China Railway 18th Bureau: Request For Snagging
China Railway 18th Bureau: Request For Snagging
PE
REQUEST FOR SNAGGING
REF. No. CR18G-RFS -073
Contract No.
Date: 1 Nov 2022
From China Railway 18th Bureau
To Engr. AdnanSaffarini -Consultant
The rectification works arestill not completed for the wall paint
Undulation issues for the gypsum ceiling
The installation worksfor the socketsand switches are not completed
Loose bathroom accessories
5 Cleaning the floors and the walls
6 Slicon works for the sanitary wares are not completed
Poor installation and finishing for the wooden cornice
Poor installation andfinishing for the wooden skirting
The grout works must be clean for the toilet marble
10 The grout works must be clean for the balcony skiring i l e c
11 Undulating and joint issues for the carpet
not installed
The joinery works are
Mattress and divan are stll not delivered
Non-slip coating to be applied for the bathroom marble
15 Minibars are still not delivered
16 TV stil not delivered
1/ GRMS glass panels still notinstalled
18 The finishing works for the doors are still
not completed
19 The installation works for the ironmongery are still not completed
InspectionNo.: