Report No:

001
Mechanical Daily Report
for the OEA Site Issue: Date:
1 25/10/2022

Mechanical Daily Report for the OEA Site 25/10/2022


Observations from the morning site walk round on the OEA site. Please note that we are aware that
works are incomplete and that they are still in progress so the below observations are intended to
assist the Contractor and to seek clarification:

1 Drainage installation is proceeding without approved drawings:

Fig 1: Level 3 toilets

2 Required for the IT/Comms room HVAC system are: FD’s, and MD. PRV in wall.
Not yet installed.
Report No:

001
Mechanical Daily Report
for the OEA Site Issue: Date:
1 25/10/2022

Fig 2: GF IT/Comms room


3 Please clarify the fire separation strategy when replacing the drainage. For example,
where will fire collars be fitted? According to the approved FLS drawings these risers
are 2 hour rated.

Fig 3: Existing drainage at GF toilets

4 No end of line flushing valves in the fire pipe system. Please clarify how the
system will be flushed.
Report No:

001
Mechanical Daily Report
for the OEA Site Issue: Date:
1 25/10/2022

Fig 4: No end of line flushing valves. Please confirm intention


regarding flushing
5  Installed fire pipe supports does not follow the approved Civil Defense approved detail
drawing, esp larger size pipe installed at 10mm for 100 dia and 12mm for 150 dia.

Fig 5: standard detail for supports from approved Civil defense drawing