Dialy Forecast - Jan 19
Dialy Forecast - Jan 19
Dialy Forecast - Jan 19
PLANT/MACHINERY MANPOWER
Plant / Machinery No. Plant / Machinery No. Trade No. Trade No.
Excavator Compactor Project Manager Bar Bender 15
Water Truck Lorry APM 1 Aluminum fwk 38
Backhoe Sky Lift Site Engineer 1 Carpenter
Crawler Crane Forklift 1 Site Agent 1 Concreter 7
Mobile Crane (25Ton) Concrete Pump 1 Site Supervisor 1 Catch Platform Installer
Mobile Crane (200Ton) Grinder 2 Site Foreman Brick Layer 38
Water Pump 1 Tower Crane 1 M&E Coordinator 1 Plasterer 16
Air Compressor Set 1 Safety Officer Skim 12
Generator Set Site Admin 2 Scaffolder 4
Welding Set 1 Safety Site Supervisor 1
Bar Bending Machine 2 Surveyor 1 M&E
Bar Cutting Machine 2 Forklift Operator 1 Electrical 12
Drill Machine 1 Security Guard 1 Plumber 12
Hacker Machine 2 General Workers 14 ELV 3
Air breaker 20lbs TC Operator 1 ACMV 4
Air breaker 60lbs Signalman 1 Earthing
Flagman 1 Fire 2
Description of work:
C&S
1. L23 Z1 SW BRC/Rebar.
2. L24 Z1 slab formwork setting up
3. L23 Z2 floor setting out. SW BRC/Rebar.
4. L23 Z3 slab BRC/Rebar. Verticality setting (Casting)
5. L23 Z3 slab & beam inspection
Architectural
1. L11, L12, L13, L14 & L15 brick work.
2. L16, L17 & L18 door frame & bathroom kickers.
3. L8 & L9 wall skim coat & plastering.
4. L7 floor screeding setting out.
5. L4 tiling work.
6. L4 plaster ceiling work.
7. L4 aluminum window installation.
8. L5 tiling work setting out.
9. L8 toilets & aircond ledge cleaning for waterproofing work. Angle fillet work.
10. L10 stiffeners at corridor area
M&E
1. L23 Z3 slab inspection
ELV
1. L23 Z3 slab conduit pipe install
2. Install cable at L17
ACMV
1. L23 Z3 slab & L23 Z2 SW drain pipe & pipe sleeve
2. L14 U2 drain pipe install
3. L15 U3 copper pipe install
ELECTRICAL
1. L23 Z3 slab conduit pipe install
2. L11 hacking work
3. L13, 17, 18 wiring work
FIRE PROTECTION
1. L23 Z3 slab riser pipe work
PLUMBING
1. L23 Z3 slab plumbing work
2. L11 sanitary pipe install
3. L11 cold water pipe install
4. L7 coring work
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
Comments
Name:
Representative of Client
Signature:
Note: To be submitted daily to Consultant before 10.00 am
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
PLANT/MACHINERY MANPOWER
Plant / Machinery No. Plant / Machinery No. Trade No. Trade No.
Excavator Compactor Project Manager 1 Bar Bender 15
Water Truck Lorry APM 1 Aluminum fwk 38
Backhoe Sky Lift Site Engineer 1 Carpenter
Crawler Crane Forklift 1 Site Agent 1 Concreter
Mobile Crane (25Ton) Concrete Pump 1 Site Supervisor 1 Catch Platform Installer
Mobile Crane (200Ton) Grinder 2 Site Foreman Brick Layer 38
Water Pump 1 Tower Crane 1 M&E Coordinator 1 Plasterer 16
Air Compressor Set 1 Safety Officer 1 Skim 12
Generator Set Site Admin 2 Scaffolder 4
Welding Set 1 Safety Site Supervisor 1
Bar Bending Machine 2 Surveyor 1 M&E
Bar Cutting Machine 2 Forklift Operator 1 Electrical 12
Drill Machine 1 Security Guard 1 Plumber 13
Hacker Machine 2 General Workers 21 ELV 3
Air breaker 20lbs TC Operator 1 ACMV 4
Air breaker 60lbs Signalman 1 Earthing
Flagman 1 Fire 2
Description of work:
C&S
1. L24 Z1 slab formwork, BRC/Rebar
2. L23 Z2 SW BRC/Rebar.
3. L24 Z2 slab setting up for shearwall
4. L23 Z2 SW inspection
Architectural
1. L11, L12, L13, L14 & L15 brick work.
2. L17, L18 & L19 door frame & bathroom kickers
3. L8 & L9 wall skim coat & plastering.
4. L7 floor screeding setting out.
5. L4 tiling work.
6. L4 plaster ceiling work.
7. L4 wall painting
8. L5 tiling work setting out.
9. L8 toilets & aircond ledge cleaning for waterproofing work. Angle fillet work.
10. L10 stiffeners at corridor area
M&E
1. L23 Z2 SW inspection
ELV
1. L23 Z2 SW and L24 Z1 slab conduit pipe
2. L18 install cable pipe
ACMV
1. L24 Z1 slab and L23 Z2 SW drain pipe & pipe sleeve
2. L14 U2 drain pipe install
3. L15 U3 copper pipe install
ELECTRICAL
1. L24 Z1 slab conduit pipe
2. L11 hacking work
3. L13,17 & 18 wiring work
FIRE PROTECTION
1. L24 Z1 slab riser work
PLUMBING
1. L24 Z1 slab plumbing work
2. L12 sanitary pipe
3. L11 cold water pipe install
4. L7 coring work
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
Comments
Name:
Representative of Client
Signature:
Note: To be submitted daily to Consultant before 10.00 am
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
PLANT/MACHINERY MANPOWER
Plant / Machinery No. Plant / Machinery No. Trade No. Trade No.
Excavator Compactor Project Manager Bar Bender 15
Water Truck Lorry APM 1 Aluminum fwk 38
Backhoe Sky Lift Site Engineer 1 Carpenter
Crawler Crane Forklift 1 Site Agent 1 Concreter 7
Mobile Crane (25Ton) Concrete Pump 1 Site Supervisor 1 Catch Platform Installer
Mobile Crane (200Ton) Grinder 2 Site Foreman Brick Layer 38
Water Pump 1 Tower Crane 1 M&E Coordinator 1 Plasterer 16
Air Compressor Set 1 Safety Officer Skim 12
Generator Set Site Admin 2 Scaffolder 4
Welding Set 1 Safety Site Supervisor 1 Waterprrofing 4
Bar Bending Machine 2 Surveyor 1 Painter 2
Bar Cutting Machine 2 Forklift Operator 1 M&E
Drill Machine 1 Security Guard 1 Electrical 12
Hacker Machine 2 General Workers 14 Plumber 13
Air breaker 20lbs TC Operator 1 ELV 3
Air breaker 60lbs Signalman 1 ACMV 4
Flagman 1 Earthing
Fire 2
Description of work:
C&S
1. L24 Z1 slab formwork BRC/Rebar. Verticality setting (Casting)
2. L24 Z2 Slab BRC/Rebar
3. L23 Z3 SW BRC/Rebar
4. L23 Z3 SW inspection.
Architectural
1. L11, L12, L13, L14 & L15 brick work
2. L15, L16, L17, L18 & L19 door frame & bathroom kickers
3. L8, L9 & L11 wall plastering.
4. L4 tiling work.
5. L4 external wall pastering work
6. L4 wall painting
7. L4 plaster ceiling work
8. L5 tiling work setting out.
9. L7 floor screeding setting out
10. L8 toilets & aircond ledge cleaning for waterproofing work. Angle fillet work.
11. L10 stiffeners at corridor area
12. L10 wall skim coating
M&E
1. L23 Z3 SW inspection
ELV
1. L23 Z2 SW & L24 Z1 slab conduit pipe
2. L18 cable install.
ACMV
1. L24 Z1 slab & L23 Z3 SW drain pipe & pipe sleeve
2. L14 U2 drain pipe install
3. L15 U3 copper pipe install.
ELECTRICAL
1. L23 Z3 SW conduit pipe install
2. L11 hacking work
3. L18 wiring work
FIRE PROTECTION
1. L24 Z1 slab riser pipe work
PLUMBING
1. L23 Z2 SW plumbing work
2. L12 sanitary pipe install
3. L10 cold water pipe install
4. L7 coring work
5. L5 mixer & hot water tank install
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
Comments
Name:
Representative of Client
Signature:
Note: To be submitted daily to Consultant before 10.00 am
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
Daily Report AM PM
PLANT/MACHINERY MANPOWER
Plant / Machinery No. Plant / Machinery No. Trade No. Trade No.
Excavator Compactor Project Manager Bar Bender 19
Water Truck Lorry APM 1 Aluminum fwk 38
Backhoe Sky Lift Site Engineer Carpenter
Crawler Crane Forklift 1 Site Supervisor 2 Concreter
Mobile Crane (25Ton) Concrete Pump 1 Site Foreman Catch Platform Installer
Mobile Crane (200Ton) Grinder 2 M&E Coordinator 1 Brick Layer 38
Water Pump 1 Tower Crane 1 Safety Officer 1 Plasterer 16
Air Compressor Set 1 Site Admin 2 Skim 12
Generator Set Safety Site Supervisor 1 Scaffolder 4
Welding Set 1 Surveyor 1 Waterproofing 2
Bar Bending Machine 2 Forklift Operator 1 Painter 3
Bar Cutting Machine 2 Security Guard 1 M&E
Drill Machine 1 General Workers 21 Electrical 12
Hacker Machine 2 TC Operator 1 Plumber 13
Air breaker 20lbs Signalman 1 ELV 3
Air breaker 60lbs Flagman 1 ACMV 4
Earthing
Fire 1
Description of work:
Architectural Architectural
1. L11, L12, L13, L14 & L15 brick work 1. L11, L12, L13, L14 & L15 brick work.
2. L15, L16, L17, L18 & L19 door frame & bathroom kickers
2. L15, L16, L17, L18 & L19 door frame & bathroom
kickers
3. L10 wall skim coating 3. L10 wall skim coating
4. L8, L9 & L11 wall plastering 4. L8, L9 & L11 wall plastering
5. L7 floor screeding setting out. 5. L4 tiling work
6. L4 tiling work 6. L4 external wall plastering
7. L4 external wall plastering. 7. L8 toilets & aircond ledge Angle filler work
8. L4 plaster ceiling work. 8. L5 wall painting work
9. L4 painting work
10. L5 tiling work setting out.
11. L8 toilets & aircond ledge Angle fillet work.
12. L10 stiffeners at corridor area.
M&E M&E
1. L23 Z3 SW inspection
ELV ELV
1. L23 Z3 slab conduit pipe 1. L23 Z3 slab conduit pipe
2. L18 install cable 2. L18 install cable
ACMV ACMV
1. L24 Z2 slab & L23 Z3 SW drain pipe & pipe sleeve 1. L24 Z2 slab & L23 Z3 SW drain pipe & pipe sleeve
ELECTRICAL ELECTRICAL
1. L24 Z2 slab conduit pipe 1. L24 Z2 slab conduit pipe
2. L11 hacking work 2. L11 hacking work
3. L18 wiring work 3. L18 wiring work
4. L3 trunking work 4. L3 trunking work
PLUMBING PLUMBING
1. L23 Z3 SW plumbing work 1. L23 Z3 SW plumbing work
2. L12 sanitary pipe 2. L12 sanitary pipe
3. L10 cold water pipe install 3. L10 cold water pipe install
4. L7 coring work 4. L7 coring work
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
Comments
Name:
Representative of Client
Signature:
Note: To be submitted daily to Consultant before 10.00 am
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
PLANT/MACHINERY MANPOWER
Plant / Machinery No. Plant / Machinery No. Trade No. Trade No.
Excavator Compactor Project Manager 1 Bar Bender 19
Water Truck Lorry APM 1 Aluminum fwk 38
Backhoe Sky Lift Site Engineer 1 Carpenter
Crawler Crane Forklift 1 Site Supervisor 2 Concreter
Mobile Crane (25Ton) Concrete Pump 1 Site Foreman Catch Platform Installer
Mobile Crane (200Ton) Grinder 2 M&E Coordinator 1 Brick Layer 38
Water Pump 1 Tower Crane 1 Safety Officer 1 Plasterer 16
Air Compressor Set 1 Site Admin 2 Skim 12
Generator Set Safety Site Supervisor 1 Scaffolder 3
Welding Set 1 Surveyor 1
Bar Bending Machine 2 Forklift Operator 1 M&E
Bar Cutting Machine 2 Security Guard 1 Electrical 5
Drill Machine 1 General Workers 21 Plumber 8
Hacker Machine 2 TC Operator 1 ELV 2
Air breaker 20lbs Signalman 1 ACMV 4
Air breaker 60lbs Flagman 1 Earthing
Fire 2
Description of work:
C&S
1. L20 Z1 slab BRC/Rebar. Verticality setting out for shear wall
2. L19 Z2 SW BRC/Rebar & formwork
3. L19 Z3 floor setting out. SW BRC/Rebar
Architectural
1. L7, L8, L9 & L10 door frame and brick work.
2. L11 door frame installation.
3. L6 wall plastering.
4. L4 floor screeding.
5. L5 toilets & aircond ledge cleaning, angle filler for
waterproofing.
6. Construct stiffener at L8 corridor area
M&E
ELV
1. L20 Z1 slab and L19 Z2 SW conduit pipe work
ACMV
1. L20 Z1 slab and L19 Z2 SW drain pipe & pipe sleeve
2. L11 unit 5 drain pipe install
3. L5 unit 6 copper pipe install
ELECTRICAL
1. L20 Z1 slab conduit pipe
2. L7 hacking work
FIRE PROTECTION
1. L11 & 12 touch up riser opening pipe
PLUMBING
1. L19 and L11 sanitary pipe riser
2. L9 sanitary pipe connection
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
Comments
Name:
Representative of Client
Signature:
Note: To be submitted daily to Consultant before 10.00 am
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
PLANT/MACHINERY MANPOWER
Plant / Machinery No. Plant / Machinery No. Trade No. Trade No.
Excavator Compactor Project Manager 1 Bar Bender 19
Water Truck Lorry APM 1 Aluminum fwk 38
Backhoe Sky Lift Site Engineer 1 Carpenter
Crawler Crane Forklift 1 Site Supervisor 2 Concreter 7
Mobile Crane (25Ton) Concrete Pump 1 Site Foreman Catch Platform Installer
Mobile Crane (200Ton) Grinder 2 M&E Coordinator 1 Brick Layer 38
Water Pump 1 Tower Crane 1 Safety Officer 1 Plasterer 16
Air Compressor Set 1 Site Admin 2 Skim 12
Generator Set Safety Site Supervisor 1 Scaffolder 3
Welding Set 1 Surveyor 1
Bar Bending Machine 2 Forklift Operator 1 M&E
Bar Cutting Machine 2 Security Guard 1 Electrical 5
Drill Machine 1 General Workers 14 Plumber 9
Hacker Machine 2 TC Operator 1 ELV 2
Air breaker 20lbs Signalman 1 ACMV 4
Air breaker 60lbs Flagman 1 Earthing
Fire 3
Description of work:
C&S
1. L20 Z1 slab BRC/Rebar. Verticality set. Casting
2. L19 Z2 SW BRC/Rebar & fromwork
3. L20 Z2 slab formwork
4. L19 Z3 SW BRC/Rebar
5. L20 Z1 slab & beam inspection
Architectural
1. L7, L8, L9 & L10 door frame and brick work.
2. L11 door frame installation
3. L6 wall plastering.
4. L4 floor screeding.
5. L5 toilets & aircond ledge cleaning, angle filler for
waterproofing.
6. Construct stifferner for L8 corridor area
7. L12 bathroom kickers
M&E
1. L20 Z1 slab inspection
ELV
1. L20 Z1 slab conduit pipe work
ACMV
1. L20 Z1 slab and L19 Z2 SW drain pipe & pipe sleeve
2. L11 unit 5 drain pipe install
3. L5 unit 6 copper pipe install
ELECTRICAL
1. L20 Z1 slab conduit pipe
2. L7 hacking work
FIRE PROTECTION
1. L13 & 14 touch up riser opening pipe
2. L20 Z1 slab riser work
PLUMBING
1. L19 Z3 SW plumbing work
2. L12 riser sanitary pipe
3. L5 cold water pipe
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
Comments
Name:
Representative of Client
Signature:
Note: To be submitted daily to Consultant before 10.00 am
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
Daily Report
Weather: √ Fine Cloudy Rain AM PM
PLANT/MACHINERY MANPOWER
Plant / Machinery No. Plant / Machinery No. Trade No. Trade No.
Excavator Compactor Project Manager Bar Bender 19
Water Truck Lorry APM 1 Aluminum fwk 38
Backhoe Sky Lift Site Engineer Carpenter
Crawler Crane Forklift 1 Site Supervisor 2 Concreter
Mobile Crane (25Ton) Concrete Pump 1 Site Foreman Catch Platform Installer
Mobile Crane (200Ton) Grinder 2 M&E Coordinator 1 Brick Layer 38
Water Pump 1 Tower Crane 1 Safety Officer 1 Plasterer 16
Air Compressor Set 1 Site Admin 2 Skim 12
Generator Set Safety Site Supervisor 1 Scaffolder 3
Welding Set 1 Surveyor 1
Bar Bending Machine 2 Forklift Operator 1 M&E
Bar Cutting Machine 2 Security Guard 1 Electrical 5
Drill Machine 1 General Workers 21 Plumber 9
Hacker Machine 2 TC Operator 1 ELV 2
Air breaker 20lbs Signalman 1 ACMV 4
Air breaker 60lbs Flagman 1 Earthing
Fire 2
Description of work:
Architectural Architectural
1. L11 door frame & brick work. 1. L7, L8, L9 & L10 brick work
2. L7, L8, L9 & L10 brick work 2. L11 brick work
3. L6 wall plastering. 3. L6 wall plastering
4. L4 floor screeding 4. Construct L8 Stiffeners at corridor area
5. L4 hallway ceiling setting out 5. L12 bathroom kickers
6. L5 toilets & aircond ledge cleaning, angle filler for waterproofing.
7. Construct L8 Stiffeners at corridor area
8. L12 bathroom kickers
9. L3 Surau ceiling groove line installation.
M&E M&E
ELV ELV
1. L19 Z3 SW conduit pipe install 1. L19 Z3 slab and L19 Z2 SW conduit pipe install
ACMV ACMV
1.L19 Z3 SW drain pipe & pipe sleeve 1.L19 Z3 SW drain pipe & pipe sleeve
ELECTRICAL ELECTRICAL
1. L19 Z3 SW conduit pipe 1. L19 Z3 SW conduit pipe
2. L7 hacking work 2. L7 hacking work
PLUMBING PLUMBING
1. L19 Z3 wall plumbing work 1. L19 Z3 wall plumbing work
2. L12 sanitary pipe riser install 2. L12 sanitary pipe riser install
3 . L6 cold water pipe 3 . L6 cold water pipe
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
Comments
Name:
Representative of Client
Signature:
Note: To be submitted daily to Consultant before 10.00 am
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
PLANT/MACHINERY MANPOWER
Plant / Machinery No. Plant / Machinery No. Trade No. Trade No.
Excavator Compactor Project Manager 1 Bar Bender 19
Water Truck Lorry APM 1 Aluminum fwk 38
Backhoe Sky Lift Site Engineer 1 Carpenter
Crawler Crane Forklift 1 Site Supervisor 2 Concreter 7
Mobile Crane (25Ton) Concrete Pump 1 Site Foreman Catch Platform Installer
Mobile Crane (200Ton) Grinder 2 M&E Coordinator 1 Brick Layer 38
Water Pump 1 Tower Crane 1 Safety Officer 1 Plasterer 16
Air Compressor Set 1 Site Admin 1 Skim 12
Generator Set Safety Site Supervisor 1 Scaffolder 3
Welding Set 1 Surveyor 1
Bar Bending Machine 2 Forklift Operator 1 M&E
Bar Cutting Machine 2 Security Guard 1 Electrical 3
Drill Machine 1 General Workers 14 Plumber 9
Hacker Machine 2 TC Operator 1 ELV 3
Air breaker 20lbs Signalman 1 ACMV 4
Air breaker 60lbs Flagman 1 Earthing
Fire
Description of work:
Architectural Architectural
1. L11 door frame & brick work. 1. L7, L8, L9 & L10 brick work
2. L7, L8, L9 & L10 brick work 2. L11 brick work
3. L6 wall plastering. 3. L6 wall plastering
4. L4 floor screeding 4. Construct L8 Stiffeners at corridor area
5. L4 hallway ceiling setting out 5. L12 bathroom kickers
6. L5 toilets & aircond ledge cleaning, angle filler for waterproofing.
7. Construct L8 Stiffeners at corridor area
8. L12 bathroom kickers
9. L3 Surau ceiling groove line installation.
M&E M&E
ELV ELV
1. L19 Z3 SW conduit pipe install 1. L19 Z3 slab and L19 Z2 SW conduit pipe install
ACMV ACMV
1.L19 Z3 SW drain pipe & pipe sleeve 1.L19 Z3 SW drain pipe & pipe sleeve
ELECTRICAL ELECTRICAL
1. L19 Z3 SW conduit pipe 1. L19 Z3 SW conduit pipe
2. L7 hacking work 2. L7 hacking work
PLUMBING PLUMBING
1. L19 Z3 wall plumbing work 1. L19 Z3 wall plumbing work
2. L12 sanitary pipe riser install 2. L12 sanitary pipe riser install
3 . L6 cold water pipe 3 . L6 cold water pipe
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
Comments
Name:
Representative of Client
Signature:
Note: To be submitted daily to Consultant before 10.00 am
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
PLANT/MACHINERY MANPOWER
Plant / Machinery No. Plant / Machinery No. Trade No. Trade No.
Excavator Compactor Project Manager 1 Bar Bender 19
Water Truck Lorry APM 1 Aluminum fwk 38
Backhoe Sky Lift Site Engineer Carpenter
Crawler Crane Forklift 1 Site Supervisor 2 Concreter
Mobile Crane (25Ton) Concrete Pump 1 Site Foreman Catch Platform Installer
Mobile Crane (200Ton) Grinder 2 M&E Coordinator 1 Brick Layer 38
Water Pump 1 Tower Crane 1 Safety Officer 1 Plasterer 16
Air Compressor Set 1 Site Admin 1 Skim 12
Generator Set Safety Site Supervisor 1 Scaffolder 3
Welding Set 1 Surveyor 1
Bar Bending Machine 2 Forklift Operator 1 M&E
Bar Cutting Machine 2 Security Guard 1 Electrical 9
Drill Machine 1 General Workers 21 Plumber 9
Hacker Machine 2 TC Operator 1 ELV 3
Air breaker 20lbs Signalman 1 ACMV 4
Air breaker 60lbs Flagman 1 Earthing
Fire 3
Description of work:
C&S
1. L20 Z1 SW BRC/Rebar & formwork
2. L21 Z1 slab formwork
3. L20 Z2 floor setting out for shear wall (SW BRC/Rebar)
4. L20 Z3 slab formwork, BRC/Rebar. Verticality setting
5. L20 Z1 SW inspection
Architectural
1. L7, L8, L9, L10 & L11 brick work
2. L6 wall plastering
3. L3 Surau water in fill for ponding test
4. Construct stifferner for L8 corridor area
5. L13 bathroom kickers
M&E
ELV
1. L20 Z1 SW conduit pipe
ACMV
1. L20 Z3 slab and L20 Z1 SW drain pipe & pipe sleeve
2. L9 unit 3 drain pipe install
3. L6 unit 6 copper pipe install
ELECTRICAL
1. L20 Z1 SW conduit pipe
2. L8 hacking work
3. L14 wiring work
FIRE PROTECTION
1. L20 Z3 slab riser pipe work
PLUMBING
1. L20 Z3 slab plumbing work
2. L12 sanitary pipe riser install
3. L6 cold water pipe
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
Comments
Name:
Representative of Client
Signature:
Note: To be submitted daily to Consultant before 10.00 am
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
PLANT/MACHINERY MANPOWER
Plant / Machinery No. Plant / Machinery No. Trade No. Trade No.
Excavator Compactor Project Manager 1 Bar Bender 19
Water Truck Lorry APM 1 Aluminum fwk 38
Backhoe Sky Lift Site Engineer Carpenter
Crawler Crane Forklift 1 Site Supervisor 2 Concreter
Mobile Crane (25Ton) Concrete Pump 1 Site Foreman Catch Platform Installer
Mobile Crane (200Ton) Grinder 2 M&E Coordinator 1 Brick Layer 38
Water Pump 1 Tower Crane 1 Safety Officer 1 Plasterer 16
Air Compressor Set 1 Site Admin 1 Skim 12
Generator Set Safety Site Supervisor 1 Scaffolder 3
Welding Set 1 Surveyor 1
Bar Bending Machine 2 Forklift Operator 1 M&E
Bar Cutting Machine 2 Security Guard 1 Electrical 9
Drill Machine 1 General Workers 21 Plumber 9
Hacker Machine 2 TC Operator 1 ELV 3
Air breaker 20lbs Signalman 1 ACMV 4
Air breaker 60lbs Flagman 1 Earthing
Fire
Description of work:
C&S
1. L21 Z1 slab BRC/Rebar
2. L20 Z2 SW BRC/Rebar & formwork
3. L20 Z3 slab BRC/Rebar. Verticality setting (Casting)
4. L20 Z2 SW inspection
Architectural
1. L7, L8, L9, L10 & L11 brick work.
2. L6 wall plastering
3. L4 tiling setting out for units
4. Construct stifferner for L8 corridor area
5. L13 bathroom kickers
M&E
1. L20 Z3 slab inspection
ELV
1. L20 Z2 SW and L20 Z3 slab conduit pipe
ACMV
1. L20 Z3 slab and L20 Z2 SW drain pipe & pipe sleeve
2. L10 unit 1 drain pipe install
3. L6 unit 6 copper pipe install
ELECTRICAL
1. L20 Z2 SW conduit pipe
2. L8 hacking work
3. L14 wiring work
FIRE PROTECTION
PLUMBING
1. L20 Z2 SW plumbing work
2. L14 sanitary pipe riser
3. L6 cold water pipe
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
Comments
Name:
Representative of Client
Signature:
Note: To be submitted daily to Consultant before 10.00 am
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
PLANT/MACHINERY MANPOWER
Plant / Machinery No. Plant / Machinery No. Trade No. Trade No.
Excavator Compactor Project Manager Bar Bender 19
Water Truck Lorry APM 1 Aluminum fwk 38
Backhoe Sky Lift Site Engineer Carpenter
Crawler Crane Forklift 1 Site Supervisor 2 Concreter
Mobile Crane (25Ton) Concrete Pump 1 Site Foreman Catch Platform Installer
Mobile Crane (200Ton) Grinder 2 M&E Coordinator 1 Brick Layer 38
Water Pump 1 Tower Crane 1 Safety Officer 1 Plasterer 16
Air Compressor Set 1 Site Admin 2 Skim 12
Generator Set Safety Site Supervisor 1 Scaffolder 3
Welding Set 1 Surveyor 1
Bar Bending Machine 2 Forklift Operator 1 M&E
Bar Cutting Machine 2 Security Guard 1 Electrical 9
Drill Machine 1 General Workers 21 Plumber 9
Hacker Machine 2 TC Operator 1 ELV 3
Air breaker 20lbs Signalman 1 ACMV 4
Air breaker 60lbs Flagman 1 Earthing
Fire 3
Description of work:
C&S
1. L21 Z1 slab BRC/Rebar. Verticality setting
2. L20 Z2 SW BRC/Rebar & formwork
3. L21 Z2 slab formwork
4. L20 Z3 floor setting out for shear wall. SW BRC/Rebar.
5. L21 Z1 slab & beam inspection
Architectural
1. L7, L8, L9, L10 & L11 brick work.
2. L6 wall plastering
3. L4 tiling setting out for units
4. Construct stifferner for L8 corridor area
5. L13 bathroom kickers
6. L5 water in fill for ponding test
M&E
1. L20 Z2 SW inspection
ELV
1. L21 Z1 slab conduit pipe
ACMV
1. L21 Z1 slab & L20 Z3 SW drain pipe & pipe sleeve
2. L11 unit 1 drain pipe install
ELECTRICAL
1. L21 Z1 slab conduit pipe
2. L8 hacking work
FIRE PROTECTION
1. L21 Z1 slab riser pipe work
PLUMBING
1. L21 Z1 slab plumbing work
2. L14 sanitary pipe riser
3. L6 cold water pipe
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
Comments
Name:
Representative of Client
Signature:
Note: To be submitted daily to Consultant before 10.00 am
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
Daily Report
Weather: √ Fine Cloudy Rain AM PM
PLANT/MACHINERY MANPOWER
Plant / Machinery No. Plant / Machinery No. Trade No. Trade No.
Excavator Compactor Project Manager 1 Bar Bender 19
Water Truck Lorry APM 1 Aluminum fwk 38
Backhoe Sky Lift Site Engineer Carpenter
Crawler Crane Forklift 1 Site Supervisor 2 Concreter 7
Mobile Crane (25Ton) Concrete Pump 1 Site Foreman Catch Platform Installer
Mobile Crane (200Ton) Grinder 2 M&E Coordinator 1 Brick Layer 38
Water Pump 1 Tower Crane 1 Safety Officer Plasterer 16
Air Compressor Set 1 Site Admin 2 Skim 12
Generator Set Safety Site Supervisor 1 Scaffolder 3
Welding Set 1 Surveyor 1
Bar Bending Machine 2 Forklift Operator 1 M&E
Bar Cutting Machine 2 Security Guard 1 Electrical 11
Drill Machine 1 General Workers 14 Plumber 9
Hacker Machine 2 TC Operator 1 ELV 3
Air breaker 20lbs Signalman 1 ACMV 4
Air breaker 60lbs Flagman 1 Earthing
Fire 3
Description of work:
C&S
1. L21 Z1 slab BRC/Rebar. Verticality setting (Casting)
2. L21 Z2 slab formwork, BRC/Rebar
3. L20 Z3 SW BRC/Rebar & formwork
4. L21 Z1 slab inspection
Architectural
1. L7, L8, L9, L10 & L11 brick work.
2. L6 wall plastering.
3. Construct stifferner for L8 corridor area
4. L13 bathroom kickers
5. L3 floor screeding
6. L6 toilets & aircond ledge cleaning for waterproofing work.
M&E
1. L21 Z1 slab inspection
ELV
1. L21 Z1 slab conduit pipe
ACMV
1. L21 Z1 slab & L20 Z3 SW drain pipe & pipe sleeve
2. L12 unit 1 drain pipe install
3. L12 unit 1 copper pipe install
ELECTRICAL
1. L20 Z3 SW conduit pipe
2. L8 hacking work
3. L14 submain work
FIRE PROTECTION
1. L21 Z1 slab riser work
2. L5 to 7 hacking for alarm bell & break glass at ST 1 & 2
PLUMBING
1. L21 Z1 slab plumbing work
2. L15 sanitary pipe riser
3. L6 cold water pipe
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
Comments
Name:
Representative of Client
Signature:
Note: To be submitted daily to Consultant before 10.00 am
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
PLANT/MACHINERY MANPOWER
Plant / Machinery No. Plant / Machinery No. Trade No. Trade No.
Excavator Compactor Project Manager Bar Bender 19
Water Truck Lorry APM 1 Aluminum fwk 38
Backhoe Sky Lift Site Engineer Carpenter
Crawler Crane Forklift 1 Site Supervisor 2 Concreter 7
Mobile Crane (25Ton) Concrete Pump 1 Site Foreman Catch Platform Installer
Mobile Crane (200Ton) Grinder 2 M&E Coordinator 1 Brick Layer 38
Water Pump 1 Tower Crane 1 Safety Officer 1 Plasterer 16
Air Compressor Set 1 Site Admin 2 Skim 12
Generator Set Safety Site Supervisor 1 Scaffolder 3
Welding Set 1 Surveyor 1
Bar Bending Machine 2 Forklift Operator 1 M&E
Bar Cutting Machine 2 Security Guard 1 Electrical 11
Drill Machine 1 General Workers 14 Plumber 10
Hacker Machine 2 TC Operator 1 ELV 3
Air breaker 20lbs Signalman 1 ACMV 4
Air breaker 60lbs Flagman 1 Earthing
Fire
Description of work:
C&S
1. L21 Z1 SW BRC/Rebar & formwork
2. L21 Z2 slab BRC/Rebar. Verticality setting (Casting)
3. L21 Z3 slab BRC/Rebar. Verticality setting
4. L21 Z1 SW and L21 Z2 slab & beam
Architectural
1. L8, L9, L10, L11 & L12 brick work.
2. L13 & L14 door frame
3. L16 brick wall setting out.
4. L7 skim coat & plastering
5. L14 bathroom kickers
6. L4 wall tiles setting out.
7. L5 floor screeding.
8. L6 toilets & aircond ledge angle filler for waterproofing work.
M&E
1. L21 Z2 slab inspection
ELV
1. L21 Z3 slab conduit pipe install
ACMV
1. L21 Z2 slab and L21 Z1 SW drain pipe & pipe sleeve
2. L12 U3 drain pipe
3. L12 U3 copper pipe install
ELECTRICAL
1. L21 Z3 slab cnduit pipe
2. L8 hacking work
3. L14 and L9 wiring work
FIRE PROTECTION
PLUMBING
1. L21 Z2 slab plumbing work
2. L16 sanitary pipe riser
3. L6 cold water pipe install
4. L10 sanitary pipe connection
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
Comments
Name:
Representative of Client
Signature:
Note: To be submitted daily to Consultant before 10.00 am
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
PLANT/MACHINERY MANPOWER
Plant / Machinery No. Plant / Machinery No. Trade No. Trade No.
Excavator Compactor Project Manager Bar Bender 19
Water Truck Lorry APM 1 Aluminum fwk 38
Backhoe Sky Lift Site Engineer Carpenter
Crawler Crane Forklift 1 Site Supervisor 2 Concreter
Mobile Crane (25Ton) Concrete Pump 1 Site Foreman Catch Platform Installer
Mobile Crane (200Ton) Grinder 2 M&E Coordinator 1 Brick Layer 38
Water Pump 1 Tower Crane 1 Safety Officer 1 Plasterer 16
Air Compressor Set 1 Site Admin 2 Skim 12
Generator Set Safety Site Supervisor 1 Scaffolder 3
Welding Set 1 Surveyor 1
Bar Bending Machine 2 Forklift Operator 1 M&E
Bar Cutting Machine 2 Security Guard 1 Electrical 13
Drill Machine 1 General Workers 21 Plumber 10
Hacker Machine 2 TC Operator 1 ELV 3
Air breaker 20lbs Signalman 1 ACMV 4
Air breaker 60lbs Flagman 1 Earthing
Fire 3
Description of work:
C&S
1. L21 Z1 SW BRC/Rebar & formwork
2. L22 Z1 slab formwork & setting out
3. L21 Z2 floor setting out. SW BRC/Rebar.
4. L21 Z3 slab BRC/Rebar. Verticality setting
Architectural
1. L8, L9, L10, L11 & L12 brick work.
2. L13 & L14 door frame
3. 7. L7 skim coat & plastering.
4. L14 bathroom kickers
5. L4 wall tiles setting out.
6. L5 floor screeding.
7. L6 toilets & aircond ledge angle filler for waterproofing work.
M&E
ELV
1. L21 Z3 slab conduit pipe install
ACMV
1. L21 Z3 slab and L21 Z2 SW drain pipe & pipe sleeve
2. L12 U3 drain pipe
3. L12 U3 copper pipe install
ELECTRICAL
1. L21 Z3 slab cnduit pipe
2. L9 hacking work
3. L14 and L10 wiring work
FIRE PROTECTION
1. L21 Z3 slab riser work
PLUMBING
1. L21 Z3 slab plumbing work
2. L16 sanitary pipe riser
3. L6 cold water pipe install
4. L10 sanitary pipe connection
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
Comments
Name:
Representative of Client
Signature:
Note: To be submitted daily to Consultant before 10.00 am
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
PLANT/MACHINERY MANPOWER
Plant / Machinery No. Plant / Machinery No. Trade No. Trade No.
Excavator Compactor Project Manager Bar Bender 19
Water Truck Lorry APM 1 Aluminum fwk 38
Backhoe Sky Lift Site Engineer Carpenter
Crawler Crane Forklift 1 Site Supervisor 1 Concreter 7
Mobile Crane (25Ton) Concrete Pump 1 Site Agent Catch Platform Installer
Mobile Crane (200Ton) Grinder 2 Site Foreman Brick Layer 38
Water Pump 1 Tower Crane 1 M&E Coordinator 1 Plasterer 16
Air Compressor Set 1 Safety Officer 1 Skim 12
Generator Set Site Admin 2 Scaffolder 3
Welding Set 1 Safety Site Supervisor 1
Bar Bending Machine 2 Surveyor 1 M&E
Bar Cutting Machine 2 Forklift Operator 1 Electrical 11
Drill Machine 1 Security Guard 1 Plumber 10
Hacker Machine 2 General Workers 14 ELV 3
Air breaker 20lbs TC Operator 1 ACMV 4
Air breaker 60lbs Signalman 1 Earthing
Flagman 1 Fire 3
Description of work:
C&S
1. L22 Z1 slab BRC/Rebar. Verticality setting (Casting).
2. L22 Z2 Slab formwork, BRC/Rebar.
3. L21 Z3 SW BRC/Rebar.
4. L21 Z3 wall & L22 Z1 slab inspection
Architectural
1. L8, L9, L10, L11 & L12 brick work.
2. L13 & L14 door frame
3. L7 wall skim coat & plastering.
4. L14 & L15 bathroom kickers
5. L4 floor tiling work.
6. L5 floor screeding.
7. L6 toilets & aircond ledge angle filler for waterproofing work.
M&E
1. L22 Z1 slab inspection
ELV
1. L21 Z3 SW conduit pipe
ACMV
1. L22 Z1 slab & L21 Z3 SW drain pipe & pipe sleeve
2. L12 U5 drain pipe
3. L11 U3 copper pipe install
ELECTRICAL
1. L21 Z3 SW conduit pipe
2. L9 hacking work
3. L15 wiring work
FIRE PROTECTION
1. L22 Z1 slab riser work
PLUMBING
1. L21 Z3 SW plumbing work
2. L10 sanitary pipe connection
3. L7 cold water pipe connection
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
Comments
Name:
Representative of Client
Signature:
Note: To be submitted daily to Consultant before 10.00 am
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
PLANT/MACHINERY MANPOWER
Plant / Machinery No. Plant / Machinery No. Trade No. Trade No.
Excavator Compactor Project Manager Bar Bender 19
Water Truck Lorry APM 1 Aluminum fwk 38
Backhoe Sky Lift Site Engineer Carpenter
Crawler Crane Forklift 1 Site Supervisor 1 Concreter 7
Mobile Crane (25Ton) Concrete Pump 1 Site Agent Catch Platform Installer
Mobile Crane (200Ton) Grinder 2 Site Foreman Brick Layer 38
Water Pump 1 Tower Crane 1 M&E Coordinator 1 Plasterer 16
Air Compressor Set 1 Safety Officer 1 Skim 12
Generator Set Site Admin 2 Scaffolder 3
Welding Set 1 Safety Site Supervisor 1
Bar Bending Machine 2 Surveyor 1 M&E
Bar Cutting Machine 2 Forklift Operator 1 Electrical 10
Drill Machine 1 Security Guard 1 Plumber 10
Hacker Machine 2 General Workers 14 ELV 3
Air breaker 20lbs TC Operator 1 ACMV 4
Air breaker 60lbs Signalman 1 Earthing
Flagman 1 Fire
Description of work:
C&S
1. L22 Z1 slab BRC/Rebar. Verticality setting (Casting).
2. L22 Z2 Slab formwork, BRC/Rebar.
3. L21 Z3 SW BRC/Rebar.
4. L21 Z3 wall & L22 Z1 slab inspection
Architectural
1. L8, L9, L10, L11 & L12 brick work.
2. L13 & L14 door frame
3. L7 wall skim coat & plastering.
4. L14 & L15 bathroom kickers
5. L4 floor tiling work.
6. L5 floor screeding.
7. L6 toilets & aircond ledge angle filler for waterproofing work.
M&E
1. L22 Z1 slab inspection
ELV
1. L21 Z3 SW conduit pipe
ACMV
1. L22 Z1 slab & L21 Z3 SW drain pipe & pipe sleeve
2. L12 U5 drain pipe
3. L11 U3 copper pipe install
ELECTRICAL
1. L21 Z3 SW conduit pipe
2. L9 hacking work
3. L15 wiring work
FIRE PROTECTION
PLUMBING
1. L21 Z3 SW plumbing work
2. L10 sanitary pipe connection
3. L7 cold water pipe connection
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
Comments
Name:
Representative of Client
Signature:
Note: To be submitted daily to Consultant before 10.00 am
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
Daily Report
Weather: Fine Cloudy √ Rain AM PM
PLANT/MACHINERY MANPOWER
Plant / Machinery No. Plant / Machinery No. Trade No. Trade No.
Excavator Compactor Project Manager Bar Bender 19
Water Truck Lorry APM 1 Aluminum fwk 38
Backhoe Sky Lift Site Agent 1 Carpenter
Crawler Crane Forklift 1 Site Engineer Concreter
Mobile Crane (25Ton) Concrete Pump 1 Site Supervisor 2 Catch Platform Installer
Mobile Crane (200Ton) Grinder 2 Site Foreman Brick Layer 38
Water Pump 1 Tower Crane 1 M&E Coordinator 1 Plasterer 16
Air Compressor Set 1 Safety Officer 1 Skim 12
Generator Set Site Admin 2 Scaffolder 3
Welding Set 1 Safety Site Supervisor 1
Bar Bending Machine 2 Surveyor 1 M&E
Bar Cutting Machine 2 Forklift Operator 1 Electrical
Drill Machine 1 Security Guard 1 Plumber
Hacker Machine 2 General Workers 21 ELV
Air breaker 20lbs TC Operator 1 ACMV
Air breaker 60lbs Signalman 1 Earthing
Flagman 1 Fire
Description of work:
Architectural Architectural
1. L8, L9, L10, L11 & L12 brick work 1. L9, L10, L11 & L12 brick work.
2. L13 & L14 door frame 2. L15 & L16 door frame install
3. L7 wall skim coat & plastering. 3. L7 wall skim coat & plastering
4. L14 & L15 bathroom kickers. 4. L14 & L15 bathroom kickers
5. L5 floor screeding 5. L5 floor screeding
6. L6 toilets & aircond ledge water in fill for ponding test 6. L4 tiling work
7. L4 tiling work.
M&E M&E
ELV ELV
1. L22 Z1 SW conduit pipe 1. L22 Z1 SW conduit pipe
ACMV ACMV
1. L22 Z2 slab & L22 Z1 SW drain pipe & pipe sleeve 1. L22 Z2 slab & L22 Z1 SW drain pipe & pipe sleeve
ELECTRICAL ELECTRICAL
1. L22 Z1 SW conduit pipe 1. L22 Z1 SW conduit pipe
2. L5 hacking work 2. L5 hacking work
3. L16 & 18 wiring work 3. L16 & 18 wiring work
PLUMBING PLUMBING
1. L22 Z1 SW SW plumbing work 1. L22 Z1 SW SW plumbing work
2. L10 sanitary pipe install 2. L10 sanitary pipe install
3. L7 cold water pipe 3. L7 cold water pipe
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
Comments
Name:
Representative of Client
Signature:
Note: To be submitted daily to Consultant before 10.00 am
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
Daily Report
Weather: √ Fine Cloudy Rain AM PM
PLANT/MACHINERY MANPOWER
Plant / Machinery No. Plant / Machinery No. Trade No. Trade No.
Excavator Compactor Project Manager Bar Bender 19
Water Truck Lorry APM 1 Aluminum fwk 38
Backhoe Sky Lift Site Agent 1 Carpenter
Crawler Crane Forklift 1 Site Engineer Concreter 7
Mobile Crane (25Ton) Concrete Pump 1 Site Supervisor 2 Catch Platform Installer
Mobile Crane (200Ton) Grinder 2 Site Foreman Brick Layer 38
Water Pump 1 Tower Crane 1 M&E Coordinator 1 Plasterer 16
Air Compressor Set 1 Safety Officer 1 Skim 12
Generator Set Site Admin 2 Scaffolder 3
Welding Set 1 Safety Site Supervisor 1
Bar Bending Machine 2 Surveyor 1 M&E
Bar Cutting Machine 2 Forklift Operator 1 Electrical 11
Drill Machine 1 Security Guard 1 Plumber 10
Hacker Machine 2 General Workers 14 ELV 3
Air breaker 20lbs TC Operator 1 ACMV 4
Air breaker 60lbs Signalman 1 Earthing
Flagman 1 Fire 4
Description of work:
Architectural
1. L9, L10, L11 & L12 brick work.
2. L15 & L16 door frame & bathroom kickers
3. L7 wall skim coat & plastering.
4. L5 floor screeding
5. L4 tiling work.
M&E
1. L22 Z1 SW & L22 Z2 slab & beam inspection
ELV
1. L22 Z3 slab conduit pipe
ACMV
1. L22 Z3 slab & L22 Z1 SW drain pipe & pipe sleeve
2. L12 U5 drain pipe
3. L11 U3 copper pipe install
ELECTRICAL
1. L22 Z3 slab conduit pipe install
2. L9 hacking work
3. L16 & 10 wiring work
FIRE PROTECTION
1. L22 Z3 slab riser pipe work
2. L3 & 4 install HR pipe level
PLUMBING
1. L22 Z3 slab plumbing work
2. L10 sanitary pipe install
3. L8 cold water pipe install
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
Comments
Name:
Representative of Client
Signature:
Note: To be submitted daily to Consultant before 10.00 am
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
PLANT/MACHINERY MANPOWER
Plant / Machinery No. Plant / Machinery No. Trade No. Trade No.
Excavator Compactor Project Manager Bar Bender 19
Water Truck Lorry APM 1 Aluminum fwk 38
Backhoe Sky Lift Site Engineer Carpenter
Crawler Crane Forklift 1 Site Supervisor 1 Concreter 7
Mobile Crane (25Ton) Concrete Pump 1 Site Agent Catch Platform Installer
Mobile Crane (200Ton) Grinder 2 Site Foreman Brick Layer 38
Water Pump 1 Tower Crane 1 M&E Coordinator 1 Plasterer 16
Air Compressor Set 1 Safety Officer 1 Skim 12
Generator Set Site Admin 2 Scaffolder 3
Welding Set 1 Safety Site Supervisor 1
Bar Bending Machine 2 Surveyor 1 M&E
Bar Cutting Machine 2 Forklift Operator 1 Electrical 11
Drill Machine 1 Security Guard 1 Plumber 12
Hacker Machine 2 General Workers 14 ELV 3
Air breaker 20lbs TC Operator 1 ACMV 4
Air breaker 60lbs Signalman 1 Earthing
Flagman 1 Fire 3
Description of work:
C&S
1. L23 Z1 slab BRC/Rebar.
2. L22 Z2 floor setting out. SW BRC/Rebar
3. L22 Z3 slab BRC/Rebar. Verticality setting (Casting)
4. L22 Z2 SW & L22 Z3 slab inspection
Architectural
1. L9, L10, L11 & L12 brick work.
2. L15 & L16 door frame & bathroom kickers
3. L7 wall skim coat & plastering.
4. L4 floor tiling work.
5. L5 floor screeding.
6. L7 toilets & aircond ledge angle filler for waterproofing work.
M&E
1. L22 Z2 SW & L22 Z3 slab inspection
ELV
1. L23 Z1 slab conduit pipe
2. L16 install cable
ACMV
1. L22 Z1 slab & L21 Z3 SW drain pipe & pipe sleeve
2. L12 U5 drain pipe
3. L11 U3 copper pipe install
ELECTRICAL
1. L23 Z1 slab conduit pipe
2. L10 hacking work
3. L11 and L16 wiring work
FIRE PROTECTION
1. L23 Z1 slab riser work
2. Install HR pipe level at L3 & 4
PLUMBING
1. L23 Z1 slab plumbing work
2. L10 sanitary pipe install
3. L9 cold water pipe install
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
Comments
Name:
Representative of Client
Signature:
Note: To be submitted daily to Consultant before 10.00 am
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
PLANT/MACHINERY MANPOWER
Plant / Machinery No. Plant / Machinery No. Trade No. Trade No.
Excavator Compactor Project Manager Bar Bender 19
Water Truck Lorry APM 1 Aluminum fwk 38
Backhoe Sky Lift Site Engineer Carpenter
Crawler Crane Forklift 1 Site Supervisor 1 Concreter
Mobile Crane (25Ton) Concrete Pump 1 Site Agent Catch Platform Installer
Mobile Crane (200Ton) Grinder 2 Site Foreman Brick Layer 38
Water Pump 1 Tower Crane 1 M&E Coordinator Plasterer 16
Air Compressor Set 1 Safety Officer 1 Skim 12
Generator Set Site Admin 2 Scaffolder 3
Welding Set 1 Safety Site Supervisor 1
Bar Bending Machine 2 Surveyor 1 M&E
Bar Cutting Machine 2 Forklift Operator 1 Electrical 11
Drill Machine 1 Security Guard 1 Plumber 12
Hacker Machine 2 General Workers 21 ELV 3
Air breaker 20lbs TC Operator 1 ACMV 4
Air breaker 60lbs Signalman 1 Earthing
Flagman 1 Fire 3
Description of work:
C&S
1. L23 Z1 slab BRC/Rebar. Verticality setting
2. L22 Z2 SW BRC/Rebar & fromwork
3. L22 Z3 floor setting out. SW BRC/Rebar
4. L23 Z1 slab & beam inspection
Architectural
1. L10, L11, L12, L13 & L14 brick work & sub frame.
2. L15, L16 & L17 door frame & bathroom kickers
3. L7 wall skim coat & plastering.
4. L4 floor tiling work.
5. L5 floor screeding.
6. L7 toilets & aircond ledge angle filler for waterproofing work.
8. L9 stiffeners at corridor area
M&E
1. L23 Z1 slab & beam inspection
ELV
1. L23 Z1 slab conduit pipe
2. L16 install cable
ACMV
1. L23 Z1 slab & L22 Z3 SW drain pipe & pipe sleeve
2. L14 U1 drain pipe install
3. L12 U1 copper pipe install
ELECTRICAL
1. L23 Z1 slab conduit pipe
2. L10 hacking work
3. L11 and L16 wiring work
FIRE PROTECTION
1. L23 Z1 slab riser work
2. Install HR pipe level at L3 & 4
PLUMBING
1. L23 Z1 slab plumbing work
2. L10 sanitary pipe install
3. L9 cold water pipe install
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
Comments
Name:
Representative of Client
Signature:
Note: To be submitted daily to Consultant before 10.00 am
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
PLANT/MACHINERY MANPOWER
Plant / Machinery No. Plant / Machinery No. Trade No. Trade No.
Excavator Compactor Project Manager Bar Bender 19
Water Truck Lorry APM 1 Aluminum fwk 38
Backhoe Sky Lift Site Engineer Carpenter
Crawler Crane Forklift 1 Site Supervisor 1 Concreter 7
Mobile Crane (25Ton) Concrete Pump 1 Site Agent 1 Catch Platform Installer
Mobile Crane (200Ton) Grinder 2 Site Foreman Brick Layer 38
Water Pump 1 Tower Crane 1 M&E Coordinator 1 Plasterer 16
Air Compressor Set 1 Safety Officer Skim 12
Generator Set Site Admin 2 Scaffolder 3
Welding Set 1 Safety Site Supervisor 1
Bar Bending Machine 2 Surveyor 1 M&E
Bar Cutting Machine 2 Forklift Operator 1 Electrical 11
Drill Machine 1 Security Guard 1 Plumber 12
Hacker Machine 2 General Workers 14 ELV 3
Air breaker 20lbs TC Operator 1 ACMV 4
Air breaker 60lbs Signalman 1 Earthing
Flagman 1 Fire 3
Description of work:
C&S
1. L23 Z1 slab BRC/Rebar. Verticality setting (Casting)
2. L22 Z2 SW BRC/Rebar & formwork.
3. L23 Z2 slab formwork setting up.
4. L22 Z3 SW BRC/Rebar.
5. L23 Z1 slab & beam.
Architectural
1. L10, L11, L12, L13 & L14 brick work & sub frame.
2. L15, L16 & L17 door frame & bathroom kickers
3. L7 wall skim coat & plastering.
4. L4 floor tiling work.
5. L4 plaster ceiling work.
6. L4 aluminum window installation.
7. L6 floor screeding.
8. L7 toilets & aircond ledge cleaning for waterproofing work.
9. L9 stiffeners at corridor area
M&E
1. L23 Z1 slab inspection
ELV
1. L22 Z3 SW conduit pipe
2. L17 installation of cable
ACMV
1. L23 Z1 slab and L22 Z3 SW drain pipe & pipe sleeve
2. L14 U2 drain pipe install
3. L12 U1 copper pipe install
ELECTRICAL
1. L23 Z3 SW conduit pipe
2. L10 hacking work
3. L13 and 17 wiring work
FIRE PROTECTION
1. L23 Z1 slab riser work
PLUMBING
1. L23 Z1 slab plumbing work
2. L10 sanitary pipe install
3. L9 cold water pipe install
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
Comments
Name:
Representative of Client
Signature:
Note: To be submitted daily to Consultant before 10.00 am
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
PLANT/MACHINERY MANPOWER
Plant / Machinery No. Plant / Machinery No. Trade No. Trade No.
Excavator Compactor Project Manager Bar Bender 15
Water Truck Lorry APM 1 Aluminum fwk 38
Backhoe Sky Lift Site Agent 1 Carpenter
Crawler Crane Forklift 1 Site Engineer Concreter 7
Mobile Crane (25Ton) Concrete Pump 1 Site Supervisor 1 Catch Platform Installer
Mobile Crane (200Ton) Grinder 2 Site Foreman Brick Layer 40
Water Pump 1 Tower Crane 1 M&E Coordinator 1 Plasterer 30
Air Compressor Set 1 Safety Officer 1 Skim 15
Generator Set Site Admin 2 Scaffolder 3
Welding Set 1 Safety Site Supervisor Waterproofing 2
Bar Bending Machine 2 Surveyor 1 M&E
Bar Cutting Machine 2 Forklift Operator 1 Electrical 11
Drill Machine 1 Security Guard 1 Plumber 12
Hacker Machine 2 General Workers 14 ELV 3
Air breaker 20lbs TC Operator 1 ACMV 4
Air breaker 60lbs Signalman 1 Earthing
Flagman 1 Fire 3
Description of work:
Architectural
1. L11, L11, L12, L13, L14 & L15 brick work
2. L16, L17 & L18 door frame & bathroom kickers
3. L8 & L9 wall skim coat & plastering
4. L7 floor screeding setting out
5. L4 tiling work
6. L4 plaster ceiling work.
7. L4 aluminum window installation
8. L5 tiling work setting out.
9. L7 ponding test.
10. L8 toilets & aircond ledge cleaning for waterproofing work.
11. L10 stiffeners at corridor area
M&E
1. L23 Z1 SW & L23 Z2 slab & beam inspection
ELV
1. L23 Z3 slab conduit pipe install
2. L17 install cable.
ACMV
1. L23 Z3 slab & L23 Z1 SW drain pipe & pipe sleeve
2. L14 U2 drain pipe install
3. L12 U1 copper pipe install
ELECTRICAL
1. L23 Z3 slab conduit pipe install
2. L10 hacking work
3. L13 & 17 wiring work
FIRE PROTECTION
1. L23 Z3 slab riser work
PLUMBING
1. L23 Z3 slab plumbing work
2. L11 sanitary pipe install
3. L11 cold water pipe
4. L7 coring work
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00*
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
Comments
Name:
Representative of Client
Signature:
Note: To be submitted daily to Consultant before 10.00 am
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
PLANT/MACHINERY MANPOWER
Plant / Machinery No. Plant / Machinery No. Trade No. Trade No.
Excavator Compactor Project Manager Bar Bender 15
Water Truck Lorry APM 1 Aluminum fwk 35
Backhoe Sky Lift Site Engineer Carpenter
Crawler Crane Forklift 1 Site Supervisor 1 Concreter
Mobile Crane (25Ton) Concrete Pump 1 Site Foreman Catch Platform Installer
Mobile Crane (200Ton) Grinder 2 M&E Coordinator 1 Brick Layer 33
Water Pump 1 Tower Crane 1 Safety Officer 1 Plasterer 26
Air Compressor Set 1 Site Admin 2 Skim 17
Generator Set Safety Site Supervisor 1 Scaffolder 3
Welding Set 1 Surveyor 1 Waterproofing 2
Bar Bending Machine 2 Forklift Operator 1 M&E
Bar Cutting Machine 2 Security Guard 1 Electrical 3
Drill Machine 1 General Workers 11 Plumber 8
Hacker Machine 2 TC Operator 1 ELV 2
Air breaker 20lbs Signalman 1 ACMV 3
Air breaker 60lbs Flagman 1 Earthing
Fire 5
Description of work:
C&S
1. L19 Z1 slab BRC/Rebar. Verticality set. Casting
2. L19 Z2 slab formwork, BRC/Rebar
3. L18 Z3 SW BRC/Rebar
4. L7 Stiffeners.
5. L18 Z3 SW & L19 Z1 slab inspection
Architectural
1. L7, L8, L9 & L10 door frame & brick work.
2. L11 door frame installation
3. L5 wall plastering
4. L6 Skimcoat
5. L4 floor screeding
M&E
1. L10 & 11 and L19 Z1 slab ELV work
2. L19 Z1 slab ELV work
3. L19 Z1 slab drain pipe & pipe sleeve
4. L19 Z1 slab electrical work
5. L19 Z1 slab and L9 & 5 plumbing work
6. L19 Z1 slab M&E inspection
Appendix
CADANGAN PEMBANGUNAN PERDANGANGAN YANG MENGANDUNGI 1 BLOK 30 TINGKAT BANGUNAN YANG
Revision: 00
MENGANDUNGI 3 TINGKAT PERDAGANGAN DAN 27 TINGKAT 258 UNIT PANGSAPURI SERVIS
Date:
Comments
Name:
Representative of Client
Signature:
Note: To be submitted daily to Consultant before 10.00 am