MASTER PLAN TIME SCHEDULE
Mini Mill Bangladesh-PL-001 - Rev.00
WBS Nome attività 2016 2017
mag giu lug ago set ott nov dic gen feb mar apr mag giu lug ago set ott nov dic gen feb mar apr mag giu lug ago set ott
1 GENERAL MILESTONES
1.1 CONTRACT EFFECTIVE DATE 01/07
ARRANGEMENT
1.4 SITE PREPARATION
1.5 SITE MOBILIZATION
2 BASIC DESIGN
2.1 Steel Structure Building (SSB)
2.2 Civil Works Basinc Eng. Steel Making Plant (SMP)
3 DETAIL DESIGN
3.1 SSB Detail Engineering
3.2 Civil Detail Eng. (Building Plints)
3.3 Civil Detail Eng. SMP
3.4 Civil Detail Eng. RM
3.5 Civil Detail Eng. AUX
3.6 Detail Eng. Equipment SMP
3.7 Detail Eng. Equipment RM
3.8 Detail Eng. Equipment AUX
4 PROCUREMENT MANUFACUTRING
4.1 SSP
4.1.1 SMP
4.1.2 RM
4.2 EQUIPMENT
4.2.1 SMP
4.2.2 RM
4.2.3 AUX
4.3 BULK MATERIALS
4.3.1 Bulk Materials
5 SHIPMENT/DELIVERY TO SITE
5.1 SSB
5.1.1 SMP
5.1.2 RM
5.2 EQUIPMENT
5.2.1 SMP
5.2.2 RM
5.2.3 AUX
5.3 BULK MATERIALS
5.3.1 Bulk Materials
6 CIVIL WORKS
6.1 Building Plints
6.2 SMP
6.3 RM
6.4 AUX
7 SSB INSTALLATION
7.1 SMP
7.2 RM
7.3 CRANES (AUX)
7.3.1 SMP
7.3.2 RM
8 MEIP INSTALLATION
8.1 SMP
8.2 RM
8.3 AUX
9 OVERALL UTILITIES PIPE RACK AND PIPING
10 INTEGRATION FACILITIES
10.1 Oxygen/Nitrogen Plant
10.2 Compressed Air Plant
10.3 Natural Gas Station
10.4 Main Substation
11 INTERCONNECTING PIPING/CABLES ROLLING MILL
15 HOT TRIALS
16 HOT TEST & PERFORMANCE TEST
17 FINAL ACCEPTANCE CERTIFICATE (FAC) 05/09