Deputy Engineer,
Mechanical Sub-Division
Shrigonda
ESTIMATE
Major Head : 4701 Capital Outlay on Major and Medium Irrigation Project.
Minor Head : 4701, Capital Outlay on Minor & Medium Irrigation Project
This estimate is prepared in the Office of Deputy Engineer, Mechanical Sub-Division, Shrigonda, Ahmednagar
for Estiimate for Jobwork of Manufacturing and supply of K T weir Straight type Needle gates of size 2.15 x 0.5
mtr.- 40 Nos with All Material, complete fabrication and Painting at Shingave K.T.Weir on Dev River Tal. &
District Ahmednagar including material, labour, workshop charges, sundry charges, handling charges,
transportation charges etc., inclusive of all taxes complete job under Mechanical sub Div. Shrigonda
Total Rs 499,566.00
General Description
This estimate is prepared in the Office of Deputy Engineer, Mechanical Sub-Division, Shrigonda, Ahmednagar
for Estiimate for Jobwork of Manufacturing and supply of K T weir Straight type Needle gates of size 2.15 x 0.5
mtr.- 40 Nos with All Material, complete fabrication and Painting at Shingave K.T.Weir on Dev River Tal. &
District Ahmednagar including material, labour, workshop charges, sundry charges, handling charges,
transportation charges etc., inclusive of all taxes complete job under Mechanical sub Div. Shrigonda
ITEM 1
Sr. No.PARTICULERS UNIT RATE QUANTITY AMOUNT RATE PER MT REMARK
A MATERIAL CHARGES
1 MILD STEEL KG 94.51 5742.54
KG Less Steel Wastages 90.01
Total Rs. 5652.53
2 RUBBER SEAL
BOTTOM MTR. 175 2.13 372.75
SIDE MTR. 175 1.04 182.00
3 HARDWARE
MS KG 90 1 90.00 83372.13
4 WELDING ROD
MS TO MS Nos. 13 35 455.00
5 CUTTING GAS
OXIGEN GAS CUB M 49.2 1.5 80.85
ACETELENE GAS CUB M 387 0.5 212.30
6 EPOXY ZINK PRIMER 1 Coat LTR. 264.65 1 290.05
7 Epoxy Paint LTR. 228.8 2 501.50
MATERIAL CHRGES FOR 1 NEEDLE GATE (TOTAL WEIGHT 94 KG) 7836.98
B MACHINARY CHARGES
1 HAND CUTTER Hr. 10 0.5 5.00
2 PUG MACHINE Hr. 17 0.5 8.50
3 HAND GRINDER Hr. 12 0.5 6.00
4 WELDING MACHINE Hr. 90 2 180.00 Steel Rate in
7474.47 RS.( As per
5 MAGNETIC DRILLING MACHINE Hr. 28 0.5 14.00 Dt.
6 HYD.PRESS MACHINE Hr. 586 0.5 293.00 05/07/2022
JPC)
7 Sand Blasting including Sand Sq.mtr 88.05 2 176.10
MACHINARY CHARGES 682.60
Add Machinery Mobilization 1.5% & Demobilization 1.5 % Charges 20.00
Total Machinery Charges Rs. 702.60
C LABOUR CHARGES
1 CREW FOR GRINDING Hr. 167.34 0.5 84.00
2 FOREMAN DAY 614 0.1 61.40
3 FITTER DAY 614 0.1 61.40
4 ASST. FITTER ( GAS CUTTER) DAY 614 0.13 79.82
5 WELDER (GENERAL) DAY 614 0.2 122.80 7149.79
6 HELPER (SEMI SKILLED MAZDOOR) DAY 568 0.2 113.60
7 Painter DAY 614 0.1 61.40
584.42
Add Highly Skilled Labour Charges 15 % 87.66
TOTAL LABOUR CHARGES Rs. 672.08
TOTALMATERIAL, MACHINARY AND LABOUR CHARGES Rs. 9211.66 97996.39
ADD INSPECTION AND QUALITY CONTROL CHARGES 1.5% of Total 138.17 1469.95
RATE PER No. & MT 9349.83 99466.34
ADD OVERHEAD CHARGES 10% of Total 934.98 9946.63
ADD LABOUR AMENITIES CHARGES 1% 93.50 994.66
TOTAL RATE PER No. & MT 10378.31 110407.63
ITEM 3
A TRANSPORTATION
Distance Upto Site appraox. 1side = 27 KM
Hence To and Fro = 54 KM