Four Lakes Task Force Reviews 2022 Progress
Four Lakes Task Force Reviews 2022 Progress
| Page 1 of 3
2022 Year in Review
December 31, 2022
| Page 2 of 3
2022 Year in Review
December 31, 2022
✓ Pounding sheet pile into the dam embankment is ✓ EPA reviewing permit
underway ✓ Construction expected to be permitted in December
✓ Fisher Contracting submits low bid and is chosen for ✓ Fisher Contracting submits low bid and is chosen for
reconstruction of Secord Dam reconstruction of Smallwood Dam
Edenville Sanford
✓ 60% Engineering Plans ✓ EGLE permit submitted November 1, 2022
✓ Engineering team is identifying pull-ahead projects in ✓ 60% dam safety design
preparation for restoration construction ✓ Submittal initiated the review process to receive a
✓ Consumers Energy is rerouting power lines around the permit for dam construction activities impacting
dam regulated environmental areas
✓ 100% design documents are expected to be completed ✓ Final permitting of Sanford Dam is expected by mid-
by mid-year 2023 with final construction planned to 2023
begin by early 2024