Two Years On - Rehabilitation of 5th Road Bridge v002 KN
Two Years On - Rehabilitation of 5th Road Bridge v002 KN
No 3 Helen Joseph Street PO Box 61877 Tel +27(0) 11 688 7851 (O)
The Bus Factory Marshalltown Fax +27(0) 11 688 7899/63
Newtown 2107 E-mail: info@jda.org.za
Johannesburg, 2000
www.jda.org.za
www.joburg.org.za
To: All news editors
For immediate release
20 December 2022
Two years since the collapse of the 5th Road Bridge we highlight how the crisis
showcased the importance of cooperative governance within the city in order respond
to complex and unexpected challenges by adapting and redirecting development
efforts to address critical needs.
Roads and bridges form a critical part of the transport infrastructure of a growing city.
The completion of the 5th Road Bridge in Northwold demonstrates the City of
Johannesburg’s commitment to providing new transport infrastructure.
Directors
L Brenner (Chairperson) S Moonsamy Acting (CEO) S Moonsamy (CFO) LB Matshidze N Ntingane S Marota A Dreyer M Malinga W Thwala M PHathutshedzo C Whittle
R Shirinda (Company Secretary)
Registration Number: 2001/005101/07
The construction and rehabilitation of the 5th Road Bridge was in line with the JDA
objectives of developing resilient, sustainable, and liveable urban areas in identified
transit nodes and corridors.
The Johannesburg Road Agency (JRA) appointed the JDA to implement the long-
term rehabilitation construction of the 5th Road Bridge. The bridge was damaged and
washed away because of the heavy flooding in December 2020.
Following the disaster, as an interim measure, the JRA appointed an engineer and a
contractor to design and construct a temporary access road off Malibongwe Drive,
north of the N1.
As part of the long-term solution to the maintenance of the 5th Road Bridge, JDA
began building the structure and the following works:
The safety of the public and all affected parties was of the utmost importance in the
project. A detailed traffic management plan (TMP) was part of this project to:
“We hope the rehabilitated 5th Road Bridge will be of great benefit to residents of
Northwold, including the Sunrise Estate Retirement Village community for whom the
bridge provides the only access to the estate,” JDA CEO Mokgema Mongane.
The rehabilitation of the bridge provided opportunities for SMMEs and local labour,
with 30% of the local spending required by the City of Johannesburg to provide access
to employment opportunities for local contractors.
This rehabilitation project formed part of the JRA Bridges Management Programme
to reach the target of 50 bridges across the city.
ENDS
Issued by:
Kenneth Nxumalo
Johannesburg Development Agency
For more information:
Elias Nkabinde
Email: enkabinde@jda.org.za
076 961 8022