Professional Documents
Culture Documents
Dilla Boq
Dilla Boq
8.1.5 Jacusie
Supply and fix standatad approved jacusie made of acrylic as shown in
the design drawing complete with all accessories and fittings for normal
operation. Price shall also inlude telephone shower units. price shall
also includeall assistance civil works essential for complete installation
of the work.
8.1.6 Shower
construct shower unit with tappred glass enclosure with non slippery
mozaic tile floor finish with 60mm corner waste outlet hole, fixing &
supporting element. All fixtures shall conform to BS 6340:1983 or
equivalent institution. Accessories like chrome plated 2pcs single faucet
(faucet type for cold & hot water supply system type 2 are 1/2"
nominal size, mounting in vertical surface & fixed outlet comply with
BS EN 200: 2008 with PN 10 ) ; chrome plate shower head with full
body spray ( shower head type no flexible & adjustable ) ;chrome
plated shower arm thread on both ends ; 50mm diameter of waste outlet
( waste outlet fittings like gasket, drain pipe, 50mm depth of seal P-
Trap, flange, strainer & drain body comply with BS EN 274 - 1:
2002 ) ; 15mm diameter & 700mm length cold & hot water supply PVC
pipe ; 15mm diameter & 1100mm length shower head riser PVC pipe ;
2pcs shut-off gate valve for hot & cold water supply pipe & all fixing &
supporting element with all other necessary accessories which complete
the set must be included & shall comply with BS standard or equivalent
institution.
8.2.3 Supply and Fixing Bronze gate valves PN-20 which shall be
compatible to the PP-R pipes on the branch pipe line for all the water
supply system as shown in the drawings
8.2.4 20mm dia pcs
8.2.5 25mm dia pcs
SPECIAL CHARACTERSTICS
Surface Preparation: Concrete surface must be clean and free of dirt,
films, coatings or other foreign matter. All surface imperfections and
protrusions are to be removed and repaired. Structurally unsound and
friable concrete must be removed and repaired.
Testing: Pond testing for at least 24 hours should be done after the
contractor has accomplished the water proofing work. The surface
should be re-treated if leakage observed; and the test should be done
on the repaired surface.
8.4.1
Supply and coat XYPEX or Equivalent Cementitious Water proofing as
per manufacturers instruction for all wet areas, toilets kitchen, etc. as
per Engineer's instruction. The contractor must consider the work as
complete set and provide appropriate measures for the connection b/n
pipes and concrete slab. After the completion of the work the contractor
should do ponding test using water at level of 20cm from floor finish
level for at least 24 hours. m2
8.4.2
Supply and install SIKA or Equivalent, 4mm thick bitumen plastometric
water proofing, manufactured from a rich mixture of bitumen and
selected polymer blended together to obtain excellent heat and UV
resistant membrane type water proofing as per manufacturers
instruction for all suspended exposed slabs, terraces, etc. as per
Engineer's instruction. m2
Fix flat strainers on the roof terminal of storm water drainage pipes as
where shown on the drawing. Price shall include all the necessary
connecting pieces including gaskets and all water tight connections as
required.
8.5.2 75mm dia no
8.5.3 Construct rectangular grill covered ditch masonry concrete as per the
detail drawing. grill shall be fabricated out of flat metal
[400x40x5(LxWxT)] welded to two angle irons of size 50x50x5mm c/c
50mm with a maximum fabrcation length of 1.5m. Price shall include
excavation, cart away and all civil assistance works.
8.5.6 Waste water Construct rectangular manhole out of 80mm thick cast
insitu cement concrete, internal dimension 600mmx600mm and
1000mm (average depth),on a base of R.C slab size,960x 960x
100mm, including benching and bottom channeling with mass C-25
concrete. The Slab shall be reinforced with diameter 10mm
reinforcement bar c/c 200mm bothways.Provide 150mm thick granular
materials beneath the slab, on a well compacted earth. Manhole shall
have pre cast R.C cover slab, each, size, 700mm x 680mm x 100mm
reinforced with diameter 8mm steel bar c/c130mm both ways,
including diameter 14mm steel ring handle with supporter bar all in
accordance with the given detail drawings . Unit price shall include
excavation of the pit to a depth of 750mm (average) and cart away of
the excavated soil.
pcs
1 20,745.31 20,745.31
1.00 417.99 417.99
628,142.33
8 DIVISION - PLUMBING
8.1 Sanitary Equipment ( Fixtures )
All fixtures which are specified below is subject to the owner's
consultant's approval, based on samples, catalogues and brochures
presented by the contractor. Unit price shall include all the necessary
fixing brackets or hooks and all assistance civil works such as chiseling
of walls, floors, beams and etc.
8.1.5 Jacusie
Supply and fix standatad approved jacusie made of acrylic as shown in
the design drawing complete with all accessories and fittings for normal
operation. Price shall also inlude telephone shower units. price shall
also includeall assistance civil works essential for complete installation
of the work.
8.1.6 Shower
construct shower unit with tappred glass enclosure with non slippery
mozaic tile floor finish with 60mm corner waste outlet hole, fixing &
supporting element. All fixtures shall conform to BS 6340:1983 or
equivalent institution. Accessories like chrome plated 2pcs single faucet
(faucet type for cold & hot water supply system type 2 are 1/2"
nominal size, mounting in vertical surface & fixed outlet comply with
BS EN 200: 2008 with PN 10 ) ; chrome plate shower head with full
body spray ( shower head type no flexible & adjustable ) ;chrome
plated shower arm thread on both ends ; 50mm diameter of waste outlet
( waste outlet fittings like gasket, drain pipe, 50mm depth of seal P-
Trap, flange, strainer & drain body comply with BS EN 274 - 1:
2002 ) ; 15mm diameter & 700mm length cold & hot water supply PVC
pipe ; 15mm diameter & 1100mm length shower head riser PVC pipe ;
2pcs shut-off gate valve for hot & cold water supply pipe & all fixing &
supporting element with all other necessary accessories which complete
the set must be included & shall comply with BS standard or equivalent
institution.
8.2.4 Supply and Fixing Bronze gate valves PN-20 which shall be
compatible to the PP-R pipes on the branch pipe line for all the water
supply system as shown in the drawings
8.2.5 20mm dia pcs
8.2.6 25mm dia pcs
SPECIAL CHARACTERSTICS
Surface Preparation: Concrete surface must be clean and free of dirt,
films, coatings or other foreign matter. All surface imperfections and
protrusions are to be removed and repaired. Structurally unsound and
friable concrete must be removed and repaired.
Testing: Pond testing for at least 24 hours should be done after the
contractor has accomplished the water proofing work. The surface
should be re-treated if leakage observed; and the test should be done
on the repaired surface.
8.4.1
Supply and coat XYPEX or Equivalent Cementitious Water proofing as
per manufacturers instruction for all wet areas, toilets kitchen, etc. as
per Engineer's instruction. The contractor must consider the work as
complete set and provide appropriate measures for the connection b/n
pipes and concrete slab. After the completion of the work the contractor
should do ponding test using water at level of 20cm from floor finish
level for at least 24 hours. m2
8.4.2
Supply and install SIKA or Equivalent, 4mm thick bitumen plastometric
water proofing, manufactured from a rich mixture of bitumen and
selected polymer blended together to obtain excellent heat and UV
resistant membrane type water proofing as per manufacturers
instruction for all suspended exposed slabs, terraces, etc. as per
Engineer's instruction. m2
Fix flat strainers on the roof terminal of storm water drainage pipes as
where shown on the drawing. Price shall include all the necessary
connecting pieces including gaskets and all water tight connections as
required.
8.5.2 75mm dia no
8.5.3 Construct rectangular grill covered ditch masonry concrete as per the
detail drawing. grill shall be fabricated out of flat metal
[400x40x5(LxWxT)] welded to two angle irons of size 50x50x5mm c/c
50mm with a maximum fabrcation length of 1.5m. Price shall include
excavation, cart away and all civil assistance works.
8.5.6 Waste water Construct rectangular manhole out of 80mm thick cast
insitu cement concrete, internal dimension 600mmx600mm and
1000mm (average depth),on a base of R.C slab size,960x 960x
100mm, including benching and bottom channeling with mass C-25
concrete. The Slab shall be reinforced with diameter 10mm
reinforcement bar c/c 200mm bothways.Provide 150mm thick granular
materials beneath the slab, on a well compacted earth. Manhole shall
have pre cast R.C cover slab, each, size, 700mm x 680mm x 100mm
reinforced with diameter 8mm steel bar c/c130mm both ways,
including diameter 14mm steel ring handle with supporter bar all in
accordance with the given detail drawings . Unit price shall include
excavation of the pit to a depth of 750mm (average) and cart away of
the excavated soil.
pcs
2 20,745.31 41,490.63
2.00 417.99 835.97
1,237,262.87
8 DIVISION - PLUMBING
8.1 Sanitary Equipment ( Fixtures )
All fixtures which are specified below is subject to the owner's
consultant's approval, based on samples, catalogues and brochures
presented by the contractor. Unit price shall include all the necessary
fixing brackets or hooks and all assistance civil works such as chiseling
of walls, floors, beams and etc.
8.1.5 Jacusie
Supply and fix standatad approved jacusie made of acrylic as shown in
the design drawing complete with all accessories and fittings for normal
operation. Price shall also inlude telephone shower units. price shall
also includeall assistance civil works essential for complete installation
of the work.
8.1.6 Shower
construct shower unit with tappred glass enclosure with non slippery
mozaic tile floor finish with 60mm corner waste outlet hole, fixing &
supporting element. All fixtures shall conform to BS 6340:1983 or
equivalent institution. Accessories like chrome plated 2pcs single faucet
(faucet type for cold & hot water supply system type 2 are 1/2"
nominal size, mounting in vertical surface & fixed outlet comply with
BS EN 200: 2008 with PN 10 ) ; chrome plate shower head with full
body spray ( shower head type no flexible & adjustable ) ;chrome
plated shower arm thread on both ends ; 50mm diameter of waste outlet
( waste outlet fittings like gasket, drain pipe, 50mm depth of seal P-
Trap, flange, strainer & drain body comply with BS EN 274 - 1:
2002 ) ; 15mm diameter & 700mm length cold & hot water supply PVC
pipe ; 15mm diameter & 1100mm length shower head riser PVC pipe ;
2pcs shut-off gate valve for hot & cold water supply pipe & all fixing &
supporting element with all other necessary accessories which complete
the set must be included & shall comply with BS standard or equivalent
institution.
8.2.4 Supply and Fixing Bronze gate valves PN-20 which shall be
compatible to the PP-R pipes on the branch pipe line for all the water
supply system as shown in the drawings
8.2.5 20mm dia pcs
8.2.6 25mm dia pcs
8.2.7 32mm dia pcs
SPECIAL CHARACTERSTICS
8.4.1
Supply and coat XYPEX or Equivalent Cementitious Water proofing as
per manufacturers instruction for all wet areas, toilets kitchen, etc. as
per Engineer's instruction. The contractor must consider the work as
complete set and provide appropriate measures for the connection b/n
pipes and concrete slab. After the completion of the work the contractor
should do ponding test using water at level of 20cm from floor finish
level for at least 24 hours. m2
8.4.2
Supply and install SIKA or Equivalent, 4mm thick bitumen plastometric
water proofing, manufactured from a rich mixture of bitumen and
selected polymer blended together to obtain excellent heat and UV
resistant membrane type water proofing as per manufacturers
instruction for all suspended exposed slabs, terraces, etc. as per
Engineer's instruction. m2
Fix flat strainers on the roof terminal of storm water drainage pipes as
where shown on the drawing. Price shall include all the necessary
connecting pieces including gaskets and all water tight connections as
required.
8.5.3 75mm dia no
8.5.4 110mm dia no
8.5.5 Construct rectangular grill covered ditch masonry concrete as per the
detail drawing. grill shall be fabricated out of flat metal
[400x40x5(LxWxT)] welded to two angle irons of size 50x50x5mm c/c
50mm with a maximum fabrcation length of 1.5m. Price shall include
excavation, cart away and all civil assistance works.
pcs
4 65,000.00 260,000.00
3.00 417.99 1,253.96
-
78.00 4,802.63 374,604.75
3.00 6,024.17 18,072.52
1,769,813.76
DIVISION - PLUMBING
Sanitary Equipment ( Fixtures )
All fixtures which are specified below is subject to the owner's
consultant's approval, based on samples, catalogues and brochures
presented by the contractor. Unit price shall include all the
necessary fixing brackets or hooks and all assistance civil works
such as chiseling of walls, floors, beams and etc.
Water closet
1.00 Supply and fix water closet, of wash down action, floor pcs 52.00
mounted, vertical outlet (floor drainage), close coupled,
made of white vitreous China (BS 3402). The fixture
shall conform to BS5503-2 or equivalent institution. The
waste fittings, connecting pieces, fixing and supporting
element and other accessories which completes the set
shall comply with the relevant clauses of BS standards
or equivalent institution.
Vanity Top
The Vanity top is to be made from water-resistant granite topping.
The front apron to have a depth of only 100mm to allow for free
access for knees.
Vanity Top size :535 x 700mm
Basin
hand wash basin to be white vitreous china with apron front of
100mmand can be fitted to the right side of the vanity.
Basin size :510 x 455mm
Fixing Brackets
Fitted to the underside of the basin with toggle bolts and screwed
to the underside of the work top
Accessories
Tap has to be provided separately for cold and hot water, model
should be REMER/JAQUAR or Equivalent chrome plated cold
and hot water tap, Complete with mixing battery plug, chrome
plated chain holder, P-smell trap with connection pipe and with all
other hose to be REMER/JAQUAR or Equivalent, necessary
accessories. Flexible hose of Length 60cm to be Vinyl coated and
should be capable of resisting pressure of 4 bar. P-smell trap
should be brass chrome plated with 50mm height of water seal and
trap. Color of the Granite topping to be decided by the Architect.
pcs 5.00
9.00 Shower
construct shower unit with tappred glass enclosure with non
slippery mozaic tile floor finish with 60mm corner waste outlet
hole, fixing & supporting element. All fixtures shall conform to
BS 6340:1983 or equivalent institution. Accessories like chrome
plated 2pcs single faucet (faucet type for cold & hot water supply
system type 2 are 1/2" nominal size, mounting in vertical surface
& fixed outlet comply with BS EN 200: 2008 with PN 10 ) ;
chrome plate shower head with full body spray ( shower head type
no flexible & adjustable ) ;chrome plated shower arm thread on
both ends ; 50mm diameter of waste outlet ( waste outlet fittings
like gasket, drain pipe, 50mm depth of seal P-Trap, flange, strainer
& drain body comply with BS EN 274 - 1: 2002 ) ; 15mm
diameter & 700mm length cold & hot water supply PVC pipe ;
15mm diameter & 1100mm length shower head riser PVC pipe ;
2pcs shut-off gate valve for hot & cold water supply pipe & all
fixing & supporting element with all other necessary accessories
which complete the set must be included & shall comply with BS
standard or equivalent institution.
Water Heater
12.00 Supply and fix ariston or equivalent water heater including all
assstance civil works.price shall also include valves and fittings
necssary for complete installation.
capacity : 50 Lit Pcs 136.00
20.00 Supply and Fixing Bronze gate valves PN-20 which shall be
compatible to the PP-R pipes on the branch pipe line for all the
water supply system as shown in the drawings
20.10 20mm dia pcs 232.00
20.20 25mm dia pcs 28.00
20.30 32mm dia pcs 5.00
20.40 40mm dia pcs 1.00
20.50 50mm dia pcs 3.00
20.60 63mm dia pcs 2.00
24.00 Supply and install Fiber Glass or Equivalent water tanks on stair
roof floor slab as where shown on the drawing.
Accessories
- Dia. 50 mm strainers with foot valve
- Dia. 50 mm HDPE drain and over flow pipe nearest storm
drain downpipe (P.Q.)
- Bronze Gate valve on drain pipe, dia. 32mm
- Dia. 100 mm vent pipe with cap
- Dia. 50 mm float valve
- Dia. 32 mm Bronze gate valve on inlet pipe
- Automatic level switch to be connected to domestic pumps to
avoid (protect) dry running.
- Dia. 32mm PPR connection pipe with Bronze gate valve.
SPECIAL CHARACTERSTICS
26.10
Supply and coat XYPEX or Equivalent Cementitious Water
proofing as per manufacturers instruction for all wet areas, toilets
kitchen, etc. as per Engineer's instruction. The contractor must
consider the work as complete set and provide appropriate
measures for the connection b/n pipes and concrete slab. After the
completion of the work the contractor should do ponding test
using water at level of 20cm from floor finish level for at least 24
hours. m2 434.00
26.20
Supply and install SIKA or Equivalent, 4mm thick bitumen
plastometric water proofing, manufactured from a rich mixture of
bitumen and selected polymer blended together to obtain excellent
heat and UV resistant membrane type water proofing as per
manufacturers instruction for all suspended exposed slabs,
terraces, etc. as per Engineer's instruction. m2 734.00
31.00 Supply and lay rodding or cleaning eye of uPVC, PN-4 on the sub
soil drainage system as where shown on the drawings. Provide
plug or screw tube plastic cap on top to external ground level.
32.00
Construct catch pit sump as per the detail drawing. The
reinforced catch pit should be externally protected with 4mm thick
TESTUDO or Equivalent water proofing membrane and the
internal part should be water proofed using semi elastic
cementitious water proofing; all as per manufacturers instruction
and recommendation. No 1
Fire Suppression
All fire fighting material shall comply with TUV ,BSI,NFPA or
equivalent institution certification and approval. Complete with
approved standard hanging and fixing material
a) diameter 40 m 20.00
b) diameter 65 m 48.00
33.00 Fire-Suppression Hose Racks
Supply and fix BS, NFPA or DIN standard, wall mounted hose
racks cabinet with full metal door model. Cabinet and door leaf
made of stainless steel 2mm thick sheets with full 180 degree
swinging action and painted with electro-statics powder paint oven
baked to temperatures flexible to -65º F (-55º C).Hose is made of
100% synthetic Light weight, Strong Single Jacket, the outer
fabric made of circular woven SYNTHETIC FIBER and root
proof yarn, while inner layer is a substrate of tropical rubber, with
working pressure 20 bar and bursting pressure 60 bar with
standard red color and Inner waterway should be smooth.1.5''size
Nozzle made of brass with Chrome plated with three way control.
Cabinet:-W=65cm,H=90cm and D=19cm, extinguisher 6kg in the
cabinet. The installation shall be tested at a pressure of 16kgf/cm2.
The hose shall be compatible to Galvanized Steel pipes,
accessories & fittings.GS pipe installation & method of
connection shall comply with the requirement of BS 4991 & BS
6920 part 2 &3 or equivalent institution. Unit price shall include
all the necessary assistance to the installation works. Fire Hose
should be resistant to such chemicals, petrol products, ozone &
U.V. exposure, hydrolysis, and rot & mildew. Made of NAFFCO
or equivalent brand .
pcs 9.00
38.00 Supply and uPVC, PN-6 pipe for waste water drainage from the
manhole to the septic tank with minimum slope as shown on the
drawing or natural ground slope which ever is greater on a firm
bed of sand 150 mm thick below and 200 mm thick above the
crown of pipe in open ground.
pcs 8.00
40.00 Construct septic tank out of reinforced concrete as per the detail
design drawing. Price shall include piping, excavation, cart away
and all assistance civil works as where shown on the detailed
drawing. Capacity of septic tank shall be 100 m3
pcs 1.00
TOTAL CARRIED TO SUMMARY
13,468.75 700,375.00
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
41,580.00 249,480.00
681.25 39,512.50
589.06 34,165.63
12,368.75 853,443.75
23,612.50 354,187.50
8,796.25 43,981.25
109,560.00 109,560.00
15,685.00 266,645.00
827.81 14,900.63
574.79 10,346.25
21,000.00 2,856,000.00
417.99 28,005.12
388.54 388.54
413.54 827.08
438.54 877.08
3,231.25 16,156.00
- -
- -
164,268.75 164,268.75
457,015.67 457,015.67
171,922.30 343,844.60
335.10 48,924.28
424.50 120,556.75
743.02 69,843.52
911.09 32,799.28
978.59 27,400.55
1,073.09 21,461.82
673.01 156,139.41
1,213.01 33,964.41
1,280.51 6,402.57
1,429.41 1,429.41
1,820.91 5,462.74
2,239.41 4,478.82
14,500.00 14,500.00
269,129.93 269,129.93
470,880.00 470,880.00
75694.50 151389
187.65 9,007.20
223.94 21,050.17
462.92 131,467.86
686.03 8,232.36
850.50 369,117.00
-
1,480.50 1,086,687.00
-
394.51 2,367.09
633.49 264,799.43
643.75 643.75
643.75 7,081.25
-
-
533.63 26,414.44
4,802.63 321,775.88
3,478.19 313,037.00
-
731.16 2,193.00
49,477.50 49,477.50
41,242.50 41,242.50
-
1,123.72 22,474.32
1,788.59 85,852.38
36,481.25 328,331.25
2,033,167.50 2,033,167.50
156,404.93 156,404.93
877.34 7,018.73
1,214.84 92,327.93
1,484.84 20,787.78
-
1,687.01 60,732.28
1,777.19 99,522.51
6,024.17 48,193.38
163,225.13 163,225.13
13,751,374.37
ANALYSIS SHEET FOR DIRECT UN
PROJECT:
WORK ITEM: 8.1.1 hand wash basin
TOTAL QANTITY OF WORK ITEM: 1.00 No
sum
Emoployment Benefit
Total = 9350.00
PROJECT:
WORK ITEM: 9.1.5 Crystall glass mirror
TOTAL QANTITY OF WORK ITEM: 1.00 No
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
sum
0.00 Emoployment Benefit
Total = 16500.00
A= Materials Unit Cost 16,500.00 Birr/Pc B= Manpower Unit Cost
Total of (1:02)
Hourly Output:
Direct Cost of Work Item = A+B+C =
Over head cost :
Profit Cost:
Total Unit Cost :
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
ANALYSIS SHEET FOR DIRECT UN
PROJECT:
WORK ITEM: 9.1.7 alumminum urinal screen
TOTAL QANTITY OF WORK ITEM: 1.00 No
sum
0.00 Emoployment Benefit
Total = 2200.00
450.00 0.00
ployment Benefit 10% 45.00 0.00
Total = 495.00 Total = 50.00
450.00 0.00
ployment Benefit 10% 45.00 0.00
Total = 495.00 Total = 50.00
450.00 0.00
ployment Benefit 10% 45.00 0.00
Total = 495.00 Total = 50.00
450.00 0.00
ployment Benefit 10% 45.00 0.00
Total = 495.00 Total = 50.00
500.00 0.00
ployment Benefit 10% 50.00 0.00
Total = 550.00 Total = 14.00
___________
0.00
450.00 0.00
ployment Benefit 10% 45.00 0.00
Total = 495.00 Total = 50.00
0.00
450.00 0.00
ployment Benefit 10% 45.00 0.00
Total = 495.00 Total = 50.00
Item
Type of material Unit Selling price w VAT
No
ANALYSIS SHEET
PROJECT:
WORK ITEM: ( 1.2 ) GS pipe dim.25mm.
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
ANALYSIS SHEET
PROJECT:
WORK ITEM: ( 1.2 ) GS pipe dim.32mm.
TOTAL QANTITY OF WORK ITEM: 1.00 ml
(A) Material Cost (1:01)
Type of Cost per
Material Unit Qty. * Rate Unit
Dim. 32mm.p ml 0.25 2200.00 550.00
Fittings ls 1 180.00 180.00
0.00
0.00
0.00
Total = 730.00
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
ANALYSIS SHEET
PROJECT:
WORK ITEM: ( 1.2 ) GS pipe dim.40mm.
TOTAL QANTITY OF WORK ITEM: 1.00 ml
ANALYSIS SHEET
PROJECT:
WORK ITEM: ( 1.2 ) GS pipe dim.50mm.
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
ANALYSIS SHEET
PROJECT:
WORK ITEM: ( 1.2 ) GS pipe dim.65mm.
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
ANALYSIS SHEET
PROJECT:
WORK ITEM: ( 1.2 ) GS pipe dim.80mm.
TOTAL QANTITY OF WORK ITEM: 1.00 ml
ANALYSIS SHEET
PROJECT:
WORK ITEM: ( 1.2 ) GS pipe dim.100mm.
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
954.97
1039.34
1123.72
1268.84
1788.59
1899.97
1974.22
4.41 Birr/m
______________
ml / hr
/ hr
(C) Equipment Cost (1:03)
Hourly Hourly
UF Rental Cost
1 15.00 15.00
0.00
0.00
0.00
0.00
Total = 15.00
4.41 Birr/m
______________
ml / hr
/ hr
4.41 Birr/m
______________
ml / hr
/ hr
4.41 Birr/m
______________
ml / hr
/ hr
4.41 Birr/m
______________
ml / hr
/ hr
4.41 Birr/m
______________
ml / hr
/ hr
4.41 Birr/m
______________
PPR PIPES
Item
Type of material Unit Selling price w VAT
No
ANALYSIS SHEET
PROJECT:
WORK ITEM: ( 1.2 ) PPR pipe dim.20mm.
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
ANALYSIS SHEET
PROJECT:
WORK ITEM: ( 1.2 ) PPR pipe dim.25mm.
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
ANALYSIS SHEET
PROJECT:
WORK ITEM: ( 1.2 ) PPR pipe dim.32mm.
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
ANALYSIS SHEET
PROJECT:
WORK ITEM: ( 1.2 ) PPR pipe dim.40mm.
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
ANALYSIS SHEET
PROJECT:
WORK ITEM: ( 1.2 ) PPR pipe dim.50mm.
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
ANALYSIS SHEET
PROJECT:
WORK ITEM: ( 1.2 ) PPR pipe dim.63mm.
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
ANALYSIS SHEET
PROJECT:
WORK ITEM: ( 1.2 ) PPR pipe dim.75mm.
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
ANALYSIS SHEET
PROJECT:
WORK ITEM: ( 1.2 ) PPR pipe dim.90mm.
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
ANALYSIS SHEET
PROJECT:
WORK ITEM: ( 1.2 ) PPR pipe dim.125mm.
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
ANALYSIS SHEET
PROJECT:
WORK ITEM: ( 1.2 ) PPR pipe dim.150mm.
TOTAL QANTITY OF WORK ITEM: 1.00 ml
1.47 Birr/m
______________
ml / hr
/ hr
1.47 Birr/m
______________
ml / hr
/ hr
4.41 Birr/m
______________
ml / hr
/ hr
4.41 Birr/m
______________
ml / hr
/ hr
4.41 Birr/m
______________
ml / hr
/ hr
4.41 Birr/m
______________
ml / hr
/ hr
44.12 Birr/m
______________
ml / hr
/ hr
44.12 Birr/m
______________
ml / hr
/ hr
44.12 Birr/m
______________
ml / hr
/ hr
44.12 Birr/m
______________
Valves S
Item
Type of material Unit Selling price w VAT
No
ANALYSIS SHEET F
PROJECT:
WORK ITEM: ( 1.2 ) Valves dim.20mm.
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
ANALYSIS SHEET F
PROJECT:
WORK ITEM: ( 1.2 ) Valves dim.25mm.
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
ANALYSIS SHEET F
PROJECT:
WORK ITEM: ( 1.2 ) Valves dim.32mm.
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
ANALYSIS SHEET F
PROJECT:
WORK ITEM: ( 1.2 ) Valves dim.40mm.
TOTAL QANTITY OF WORK ITEM: 1.00 ml
(A) Material Cost (1:01)
Type of Cost per
Material Unit Qty. * Rate Unit
Dim. 40mm.p ml 1 1050.00 1050.00
Total = 1050.00
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
ANALYSIS SHEET F
PROJECT:
WORK ITEM: ( 1.2 ) Valves dim.50mm.
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
ANALYSIS SHEET F
PROJECT:
WORK ITEM: ( 1.2 ) Valves dim.63mm.
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
final price
673.01
1213.01
1280.51
1429.41
1820.91
2239.41
4.41 Birr/m
______________
ml / hr
/ hr
4.41 Birr/m
______________
ml / hr
/ hr
4.41 Birr/m
______________
ml / hr
/ hr
(C) Equipment Cost (1:03)
Hourly Hourly
UF Rental Cost
1 15.00 15.00
Total = 15.00
4.41 Birr/m
______________
ml / hr
/ hr
4.41 Birr/m
______________
ml / hr
/ hr
4.41 Birr/m
______________
uPVC pipes
Item
Type of material Unit Selling price w VAT
No
INTERNAL INSTALLAT
ANALYSIS SHEET FOR DIRECT
PROJECT:
WORK ITEM: ( 1.2 ) uPVC PN6 pipe Ø =50 mm
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
SITE WORK INSTALLAT
ANALYSIS SHEET FOR DIRECT
PROJECT:
WORK ITEM: ( 1.2 ) uPVC PN6 pipe Ø =160 mm
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
SITE WORK INSTALLAT
ANALYSIS SHEET FOR DIRECT
PROJECT:
WORK ITEM: ( 1.2 ) uPVC PN6 pipe Ø =160 mm
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
PROJECT:
WORK ITEM: ( 9.3.3 ) uPVC PN6 pipe Ø =110 mm
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
PROJECT:
WORK ITEM: ( 9.3.3 ) upvc strianer Ø =75 mm
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
PROJECT:
WORK ITEM: ( 9.3.3 ) upvc strianer Ø =110 mm
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
Working
Rate
187.65
223.94
462.92
686.03
731.16
INTERNAL INSTALLATIONS
NALYSIS SHEET FOR DIRECT UNIT COST
Manpower Unit Cost 29.59 Birr/m C= Equipment Unit Cost 4.41 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: _______________
rect Cost of Work Item = A+B+C = 139.00 Birr/m
Over head cost : 20% 27.80 "
Profit Cost: 15% 20.85 "
Total Unit Cost : 187.65 Birr/m
__________________
Manpower Unit Cost 29.59 Birr/m C= Equipment Unit Cost 4.41 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: _______________
rect Cost of Work Item = A+B+C = 165.88 Birr/m
Over head cost : 20% 33.18 "
Profit Cost: 15% 24.88 "
Total Unit Cost : 223.94 Birr/m
__________________
Manpower Unit Cost 29.56 Birr/m C= Equipment Unit Cost 4.41 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: _______________
rect Cost of Work Item = A+B+C = 508.17 Birr/m
Over head cost : 20% 101.63 "
Profit Cost: 15% 76.23 "
Total Unit Cost : 686.03 Birr/m
__________________
Manpower Unit Cost 29.59 Birr/m C= Equipment Unit Cost 4.41 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: _______________
rect Cost of Work Item = A+B+C = 541.60 Birr/m
Over head cost : 20% 108.32 "
Profit Cost: 15% 81.24 "
Total Unit Cost : 731.16 Birr/m 312.00
__________________
Manpower Unit Cost 35.47 Birr/m C= Equipment Unit Cost 36.76 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: _______________
rect Cost of Work Item = A+B+C = 1,249.64 Birr/m
Over head cost : 20% 249.93 "
Profit Cost: 15% 187.45 "
Total Unit Cost : 1687.01 Birr/m
__________________
Manpower Unit Cost 35.47 Birr/m C= Equipment Unit Cost 36.76 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: _______________
rect Cost of Work Item = A+B+C = 1,316.44 Birr/m
Over head cost : 20% 263.29 "
Profit Cost: 15% 197.47 "
Total Unit Cost : 1777.19 Birr/m
__________________
Manpower Unit Cost 35.47 Birr/m C= Equipment Unit Cost 36.76 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: _______________
rect Cost of Work Item = A+B+C = 2,576.44 Birr/m
Over head cost : 20% 515.29 "
Profit Cost: 15% 386.47 "
Total Unit Cost : 3478.19 Birr/m
__________________
Manpower Unit Cost 35.47 Birr/m C= Equipment Unit Cost 36.76 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: _______________
rect Cost of Work Item = A+B+C = 1,416.64 Birr/m
Over head cost : 20% 283.33 "
Profit Cost: 15% 212.50 "
Total Unit Cost : 1912.46 Birr/m
__________________
Manpower Unit Cost 35.47 Birr/m C= Equipment Unit Cost 36.76 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: _______________
rect Cost of Work Item = A+B+C = 1,516.84 Birr/m
Over head cost : 20% 303.37 "
Profit Cost: 15% 227.53 "
Total Unit Cost : 2047.73 Birr/m
__________________
RTIME RELATED TO TARGETED OUTPUT.
Manpower Unit Cost 35.47 Birr/m C= Equipment Unit Cost 36.76 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: _______________
rect Cost of Work Item = A+B+C = 1,583.64 Birr/m
Over head cost : 20% 316.73 "
Profit Cost: 15% 237.55 "
Total Unit Cost : 2137.91 Birr/m
__________________
Manpower Unit Cost 35.47 Birr/m C= Equipment Unit Cost 36.76 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: _______________
rect Cost of Work Item = A+B+C = 1,683.84 Birr/m
Over head cost : 20% 336.77 "
Profit Cost: 15% 252.58 "
Total Unit Cost : 2273.18 Birr/m
__________________
Manpower Unit Cost 29.59 Birr/m C= Equipment Unit Cost 1.76 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: _______________
rect Cost of Work Item = A+B+C = 292.23 Birr/m
Over head cost : 20% 58.45 "
Profit Cost: 15% 43.83 "
Total Unit Cost : 394.51 Birr/m
__________________
Manpower Unit Cost 29.59 Birr/m C= Equipment Unit Cost 1.76 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: _______________
rect Cost of Work Item = A+B+C = 469.25 Birr/m
Over head cost : 20% 93.85 "
Profit Cost: 15% 70.39 "
Total Unit Cost : 633.49 Birr/m
__________________
Manpower Unit Cost 68.00 Birr/m C= Equipment Unit Cost 6.00 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: _______________
rect Cost of Work Item = A+B+C = 237.50 Birr/m
Over head cost : 20% 47.50 "
Profit Cost: 15% 35.63 "
Total Unit Cost : 320.63 Birr/m
__________________
Manpower Unit Cost 72.00 Birr/m C= Equipment Unit Cost 6.00 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output: _______________
rect Cost of Work Item = A+B+C = 281.50 Birr/m
Over head cost : 20% 56.30 "
Profit Cost: 15% 42.23 "
Total Unit Cost : 380.03 Birr/m
__________________
ost (1:03)
Hourly
Cost
15.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
15.00
ost (1:03)
Hourly
Cost
15.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
15.00
ost (1:03)
Hourly
Cost
15.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
15.00
ost (1:03)
Hourly
Cost
125.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
125.00
ost (1:03)
Hourly
Cost
125.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
125.00
ost (1:03)
Hourly
Cost
125.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
125.00
ost (1:03)
Hourly
Cost
125.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
125.00
ost (1:03)
Hourly
Cost
125.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
125.00
ost (1:03)
Hourly
Cost
125.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
125.00
ost (1:03)
Hourly
Cost
125.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
125.00
ost (1:03)
Hourly
Cost
6.00
0.00
0.00
0.00
0.00
6.00
ost (1:03)
Hourly
Cost
6.00
0.00
0.00
0.00
0.00
6.00
ost (1:03)
Hourly
Cost
6.00
0.00
6.00
ost (1:03)
Hourly
Cost
6.00
0.00
6.00
water proofing
Item Selling price w
Type of material Unit
No VAT
1 cementatious m2 530.00
2 membrane m2 640.00
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
Working
Rate
850.50
1,480.50
3)
Hourly
Cost
200.00
0.00
0.00
200.00
3)
Hourly
Cost
200.00
0.00
0.00
200.00
ANALYSIS SHEET FOR DIRECT
PROJECT:
WORK ITEM: ( 9.3.5 ) water tanker
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
SIS SHEET FOR DIRECT UNIT COST
03)
Hourly
Cost
35.50
0.00
0.00
0.00
0.00
35.50
03)
Hourly
Cost
35.50
0.00
0.00
0.00
0.00
35.50
03)
Hourly
Cost
250.00
0.00
0.00
0.00
0.00
250.00
HDPE PIPES
Item
Type of material Unit Selling price w VAT
No
PROJECT:
WORK ITEM: ( 1.2 ) HDPE pipe dim.20mm.
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
PROJECT:
WORK ITEM: ( 1.2 ) HDPE pipe dim.25mm.
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
ANALYSIS SHEET
PROJECT:
WORK ITEM: ( 1.2 ) HDPE pipe dim.32mm.
TOTAL QANTITY OF WORK ITEM: 1.00 ml
PROJECT:
WORK ITEM: ( 1.2 ) HDPE pipe dim.40mm.
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
ANALYSIS SHEET
PROJECT:
WORK ITEM: ( 1.2 ) HDPE pipe dim.50mm.
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
ANALYSIS SHEET
PROJECT:
WORK ITEM: ( 1.2 ) HDPE pipe dim.63mm.
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
ANALYSIS SHEET
PROJECT:
WORK ITEM: ( 1.2 ) HDPE pipe dim.75mm.
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
ANALYSIS SHEET
PROJECT:
WORK ITEM: ( 1.2 ) HDPE pipe dim.90mm.
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
ANALYSIS SHEET
PROJECT:
WORK ITEM: ( 1.2 ) HDPE pipe dim.110mm.
TOTAL QANTITY OF WORK ITEM: 1.00 ml
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*: INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**: INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETE
Final price
607.34
674.84
742.34
809.84
877.34
1025.84
1214.84
1322.84
1484.84
4.41 Birr/m
______________
ml / hr
/ hr
4.41 Birr/m
______________
ml / hr
/ hr
4.41 Birr/m
______________
ml / hr
/ hr
4.41 Birr/m
______________
ml / hr
/ hr
4.41 Birr/m
______________
ml / hr
/ hr
4.41 Birr/m
______________
ml / hr
/ hr
4.41 Birr/m
______________
ml / hr
/ hr
4.41 Birr/m
______________
ml / hr
/ hr
4.41 Birr/m
______________
ANALYSIS SHEET FOR DIRECT UNIT
PROJECT:
WORK ITEM: ( 9.3.8 ) MANHOLE [600x600mm]
TOTAL QANTITY OF WORK ITEM: 1.00 No