Project Schedule Patay2 Chip Year 1 Year 2 Year 3

Year 4
1st half 2nd half 1st half 2nd half 1st half 2nd half 1st
half 2nd half
Development Cost $(5,000,000) $(5,000,000) $(5,000,000)
$(5,000,000)
Pilot Testing $(2,500,000) $(2,500,000)
Debug $(1,500,000) $(1,500,000)
Ramp-up Cost $(3,000,000)
Advance Marketing $(5,000,000)
Marketing and Support Cost $(500,000) $(500,000)
$(500,000) $(500,000)
Production Volume 125000 125000 75000 75000
Unit Production Cost $(655) $(655) $(545)
$(545)
Production Cost $(81,875,000) $(81,875,000)
$(40,875,000) $(40,875,000)
Interest rate (10%)
Sales Volume 125000 125000 75000 75000
Unit Price $820 $820 $650 $650
Sales Revenue $102,500,000 $102,500,000
$48,750,000 $48,750,000

Period Cash Flow $(5,000,000) $(5,000,000) $(9,000,000)


$(17,000,000) $20,125,000 $20,125,000 $7,375,000 $7,375,000
PV Year 1, r = 10% $(5,000,000) $(4,761,905) $(8,163,265)
$(14,685,239) $16,556,887 $15,768,464 $5,503,339 $5,241,275

Project NPV $4,030,365