Request For Snagging: China Railway 18th Bureau

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Eng.

Adnan Saffarini
PROPOSED LUXURY HOTEL (OASIs)- 3B+G+1+M+6+P

REQUEST FOR SNAGGING


Contract No REF. No. CR18G-RFS-072
From China Railway 18th Bureau Date: Nov 2022
To Engr. Adnan Saffarini -Consultant
Zone Level Room No.: Room Title: Relevent:
4 A05 Standard Room RFS No.: CR186-RFS-072 Rev.: 1

Date of Inspection No. 2 Inspector Name Date of RFS:


Discipline
Nov 2022 Engr. Saif Wasef Architectural

EAS Representative: CR18G QA/QC: Roald


Re-Inspection Record
Accepted () Rejected (x)
Item Inspection Comments
(2) (3) 4)

The rectification works are still notcompleted for thewallpaint


X
Undulation issues for the gypsum ceiling
Theinstallation works for the sockets and switches are notcompleted
4 Loose bathroom accessories
|Cleaning the floors and the walls
Silicon works for the sanitary wares are not completed
Poor installtion and finishing for the wooden cornice
Poor installation and finishing for the wooden skirting
8
9 The grout works must be clean for the toilet marble
0 The grout works must be clean for the balcony skirting \ a s
1 Undulating and joint issues for the carpet

12 The joinery works are not installed

13 Mattress and divan are still not delivered

4 Non-slip coating to be applied for the bathroom marble


5 Minibars are still not delivered

TV still notdelivered
7 GRMS glass panels still not installed
The finishing works for the doors are still not completed
18
19 The installation works for the ironmongery are still not completed

Commn

Inspection No.:
CR18G Construction Manager
EAS Rep
Contractors QA/QC
Roald ECEIVEN
21 2322.
Eng Adnan Saffarini BY: 4
Page 1of1 A05
20-11-22