CARRIAGE OF MATERIALS BY MECHANICAL TRANSPORT FOR THE YEAR 2003-2004 (PONDICHERRY REGION) - CALCULATION DETAILS.

---------- ------------------------------------- ------------ ------------- --------------- ------------------ ------------- ------------- ------------ ------------
COST PER LITRE
Diesel 23.00
Mobile oil 70.00
HIRE CHARGE/DAY(8hrs)
Truck 1200.00
Rate of Belder 85.00

CONSUMPTION-Km/Litre
Diesel 5
Mobile oil 140

Incidental charges-sand 5.10


Loading charge-cement 25.45
Unloading charge-cement 25.45

CAPACITY PER TRIP


AFTER DEDUCTION OF
VOIDS
1 Lime,Moorum and cum 8
building rubbish
2 Earth cum 6.4
3 Manure or Sludge cum 7.36
4 Excavated rocks cum 4
5 Sand,Stone metal
below 40mm nominal
size cum 8
6 Stone metal 40mm and
above. cum 7.36
7 Soling stone cum 6.8
8 Bricks 1000nos 3
9 Tiles 1000nos 5
10 Cement,Stone blocks tonne 9
G.I.,C.I.,A.C.,and
CC. pipes below 100mm
dia.and other heavy
materials.
11 Steel tonne 9
12 Timber cum 7
13 Tar,Bitumen tonne 8
14 Salvent qtl 80
15 Steam coal tonne 7
16 S.W.pipes-
(a)100mm dia. 100 m 6

Pondicherry Page B -89


(b)150mm dia. 100 m 3
(c)200mm dia. 100 m 1.8
(d)230mm dia. 100 m 1.26
(e)250mm dia. 100 m 1.05
(f)300mm dia. 100 m 0.84
(g)350mm dia. 100 m 0.6
(h)400mm dia. 100 m 0.42
(i)450mm dia. 100 m 0.33
(j)500mm dia. 100 m 0.3
(k)600mm dia. 100 m 0.24
17 R.C.C.pipes,A.C.pipes
Hume Steel and C.I.
pipes
(a)100 mm dia 100 m 3.66
(b)125 mm dia 100 m 2.74
(c)150 mm dia 100 m 2.196
(d)200 mm dia 100 m 1.35
(e)250 mm dia 100 m 0.95
(f)300 mm dia 100 m 0.7686
(g)350 mm dia 100 m 0.649
(h)400 mm dia 100 m 0.4026
(i)450,500 mm dia 100 m 0.3294
(j)600,700,750 and
800 mm dia. 100 m 0.2196
(B)BY MECHANICAL TRANSPORT (Including loading, unloading and stacking)
---------- ------------------------------------- ------------ ------------- --------------- ------------------ ------------- ------------- ------------ ------------ ------------ ------------- ------------- -------------
Lead in Average No.of Km.done Total Total Cost of Hire Total Cost per Increase
Kms. Speed(Km) trips 2NL+6 Cost of Cost of 6 Bel- charge cost trip in cost
(L) (S) (N) diesel mob.oil ders truck (5+6+7+8) 8/3
---------- ------------------------------------- ------------ ------------- --------------- ------------------ ------------- ------------- ------------ ------------ ------------ ------------- ------------- -------------
1 2 3 4 5 6 7 8 9 9 10
---------- ------------------------------------- ------------ ------------- --------------- ------------------ ------------- ------------- ------------ ------------ ------------ ------------- ------------- -------------
1 16 7.11 20.22 93.01 10.11 0.00 1200.00 1303.12 183.28 27.03
2 17 6.48 31.92 146.83 15.96 0.00 1200.00 1362.79 210.31 27.03
3 17.5 5.96 41.76 192.1 20.88 0.00 1200.00 1412.98 237.08 26.77
4 18 5.54 50.32 231.47 25.16 0.00 1200.00 1456.63 262.93 25.85
5 18.5 5.19 57.9 266.34 28.95 0.00 1200.00 1495.29 288.11 25.18
6 19 4.90 64.8 298.08 32.4 0.00 1200.00 1530.48 312.34 24.23
7 19.5 4.66 71.24 327.7 35.62 0.00 1200.00 1563.32 335.48 23.14
8 20 4.44 77.04 354.38 38.52 0.00 1200.00 1592.9 358.76 23.28
9 20.5 4.26 82.68 380.33 41.34 0.00 1200.00 1621.67 380.67 21.91
10 21 4.10 88 404.8 44 0.00 1200.00 1648.8 402.15 21.48
11 21.5 3.95 92.9 427.34 46.45 0.00 1200.00 1673.79 423.74 21.59
12 22 3.83 97.92 450.43 48.96 0.00 1200.00 1699.39 443.71 19.97
13 22.5 3.71 102.46 471.32 51.23 0.00 1200.00 1722.55 464.3 20.59

Pondicherry Page B -90


14 23 3.61 107.08 492.57 53.54 0.00 1200.00 1746.11 483.69 19.39
15 23.5 3.51 111.3 511.98 55.65 0.00 1200.00 1767.63 503.6 19.91
16 24 3.43 115.76 532.5 57.88 0.00 1200.00 1790.38 521.98 18.38
17 24.5 3.35 119.9 551.54 59.95 0.00 1200.00 1811.49 540.74 18.76
18 25 3.28 124.08 570.77 62.04 0.00 1200.00 1832.81 558.78 18.04
19 25.5 3.21 127.98 588.71 63.99 0.00 1200.00 1852.7 577.16 18.38
20 26 3.15 132 607.2 66 0.00 1200.00 1873.2 594.67 17.51
21 26.5 3.09 135.78 624.59 67.89 0.00 1200.00 1892.48 612.45 17.78
22 27 3.04 139.76 642.9 69.88 0.00 1200.00 1912.78 629.2 16.75
23 27.5 2.99 143.54 660.28 71.77 0.00 1200.00 1932.05 646.17 16.97
24 28 2.95 147.6 678.96 73.8 0.00 1200.00 1952.76 661.95 15.78
25 28.5 2.90 151 694.6 75.5 0.00 1200.00 1970.1 679.34 17.39
26 29 2.86 154.72 711.71 77.36 0.00 1200.00 1989.07 695.48 16.14
27 29.5 2.83 158.82 730.57 79.41 0.00 1200.00 2009.98 710.24 14.76
28 30 2.79 162.24 746.3 81.12 0.00 1200.00 2027.42 726.68 16.44
29 30.5 2.76 166.08 763.97 83.04 0.00 1200.00 2047.01 741.67 14.99
30 31 2.73 169.8 781.08 84.9 0.00 1200.00 2065.98 756.77 15.1
---------- ------------------------------------- ------------ ------------- --------------- ------------------ ------------- ------------- ------------ ------------ ------------ ------------- ------------- -------------
N=8/((2L/S)+1)
Total cost of diesel= Cost of diesel*(Km.done/Km.per litre of diesel)
Total cost of mob.oil=Cost of mob.oil*(Km.done/Km.per litre of oil)

Pondicherry Page B -91


CARRIAGE OF MATERIALS BY MECHANICAL TRANSPORT INCLUDING LOADING, UNLOADING AND STACKING
FOR THE YEAR 2003-2004 (PONDICHERRY REGION)
---------- ------------------------------------- ------------ ------------- --------------- ------------------ ------------- ------------- ------------ ------------ ------------ ------------- ------------- -------------
Code Materials Unit Incidental Rate Loading Unloading
Charges --------------- ------------------ ------------- ------------- ------------ ------------ ------------ ------------- charge charge
to be 1Km 2Km 3Km 4Km 5Km Beyond Beyond Beyond
adopted 5Km 10Km 20Km
initially upto upto per Km
10 Km 20 Km
per Km per Km
---------- ------------------------------------- ------------ ------------- --------------- ------------------ ------------- ------------- ------------ ------------ ------------ ------------- ------------- -------------
1 2 3 4 4 5 6 7 8 9 10 11 12 13
---------- ------------------------------------- ------------ ------------- --------------- ------------------ ------------- ------------- ------------ ------------ ------------ ------------- ------------- -------------
1.1.1 a) Lime moorum, building
rubbish, earth, manure
or sludge and excavated
rocks:

i) Lime,Moorum,Gravel cum 7.65 22.91 26.29 29.64 32.87 36.01 2.85 2.41 2.03 8.91 8.91
Surki,building rubbish
and brick jelly
ii) Earth cum 4.25 28.64 32.86 37.04 41.08 45.02 3.56 3.01 2.53 10.18 10.18
iii) Manure or Sludge cum 7.65 24.90 28.57 32.21 35.72 39.15 3.10 2.62 2.20 8.91 8.91
iv) Excavated rocks cum 15.30 45.82 52.58 59.27 65.73 72.03 5.70 4.81 4.05 17.82 17.82

a) Sand, stone aggregate


and soling stone

i) Sand cum 5.10 22.91 26.29 29.64 32.87 36.01 2.85 2.41 2.03 10.18 10.18

ii) Stone aggregate


below 40mm nominal
size cum 51.00 22.91 26.29 29.64 32.87 36.01 2.85 2.41 2.03 13.49 13.49
iii) Stone aggregate 40mm
and above cum 51.00 24.90 28.57 32.21 35.72 39.15 3.10 2.62 2.20 13.49 13.49

iv) Soling stone and cum 38.25 26.95 30.93 34.86 38.67 42.37 3.35 2.83 2.38 10.18 10.18
masonary stone
1.1.2 Bricks 1000nos 38.25 61.09 70.10 79.03 87.64 96.04 7.60 6.42 5.40 15.27 15.27
1.1.3 Tiles 1000nos 17.85 36.66 42.06 47.42 52.59 57.62 4.56 3.85 3.24 6.36 6.36

Pondicherry Page B -92


---------- ------------------------------------- ------------ ------------- --------------- ------------------ ------------- ------------- ------------ ------------ ------------ ------------- ------------- -------------
1 2 3 4 4 5 6 7 8 9 10 11 12 13
---------- ------------------------------------- ------------ ------------- --------------- ------------------ ------------- ------------- ------------ ------------ ------------ ------------- ------------- -------------
1.1.4 Cement,Stone blocks tonne 17.85 20.36 23.37 26.34 29.21 32.01 2.53 2.14 1.80 25.45 25.45
G.I.,C.I.,A.C.,and
CC. pipes below 100mm
dia.,other heavy materials
rice and wheat.
1.1.5 Steel and Iron works tonne 17.85 20.36 23.37 26.34 29.21 32.01 2.53 2.14 1.80 25.45 25.45
1.1.6 Timber cum 7.65 26.18 30.04 33.87 37.56 41.16 3.26 2.75 2.32 8.91 8.91
1.1.7 Tar,Bitumen tonne 38.25 22.91 26.29 29.64 32.87 36.01 2.85 2.41 2.03 19.09 19.09
1.1.7A Solvent qtl 3.83 2.29 2.63 2.96 3.29 3.60 0.29 0.24 0.20 1.91 1.91
1.1.8 Steam coal tonne 7.65 26.18 30.04 33.87 37.56 41.16 3.26 2.75 2.32 8.91 8.91
1.1.9 S.W.pipes-
(a)100mm dia. 100 m 20.83 30.55 35.05 39.51 43.82 48.02 3.80 3.21 2.70 29.69 29.69
(b)150mm dia. 100 m 41.65 61.09 70.10 79.03 87.64 96.04 7.60 6.42 5.40 59.38 59.38
(c)200mm dia. 100 m 69.42 101.82 116.84 131.71 146.07 160.06 12.67 10.69 9.01 98.97 98.97
(d)230mm dia. 100 m 99.17 145.46 166.91 188.16 208.67 228.66 18.10 15.28 12.87 141.39 141.39
(e)250mm dia. 100 m 119.00 174.55 200.30 225.79 250.41 274.39 21.72 18.33 15.44 169.67 169.67
(f)300mm dia. 100 m 148.75 218.19 250.37 282.24 313.01 342.99 27.15 22.92 19.30 212.08 212.08
(g)350mm dia. 100 m 208.25 305.47 350.52 395.13 438.22 480.18 38.02 32.08 27.02 296.92 296.92
(h)400mm dia. 100 m 297.50 436.38 500.74 564.48 626.02 685.98 54.31 45.83 38.60 424.17 424.17
(i)450mm dia. 100 m 378.64 555.39 637.30 718.42 796.76 873.06 69.12 58.33 49.12 539.85 539.85
(j)500mm dia. 100 m 416.50 610.93 701.03 790.27 876.43 960.37 76.03 64.17 54.03 593.83 593.83
(k)600mm dia. 100 m 520.63 763.67 876.29 987.83 1095.54 1200.46 95.04 80.21 67.54 742.29 742.29
1.1.10 R.C.C.pipes,A.C.pipes
Steel cylinder,R.C.Pipes,
C.I.Pipes and Unrein-
forced cement pipes
(a)100 mm dia 100 m 34.14 50.08 57.46 64.78 71.84 78.72 6.23 5.26 4.43 48.67 48.67
(b)125 mm dia 100 m 45.60 66.89 76.76 86.53 95.96 105.15 8.32 7.03 5.92 65.02 65.02
(c)150 mm dia 100 m 56.90 83.46 95.77 107.96 119.73 131.20 10.39 8.77 7.38 81.12 81.12
(d)200 mm dia 100 m 92.56 135.76 155.79 175.61 194.76 213.41 16.90 14.26 12.01 131.96 131.96
(e)250 mm dia 100 m 131.53 192.93 221.38 249.56 276.77 303.27 24.01 20.26 17.06 187.53 187.53
(f)300 mm dia 100 m 162.57 238.46 273.63 308.46 342.09 374.85 29.68 25.05 21.09 231.79 231.79
(g)350 mm dia 100 m 192.53 282.40 324.05 365.30 405.13 443.93 35.15 29.66 24.98 274.5 274.5
(h)400 mm dia 100 m 310.36 455.24 522.38 588.87 653.08 715.62 56.66 47.81 40.26 442.5 442.5
(i)450,500 mm dia 100 m 379.33 556.41 638.46 719.73 798.21 874.65 69.25 58.44 49.21 540.83 540.83
(j)600,700,750 and
800 mm dia. 100 m 568.99 834.61 957.70 1079.60 1197.31 1311.98 103.87 87.66 73.82 811.25 811.25

Note:
1. The above rates includes stacking charges.
2. For Code No. 1.1.1 the rates will be applicable to net quantities after deduction of prescribed percentage
for voids mentioned in the C.P.W.D. specification under Sub-Head "Carriage of Materials".

Pondicherry Page B -93


CARRIAGE OF MATERIALS BY MECHANICAL TRANSPORT INCLUDING LOADING, UNLOADING AND STACKING
FOR THE YEAR 2003-2004 (PONDICHERRY REGION)

Code Materials Unit Incidental Rate Loading Unloading


Charges 1Km 2Km 3Km 4Km 5Km Beyond Beyond Beyond charge charge
to be 5Km 10Km 20Km
adopted upto upto per Km
initially 10 Km 20 Km
per Km per Km
1 2 3 4 4 5 6 7 8 9 10 11 12 13
1.1.1 a) Lime moorum, building
rubbish, earth, manure
or sludge and excavated
rocks:

i) Lime,Moorum,Gravel cum 7.65 22.91 26.29 29.64 32.87 36.01 2.85 2.41 2.03 8.91 8.91
Surki,building rubbish
and brick jelly
ii) Earth cum 4.25 28.64 32.86 37.04 41.08 45.02 3.56 3.01 2.53 10.18 10.18
iii) Manure or Sludge cum 7.65 24.9 28.57 32.21 35.72 39.15 3.1 2.62 2.2 8.91 8.91
iv) Excavated rocks cum 15.3 45.82 52.58 59.27 65.73 72.03 5.7 4.81 4.05 17.82 17.82

a) Sand, stone aggregate


and soling stone

i) Sand cum 5.1 22.91 26.29 29.64 32.87 36.01 2.85 2.41 2.03 10.18 10.18

ii) Stone aggregate


below 40mm nominal
size cum 51 22.91 26.29 29.64 32.87 36.01 2.85 2.41 2.03 13.49 13.49
iii) Stone aggregate 40mm
and above cum 51 24.9 28.57 32.21 35.72 39.15 3.1 2.62 2.2 13.49 13.49

iv) Soling stone and cum 38.25 26.95 30.93 34.86 38.67 42.37 3.35 2.83 2.38 10.18 10.18
masonary stone
1.1.2 Bricks 1000nos 38.25 61.09 70.1 79.03 87.64 96.04 7.6 6.42 5.4 15.27 15.27
1.1.3 Tiles 1000nos 17.85 36.66 42.06 47.42 52.59 57.62 4.56 3.85 3.24 6.36 6.36

Pondicherry Page B -113


1 2 3 4 4 5 6 7 8 9 10 11 12 13

1.1.4 Cement,Stone blocks tonne 17.85 20.36 23.37 26.34 29.21 32.01 2.53 2.14 1.8 25.45 25.45
G.I.,C.I.,A.C.,and
CC. pipes below 100mm
dia.,other heavy materials
rice and wheat.
1.1.5 Steel and Iron works tonne 17.85 20.36 23.37 26.34 29.21 32.01 2.53 2.14 1.8 25.45 25.45
1.1.6 Timber cum 7.65 26.18 30.04 33.87 37.56 41.16 3.26 2.75 2.32 8.91 8.91
1.1.7 Tar,Bitumen tonne 38.25 22.91 26.29 29.64 32.87 36.01 2.85 2.41 2.03 19.09 19.09
1.1.7A Solvent qtl 3.83 2.29 2.63 2.96 3.29 3.6 0.29 0.24 0.2 1.91 1.91
1.1.8 Steam coal tonne 7.65 26.18 30.04 33.87 37.56 41.16 3.26 2.75 2.32 8.91 8.91
1.1.9 S.W.pipes-
(a)100mm dia. 100 m 20.83 30.55 35.05 39.51 43.82 48.02 3.8 3.21 2.7 29.69 29.69
(b)150mm dia. 100 m 41.65 61.09 70.1 79.03 87.64 96.04 7.6 6.42 5.4 59.38 59.38
(c)200mm dia. 100 m 69.42 101.82 116.84 131.71 146.07 160.06 12.67 10.69 9.01 98.97 98.97
(d)230mm dia. 100 m 99.17 145.46 166.91 188.16 208.67 228.66 18.1 15.28 12.87 141.39 141.39
(e)250mm dia. 100 m 119 174.55 200.3 225.79 250.41 274.39 21.72 18.33 15.44 169.67 169.67
(f)300mm dia. 100 m 148.75 218.19 250.37 282.24 313.01 342.99 27.15 22.92 19.3 212.08 212.08
(g)350mm dia. 100 m 208.25 305.47 350.52 395.13 438.22 480.18 38.02 32.08 27.02 296.92 296.92
(h)400mm dia. 100 m 297.5 436.38 500.74 564.48 626.02 685.98 54.31 45.83 38.6 424.17 424.17
(i)450mm dia. 100 m 378.64 555.39 637.3 718.42 796.76 873.06 69.12 58.33 49.12 539.85 539.85
(j)500mm dia. 100 m 416.5 610.93 701.03 790.27 876.43 960.37 76.03 64.17 54.03 593.83 593.83
(k)600mm dia. 100 m 520.63 763.67 876.29 987.83 1095.54 1200.46 95.04 80.21 67.54 742.29 742.29
1.1.10 R.C.C.pipes,A.C.pipes
Steel cylinder,R.C.Pipes,
C.I.Pipes and Unrein-
forced cement pipes
(a)100 mm dia 100 m 34.14 50.08 57.46 64.78 71.84 78.72 6.23 5.26 4.43 48.67 48.67
(b)125 mm dia 100 m 45.6 66.89 76.76 86.53 95.96 105.15 8.32 7.03 5.92 65.02 65.02
(c)150 mm dia 100 m 56.9 83.46 95.77 107.96 119.73 131.2 10.39 8.77 7.38 81.12 81.12
(d)200 mm dia 100 m 92.56 135.76 155.79 175.61 194.76 213.41 16.9 14.26 12.01 131.96 131.96
(e)250 mm dia 100 m 131.53 192.93 221.38 249.56 276.77 303.27 24.01 20.26 17.06 187.53 187.53
(f)300 mm dia 100 m 162.57 238.46 273.63 308.46 342.09 374.85 29.68 25.05 21.09 231.79 231.79
(g)350 mm dia 100 m 192.53 282.4 324.05 365.3 405.13 443.93 35.15 29.66 24.98 274.5 274.5
(h)400 mm dia 100 m 310.36 455.24 522.38 588.87 653.08 715.62 56.66 47.81 40.26 442.5 442.5
(i)450,500 mm dia 100 m 379.33 556.41 638.46 719.73 798.21 874.65 69.25 58.44 49.21 540.83 540.83
(j)600,700,750 and
800 mm dia. 100 m 568.99 834.61 957.70 1079.6 1197.31 1311.98 103.87 87.66 73.82 811.25 811.25

Note:
1. The above rates includes stacking charges.
2. For Code No. 1.1.1 the rates will be applicable to net quantities after deduction of prescribed percentage
for voids mentioned in the C.P.W.D. specification under Sub-Head "Carriage of Materials".