 31
Example 1- Solution
z= (38-33)/5
z=1
Probability =0.5 +0.3413=0.8413
z=1.6 z= - 0.4
1.6=(X-33)/5 -0.4=(X-33)/5
1.6*5=X-33 -0.4*5=X-33
Title / Author: Project Management/Anand Dhutraj Page No. 36
X=41 days X=31 days
NLDIMSR
Example 2
The details of various activities of a project are given below:
Time in days
Activity Predecessor
to tm tp
A - 1 3 7
B - 1 2 4
C A 2 4 8
D A 2 5 11
E B 3 6 12
F C,D 3 7 15
G D,E 1 4 10
H F,G 2 6 14
i. Draw the network diagram and find critical path & critical time
ii. What will be the probability of completing project in 20 days?
iii. Find Total float, Free Float, Independent Float & Interference float for all activities.
Example 2 – Solution
8.83, 8.83
3.33, 3.33
Time in days 𝑏−𝑎 2
Activity Predecessor 𝜎𝑡2 = 16.5, 16.5 23.17, 23.17
6
to tm tp
A - 1 3 7 3.33 1.00
B - 1 2 4 2.17 0.25 0, 0
C A 2 4 8 4.33 1.00
D A 2 5 11 5.50 2.25
E B 3 6 12 6.50 2.25
8.83, 8.83
F C,D 3 7 15 7.67 4.00
G D,E 1 4 10 4.50 2.25
2.17, 2.33
H F,G 2 6 14 6.67 4.00
Example 2 – Solution
Paths Duration
1-2-4-6-7 (A-C-F-H) 22
1-2-5-6-7 (A-D-G-H) 20
1-2-5-4-6-7 (A-D-F-H) 23.17
1-3-5-6-7 (B-E-G-H) 19.83
Standard deviation=Sqrt(Sum of variances of critical activities)= 3.354
Te=
X=20
23.17
𝜎 = 3.354
z=(20-23.17)/3.354
-0.95
Example 2 – Solution
2.17, 2.33
Free Inter
Head Slack Tail Slack Total Float Ind Float
Float Float
LST-EST or
Activity Duration EST EFT LST LFT TF-HS FF-TS HS
LFT - EFT
A 3.33 0 3.33 0.00 3.33 0 0 0.00 0.00 0.00 0
B 2.17 0 2.17 0.16 2.33 0.16 0 0.16 0.00 0.00 0.16
C 4.33 3.33 7.66 4.50 8.83 0 0 1.17 1.17 1.17 0
D 5.50 3.33 8.83 3.33 8.83 0 0 0.00 0.00 0.00 0
E 6.50 2.17 8.67 2.33 8.83 0 0.16 0.16 0.16 0.00 0
F 7.67 8.83 16.50 8.83 16.5 0 0 0.00 0.00 0.00 0
G 4.50 8.83 13.33 12.00 16.5 0 0 3.17 3.17 3.17 0
H 6.67 16.5 23.17 16.50 23.17 0 0 0.00 0.00 0.00 0
Example 3
A project consisting of 7 activities has the following information (All duration are in weeks):
Time in weeks
Activity
Optimistic (a) Most Likely (m) Pessimistic (b)
1-2 1 1 7
1-3 1 4 7
1-4 2 2 8
2-5 1 1 1
3-5 2 5 14
4-6 2 5 8
5-6 3 6 15
i. Draw the network diagram and find critical path & critical time
ii. What will be the probability that the project will be extended to 20 weeks?
iii. Find Total float, Free Float, Independent Float & Interference float for all activities.
Example 3 – Solution
1-2 1 1 7 2 1
1-3 1 4 7 4 1
1-4 2 2 8 3 1
2-5 1 1 1 1 0
3-5 2 5 14 6 4
4-6 2 5 8 5 1
5-6 3 6 15 7 4
Example 3 – Solution
Paths Duration
1-2-5-6 10
1-3-5-6 17
1-4-6 8
X=20 Te=17
sigma=3
z=(20-17)/3
1.00
Probability = 0.5
+0.3413
0.8413
Types of Risks
• Project specific risk
• Competitive risk
• Industry specific risk
• Technology risk
• Legal risk
• Commodity risk
• International Risk
• Market Risk
The Risk
Management
Process
Managing Risk
• Step 1: Risk Identification
• Generate a list of possible risks through brainstorming, problem
identification and risk profiling.
• Macro risks first, then specific events
• Step 2: Risk Assessment
• Scenario analysis for event probability and impact
• Risk assessment matrix
• Failure Mode and Effects Analysis (FMEA)
• Probability analysis
• Decision trees, NPV, and PERT
• Semiquantitative scenario analysis
4 User Interface
Backlash problems
Red zone (major risk)
Likelihood
System
2 freezing
Hardware
1
malfunc-
tioning
1 2 3 4 5
Impact
Title / Author: Project Management/Anand Dhutraj Page No. 55
NLDIMSR
Contingency Planning
• Contingency Plan
• An alternative plan that will be used if a possible foreseen risk event actually
occurs.
• A plan of actions that will reduce or mitigate the negative impact
(consequences) of a risk event.
• Risks of Not Having a Contingency Plan
• Having no plan may slow managerial response.
• Decisions made under pressure can be potentially dangerous and costly.
The Change
Control Process
Thank you!