Scadapak SJJTG

[Company Name] Project Start: Sun, 1/1/2023


[Project Lead] Today: Sun, 12/31/2023
Display Week: 1 Jan 2, 2023 Jan 9, 2023 Jan 16, 2023 Jan 23, 2023 Jan 30, 2023 Feb 6, 2023 Feb 13, 2023 Feb 20, 2023
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
ASSIGNED
TASK PROGRESS START END M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
TO

Contract & Procurement


RFQ 1/1/23 1/4/23
Issue PO 3/1/23 3/4/23
Fabrication & Manufacturing
Engineering
Site visit workscoping
Final Design
Task 3
Task 4
Task 5
Logistics
Task 1
Task 2
Task 3
Task 4
Task 5
Installation
Task 1
Task 2
Task 3
Task 4
Task 5

Insert new rows ABOVE this one