Instructions
A) Evaluate one of the example team charter on the next pages
1. Identify potential improvements
2. Evaluate the selected charter using the SMART criteria.
3. Prepare to discuss your conclusions.
Answer.
For question A. we choose Example: Team Charter – Improve Customer
Satisfaction.
1. Identify potential improvements.
Business Case
Our current delivery time average is 65% for Product XY and 75% for
Product ZY. Our customer are expecting 100% on time. As a result of
our on time performance, we have low customer satisfaction,
experience a higher level of expedites, and lower manufacturing
efficients. By improving our on time performances, we will improve
customer satisfaction, decrease the number of expedites, and lower
work process.
Opportunity Statement
We currently have an average on time delivery of 65% for Product XY
and 75% for Product ZY. Our customers expect 100% on time. This
problems will occur when the manufacturing process does not follow
the due date. By completing this project, customers satisfaction will
increase and at once increasing the number of new customers. Cost of
doing nothing, company will facing failures.
Goal Statement
Reduce manufacturing through put time (wip).
Identify and correct the causes of late orders.
Improve our on time delivery to 98% by the fourth quarter.
Project Scope
Order Entry
Start: receipt of customer order
Stop: entry of order into computer
Manufacturing
Start: shop order preparation
Stop: close out of order
Shipping
Start: printing of shop and shipper
Stop: order shipped
Team Selection
Albert Sponsor
Barry Master Black Belt
Carrie Black Belt
Denise Dispatch Supervisor
Eric Senior Dispatcher
Frank Administrative Manager
Gwen Truck Loader
Hillary Truck Loader
Specific
Yes, it address a real business problem (customer satisfaction).
Measurable
Yes, we able to measure the problem (delivery time average is 65% for
Product XY and 75% for Product ZY), establish a baseline (Customers
are expecting 100% on time), and set targets for improvement (improve
delivery time to 98% by the fourth quarter).
Attainable
Project completion date is realistic which is only 5 weeks.
Relevant
Yes, it relate to business objective (satisfied the customer).
Time Bound
Yes, date for completion is set in Project Plan