Professional Documents
Culture Documents
06 - Construction Estimate
06 - Construction Estimate
Special Topic:
Construction
Estimate &
Productivity
by:
Ar. REYNALDO C. VENTURA, JR.
MSCM, UAP, Int’l Assoc. AIA, PEM, ACP
1
1/17/20
on Estimating:
2
1/17/20
3
1/17/20
PURPOSE OF AN ESTIMATE
PURPOSE OF AN ESTIMATE
According to Owner
4
1/17/20
PURPOSE OF AN ESTIMATE
According to Contractor
PURPOSE OF AN ESTIMATE
According to Architect/Engineer
5
1/17/20
Types of Estimates
Analogous Estimating - Uses historical
information and expert judgment.
Parametric Estimating - Uses a
statistical relationship between
relevant historical data and other
variables (example: square meters in
construction).
Bottom-up Estimating - The detailed
cost is then summarized or “rolled up”
to higher levels for subsequent
reporting and tracking purposes.
KINDS OF ESTIMATES
1. Preliminary
2. Unit price
3. Assembly or Conceptual Cost
4. Detailed estimate
Accuracy
within
20% Preliminary
10% Assembly
5% Detailed
Time
6
1/17/20
KINDS OF ESTIMATES
1. Preliminary Estimate
Ø A cost prediction based solely on
size and/or capacity of a proposed
project.
Ø Prepare before any design is
completed.
Ø Rely on broad data from already
executed similar project
KINDS OF ESTIMATES
1. Preliminary Estimate
ADVANTAGE
✣ Allows a quick determination of
the feasibility of a project
✣ A quick screening on alternatives,
etc. (e.g., should it be a concrete
building or a steel building !).
7
1/17/20
KINDS OF ESTIMATES
1. Preliminary Estimate
EXAMPLE:
• Parking Garage
$15.0/sq. ft or $4500/parking
space
• High School
$80 to 110/sq. ft or $40,000/
student seat
• Medical Centers
$90 to 130/sq. ft
KINDS OF ESTIMATES
2. Unit Price Estimate
Ø Unit prices are obtained from
data on projects already
performed.
Ø Cost of labor, material, and
equipment for all units of work
are added together and divided
by the number of units involved
8
1/17/20
KINDS OF ESTIMATES
2. Unit Price Estimate
EXAMPLE:
____________________________________________________
Work Item Estimated
Quantity Unit Price Total
____________________________________________________
Site Preparation 50,000 sq. yd $ 7 $ 350,000
Earth Excavation 100,000 cu.yd. $ 12 $ 1,200,000
Paving 50,000 sq.yd. $ 8 $ 400,000
Total bid price $ 1,950,000
____________________________________________________
KINDS OF ESTIMATES
3. Assembly or Conceptual Estimate
Ø Performed when conceptual
design decisions are being made.
Ø Work package concept can be
used to determine the element or
assembly to be studied
Ø Need a breakdown of cost of a
completed project into its
functional elements to find the
relationship between element
cost and project cost
9
1/17/20
KINDS OF ESTIMATES
3. Assembly or Conceptual Estimate
EXAMPLE:
KINDS OF ESTIMATES
4. Detailed (Definitive) Estimate
Ø Prepared after drawings and
specification are completed.
Ø Requires a complete quantity
takeoff based on drawing and the
complete set of contract
documents
Ø Need information on labor rate
"productivity", material cost, cost
of renting or purchasing
equipment
10
1/17/20
KINDS OF ESTIMATES
4. Detailed (Definitive) Estimate
EXAMPLE:
Estimating Theory
11
1/17/20
Ø Ellipse Area
= (π) (short radius) (long radius)
= (π) (3) (5)
= 11.78 units
12
1/17/20
13
1/17/20
Note:
1 sq. unit =
0.25 sq. units
CALCULATED
ELLIPSE
= 11.78 UNITS
14
1/17/20
15
1/17/20
16
1/17/20
Estimating Team
Lead Estimator
• Experience in construction scheduling
• Ability to read & interpret plans
• Understanding of specifications
• Familiar with construction techniques
• Knowledge of circumstances &
conditions affecting costs
• Ability to determine costs of
construction
• Ability to perform mathematics
manually
17
1/17/20
Source: https://www.payscale.com/research/PH/Job=Cost_Estimator/Salary
18
1/17/20
Source: https://www.glassdoor.com/Salaries/construction-estimator-salary-SRCH_KO0,22.htm
19