Question Paper Code : 90873
B.E/B.Tech. DEGREE EXAMINATIONS, NOVEMBER/DECEMBER 2022.
Seventh/Eighth/Nineth Semester
Mechanical Engineering
ME 8793 - PROCESS PLANNING AND COST ESTIMATION
(Common to Manufacturing Engineeri ial Science and
. ° ' Engineering/ /Material :
Engineering/Mechanical Engineering (Gandwichy/Mechanical and Automation
Engineering/Mechatronies Engineering/ /Production Engineering/Roboties and
Automation)
(Regulations 2017)
Maximum : 100 marks
Time : Three hours
PP w ys
ex
10.
11. @
Answer ALL questions.
PART A — (10 x 2= 20 marks)
List the variables to be considered while purchasing a machine to a
manufacturing unit.
What is the current importance of Computer Added Process Planning (CAPP)?
What is the purpose of Process Planning?
What costs are associated with manufacturing?
Draw the cost ladder diagram with its constituent cost elements.
Draw the block diagram to show the build-up of total cost and selling price of a
component.
What factors are considered while evaluating the cost of a welded joint?
What is shrinkage allowance?
What are the elements of machining time?
What are the standard data requirements for calculating cutting time in a
shaping operation?
PART B— (5 x 13 = 65 marks)
Using proper sub-headings, explain the steps in the process selection
process with an example.
Or
(6) Draw a component of your choice and discuss the steps to be performed in
production equipment and tool selection process.13.
14.
b)
(a)
)
(a)
A compon,
ent can be prod
lathe. The different con faeteng neither &
tore forthe ens caratan lathe of an automatic
‘ines are given below.
Fixed cost = Re.500
Variable cos
t= Re 3
Machine 11 3 per piece
Fixed cost = Rs.1,500
Variable cost = Ra.1 per piece
Assume that cyc
yele ti
the machines, Which fF Productio
ich machine will you of the component is same for bot
‘You select for produci a
ing
( 800,
(ii) 700 components? Mm
Or 6
Discuss the ste
PS involved in
engineer conclude your view on the mat Eigasing stiviies and s0 90
need of Operation planning sheet.
Explain th
xp e methods of costing followed in a manufacturing unit.
Or
Detail the elements of cost u dings.
inder suitabl
‘A llap welded joint is to be made as shown ri teow ms es
Weld :
+
10mm
10mm x,
Figure. 1 Lap welded joint
Estimate the cost of weld from the following data:
@ Thickness of plate = 10mm
(i) Electrode diameter = 6mm
(ii) Minimum are voltage = 30 Volts
(iv) Current used = 250 Amperes
(v) Welding speed = 10 meters/hour
(vi) Electrode used per meter of weld = 0.350 kes
(vii) Labour rate = Rs, 40 per hour
Rs. 3 per kWh
(viii) Power rate
(ix) Electrode rate = Rs, 8.00 per ke
(%) Efficiency of welding m/c = 50 percent
04
(xi) Connecting ratio
(xii) Overhead charges
(xiii) Labour accomplishment factor
Or
80 percent of direct charges
= 60 percent
90873) A P
the ete Component is to be manufactured as per figure 2. Estimate
' Price per piece from the following data:
ay of material = 7.2grams/ec
ce of molten metal at cupola spout = Re, 20 per ke,
ess scrap 20% of net weight
Scrap return value = Rs. 6perkg
= Rs.30 per hour
Administrative overheads
= 20 percent of factory cost
Sales overheads
Profit = 20 percent of factory cost
Other expenditures are:
Operation Time Labour cost/hour Shop overhead/
(minutes) in rupees. _—_—=hour in rupees
Molding and pouring 15 20 60
Shot blasting 5 10 ay
Fettling 10 ”
EN
WY
i
%
et
(a) Component as cast (b) Finished component
Figure 2
All dimensions are in mm
15. (a) ATT-slot is to be cut in a C.I slab as shown in figure 3. Take cutting speed
25 m/min feed is .25 mm/rev. Diameter of cutter for channel milling is
80 mm. Estimate the machining time.
Figure 3
All dimensions are in mm
Or
3ining time to turn the dimensions shown in figure 4
ne] bar of 100 mm, The cutting speed with HSS
@) Calculate the mach
2.0.8 mm/rev., depth of cut is 3 mm per pass
starting from @ mr
tool 80 m/min and
d feed
Figure 4
‘All dimensions are in mm
PART C — (1x 15 = 15 marks)
der the component as shown in figure 5. The component is to be
made from mild steel with carbide tooling at a constant surface speed of
100 m/min. on a lathe with a maximum spindle speed of 1500 rev/min.
The machining allowance is 2 mm.
16. (a) Consi
Determine :
@ if the lathe is capable of turning the component at the required
®
surface speed;
le.
(i) _ the total machining time for the component if the lathe is capabl
@
Figure 5 Cylindrical Component
All dimensions are in mm
Or
Iculation by considering basic
(b) Discuss the importance of machine time cal
rat least 2 different
formulae, tables of variables and constants for
machining operations with appropriate examples.
4 90873