Professional Documents
Culture Documents
GCS 5910 - Lighting (20091231)
GCS 5910 - Lighting (20091231)
Lighting
General Electricity
Company Of Libya
Table of Contents
1. Scope ············································································································· 1
2. Flowchart ····································································································· 1
3. Construction method··················································································· 2
3.1 General lightings ········································································································· 2
3.2 Emergency DC lighting······························································································ 2
3.3 Substation Power Supplies and Lighting (Cable Trench)····································· 3
3.3.1 Power Supplies································································································ 3
3.3.2 Switchboard Designs······················································································· 3
3.3.3 Wire ················································································································· 4
3.3.4 Wire Connections ···························································································· 5
3.3.5 Boxes··············································································································· 5
3.3.6 Lighting Equipment and Auxiliary Apparatus ················································ 5
3.4 Construction method·································································································· 6
3.4.1 Materials acceptance ······················································································· 6
3.4.2 Installation preparation···················································································· 7
3.4.3 Illumination panel installation········································································· 7
3.4.4 Conduit installation ························································································· 7
3.4.5 Illuminator installation ···················································································· 7
3.4.6 Laying and connecting the cable····································································· 7
3.4.7 Check installation···························································································· 8
4. Work Procedure··························································································· 9
4.1 Lighting Installation ··································································································· 9
5. Checklist ····································································································· 11
Appendix A. Safety Inspection ····································································· 12
i
List of Tables
ii
List of Figures
Abbreviations
iii
Lighting
1. Scope
This standard is applicable when installing the lighting system, in order to supply
convenient work areas in 66kV and 30kV substations.
2. Flowchart
Material acceptance
Installation preparation
Panel installation
Conduit installation
3. Construction method
3.1 General lightings
Adequate illumination gives a person maximum working efficiency, convenience and a
comfortable environment during substation operation and maintenance work. Therefore, it
is recommended that standard illumination of each area comply with the following table
<Table 1> Standard illumination
Area Illumination (lx) Remark
Switch-room 400
Control room 500
Office room 500
Battery room 100
Auxiliary TR room 100
Telecommunication room 300
Floodlight (outdoor switchyard) 20
Entrance hall, lobby 100
Corridor, passageway, stair 100
Lavatory, storeroom 100
Perimeter lighting 10
Exterior lighting, etc 15
Note: The mounting height of the fittings above the working plane are usually taken as 0.85m
above floor level
(c) Ratings for ATS, MCCB and ELB should be enough large considering load
capacity.
(d) Considering spaces and conditions for vertical holes and ventilation holes, lead-in
switchboards and ATS boards can be combined into one switchboard.
3.3.3 Wire
(a) By calculating load currents, voltage drop of wires should not exceed a limit
specified in the interior wire standards.
(b) Considering construction costs regarding the number of lead-in spot, most
economical specifications should be selected.
(c) Wires should be distinguished by its color according to phase.
(d) (A phase: red, B phase: white, C phase: blue, N phase: green)
(e) Method for supporting wires
▪ Using stainless steel clips, support wires below 1.2m high using stainless steel
channels
▪ The length of C channel is 100mm for one strand, 200mm for two strands, 300mm
for three to four strands, 500mm for five to 8 strands, 800mm for nine to twelve
strands, and 1000mm for thirteen or more. The length should be selected
considering final equipment capacity including fire-fighting equipment.
▪ C channels, boxes and auxiliary apparatus should be tied tightly using set anchor
bolts. The specifications for set anchor bolts are as follows
C channels, lighting equipment and boxes: 1/4″× 50㎜
(If the length of C channel is 800mm or more, use 3 set anchors for supporting.)
Panel board : 3/8″× 70㎜
▪ Attach labels specifying uses of wires every 100m of installed
▪ Using cable glands in accordance with wire specifications, lead-in holes of
switchboards, boxes and lighting equipment should be water-proof.
3.3.5 Boxes
(a) Boxes have water-proof structure with anti-corrosive, durable and anti-impactive
features in accordance with IP67 of IEC 60529. It should have a figure
facilitating attachment to concrete structures.
(b) Size and installation location of boxes are as follows:
< Table 3> Size and Installation Location
340×250×150
Full Box Branch spot
600×300×150
E xAx D
N=
µxF
(b) Lay the cable along wire tracks as stated in the cable laying plan.
(c) Interconnect the wires with insulated sleeves using any proper connection method
(such as mechanical pressing connection)
(d) Completely insulate connected parts in order to avoid the electric leakage.
4. Work Procedure
4.1 Lighting Installation
Procedure Figures
4.1.1. Material acceptance
(a) Supervisors need to check the standard of material; such as GDS and GES
(b) Accept material after checking the name, standard, quantity and length in the
material list.
(c) Materials should be carried and handled with care to prevent damage or loss
5. Checklist
< Table 4> Check List for Lighting
Check List
Project Date
Contract
Location
Company
Used materials is
accorded with GES
Use proper
Select materials stabilizer
considering
position
Use proper
illumination
considering
Illumination
position
Uniform
illumination
Proper switch
position
Lighting
Earth condition of
equipment
lighting equip.
installation
Noise or vibration
when lighting on
Supervisor Name : (Signature)
Contractor Name : (Signature)
Safety Inspection
Project Supervisor
Date Site