Excavation Work Procedure
Excavation Work Procedure
Excavation Work Procedure
Lee, Min
March 15, Marie Gi Bok Kim J.W Doo J.H.Lee H.S.Woo
A For Approval Seok
2017 Bernadas
Contractor
Masinloc Power Plant Expansion Project Doc. No 0-WD890 - CA731 - 00306
Work Procedure for STG, STB Rev. No. A
and CCB Excavation Work Page 2 of 11
TABLE OF CONTENTS
1.0 PURPOSE………………………………………………………………….. 3
2.0 SCOPE……………………………………………………………………… 3
1.0 INTRODUCTION
1.1 Location & Layout
CCB
STG
1.2 Purpose
This provides the procedure for constructing a Steam Turbine Generator & Building, Central
Control Building includes rebar works, form works, anchor bolt setting, concreting works, stripping of
forms, concrete curing, backfilling/compaction for Masinloc Power Plant Expansion Project.
2.0 SCOPE
2.1 This procedure is applicable for constructing a Steam Turbine Generator & Building, Central
Control Building. In accordance with the specification and approved standard drawing for the
Masinloc Coal Power Plant Expansion Project.
2.1.1 PROCEDURE
2.1.1.1 Survey Works
2.1.1.2 Layout & Marking
2.1.1.3 Dewatering
2.1.1.4 Excavation
2.1.1.5 Levelling & Compaction
2.1.1.6 Backfilling
2.1.1.7 Disposal
3.0 REFERENCES
3.1 All activities must be performed in accordance with the law and all regulatory regimes; codes
and standard; and specifications.
3.1.1 Metric (SI) unit - shall be the standard form of measurement to be used for this
project
Masinloc Power Plant Expansion Project Doc. No 0-WD890 - CA731 - 00306
Work Procedure for STG, STB Rev. No. A
and CCB Excavation Work Page 4 of 11
3.1.2 Latest edition of the following codes; standard and project specifications from the
date of awarding the main contract shall be used as reference unless otherwise
noted.
3.1.2.1 American Standards
3.1.2.1.1 ASTM: American Society for Testing and Materials
4.0 DEFINITION
4.1 Project : Masinloc Coal Fired Expansion Power Plant Project
4.2 Owner : AES Philippines
4.3 Contractor : Ventanas Philippines Construction Inc.
4.4 Sub – contractor : GTC Global
4.5 JESA : Job Environmental and Safety Assessment
4.6 HSE : Health, Safety and Environment
5.1 VPCI Project Manager - shall be the overall responsible for the implementation of this
procedure ensuring that works are completed on schedule and in conformity with
drawings and specifications.
5.2 VPCI Project EHS Manager shall ensure safe implementation of this procedure promoting an
Incident and Injury Free environment.
5.3 VPCI & GTC Global Inc. QA/QC Engineer shall be responsible for the implementation
of construction specification and standards and see to it that this
written method statement of the work shall be carried out.
5.4 GTC Global Inc. Construction Manager – shall have the overall responsibility for the
direction, monitoring, coordination and control of all the construction activities attached
and related to concrete works and the overall Health and Safety procedure.
5.5 GTC Global Inc. HSE Engineer along with the Safety Officer shall ensure
implementation of all safety procedures, safety measures related to the nature of works
being carried out and in accordance with the HSE Plan.
5.6 GTC Global Site Supervisor shall be directly involved in the planning and execution of
the activities. He shall be responsible for the preparation of work plan, safety action
plan and safety.
Masinloc Power Plant Expansion Project Doc. No 0-WD890 - CA731 - 00306
Work Procedure for STG, STB Rev. No. A
and CCB Excavation Work Page 5 of 11
6.0 Resources
7.0 Procedure
Survey
Works
c
Marking &
Layout
c
c
Excavation
Masinloc Power Plant Expansion Project Doc. No 0-WD890 - CA731 - 00306
Work Procedure for STG, STB Rev. No. A
and CCB Excavation Work Page 6 of 11
Dewatering
c
Sub-grade
levelling &
Compaction
c
Sub-
structures
c
Backfilling
Compaction
Disposal
7.1 SURVEYING
7.2 PERMITTING
7.2.1 Prior to start of any activity, necessary permits should first be accomplished
according to scope of work that are to be conducted.
7.3.5 Access roads shall be provided on strategic sides of the excavation area (North &
East Side). The access road should have a width of 7m. Unsuitable/excess
materials will be disposed outside the 5km. radius.
7.3.6 First to excavate is MF6 where condensate pit is located. MF2 @ Grid AA-AB/A3-A4
will follow. After condensate pit backfilling and compaction is done, STG foundation
@ Grid AB-AD/A2-A6, excavation will proceed together with elevation +1.5m. As
excavation and backfilling is in progress elevation +0.3 will follow and lastly
elevation +2.5m will take place.
7.4.1 Disposal
7.4.1.1 Excavated materials suitable for reuse in the works shall be used for filling
materials, but should be tested and accepted by AES.
7.4.1.2 Excavated materials unsuitable for reuse and surplus shall be removed to
laydown area.
8.1 All personnel must wear appropriate PPE at all times. Personnel are empowered to stop work if
safety precautions are not in place.
8.2 The Job Site Supervisor shall ensure that all Safety requirements are put in practice, copy of MS
and JHA (Attached) are available on site for guidance and consultation.
8.3 Contractor Safety Representative shall carry out the safety site inspection to ensure the safety
requirements laid out in the safe work plan are followed during and after the completion of the
works.
8.4 Job Site Supervisor and Safety Representative shall be present at all time while works are in
progress.
8.5 Appropriate PTW to be prepared and implemented, modification without OWNER approval is
prohibited.
8.6 Assessed risk as necessary and communicated to concerned parties prior to start of any work.
8.7 Safety briefing / Tool box talk must be conducted by Supervisors prior to start of work in the
language of workforce.
8.8 Incidents and injuries, damaged to property or near misses should be reported.
8.10 A clear and good communication must be maintained by all personnel involved on the
activity.
8.11 Personnel must be trained/experienced and familiarized with the scope of works to be
undertaken. The location of marshalling point must be identified, emergency evacuation
procedure must be clear to all workers, exercises must be conducted.
8.12 Contractor Safety Manager / Representative shall review Safety Action Plan.
7.0 Attachment
Attachment # 01.
Masinloc Power Plant Expansion Project Doc. No 0-WD890 - CA731 - 00306
Work Procedure for STG, STB Rev. No. A
and CCB Excavation Work Page 10 of 11
Attachment # 02.
Masinloc Power Plant Expansion Project Doc. No 0-WD890 - CA731 - 00306
Work Procedure for STG, STB Rev. No. A
and CCB Excavation Work Page 11 of 11
Risk Assessment