Viale Marconi, 20 Dalmine (BG) ITALY - tel. +39-035-566-610 fax +39-035-566-611 e-mail: info@ferretti-group.

com
Primetals
MASTER PLAN TIME SCHEDULE
Mini Mill Bangladesh-PL-001 - Rev.00
WBS Nome attività 2016 2017
mag giu lug ago set ott nov dic gen feb mar apr mag giu lug ago set ott nov dic gen feb mar apr mag giu lug ago set ott
1 GENERAL MILESTONES
1.1 CONTRACT EFFECTIVE DATE 01/07

1.2 KICK OFF MEETING 08/07

1.3 FINAL TECHNOLOGICAL PLANT LAYOUT & GENERAL 08/07

ARRANGEMENT
1.4 SITE PREPARATION
1.5 SITE MOBILIZATION
2 BASIC DESIGN
2.1 Steel Structure Building (SSB)
2.2 Civil Works Basinc Eng. Steel Making Plant (SMP)

2.3 Civil Works Eng. Rolling Mill (RM)


2.4 Civil Works Eng. Auxiliaries Plant (AUX)

2.5 Basic Eng. Equipment SMP


2.6 Basinc Eng. Equipment RM
2.7 Basinc Eng. Equipment AUX
2.8 Eng. Approved 01/01

3 DETAIL DESIGN
3.1 SSB Detail Engineering
3.2 Civil Detail Eng. (Building Plints)
3.3 Civil Detail Eng. SMP
3.4 Civil Detail Eng. RM
3.5 Civil Detail Eng. AUX
3.6 Detail Eng. Equipment SMP
3.7 Detail Eng. Equipment RM
3.8 Detail Eng. Equipment AUX
4 PROCUREMENT MANUFACUTRING
4.1 SSP
4.1.1 SMP
4.1.2 RM
4.2 EQUIPMENT
4.2.1 SMP
4.2.2 RM
4.2.3 AUX
4.3 BULK MATERIALS
4.3.1 Bulk Materials
5 SHIPMENT/DELIVERY TO SITE
5.1 SSB
5.1.1 SMP
5.1.2 RM
5.2 EQUIPMENT
5.2.1 SMP
5.2.2 RM
5.2.3 AUX
5.3 BULK MATERIALS
5.3.1 Bulk Materials
6 CIVIL WORKS
6.1 Building Plints
6.2 SMP
6.3 RM
6.4 AUX
7 SSB INSTALLATION
7.1 SMP
7.2 RM
7.3 CRANES (AUX)
7.3.1 SMP
7.3.2 RM
8 MEIP INSTALLATION
8.1 SMP
8.2 RM
8.3 AUX
9 OVERALL UTILITIES PIPE RACK AND PIPING

9.1 Overall Utilities Pipe Rack And Piping


9.2 Permanent Utilities 31/08

9.3 Temporary Utilities and Power Available 29/12

9.4 MECHANICAL COMPLETION SMP 28/04

9.5 MECHANICAL COMPLETION RM 28/04

9.6 MECHANICAL COMPLETION AUX 10/03

10 INTEGRATION FACILITIES
10.1 Oxygen/Nitrogen Plant
10.2 Compressed Air Plant
10.3 Natural Gas Station
10.4 Main Substation
11 INTERCONNECTING PIPING/CABLES ROLLING MILL

11.1 Interconnecting Piping/Cables


12 COLDTEST
12.1 SMP
12.2 RM
12.3 AUX
13 FUNCTIONAL TEST
14 PROVISIONAL ACCEPTANCE CERTIFICATE (PAC) 19/06

15 HOT TRIALS
16 HOT TEST & PERFORMANCE TEST
17 FINAL ACCEPTANCE CERTIFICATE (FAC) 05/09

Progetto: Mini Mill Bangladesh Attività Divisione Cardine Riepilogo Riepilogo progetto Attività esterne Cardine esterno Avanzamento Scadenza
Data: lun 15/06/15

Pagina 1