Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

CIVIL WORKS FOR NEW PET LINE AT KPGF CCI PLANT

Daily Progress Report


REPORTED BY AREAA BANU MUKHTAR CONSTRUCTION -LLP
REPORT NO 6
DATE 26-Nov-2022
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

Skilled Labour Steel Fixer


Skilled Labour Carpenter

Mechanical Supervisor
Skilled Labour Mason

Machinery Operators
Admin and Account
QS/ Office Engineer

Dismentaling team
Staff &
Project Manager

Workers
Supervisor Civil
Site in Charge

HSE Engineer

Electician
Surveyor

Drivers

Total
Strength 0 1 0 1 1 1 1 4 0 0 0 1 1 1 5 17
TODAY WEATHER oC

Leveling and dressing of production area is complete. Morning 9


Compaction of production area is in progress. Afternoon 19
WTP area walk way dismentling work is in progress. EQUIPMENT
No Equipment Required Current
1 Excavator/Jack Hammer 1 0
2 Plate Compactor 1 1
3 Asphalt concrete cutting machine 2 2
4 Hilti drill machine 1 1
5 Tractor with Trolly 4 4
6 Grinder 4" 1 1
7 Grinder 9" 1 1
8 Power cutter 14" 1 1
9 Concrete Breaker (Hilti) 1 1
10 Double Cabine 1 1
11 Suzukai carry 1 0
12 Level Machine 2 2
13 Fire Extinguisher 4 4
14 Vibrator and Convertor 1 0
15 Welding Plant 1 1
16 Generator 6KVA 1 1

TOMORROW MATERIAL DETAIL


Compaction in Production area No Material Unit In Stock
SS channel exvaction of Production area. 1 Tarpulin Sheet no 15.00
WTP walkway dismentling. 2 Polythene Sheet rolls 4.00
3 Wooden Planks 13'x12"x2" no 40.00
4 XPS insulation Board 38mm S.ft 270.00
5
6
7
No Description Unit W. Done
1
2
3
4
5
6
7
8
9
10
11
12
13
NOTES/REMARKS

Contractor Project Consultant Client


CIVIL WORKS FOR NEW PET LINE AT KPGF CCI PLANT
DAILY PROGRESS PICTURES
Date: 11/26/2022

5. 6.

You might also like