Professional Documents
Culture Documents
3280-45C1 D1
3280-45C1 D1
3280-45C1 D1
6. TESTING ............................................................................................................................... 11
6.1 Drainage and Sewer Pipework........................................................................................ 11
6.2 Water Test ...................................................................................................................... 11
6.3 Air Test ........................................................................................................................... 12
6.4 Manholes ........................................................................................................................ 12
6.5 Clear and Flush all Drains............................................................................................... 12
6.6 Test Programmes ........................................................................................................... 12
6.7 Records of Tests............................................................................................................. 12
7. DISPOSAL OF MATERIALS AND TEST FLUIDS .................................................................. 12
1. SCOPE
The work covered by this Specification includes pipe bedding, laying and jointing of
concrete, ductile iron, GRP, plastic and carbon steel pipes, all materials used in the
construction of the underground drainage systems and surface water ditch systems.
Contractor shall comply with all requirements and conditions set out in this
Specification.
2. REFERENCES
All materials and workmanship shall comply with the relevant sections of the latest
editions of the following Standards and Codes of Practice, unless otherwise specified
herein.
BS EN 545 - Ductile iron pipes, fittings, accessories and their joints for
water pipelines – Requirements and test methods
BS EN 598 - Ductile iron pipes, fittings, accessories and their joints for
sewerage applications – Requirements and test methods
3. MATERIALS
3.2 Pipework
3.2.1 General
All pipework supplied by Contractor, for use in the works, shall be obtained from an
approved Manufacturer. Contractor shall forward to the Engineer, certificates from the
Manufacturer certifying that the pipes and fittings have been tested and comply with
the appropriate standard, before despatch.
Concrete pipes shall comply with the requirements of BS 5911 or BS 1916 and the
strength class shall be as indicated on the drawing.
Steel pipes for the use in the surface water, hydrocarbon and chemical drainage
system shall be in accordance with BS EN 10224. Buried pipework shall be provided
with an external corrosion protection system and where necessary be cathodically
protected.
Lined steel pipes for the use in contaminated, uncontaminated, hydrocarbon and
surface water systems shall be in accordance with BS EN 10224. Buried pipework shall
be provided with an external corrosion protection system and where necessary be
cathodically protected.
The type of internal lining will be dependent on the wastewater properties, operating
temperature and shall be in accordance with BS EN 10224 annex D.
GRP pipes for sewage, surface water and certain chemical effluents shall be in
accordance with BS EN 1796. The resin type, pipe properties and construction shall
be considered in relation to the wastewater being carried and the surface / ground
loading criteria employed.
uPVC pipes for uncontaminated and sewage systems shall be in accordance with BS
EN 1401.
The method of installation and materials used for jointing of the different pipe material
types above shall be in accordance with the relevant Manufacturer's recommendations
and instructions, and shall be suitable for the expected operating conditions,
temperature range, differential settlement and wastewater expected within the system.
Steel pipes and fittings shall be provided with external corrosion protection in
accordance with Specification for Coating and wrapping of buried pipe work document
no. 3280-83A4
Where necessary, other metallic pipework including cast iron and ductile iron may
require additional protection in addition to that supplied by the pipe manufacturer.
Pipe bedding & surround for carbon steel, GRP and uPVC pipes shall comprise of
natural sand well graded and free from contamination and deleterious material.
Alternatively manholes, catch basins, sumps and pits may be constructed from either
engineering brickwork or in-situ concrete. Reinforcement size, spacing and location
shall be indicated on the drawings.
3.7 Waterstops
Waterstops installed in concrete structures shall be a proprietary PVC or rubber
material to provide a permanent liquid-tight seal. The type of waterstop shall be
selected in consultation with the manufacturer.
Pipes cast into or passing through drainage structures shall have a hydrophilic
waterstop bonded to the external face of the pipe located at the midpoint of the wall or
slab.
3.10 Membranes
Geotextiles utilised for erosion control shall be in accordance with BS EN 13253.
3.11 Keys
Contractor shall provide and hand over to the Client at completion of the works, two
sets of lifting/locking keys to suit each specific pattern of installed manhole
3280-45C1.docx DSN: 941
SPECIFICATION FOR 3280-45C1
MATERIALS AND FOSTER WHEELER PAGE 8 OF 12
WORKMANSHIP ENGINEERING STANDARD REV D1
cover/grating.
4.1 General
All materials shall be stored in such a manner as to protect them from deterioration and
contamination from whatever source.
4.3 Pipework
All pipes and fittings shall be thoroughly inspected on delivery and again before being
placed in position. Throughout the operations of delivery, handling, storing and
transporting on or about the site, Contractor shall use such methods, plant and
equipment as will prevent damage to the pipes and to any coating. Impacts shall be
avoided. Ropes, cables and hooks shall not be used during handling. Instead, wide
straps shall be used and shall be of a length suited to the diameter of the pipes.
During storage, the pipes shall not be placed directly on the ground and shall not be
stored one on top of another. They shall be placed on wide timber bearers with
suitable interplacing of a protective material.
Coated and wrapped carbon steel, uPVC and PE pipework shall be protected from the
direct rays of the sun. To avoid damage to linings or pipes and fittings special care and
attention shall be taken when lifting, moving and placing pipe on site.
5. WORKMANSHIP
5.2 Bedding
A bed of selected bedding material as specified in Clause 3.3 and shall be laid and
compacted to 100mm minimum thickness over the full width of the trench, where the
bed thickness is measured from the bottom of pipe to the trench bottom. The minimum
bed thickness shall be increased to 150mm in rock or hard soil conditions. The bed
shall be scooped out locally at pipe sockets where socketed pipes are used. The bed
thickness under sockets shall not be less than 50mm.
Pipes shall be adjusted to line and level within tolerances specified in the design to
3280-45C1.docx DSN: 941
SPECIFICATION FOR 3280-45C1
MATERIALS AND FOSTER WHEELER PAGE 9 OF 12
WORKMANSHIP ENGINEERING STANDARD REV D1
ensure that pipe barrels rest uniformly on the bedding along their whole length. Where
sidefill is required, further selected backfill material shall be laid and compacted
uniformly by hand halfway up each side of the pipe.
Pipe laying should commence at the downstream end of the system. Immediately
following the excavation of the trench, the pipe shall be laid and jointed in accordance
with the Manufacturer's recommendations and as detailed on the drawings. Joints shall
be undamaged and clean. Brick or other hard blocks, etc shall not be placed under the
pipes for temporary support.
Cutting of pipe shall be carried out with manufacturer’s recommended tools and
procedures. Damage to internal and external coatings and or linings shall be repaired
in accordance with manufacturer’s instructions.
The full length of each section of pipe shall rest solidly upon the pipe bed. A pipe that
has the gradient or joint disturbed after laying shall be taken up and relaid. Pipes shall
not be laid when trench conditions are unsuitable for the work. When work is not in
progress open ends of pipes, fittings and valves shall be securely closed so that no
water, sand or other substance will enter the pipes or fittings. Pipe ends left for future
connection shall be valved, plugged or capped.
Each length of pipe shall be laid in a dead straight line both in the horizontal and
vertical planes, the levels and/or gradients shown on the drawings being rigidly
adhered to, unless otherwise approved by the Engineer. Permanent adjustments to line
and/or level shall not be achieved by local packing. As the work progresses the interior
of the pipe shall be cleared of all superfluous materials. As soon as possible after the
joint is made, sufficient backfill material shall be placed along the pipe to prevent pipe
movement of line or grade and the invert level checked.
locations indicated on the drawings and in accordance with the details shown.
Bases to manholes etc shall be cast in concrete and be 150mm minimum thickness.
The minimum size of the base shall be equal to the external dimensions of the
manhole chamber.
Concrete manholes shall be constructed with precast concrete sections complying with
the relevant requirements of BS 5911 or BS 1917 with ogee or similar approved joints.
A chamber ring with openings for the drain inlets and outlets shall be set vertically in
the manhole base, and subsequent sections added, as required, and set vertically, to
build the manhole up to surface level.
Care shall be taken to locate step irons in succeeding precast units vertically above
step irons in proceeding units.
All spun concrete manhole sections shall be supplied with mastic fillets at the joints to
provide watertight seals.
Bed the top pre-cast concrete section dry pending completion of surrounding levels.
Replace or adjust as necessary to give accurate and even final levels.
Flexible joints shall be provided on all rigid pipes projecting through manhole walls
positioned minimum 150mm from external face of walls where connected to drain runs
jointed with flexible joints.
All frames shall be solidly bedded so that the manhole cover is even with the
surrounding finished surface. Any installed cover or frame not level or that allows
rocking of the cover, shall be made level or replaced at Contractor's expenses.
Building debris being allowed to accumulate in drains shall require rodding and clearing
out at Contractor's expense.
6. TESTING
The leak test shall comprise of either a water test in accordance with clause 6.2 or an
air test in accordance with Clause 6.3 of this Specification. Sections between manholes
shall be tested separately unless otherwise specified. All the necessary apparatus and
attendance for the test shall be provided by Contractor.
Pipework failing to satisfy the requirements of the water test shall be taken up, re-laid
and re-jointed as necessary and again tested to establish watertightness; at no extra
cost.
The drainage system shall not be deemed to have failed by means of an air test. A
water test should be carried out prior to the rejection of the system.
- Unless otherwise agreed by the Engineer the test shall commence one
hour after filling the test section, at which time the water level in the feed
pipe shall be made up to produce the required test head. The test shall be
continued for sufficient time to allow the Engineer to inspect the pipeline
and satisfy himself regarding its watertightness and in any case for not less
than one hour.
- The test requirement is satisfied if the amount of water added is not greater
than:
The system is deemed to have passed the test if there is no fall in the head of water
during the test period.
6.4 Manholes
Each manhole shall be tested for watertightness in the presence of the Engineer by
filling with water to a level not exceeding 1.2m above the pipe soffit level or to ground
level. Contractor shall be responsible for locating, making good any leakages and the
work will be accepted as satisfactory only when a visual inspection for watertightness
reveals no leaks or external damp patches. This test is to be carried out prior to the
placing of the backfill material.