JHA For Demolition of Hume Pipe
JHA For Demolition of Hume Pipe
Prepared By
MPMC: Technip India Limited (Contractor Site
Partha Lahkar
Engg)
Page 1 of 2
JHA FOR DEMOLITION
-All Utilities Lines Impact/ Collision with Use all mandatory PPE
-Electric cables obstacles/vehicles (fixed or
movement) All utility services such as
electricity, telephone,gas and
Electric shock , explosion , jet, etc water must be shut off and the
main supplies disconnected
outside the line of the demolition
work.
2. Machine moving Vibration – Noise Safe area with barricade around
demolition area.
(Poklain) Machines/Tools contact with moving
and rotating parts
3. Demolishing General Hazards (Cut, Abrasion, The hazard of material inside the
Puncture, etc.) during normal activity structure to demolish shall be
Collapse/Cave in/Compression considered.
Material/falls Use of masks.
Dust and Fibres (Asbestos) Wet the area (water spraying) for
dust abatement/minimisation
Material disposal