Excavation

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 1

SL.

NO DESCRIPTION UNIT QTY REMARKS

1 BLOCK 2 -( Diff in lvl 104.2-104.00 ) Cum 200 Stilt + GF + 12 Floors


Footings Below Stilt Floor Cum 500 72 no's footing considered for excavation (2 x 2 x 1.5mtr)

2 BLOCK 1 (excavation for Basement) Cum 19200 Basement + Stilt + GF + 12 Floors (depth of excavation considered 3.7mtr)
Footings Below Basement Lvl Cum 792 132 no's footing considered for excavation (2 x 2 x 1.5mtr)

Grand Total Cum 20692 = 21000 cum (7,41,500 CFT)

AVERAGE NGL LVL IS = 104.20


TROPICA (PHASE 1 ) TOTAL = 312 UNITS