Professional Documents
Culture Documents
Guc 1788 58 26428 2022-11-26T23 15 35
Guc 1788 58 26428 2022-11-26T23 15 35
(PM/CM)
• When will the resource be needed for each task (task start time, duration and finish)?
• At what rate will the resource be used on the task (how much or how many per day)?
• What happens if other projects that we are doing need the same resources at the same time?
Labour productivity
• Productivity in the construction industry is a major concern among all segments.
• productivity is often defined as units or value of output divided by hours of labour or equipment
input
(Adrian, 1987)
Productivity
• e.g. productivity of a carpenter crew installing wall panels was 15m2/labour hour
or
❑Time
❑Resource
❑Mixed
Resource Allocation
• Additional resources may be available—but at such a premium that they are treated as limited
Resource Management
• It may simply be more costly to “double up” on resources at certain times in a project
• Added cost may be justified if the contract places a tight constraint on the project completion
date
• Since the duration of the project is fixed, critical activities are not manipulated
6
Resources
Resource
4 imbalance
A D F
B
2 E
C
2 4 6 8 10 12 14
Project Days
Creating Resource Loading Charts
4. Rearrange activities within their float to create
a more level profile. Splitting C creates a more
8 level project.
6
Resources
4 C
A D F
B
2 E
C
2 4 6 8 10 12 14
Project Days
Manual Solution for Allocation
Resource limits
are not to be
exceeded under
any circumstances
EF
LS TF
5 6 6 8
6 1 7 7 1 9
1 5 5 9 9 15
The resource limits: 1 0 5 5 0 9 9 0 15
5M (masons)
0 1 15 16
2H (helpers) 0 0 1 15 0 16
1 3 3 6 7 9
Resource limits 7 6 9 10 7 13 13 6 15
are not to be
exceeded under
any circumstances 3 7
9 6 13
EF
LS
3 5
11 8 13
Project duration is 20 days—4 days longer
than if the resource limits had been ignored