Proposed Construction of RO Tanks for M/s SCOTTS Garments Ltd, @ Doddaballapur, Bangalore Rural Dist.
Quotation for RO Tanks (with Materials)
Measurement Qty Unit Rate Amount Remarks
Sl.No Description of Items Nos
L B D

Providing and laying in position reinforced cement concrete of Design mix M25 with OPC
cement @ 320kgs, with 20mm and down size graded granite metal coarse aggregates
@0.69cum and fine aggregtes @ 0.460 cum, with super plasticisers @ 3 liters confirming
to IS 9103-1999 reafirmed-2008, machine mixed, concrete laid in layers not exceeding 15
1 cms thick, vibrated for all works in foundation for footings, pedastals, retaining walls, return
walls, walls (any thickness) including attached pilasters, columnspillars, posts, struts,
buttresses, bed blocks, anchor blocks & plinths etc., including cost of all materials, labour,
HOM of machinery, curing, complete but excluding cost of reinforcement as per
specifications. etc., complete.

Long walls - New walls 2 15.00 0.30 0.60 5.400


Short walls - New Walls 3 6.60 0.30 0.60 3.564
Old walls - 1 24.00 0.30 1.20 8.640
Slab 1 6.00 1.20 0.20 1.440
Total Qty 19.044 Cum 7500.00 142,830.00

Providing and removing centering, shuttering, strutting, propping etc., and removal of form
2 work for slab, Retaining walls, Lift walls, Columns for mass concrete including cost of all
materials, labour complete as per specificaitons.etc.,
Long walls - New walls 4 15.00 - 0.60 36.00
Short walls - New Walls 6 6.60 - 0.60 23.76
Old walls - 2 24.00 - 1.20 57.60
Slab 1 6.00 - 1.20 7.20
Total Qty 124.560 Sqm 700.00 87,192.00

Providing T.M.T steel reinforcement for R.C.C work including straightening, cutting,
bending, hooking, placing in position, lapping and / or welding wherever required, tying
3 with binding wire and anchoring to the adjoining members wherever necessary complete
as per design (laps, hooks and wastage shall not be measured and paid) cost of materials,
labour, HOM of machinery complete as per specifications etc.,

Distruption bars - 16mm dia


Slab - Steel @ 100 c/c 1 500.00 1 1.00 500.000
Total Qty 500.000 Kg 78.00 39,000.00

Providing and mixing water-proofing compound of approved make in base coat (Fosroc
conplast WL) including treating of construction joints with fosroc GP2, pressure grouting
4 with cebex100, 2 coats brushbond RFX(1.5mm thk) and The rate to include the cost of two
coats including hacking, scaffolding, groves, patta, drp moulds, curing - Fosroc authorised
applicator to be used for the construction joint treatment work (for Internal Surfaces)

Tank 1 1 24.00 - 3.20 76.80


Tank 2 1 24.00 - 3.20 76.80
Flooring 2 6.00 - 6.00 72.00
Total Qty 225.600 Sqm 700.00 157,920.00

Providing and doing internal cement plaster 20mm thick in two coats, for wall at all levels,
first coat 1:4 mix and second coat 1:3 mix cement mortar including scaffolding, curing etc.
including providing and mixing water-proofing compound of approved make in base
5 coat(Fosroc conplast WL) The rate to include the cost of first coat of not less than 13 mm
thickness, second coat 7 mm thick including hacking, scaffolding, groves, patta, drp
moulds, curing - Fosroc authorised applicator to be used for the construction joint
treatment work (for Internal Surfaces

Tank 1 1 24.00 - 3.20 76.80


Tank 2 1 24.00 - 3.20 76.80
Flooring 2 6.00 - 6.00 72.00
Total Qty 225.600 Sqm 400.00 90,240.00

Providing 18mm thick external cement plaster in single coat with cement mortar 1:4, to rcc
walls including rounding off corners wherever required smooth rendering, : Providing and
6
removing scaffolding, including cost of materials, labour, curing complete as per
specifications.

Long walls 2 13.00 - 1.00 26.00


Short walls 2 6.00 - 1.00 12.00
Total Qty 38.000 Sqm 450.00 17,100.00

Amount in Rs 534,282.00
GST @ 18% 96,171.00
Total Amount in Rs 630,453.00